MONTHYEARRS-14-295, Proposed Alternative Testing Requirements for Code Class 1, 2, and 3 Snubbers2014-12-0101 December 2014 Proposed Alternative Testing Requirements for Code Class 1, 2, and 3 Snubbers Project stage: Request RS-15-131, Response to Request for Additional Information Regarding Proposed Alternative Testing Requirements for Code Class 1, 2, and 3 Snubbers2015-05-0101 May 2015 Response to Request for Additional Information Regarding Proposed Alternative Testing Requirements for Code Class 1, 2, and 3 Snubbers Project stage: Response to RAI ML15301A8702015-11-0505 November 2015 Relief from the Requirements of the ASME Code Concerning Snubber Inspection Interval for the Thrid10-Year Interval Inservice Inspection Program (CAC No. MF5334)(RS-14-295) Project stage: Approval 2015-11-05
[Table View] |
|
---|
Category:Letter type:RS
MONTHYEARRS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-090, Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2023-09-0707 September 2023 Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-081, Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation2023-08-21021 August 2023 Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation RS-23-085, Supplemental Information Related to Request for Partial Site Release2023-08-0303 August 2023 Supplemental Information Related to Request for Partial Site Release RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-073, Request for Partial Site Release2023-06-0707 June 2023 Request for Partial Site Release RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-039, Request for License Amendment to Revise Technical Specifications Section 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air2023-03-0101 March 2023 Request for License Amendment to Revise Technical Specifications Section 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 RS-23-002, Application to Adopt TSTF-332, ECCS Response Time Testing2023-01-13013 January 2023 Application to Adopt TSTF-332, ECCS Response Time Testing RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-22-121, Notice of Intent to Pursue Subsequent License Renewal Applications2022-11-0909 November 2022 Notice of Intent to Pursue Subsequent License Renewal Applications RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration RS-22-107, Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2022-09-29029 September 2022 Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station RS-22-093, Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans2022-08-18018 August 2022 Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans RS-22-089, Additional Information Supporting Request for License Amendment to Revise the Secondary Containment Design Basis to Credit the Fuel Building Railroad Airlock2022-07-25025 July 2022 Additional Information Supporting Request for License Amendment to Revise the Secondary Containment Design Basis to Credit the Fuel Building Railroad Airlock RS-22-061, Request for License Amendment to Adopt TSTF-269, Revision 2, Allow Administrative Means of Position Verification for Locked or Sealed Valves2022-05-24024 May 2022 Request for License Amendment to Adopt TSTF-269, Revision 2, Allow Administrative Means of Position Verification for Locked or Sealed Valves RS-22-060, Request for License Amendment to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2022-05-24024 May 2022 Request for License Amendment to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling RS-22-068, Constellation Radiological Emergency Plan Addendum Revision2022-05-19019 May 2022 Constellation Radiological Emergency Plan Addendum Revision RS-22-055, Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan2022-04-18018 April 2022 Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan RS-22-051, Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists2022-04-12012 April 2022 Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists RS-22-020, Request for License Amendment to Revise the Secondary Containment Design Basis to Credit the Fuel Building Railroad Airlock2022-04-0707 April 2022 Request for License Amendment to Revise the Secondary Containment Design Basis to Credit the Fuel Building Railroad Airlock RS-22-049, Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for2022-04-0404 April 2022 Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for V RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations RS-22-027, Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated2022-02-23023 February 2022 Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated P RS-22-023, Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement2022-02-23023 February 2022 Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement RS-22-019, Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists2022-02-16016 February 2022 Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists RS-22-015, Notification of Completion of License Transfer and Request to Continue Processing Pending NRC Actions Previously Requested by Exelon Generation Company, LLC2022-02-0101 February 2022 Notification of Completion of License Transfer and Request to Continue Processing Pending NRC Actions Previously Requested by Exelon Generation Company, LLC RS-22-004, Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2022-01-0404 January 2022 Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RS-21-121, Proposed Changes to Decommissioning Trust Agreements and Master Terms2021-12-15015 December 2021 