Revision of Schedule for the Conduct of Review of the Susquehanna Electric Station, Units 1 & 2, License Renewal Application
ML080850119
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 05/01/2008
From: Gettys E
NRC/NRR/ADRO/DLR
To: Mckinney B
Susquehanna
Gettys Evelyn, NRR/DLR/RLRA 415-4029
References
Download: ML080850119 (6)


Text

May 1, 2008 Mr. Britt T. McKinney Sr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION

Dear Mr. McKinney:

Enclosed is a revised schedule for the review of the Susquehanna Steam Electric Station, Units 1 and 2, license renewal application. If you have any questions on the revised schedule, please contact me by telephone at 301-415-4029 or via e-mail at ehg2@nrc.gov. Sincerely,

/RA/ Evelyn Gettys, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation

Docket Nos. 50-387 and 50-388

Enclosure:

As stated

cc w/encl: See next page

ML080580119 OFFICE PM:RPB1:DLR LA:DLR BC:RPB1:DLR BC:RPB1:DLR NAME EGettys SFigueroa DStuyvenberg LLund DATE 03/26/08 03/26/08 03/31/08 05/01/08 SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REVISION OF SCHEDULE Milestone Schedule Actual Receive license renewal application (LRA) 09/15/06 09/13/06 Publish Federal Register Notice (FRN) - LRA receipt and availability 09/25/06 09/26/06 Publish FRN - LRA acceptability, environmental scoping period, and opportunity for hearing 10/30/06 10/30/06 Public Meeting - license renewal process and environmental scoping 11/15/06 11/15/06 Audit - scoping and screening methodology 12/11-15/06 12/11-15/06 Environmental scoping periods ends 01/02/07 01/02/07 Audit - aging management 05/05/08 Audit - environmental 05/14-18/07 05/15-17/07 Audit - aging management (optional) 6/23/08 Issue environmental requests for additional information (RAIs) 07/13/07 07/13/07 Issue safety RAIs 07/13/08 Receive responses for environmental RAIs 08/13/07 08/01/2007 Receive responses for safety RAIs 08/12/08 Inspection - scoping, screening, and AMPs 08/11/08 Inspection (optional) TBD Issue draft supplemental environmental impact statement (SEIS) 04/25/08 04/25/08 Publish FRN - availability and comment on draft SEIS 05/07/08 Public Meeting - draft SEIS 05/28/08 Issue safety evaluation report (SER) with open item(s) 03/03/09 End of comment period for the draft SEIS 07/21/08 Advisory Committee on Reactor Safeguards (ACRS) subcommittee meeting on SER with open item(s) 04/09 Issue final SEIS 03/11/09 Issue SER 08/28/09 Publish FRN - availability of final SEIS 03/18/09 ACRS full committee meeting on SER 10/09 NRR decision 12/07/09

ENCLOSURE Letter to B. McKinney from E. Gettys, dated May 1, 2008 DISTRIBUTION

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION HARD COPY: DLR RF E-MAIL: PUBLIC SSmith (srs3) SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSrxb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter --------------- EGettys FJaxheimer Susquehanna Steam Electric Station, Units 1 and 2 cc: Cornelius J. Gannon Vice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467

Robert M. Paley General Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467 Rocco R. Sgarro Manager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179

Supervisor - Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467

Michael H. Crowthers Supervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Ronald E. Smith General Manager - Site Preparedness and Services PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Manager - Quality Assurance PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467 Luis A. Ramos Community Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467

Bryan A. Snapp, Esq. Associate General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179

Supervisor - Document Control Services PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179

Richard W. Osborne Allegheny Electric Cooperative, Inc. 212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266

Director, Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4 Berwick, PA 18603-0035 Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406

Susquehanna Steam Electric Station, Units 1 and 2 cc:

Board of Supervisors Salem Township P.O. Box 405 Berwick, PA 18603-0035