MONTHYEARML24221A4172024-08-0101 August 2024 DC Cook 2024 PI&R Inspection Request for Information ML24178A0432024-06-26026 June 2024 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - License Amendment Request Regarding Neutron Flux Instrumentation ML24156A0072024-05-30030 May 2024 NRR E-mail Capture - Final RAI - D.C. Cook Nuclear Plant, Unit Nos. 1 and 2 - License Amendment Request Regarding Reserve Feed Enclosure ML24156A0052024-05-22022 May 2024 NRR E-mail Capture - D.C. Cook Nuclear Plant, Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Reserve Feed Enclosure ML24103A1392024-04-12012 April 2024 NRR E-mail Capture - D.C. Cook Nuclear Plant, Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Adoption of 10 CFR 50.69 ML24096A1132024-04-0505 April 2024 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Delay in Issuance of License Amendment Regarding Neutron Flux Instrumentation ML24093A0582024-04-0202 April 2024 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 1 - Acceptance of License Amendment Request Regarding Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System, ML23361A1022023-12-21021 December 2023 Security Rule Exemption Request - ISFSI Docket No. Reference ML23321A1222023-11-17017 November 2023 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - License Amendment Request Regarding Neutron Flux Instrumentation ML23052A1502023-02-21021 February 2023 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Neutron Flux Instrumentation ML22307A2532022-11-0303 November 2022 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Verbal Authorization of Relief Request ISIR-5-06 Regarding Alternative to N-729-6 for RPV Head Visual Examination ML22122A0902022-04-29029 April 2022 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-554, Revision 1 ML22250A6712022-02-16016 February 2022 Outline Submittal Notification Email DC-Cook 2022 ML21341A6252021-12-0707 December 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-577, Revision 1 ML21307A3352021-11-0303 November 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Final RAI - License Amendment Request Regarding Containment Water Level Instrumentation ML21236A0262021-08-23023 August 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance of License Amendment Regarding Changes to Reactor Vessel Heatup and Cooldown Curves and Low Temperature Overpressure Protection System Requirements ML21140A3052021-05-20020 May 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request ISIR-4-11, Impractical Examinations for the Fourth 10-Year ISI Interval ML21113A2812021-04-23023 April 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Containment Water Level Instrumentation ML21089A0222021-03-24024 March 2021 DC Cook Power Operated Valves (POV) Preliminary Request for Information ML21082A0262021-03-22022 March 2021 Acceptance of Relief Request ISIR-4-11, Impractical Examinations for the Fourth 10-Year ISI Interval ML21049A2682021-02-16016 February 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Final RAI - License Amendment Request for One-Time Extension Containment Type a ILRT ML21026A3472021-01-26026 January 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request REL-PP2 for Pump and Valve IST Fifth 10-year Interval ML21008A4742021-01-0808 January 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance of License Amendment Request for One-Time Extension Containment Type a ILRT ML20366A1012020-12-31031 December 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance of License Amendment Request for One-Time Deferral of Steam Generator Inspection ML20316A0152020-11-0606 November 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of Relief Request REL-PP2 for Pump and Valve IST Fifth 10-year Interval ML20318A0202020-10-16016 October 2020 NRR E-mail Capture - Regarding Public Comment on D.C. Cook, Unit 1 Request for Relief from Nozzle Inspections, Code Case N-729 ML20289A7122020-10-15015 October 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 1 - Verbal Authorization of Relief Request ISIR-5-04 Regarding Alternative to N-729-6 for RPV Head Visual Examination ML20290A4252020-10-15015 October 2020 Verbal Authorization of Relief Request ISIR-5-04 Regarding Alternative to N-729-6 for RPV Head Visual Examination ML20318A0192020-10-15015 October 2020 NRR E-mail Capture - (External_Sender) Supplemental Public Comment on D.C. Cook, Unit 1 Request for Relief from Nozzle Inspections, Code Case N-729 ML20289A1192020-10-0909 October 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of Relief Request for Alternative to N-729-4 for RPV Head Visual Examination ML20318A0182020-10-0909 October 2020 NRR E-mail Capture - (External_Sender) Public Comment on D.C. Cook, Unit 1 Request for Relief from Nozzle Inspections, Code Case N-729 ML20181A4122020-06-29029 June 2020 NRR E-mail Capture - Final RAI - D.C. Cook 1 - One-Time Extension, Containment