Proposed Changes to Decommissioning Trust Agreements and Master Terms RS-21-102, Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors2021-09-29029 September 2021 Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-21-091, Implementation of Insider Threat Program Requirements Associated with the Voluntary Security Clearance Program and Advisement of Leadership Changes2021-09-13013 September 2021 Implementation of Insider Threat Program Requirements Associated with the Voluntary Security Clearance Program and Advisement of Leadership Changes RS-21-087, Additional Information Supporting Request for License Amendment to Revise Degraded Voltage Relay Allowable Values2021-08-31031 August 2021 Additional Information Supporting Request for License Amendment to Revise Degraded Voltage Relay Allowable Values RS-21-078, Response to Request for Additional Information for Application to Revise Technical Specification to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements, and TSTF-583-T, TSTF-582 Diesel2021-08-19019 August 2021 Response to Request for Additional Information for Application to Revise Technical Specification to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements, and TSTF-583-T, TSTF-582 Diesel RS-21-076, Application to Adopt TSTF-273, Safety Function Determination Program Clarifications2021-07-30030 July 2021 Application to Adopt TSTF-273, Safety Function Determination Program Clarifications RS-21-070, Proposed Alternative to Utilize Code Case N-8932021-06-30030 June 2021 Proposed Alternative to Utilize Code Case N-893 RS-21-063, Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2021-06-30030 June 2021 Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RS-21-069, Third Inservice Inspection Interval Relief Request I3R-182021-06-28028 June 2021 Third Inservice Inspection Interval Relief Request I3R-18 RS-21-054, Response to NRC Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations2021-04-29029 April 2021 Response to NRC Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations RS-21-039, Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments2021-03-25025 March 2021 Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments RS-21-037, Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-505, Revision 22021-03-23023 March 2021 Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-505, Revision 2 RS-21-028, Fitness for Duty Performance Data Reports - Annual 20202021-02-26026 February 2021 Fitness for Duty Performance Data Reports - Annual 2020 RS-21-032, Amended Decommissioning Trust Agreements2021-02-25025 February 2021 Amended Decommissioning Trust Agreements RS-21-014, License Amendment Request for One-Time Extension of the Containment Type a Integrated Leakage Rate Test Frequency2021-02-24024 February 2021 License Amendment Request for One-Time Extension of the Containment Type a Integrated Leakage Rate Test Frequency RS-21-030, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2021-02-24024 February 2021 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-21-005, Request for License Amendment to Revise Degraded Voltage Relay Allowable Values2021-01-20020 January 2021 Request for License Amendment to Revise Degraded Voltage Relay Allowable Values RS-21-001, Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping2021-01-0404 January 2021 Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping 2023-09-07
[Table view] |
Text
Exelon Generation RS-15-131 10 CFR 50.55a May 1, 2015 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-001
Subject:
Clinton Power Station, Unit 1 Facility Operating License No. NPF-62 NRG Docket No. 50-461 Response to Request for Additional Information Regarding Proposed Alternative Testing Requirements for Code Class 1, 2, and 3 Snubbers
References:
(1) Letter from Patrick A. Simpson (Exelon Generation Company, LLC) to U.S. NRG, "Proposed Alternative Testing Requirements for Code Class 1, 2, and 3 Snubbers," dated December 1, 2014, (ADAMS Accession No. ML 14335A539)
(2) Letter from Blake Purnell (U.S. NRG) to Bryan C. Hanson (Exelon Generation Company, LLC), "Clinton Power Station, Unit 1 -Request for Additional Information Regarding Relief Request 13R-11 (TAC No. MF5334)," dated April 16, 2015, (ADAMS Accession No. ML 15068A421)
In Reference 1, Exelon Generation Company, LLC, (EGG) requested, in accordance with 10 CFR 50.55a, "Codes and Standards," paragraph (a)(3)(i), NRG authorization of a request for a proposed alternative to the requirements of the American Society of Mechanical Engineers (ASME). "Code for Operation and Maintenance of Nuclear Power Plants," Boiler and Pressure Vessel (B&PV) Code,Section XI, 2004 Edition and No Addenda for Clinton Power Station (CPS). In accordance with 10 CFR 50.55a(b)(3)(v) the inservice testing of snubbers are performed in accordance with the 2004 Edition of ISTD Paragraph ISTD-5200.
Paragraph ISTD-5200, "lnservice Operational Readiness Testing," requires CPS to perform snubber testing for operational readiness during each fuel cycle. CPS will be transitioning to a 12 month fuel cycle beginning in the Spring of 2015; performing a refueling outage every 12 months. CPS intends to alternately schedule one short outage that will focus primarily on refueling activities with minimal maintenance activities (i.e., "refueling only outages")
and one more traditional refueling outage consisting of both refueling activities and maintenance activities (i.e., "refueling/maintenance outages").
