Letter Sequence Withholding Request Acceptance | |
---|---|
TAC:MB5498, (Open) | |
Initiation Administration Results
Other: | |
MONTHYEARML0226001362002-10-0202 October 2002
[Table View]Request for Additional Information Regarding License Amendment Request, Power Uprate Measurement Uncertainty Recapture, Dated June 28, 2002 Project stage: RAI ML0229102872002-10-15015 October 2002 Supplement to License Amendment Request for Appendix K Measurement Uncertainty Recapture - Power Uprate Request Project stage: Supplement ML0229100212002-10-15015 October 2002 Response to Nuclear Regulatory Commission Request for Additional Information Regarding License Amendment Request for Appendix K Measurement Uncertainty Recapture - Power Uprate Request Project stage: Request ML0233602382002-10-17017 October 2002 Submittal of Power Measurement Uncertainty Calculation in Support of License Amendment Request for Appendix K Measurement Uncertainty Recapture Power Uprate Request Project stage: Request ML0231204492002-11-0707 November 2002 Second Request for Additional Information Regarding License Amendment Request, Power Uprate Measurement Uncertainty Recapture. Project stage: RAI ML0232500182002-11-15015 November 2002 Submittal of Change to Power Measurement Uncertainty Calculation in Support of License Amendment Request for Appendix K Measurement Uncertainty Recapture - Power Uprate Request Project stage: Request ML0234402102002-12-0606 December 2002 Submittal of Change Sheet 2 to Power Measurement Uncertainty Calculation in Support of License Amendment Request for Appendix K Measurement Uncertainty Recapture - Power Uprate Request Project stage: Request ML0234701262002-12-20020 December 2002 Amendment 273 to License DPR-58, Increasing Licensed Reactor Core Power Level by 1.66 Percent Project stage: Acceptance Review ML0235300312002-12-20020 December 2002 DC Cook, Units 1 and 2 - Letter Regarding Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance 2002-11-15 |
ML023530031 | |
Person / Time | |
---|---|
Site: | Cook |
Issue date: | 12/20/2002 |
From: | Stang J NRC/NRR/DLPM/LPD3 |
To: | Bakken A Indiana Michigan Power Co |
References | |
TAC MB5498 | |
Download: ML023530031 (4) | |
Similar Documents at Cook | |
---|---|
Category:Letter
MONTHYEARAEP-NRC-2024-80, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2024-10-15015 October 2024
[Table view]Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-79, Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask2024-09-26026 September 2024 Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask AEP-NRC-2024-78, Reply to a Notice of Violation: EA-24-0472024-09-23023 September 2024 Reply to a Notice of Violation: EA-24-047 05000316/LER-2024-002-01, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-09-12012 September 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak IR 05000315/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000315/2024402 and 05000316/2024402, Independent Spent Fuel Storage Installation Security Inspection Report 07200072/2024401 AEP-NRC-2024-69, Core Operating Limits Report2024-09-0909 September 2024 Core Operating Limits Report IR 05000315/20243012024-09-0505 September 2024 NRC Initial License Examination Report 05000315/2024301 and 05000316/2024301 ML24225A0022024-09-0303 September 2024 Issuance of Amendment Nos. 363 and 344 Revising Technical Specifications Section 3.8.1, AC Sources-Operating, for a One-Time Extension of a Completion Time IR 05000315/20240112024-08-30030 August 2024 NRC Inspection Report 05000315/2024011 and 05000316/2024011 and Notice of Violation AEP-NRC-2024-76, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-08-28028 August 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-51, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2024-08-28028 August 2024 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes 05000316/LER-2024-003, Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage2024-08-22022 August 2024 Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage IR 05000315/20240052024-08-21021 August 2024 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2024005 and 05000316/2024005) AEP-NRC-2024-61, Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request2024-08-15015 August 2024 Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request ML24221A2702024-08-0808 August 2024 Unit 2 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-62, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-08-0707 August 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask ML24256A1482024-08-0202 August 2024 2024 Post Examination Submittal Letter AEP-NRC-2024-47, Form OAR-1, Owners Activity Report2024-07-30030 July 2024 Form OAR-1, Owners Activity Report ML24183A0162024-07-25025 July 2024 Review of Reactor Vessel Material Surveillance Program Capsule W Technical Report ML24169A2142024-07-25025 July 2024 Issuance of Amendment No. 362 Regarding Change to Technical Specification 3.4.12, Low Temperature Overpressure Protection System IR 05000315/20240022024-07-24024 July 2024 Integrated Inspection Report 05000315/2024002 and 05000316/2024002 ML24197A1262024-07-15015 July 2024 Unit 2 - Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-52, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-07-15015 July 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak ML24191A0692024-07-0909 July 2024 Operator Licensing Examination Approval - Donald C. Cook Nuclear Power Plant, July 2024 AEP-NRC-2024-56, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-07-0808 July 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24176A1012024-06-21021 June 2024 57143-EN 57143 - Paragon Energy Solutions - Update 1 (Final) - 10CFR Part 21 Final Notification: P21-05242024-FN, Rev. 0 AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring ML24163A0132024-06-12012 June 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000315/2024012 and 05000316/2024012 AEP-NRC-2024-23, Core Operating Limits Report2024-05-23023 May 2024 Core Operating Limits Report AEP-NRC-2024-30, Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip2024-05-20020 May 2024 Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection AEP-NRC-2024-40, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-05-16016 May 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-41, Annual Radiological Environmental Operating Report2024-05-15015 May 2024 Annual Radiological Environmental Operating Report IR 05000315/20240012024-05-14014 May 2024 Integrated Inspection Report 05000315/2024001 and 05000316/2024001 AEP-NRC-2024-26, Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 492024-05-14014 May 2024 Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 49 AEP-NRC-2024-07, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2024-05-14014 May 2024 Unit 2 - Transmittal of Report of Changes to the Emergency Plan IR 05000315/20244012024-05-14014 May 2024 – Security Baseline Inspection Report 05000315/2024401 and 05000316/2024401 ML24115A2152024-05-0707 May 2024 LTR: CNP Non-Acceptance with Opportunity TS 3-8-1 AEP-NRC-2024-24, Form OAR-1, Owners Activity Report2024-05-0707 May 2024 Form OAR-1, Owners Activity Report ML24256A1472024-05-0606 May 2024 DC Cook 2024 NRC Examination Submittal Letter: Submittal ML24116A0002024-05-0202 May 2024 – Regulatory Audit in Support of Review of the Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors AEP-NRC-2024-35, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-30030 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2024-28, 2023 Annual Radioactive Effluent Release Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report AEP-NRC-2024-31, Annual Report of Individual Monitoring2024-04-24024 April 2024 Annual Report of Individual Monitoring AEP-NRC-2024-29, (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-072024-04-0303 April 2024 (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-07 AEP-NRC-2024-02, Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-04-0303 April 2024 Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-19, Annual Report of Property Insurance2024-04-0101 April 2024 Annual Report of Property Insurance AEP-NRC-2024-04, License Amendment Request Regarding a Change to Unit 1 Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System2024-03-0606 March 2024 License Amendment Request Regarding a Change to Unit 1 Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System ML24073A2342024-03-0606 March 2024 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors 2024-09-09 |