MONTHYEARHNP-18-050, Request to Extend Reactor Vessel Surveillance Capsule Report Submission Date2018-09-17017 September 2018 Request to Extend Reactor Vessel Surveillance Capsule Report Submission Date HNP-18-004, License Amendment Request to Change Shearon Harris Nuclear Power Plant, Unit 1, Emergency Plan Emergency Action Level Scheme2018-08-13013 August 2018 License Amendment Request to Change Shearon Harris Nuclear Power Plant, Unit 1, Emergency Plan Emergency Action Level Scheme HNP-18-035, Relief Request I3R-18, Alternative Repair and Replacement Testing Requirements for the Containment Building Equipment Hatch Sleeve Weld, Lnservice Inspection Program for Containment, Third Ten-Year Interval2018-06-0404 June 2018 Relief Request I3R-18, Alternative Repair and Replacement Testing Requirements for the Containment Building Equipment Hatch Sleeve Weld, Lnservice Inspection Program for Containment, Third Ten-Year Interval HNP-18-049, Submittal of 1 0 CFR 50.54(q) Evaluation Form of Changes to Procedure EMP-420, Emergency Program Maintenance, Revision 192018-05-0303 May 2018 Submittal of 1 0 CFR 50.54(q) Evaluation Form of Changes to Procedure EMP-420, Emergency Program Maintenance, Revision 19 HNP-18-023, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes2018-05-0202 May 2018 Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes HNP-18-042, Annual Environmental (Non-radiological) Operating Report2018-04-30030 April 2018 Annual Environmental (Non-radiological) Operating Report HNP-18-032, Annual Radiological Environmental Operating Report2018-04-25025 April 2018 Annual Radiological Environmental Operating Report HNP-18-031, Annual Radioactive Effluent Release Report2018-04-25025 April 2018 Annual Radioactive Effluent Release Report HNP-18-047, Relief Request I4R-18, Reactor Vessel Closure Head Nozzle Repair Technique, Inservice Inspection Program, Fourth Ten-Year Interval, Non-Proprietary Version of Calculation2018-04-20020 April 2018 Relief Request I4R-18, Reactor Vessel Closure Head Nozzle Repair Technique, Inservice Inspection Program, Fourth Ten-Year Interval, Non-Proprietary Version of Calculation HNP-18-045, Submittal of Relief Request I4R-18, Reactor Vessel Closure Head Nozzle Repair Technique, Inservice Inspection Program, Fourth Ten-Year Interval2018-04-18018 April 2018 Submittal of Relief Request I4R-18, Reactor Vessel Closure Head Nozzle Repair Technique, Inservice Inspection Program, Fourth Ten-Year Interval HNP-18-044, Cycle 22 Core Operating Limits Report, Revision O2018-04-16016 April 2018 Cycle 22 Core Operating Limits Report, Revision O HNP-18-039, Supplement to License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses2018-04-13013 April 2018 Supplement to License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses HNP-18-021, Annual Report in Accordance with Technical Specification 6.9.1.22018-02-19019 February 2018 Annual Report in Accordance with Technical Specification 6.9.1.2 HNP-18-020, Supplement to Response to Request for Additional Information Regarding License Amendment Request for Spent Fuel Storage Pool Criticality Analyses2018-02-16016 February 2018 Supplement to Response to Request for Additional Information Regarding License Amendment Request for Spent Fuel Storage Pool Criticality Analyses HNP-18-019, Cycle 21 Core Operating Limits Report, Revision 12018-02-14014 February 2018 Cycle 21 Core Operating Limits Report, Revision 1 HNP-18-017, CFR 50.54(q) Evaluations2018-02-0505 February 2018 CFR 50.54(q) Evaluations HNP-18-001, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors.2018-02-0101 February 2018 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors. HNP-18-002, Response to Request for Additional Information Regarding a License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements2018-01-22022 January 2018 Response to Request for Additional Information Regarding a License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements HNP-18-003, Response to Request for Additional Information Regarding License Amendment Request for Spent Fuel Storage Pool Criticality Analyses2018-01-18018 January 2018 Response to Request for Additional Information Regarding License Amendment Request for Spent Fuel Storage Pool Criticality Analyses HNP-18-007, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Supplement Regarding De Minimis Penetrations2018-01-11011 January 2018 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Supplement Regarding