This request proposed allowing testing of these snubbers on the current 24 month testing frequency.
This will allow CPS to maintain a minimal amount of testing during the "refueling only outage" and still maintain the same level of quality May 1, 2015 U. S. Nuclear Regulatory Commission Page2 and safety by continuing the two year frequency that these snubbers have historically been tested at during the "refueling/maintenance outage." In Reference 2, the NRC requested that EGC provide additional information to support their review of the subject relief request (i.e., Reference 1). The response to these requests is provided in Attachment
- 1. The information requested in Reference 2 was discussed during a February 23, 2015 teleconference between EGC and the NRC. As requested in Reference 2 it was agreed that EGC would provide the requested information to the NRC on or before May 29, 2015. This letter contains no new regulatory commitments.
If you have any questions concerning this letter, please contact Timothy A. Byam at (630) 657-2818.
Patrick R. Simpson Manager -Licensing Exelon Generation Company, LLC
Attachment:
Response to Request for Additional Information cc: NRC Regional Administrator, Region Ill NRC Senior Resident Inspector
-Clinton Power Station Illinois Emergency Management Agency -Division of Nuclear Safety ATTACHMENT Response to Request for Additional Information In a letter from Blake Purnell (U.S. NRC) to Bryan Hanson (Exelon Generation Company, LLC), "Clinton Power Station, Unit 1 -Request for Additional Information Regarding Relief Request 13R-11 (TAC No. MF5334)," dated April 16, 2015, the following requests for additional information were provided.
By application dated December 1, 2014 (Agencywide Documents Access and Management System Accession No. ML 14335A539), Exelon Generation Company, LLC (the licensee) submitted a request in accordance with Paragraph 50.55a(a)(3)(i) of Title 10 of the Code of Federal Regulations for a proposed alternative to the requirements of the American Society of Mechanical Engineers (ASME), Code for Operation and Maintenance of Nuclear Power Plants (OM Code), and ASME Boiler and Pressure Vessel (B&PV) Code,Section XI, 2004 Edition and no addenda for Clinton Power Station (CPS), Unit 1. The proposed alternative would permit the licensee to perform inservice testing of Code Class 1, 2, and 3 snubbers every 2 years or every other refueling outage in lieu of the requirement to perform testing every refueling outage. The reason for the request is to support the CPS transition from 2-year to 1-year refueling cycles. The NRG staff has reviewed the relief request and determined that it needs additional information to complete its review. NRCRAI 1: The submitted relief request is for the third 1 a-year inservice inspection (IS/) interval at CPS. Provide the start and end dates of the third 10-year ISi interval.
EGC Response to NRC RAI 1: CPS is currently in the third ISi interval.
As documented in Reference 1, the third ISi interval started on July 1, 2010 and will end on June 30, 2020. NRCRAl2: The relief request states that the proposed alternative to the snubber testing requirements in ASME B&PV Code,Section XI, and Section ISTD-5200 of the ASME OM Code is to test every 2 years or every other refueling outage. This implies that CPS has a choice of testing frequencies, such that if the refueling outage schedules change the interval between snubber tests may exceed 2 years. Provide justification for the proposed testing of every other refueling outage given that CPS is not limited to a 12-month refueling cycle. EGC Response to NRC RAI 2: It was not the intent of EGC to allow CPS to have a choice of testing frequencies under the subject relief request. EGC intends to continue testing snubbers every 24 months consistent with the current snubber testing frequency.
The wording used in the relief request was to support the EGC request for relief from the Code requirement of testing snubbers every refueling outage and allow testing every other refueling outage; which is equivalent to every 24 months.
ATTACHMENT Response to Request for Additional Information REFERENCE
- 1. Letter from Robert D. Carlson (U.S. NRC) to Michael J. Pacilio (Exelon Generation Company, LLC), "Clinton Power Station, Unit No. 1 -Relief Requests 13R-01, 13R-02, l3R-03, 13R-04, and 13R-05 Associated with the Third lnservice Inspection Interval (TAC Nos. ME2987, ME2988, ME2989, ME2990, and ME2991)," dated December 22, 2010 (ADAMS Accession No. ML 103360335)