Type a ILRT Frequency ML20149K6272020-05-28028 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment and Exemptions Regarding UFSAR 10 CFR 50.71(e)(4) Update Schedule (Epids: L-2020-LLA-0100, L-2020-LLE-0052, L-2020-LLE-0053) ML20149K4332020-05-26026 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-567, Revision 1 ML20141L6062020-05-20020 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-541, Revision 2 ML20141L8112020-05-20020 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of Relief Request Regarding Impracticality for Inservice Inspection for Certain Welds ML20136A5162020-05-15015 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-412, Revision 3 ML20133J9662020-05-11011 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 1 - Acceptance of License Amendment Regarding Changes to Reactor Vessel Heatup and Cooldown Curves and Low Temperature Overpressure Protection System Requirements ML20232B4562020-04-27027 April 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Fragility Questions ML20232B4432020-03-25025 March 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Plant Response Model Questions ML19345F9382019-12-0909 December 2019 D.C. Cook 50.54(f) SPRA Submittal - Completeness Review Done and Path Forward ML19333B8042019-11-29029 November 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Adopt TSTF-569 (L-2019-LLA-0248) ML19309F9212019-11-0505 November 2019 Request for Eportal Access for Audit Review of the DC Cook SPRA Supporting Documents ML19270E7372019-09-26026 September 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Adopt TSTF-421, Reactor Coolant Pump Flywheel Inspection Program ML19207A4642019-07-26026 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Delete Diesel Generator Load Test Resistor Banks ML19204A0962019-07-23023 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Request for Additional Information Related to Unit 2 Leak Before Break Analysis and Deletion of Containment Humidity Monitors for Unit Nos. 1 and 2 ML19211C3032019-07-0303 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 & 2 - Request for Additional Information Related to LAR to Address NSAL-15-1 ML19175A3032019-06-24024 June 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance Review for LAR to Revise Battery Monitoring and Maintenance TS ML19092A4802019-04-0202 April 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Adopt TSTF-563 ML19092A4792019-04-0202 April 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Address Issues Identified in Westinghouse Document NSAL-15-1 2024-08-01
[Table view] |
Text
Wengert, Thomas From: Sent: To: Cc:
Subject:
Attachments:
Helen, Wengert, Thomas Tuesday, October 08, 2013 5:59 PM . hletheridge@aep.com
- 'mkscarpello@aep.com' (mkscarpello@aep.com)
DC Cook Emergency LAR Draft RAI Revision 1 D.C. Cook Draft RAI Rev 110-8-B.pdf As clarified during this afternoon's conference call, I have revised the typographical error in RAI 4. Please see attached Revision 1 of the RAI set for the subject LAR. Call me if you have any questions
.. _ Regards, Tom Wengert Project Manager NRRIDORLILPL3-1 (301) 415-4037 1 D.C. Cook Emergency License Amendment Request Request for Additional Information
-Revision 1 Containment and Ventilation Systems Branch (SCVB) 1. Section 3.3 states that a modification is to be installed during the next refueling outage in Fall2014.
When was this modification initiated?
When was it initially scheduled for installation?
Was it ever deferred from a previous outage? 2. Section 3.2 second paragraph states "Radiation and high access that would allow visual observation or repair of re hazards precluded A and Train B lower igniters A35." Citing this in strings powered by Phase 3, except for Train A exception for igniter A35, could it be energized a for the "glow" and perhaps determine if it is the would verify that Regions 12, 13, 14, 15 & 1 determining if Condition .B is actually met? nt entry made to observe it n phase 3 igniter which ble igniter thus Tech Spec Branch The LAR states: "The proposed TS Mode 1 until the affected ignitors can be preferable to the transient that wou 3. 4. rcrTl<>nT of the affected safety hazards. end cycle 25, explain why the in your response to RAI #3 to facilitate ing to power operation. , . Surveillance ifli7!:1tif.1'n, or in to assure that the necessary quality of at facility operation will be within safety limits, and met." 5. cification changes would allow a relaxation of the ition A, Required Action A.2 Completion Time from once per 7 -days to the SR Frequency of 184 days . . l'J..,.,il..,U ignitor failure mechanism (operation at excessive voltage) and the method of (TS Surveillance testing), explain how the relaxation of testing of the Operable DIS Train provides assurance that the LCO is met. 6. Footnote 2 on proposed TS page 3.6.9-2 appears to be incomplete (Regions 15 and 16 are not addressed).
Confirm.