De Minimis Penetrations HNP-18-006, Submittal of 14-Day Special Report for Accident Radiation Monitors2018-01-0404 January 2018 Submittal of 14-Day Special Report for Accident Radiation Monitors HNP-17-093, Supplement to License Amendment Request Proposing a New Set of Fission Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 32017-11-29029 November 2017 Supplement to License Amendment Request Proposing a New Set of Fission Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3 HNP-17-078, Response to Request for Additional Information Regarding a License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements2017-11-27027 November 2017 Response to Request for Additional Information Regarding a License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements HNP-17-082, Response to Request for Additional Information Regarding License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Limit Detailed In..2017-10-30030 October 2017 Response to Request for Additional Information Regarding License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Limit Detailed In.. HNP-17-084, Response to Request for Additional Information Regarding a License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements2017-10-30030 October 2017 Response to Request for Additional Information Regarding a License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements HNP-17-025, Fourth Interval Lnservice Inspection Plan, Third Interval Containment Lnservice Inspection Plan, and Fourth Interval Lnservice Inspection Pressure Test Plan2017-10-23023 October 2017 Fourth Interval Lnservice Inspection Plan, Third Interval Containment Lnservice Inspection Plan, and Fourth Interval Lnservice Inspection Pressure Test Plan HNP-17-072, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis2017-10-19019 October 2017 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis HNP-17-077, License Amendment Request Regarding Rod Control Movable Assemblies Technical Specifications2017-10-10010 October 2017 License Amendment Request Regarding Rod Control Movable Assemblies Technical Specifications HNP-17-076, Supplement to License Amendment Request to Relocate Technical Specification Cycle-Specific Parameters to the Core Operating Limits Report, Delete Reference to Plant Procedure PLP-106, and Delete Duplicate Reporting Requirements.2017-10-0202 October 2017 Supplement to License Amendment Request to Relocate Technical Specification Cycle-Specific Parameters to the Core Operating Limits Report, Delete Reference to Plant Procedure PLP-106, and Delete Duplicate Reporting Requirements. HNP-17-073, Supplemental Information for License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses2017-09-14014 September 2017 Supplemental Information for License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses HNP-17-062, Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 3, Flooding Focused Evaluation Summary Submittal2017-09-13013 September 2017 Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 3, Flooding Focused Evaluation Summary Submittal HNP-17-061, Supplement to License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses2017-07-20020 July 2017 Supplement to License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses HNP-17-008, License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses2017-06-28028 June 2017 License Amendment Request Regarding Spent Fuel Storage Pool Criticality Analyses HNP-17-003, License Amendment Request for Emergency Diesel Generator Surveillance Requirements Regarding Voltage and Frequency Limits and the Voltage Limit for Emergency Diesel Generator Load Rejection2017-06-0505 June 2017 License Amendment Request for Emergency Diesel Generator Surveillance Requirements Regarding Voltage and Frequency Limits and the Voltage Limit for Emergency Diesel Generator Load Rejection HNP-17-040, Snubber Program Plan2017-06-0101 June 2017 Snubber Program Plan HNP-17-051, 10 CFR 50.54(q) Evaluation2017-05-24024 May 2017 10 CFR 50.54(q) Evaluation HNP-17-050, Transmittal of 10 CFR 50.54(q) Evaluation for Revision 21 to PEP-250, Activation and Operation of the Joint Information Center2017-05-24024 May 2017 Transmittal of 10 CFR 50.54(q) Evaluation for Revision 21 to PEP-250, Activation and Operation of the Joint Information Center HNP-17-041, Response to Request for Additional Information Regarding License Amendment Request to Relocate Technical Specification Cycle-Specific Parameters to the Core Operating