Finding | |
---|---|
Title | Failure to Adequately Establish the Radiological Conditions In A Locked High Radiation Area to Allow Workers to Be Properly Briefed Prior to Entry |
Description | A finding of very low safety significance and an associated NCV of Technical Specification 5.7.1 was self-revealed following worker entry into the fuel pool cooling and cleanup (FPCC) heat exchanger room. At the time, the FPCC heat exchanger room was being controlled as a locked high radiation area (HRA). The licensee failed to adequately determine radiological dose rates in the room to ensure workers were briefed accurately on the radiological conditions prior to entry. On March 12, 2010, workers involved in tag-out activities in the room encountered greater than expected dose rates. After completion of the tag-out activity, the licensee identified that the electronic dosimeter (ED) worn by one of the workers had a dose rate of 550 mrem/hour and had alarmed. The workers were briefed to expect dose rates no greater than 150 mrem/hour based on the radiation survey used to support the briefing. The radiological information conveyed to the workers through a briefing by the radiation protection (RP) staff was inadequate because it was based on an incomplete survey. As part of the licensees corrective actions, lessons learned were shared with the RP staff to address survey adequacy and for enhanced communications with workers during pre-job briefings. The inspectors identified Example 6(h) of IMC 0612, Appendix E, as similar to the performance issue. The workers were not made aware of the radiological conditions before entry into the room. Therefore, as provided in Example 6(h), the inspectors determined that the performance deficiency was more than minor. Additionally, the performance deficiency impacted the program and process attribute of the Occupational Radiation Safety Cornerstone and adversely affected the cornerstone objective of ensuring adequate protection of worker health and safety from exposure to radiation, in that, worker entry into areas without knowledge of the radiological conditions placed them at increased risk for unnecessary radiation exposure. The finding was determined to be of very low safety significance because the problem was not an as-low-asreasonably- achievable (ALARA) planning issue, there was no overexposure, nor substantial potential for an overexposure, and the licensees ability to assess dose was not compromised. The inspectors determined that the cause of this issue involved the cross-cutting component of work control in the human performance cross-cutting area (H.3.(a)), in that work activities were not adequately planned by incorporating job site radiological conditions. Specifically, the pre-job briefing did not utilize complete and accurate survey maps for the areas being entered into by the workers assigned to conduct tasks in the FPCC heat exchanger room. |
Site: | Perry ![]() |
---|---|
Report | IR 05000440/2010003 Section 2RS1 |
Date counted | Jun 30, 2010 (2010Q2) |
Type: | NCV: Green |
cornerstone | Or Safety |
Identified by: | Self-revealing |
Inspection Procedure: | IP 71124.01 |
Inspectors (proximate) | R Winter F Ramirez M Marshfield T Bilik W Slawinski M Phalen R Baker J Bozga N Feliz T Hartman V Myers |
CCA | H.5, Work Management |
INPO aspect | WP.1 |
' | |