Limits Report, Delete Reference to Plant Procedure PLP-106, and Delete2017-05-22022 May 2017 Response to Request for Additional Information Regarding License Amendment Request to Relocate Technical Specification Cycle-Specific Parameters to the Core Operating Limits Report, Delete Reference to Plant Procedure PLP-106, and Delete Du HNP-17-033, License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3, Footnote 112017-05-22022 May 2017 License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3, Footnote 11 HNP-17-049, Transmittal of 10 CFR 50.54(q) Evaluation and Revision 26 to PEP-110, Emergency Classification and Protective Action Recommendations.2017-05-18018 May 2017 Transmittal of 10 CFR 50.54(q) Evaluation and Revision 26 to PEP-110, Emergency Classification and Protective Action Recommendations. HNP-17-047, 10 CFR 50.54(q) Evaluation2017-05-18018 May 2017 10 CFR 50.54(q) Evaluation HNP-17-048, Transmittal of 10 CFR 50.54(q) Evaluation and Revision 28 to PEP-230, Control Room Operations.2017-05-18018 May 2017 Transmittal of 10 CFR 50.54(q) Evaluation and Revision 28 to PEP-230, Control Room Operations. HNP-17-046, 10 CFR 50.54(q) Evaluation2017-05-18018 May 2017 10 CFR 50.54(q) Evaluation HNP-17-024, Annual Environmental (Nonradiological) Operating Report2017-04-28028 April 2017 Annual Environmental (Nonradiological) Operating Report HNP-17-023, Annual Radioactive Effluent Release Report2017-04-28028 April 2017 Annual Radioactive Effluent Release Report HNP-17-034, Response to Request for Additional Information Regarding License Amendment Request to Relocate Technical Specification Cycle-Specific Parameters to the Core Operating Limits Report, Delete Reference to Plant Procedure PLP-106..2017-04-25025 April 2017 Response to Request for Additional Information Regarding License Amendment Request to Relocate Technical Specification Cycle-Specific Parameters to the Core Operating Limits Report, Delete Reference to Plant Procedure PLP-106.. HNP-17-035, Request for Pilot Plant Status and Fee Waiver to Implement Tornado Missile Risk Evaluator2017-04-12012 April 2017 Request for Pilot Plant Status and Fee Waiver to Implement Tornado Missile Risk Evaluator HNP-17-045, 10 CFR 50.54(q) Evaluation of Change in Emergency Plan Implementation Procedure PEP-241, Revision 7, Technical Support Center (TSC) Emergency Ventilation System Operation2017-03-30030 March 2017 10 CFR 50.54(q) Evaluation of Change in Emergency Plan Implementation Procedure PEP-241, Revision 7, Technical Support Center (TSC) Emergency Ventilation System Operation HNP-17-014, Annual Report in Accordance with Technical Specifications, Section 6.9.1.22017-02-16016 February 2017 Annual Report in Accordance with Technical Specifications, Section 6.9.1.2 HNP-17-015, Summary of 10 CFR 50.54(q) Evaluation2017-02-15015 February 2017 Summary of 10 CFR 50.54(q) Evaluation 2018-09-17
[Table view] |
Text
Ernest J. Kapopoulos, Jr.DUKE Vice President DUKER Harris Nuclear Plant EN ERGY 5413 Shearon Harris Rd New Hill NC 27562-9300 919-362-2502 10 CFR 50.54(f)January 29, 2014 Serial: HNP-14-007 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555 Duke Energy Progress, Inc. (Duke Energy)Shearon Harris Nuclear Power Plant, Unit 1 Docket No. 50-400
Subject:
Response to Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Flooding Walkdowns, Regarding Available Physical Margin Assessments
References:
- 1. NRC Letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident; dated March 12, 2012, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12053A340)
- 2. NEI 12-07, Guidelines for Performing Verification Walkdown of Plant Flood Protection Features, Revision 0-A, dated May 2012 3. NRC Letter to Nuclear Energy Institute (NEI), Endorsement of Nuclear Energy Institute (NEI) 12-07, "Guidelines for Performing Verification Walkdowns of Plant Flood Protection Features," dated May 31, 2012, (ADAMS Accession No. ML12144A142)
- 4. Duke Energy Letter to NRC, Shearon Harris Nuclear Power Plant, Unit No. 1, Response to Recommendation 2.3 Flooding Walkdown of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated November 27, 2012 5. NRC letter, Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Flooding Walkdowns; dated December 23, 2013 (ADAMS Accession No. ML13325A891)
Ladies and Gentlemen:
On March 12, 2012, the Nuclear Regulatory Commission (NRC) staff issued Reference 1 requesting information pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f).
Enclosure 4 of that letter contains specific requested information associated with Near-Term Task Force Recommendation 2.3 for Flooding.
Nuclear Energy Institute (NEI)12-07 (Reference
- 2) was endorsed by NRC letter dated May 31, 2012 (Reference 3). By Reference 4, Duke Energy submitted the 180-day response to Reference 1, for Shearon Harris Nuclear Power Plant, Unit 1, requiring the flooding walkdown report addressing the items in Appendix D of NEI 12-07 (Reference 2).
U.S. Nuclear Regulatory Commission HNP-14-007 Page 2 Following the NRC staff's initial review of the walkdown reports, regulatory site audits were conducted by the NRC staff at a sampling of plants. Based on the walkdown report reviews and site audits, additional information was determined to be necessary to allow the NRC staff to complete its assessments.
By letter dated December 23, 2013 (Reference 5), the NRC requested additional information regarding the determination and documentation of available physical margin (APM) during flooding walkdowns.
The NRC staff requested that a response be provided no later than January 31, 2014. The Duke Energy response for Shearon Harris Nuclear Power Plant, Unit 1, is enclosed.This letter contains no new Regulatory Commitments and no revision to existing Regulatory Commitments.
Should you have any questions regarding this submittal, please contact Dave Corlett, Regulatory Affairs Manager, at (919) 362-3137.I declare under penalty of perjury that the foregoing is true and correct.Executed on January 29, 2014.Sincerely, Ernest J. Kapopoulos, Jr.
Enclosure:
Shearon Harris Nuclear Power Plant, Unit 1, Response to the NRC Request for Additional Information (RAI) Regarding Available Physical Margin During Flooding Walkdowns cc: Mr. J. D. Austin, NRC Sr. Resident Inspector, HNP Mr. A. Hon, NRC Project Manager, HNP Mr. V. M. McCree, NRC Regional Administrator, Region II U.S. Nuclear Regulatory Commission HNP-14-007, Enclosure Enclosure Shearon Harris Nuclear Power Plant, Unit I Response to the NRC Request for Additional Information (RAI)Regarding Available Physical Margin During Flooding Walkdowns U.S. Nuclear Regulatory Commission HNP-14-007, Enclosure Page 1 of 3 Determination and Documentation of Available Physical Margin
Background:
The NRC staff observed that several licensees did not consistently determine and/or document available physical margin (APM) in a manner that met the expected interpretation of NEI 12-07 during audits associated with review of the Near-Term Task Force Recommendation 2.3 report submittals.
APM is defined in Section 3.13 of NEI 12-07 and the process for obtaining and evaluating APM values is described in Section 5.8 of NEI 12-07. Consistent with NEI 12-07, a numerical value for APM should be determined and documented for every applicable flood protection feature (e.g., wall, penetration, berm, door, etc.). This would normally be a numerical value reflecting the difference between the licensing basis flood height at the location of the feature and the point at which the function of the flood protection feature is compromised (e.g., the top of a barrier or the height of the first unseated penetration in a barrier) such that the resulting flood can affect a structures, systems, and components important to safety. Next, in accordance with Section 5.8 of NEI12-07, if the APM appears to be small and the consequences of flooding appear to be significant, the licensee should enter the condition into the corrective action program (CAP) and appropriate action be taken. While NEI 12-07 does not require that a specific numerical threshold value for "small" APM be defined for each site, doing so establishes a consistent basis for determining what instances need to be entered into the CAP. If a numerical APM value cannot be determined for any flood protection feature, the licensee should perform an assessment of the ability of the barrier to withstand the licensing basis flood plus the contribution of the additional water corresponding to the pre-established small-margin threshold value. If the barrier can withstand this flood, the APM for the feature is"not small" and further evaluation in accordance with Section 5.8 of NEI 12-07 is not required.
It is further noted that conclusions regarding "large" values of APM should be based on engineering evaluations or existing design documents.
Licensees should ensure that the process for APM determination and evaluation used during their flooding walkdowns is consistent with the guidance in NEI 12-07. The intent of this request for additional information (RAI) is not to repeat the flooding walkdowns or perform an extensive revision of the walkdown record forms and other paperwork.
Instead the purpose is to verify or modify the process used to determine APM such that every site is aware of the margin at each of its flood protection features and take appropriate interim actions when the APM is small and the consequences are significant.
Instances where numerical values for APM were not determined, or where the basis for the APM was found to be questionable, should be rectified by either the documentation of a specific value or an explanation of why a non-numerical value is appropriate.
U.S. Nuclear Regulatory Commission HNP-14-007, Enclosure Page 2 of 3 NRC RAI Item 1: Confirmation that the process for evaluating APM was reviewed;Response to RAI Item 1: Duke Energy has completed a review of the flooding design basis walkdown process used at Shearon Harris Nuclear Power Plant to evaluate APMs.NRC RAI Item 2: Confirmation that the APM process is now or was always consistent with the guidance in NEI 12-07 and discussed in this RAI;Response to RAI Item 2: The original walkdown effort followed the guidance provided in NEI 12-07. Although the original walkdown effort followed the guidance provided in NEI 12-07, APMs were not determined for the seals associated with flood protection features.
Where the APM is undetermined, it has been entered into the CAP (CR 663490).NRC RAI Item 3: If changes are necessary, a general description of any process changes to establish this consistency; Response to RAI Item 3: CAP entry CR 663490 addresses the following process changes consistent with the information provided in this RAI and in NEI 12-07:* Determine appropriate APM values for seals associated with flood protection features in accordance with the guidance provided in NEI 12-07 and this RAI.* The development of small margin definitions to be used in place of engineering judgment for identifying small margin concerns.* A review of APMs against the small margin definitions to validate reviews which previously utilized engineering judgment to identify small margin concerns.NRC RAI Item 4: As a result of the audits and subsequent interactions with industry during public meetings, NRC staff recognized that evaluation of APM for seals (e.g., flood doors, penetrations, flood gates, etc.) was challenging for some licensees.
Generally, licensees were expected to use either Approach A or Approach B (described below) to determine the APM for seals: a) If seal pressure ratings were known, the seal ratings were used to determine APM (similar to example 2 in Section 3.13 of NEI 12-07). A numerical value for APM was documented.
No further action was performed if the APM value was greater than the pre-established small-margin threshold value. If the APM value was small, an assessment of "significant consequences" was performed and the guidance in NEI 12-U.S. Nuclear Regulatory Commission HNP-14-007, Enclosure Page 3 of 3 07 Section 5.8 was followed.b) If the seal pressure rating was not known, the APM for seals in a flood barrier is assumed to be greater than the pre-established small-margin threshold value if the following conditions were met: (1) the APM for the barrier in which the seal is located is greater than the small-margin threshold value and there is evidence that the seals were designed/procured, installed, and controlled as flooding seals in accordance with the flooding licensing basis. Note that in order to determine that the seal has been controlled as a flooding seal, it was only necessary to determine that the seal configuration has been governed by the plant's design control process since installation.
In this case, the APM for the seal could have been documented as "not small".As part of the RAI response, state if either Approach A or Approach B was used as part of the initial walkdowns or as part of actions taken in response to this RAI. No additional actions are necessary if either Approach A or B was used.If neither Approach A or B was used to determine the APM values for seals (either as part of the walkdowns or as part of actions taken in response to this RAI), then perform the following two actions:* Enter the condition into the CAP (note: it is acceptable to utilize a single CAP entry to capture this issue for multiple seals). CAP disposition of "undetermined" APM values for seals should consider the guidance provided in NEI 12-07, Section 5.8. The CAP disposition should confirm all seals can perform their intended safety function against floods up to the current licensing basis flood height. Disposition may occur as part of the Integrated Assessment.
If an Integrated Assessment is not performed, determine whether there are significant consequences associated with exceeding the capacity of the seals and take interim action(s), if necessary, via the CAP processes.
These actions do not need to be complete prior to the RAI response.* Report the APM as "undetermined" and provide the CAP reference in the RAI response.Response to RAI Item 4: Neither Approach A or B, as described above, were used to determine the APM values for the penetration seals. Seals that were accessible were inspected as part of the original walkdowns for signs of degradation, and corrective actions were taken, when appropriate.
As part of the actions taken to address this RAI, the seals have been assigned an APM value of"undetermined" and have been entered into the CAP process (CR 663490) for further evaluation of their available physical margin.