Monthly Operating Rept for Aug 1995 for Salem Unit 2. W/950911 Ltr
ML18101B002
Person / Time
Site: Salem PSEG icon.png
Issue date: 08/31/1995
From: WARREN C
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9509190121
Download: ML18101B002 (7)


Text

,-* Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038-0236 Nuclear Business Unit U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555

  • Attn.: Document Control Desk MONTHLY OPERATING REPORT SALEMNO. 2 DOCKET NO: 50-311 September 11, 1995 In compliance with Section 6.9.1.6, Reporting Requirements for the Salem Technical Specifications, the original copy of the monthly operating reports for the month of August are being sent to you. RH:vls Enclosures C Mr. Thomas T. Martin Sincerely yi!

General Manager -Salem Operations Regional Administrator USNRC, Region I 631 Park Avenue King of Prussia, PA 19046 8-1-7.R4 9509190121 950911 PDR ADOCK 05000311 _ R._ .. ___ .........

  • --__

.. The power is in your hands. 95-2168 REV. 6/94 __ _j

DAILY UNIT POWER Docket No.: 50-311 Unit Name: Salem #2 Date: 09/11/95

  • Phillips Completed by: Robert Telephone:

339-2735 Month August 1995 Day Average Daily Power Level Day Average Daily Power Level (MWe-NET) (MWe-NET) 1 0 17 0 2 0 18 0 3 0 19 0 4 0 20 0 5 0 21 0 6 0 22 0 7 0 23 0 8 0 24 0 9 0 25 0 10 0 26 0 11 0 27 0 12 0 28 0 13 0 29 0 14 0 30 0 15 0 31 0 16 0 P. 8.1-7 Rl OPERATING DATA REPORT Docket No: . Date: Completed by: Robert Phillips Telephone:

Operating Status L Unit Name Salem No. 2 Notes 2 . Reporting Period August, 1995 3. Licensed Thermal Power (MWt) 3411 4. Nameplate Rating (Gross MWe) 1170 5. Design Electrical Rating (Net MWe) 1115 6. Maximum Dependable Capacity(Gross MWe) 1149 7. Maximum Dependable Capacity (Net MWe) 1106 8. If Changes Occur in Capacity Ratings (items 3 through 7) Report, Give Reason NA 9. Power Level to Which Restricted, if any (Net MWe) 10. Reasons for Restrictions, if any ii. Hours in Reporting Period 12. No. of Hrs. Rx. was Critical 13. Reactor Reserve Shutdown Hrs. 14. Hours Generator On-Line 15. Unit Reserve Shutdown Hours 16. Gross Thermal Energy Generated (MWH) Gross Elec. Energy Generated (MWH) 18. Net Elec. Energy Gen. (MWH) 19. Unit Service Factor 20. Unit Availability Factor 21. Unit Capacity Factor (using MDC Net) 22. Unit Capacity Factor (using DER Net) 23. Unit Forced Outage Rate This Month 744 0 0 0 0 0 0 -7400 0 0 0 0 100 N A Year to Date 5831 2468.4 0 2261.6 0 6807220.8 2198890 2033700 38.8 38.8 31. 5 31. 3 54.9 50-311 09/11/95 339-2735 since Last N/A Cumulative 121704 78083.6 0 75229.5 0 187781005 78648898 74757244 61. 8 61. 8 55.5 55.1 23.4 24. Shutdowns scheduled over next 6 months (type, date and duration of each) To be determined.

25. If shutdown at end of Report Period, Estimated Date of Startup: To be determined.

8-1-7.R2 NO. DATE 2692 8-1-95 F 2 F: Forced S: Scheduled DURATION TYPE 1 (HOURS) REASON 2 744 A Reason A-Equipment Failure (explain)

B-Maintenance or Test C-Refueling D-Requlatory Restriction UNIT SHUTDOWN AND POWER REDUCTIONS REPORT MONTH AUGUST 1995 METHOD OF SHUTTING DOWN REACTOR 4 LICENSE EVENT REPORT # .. _________

SH 3 Method: 1-Manual 2-Manual *Scram SYSTEM CODE 4 E-Operator Training & License Examination F-Administrative 3-Automatic Scram 4-Continuation of Previous Outage 5-Load Reduction 9-0ther G-Operational Error (Explain)

H-Other (Explain)

COMPONENT CODE 5 DOCKET NO.: _,5""'0'""'--=3_,_1..:...1 UNIT NAME: Salem #2 DATE: 9-10-95 COMPLETED BY: Robert Phillips TELEPHONE:

609-339-2735 . CAUSE AND CORRECTIVE ACTION TO PREVENT RECURRENCE CKTBRK BREAKER FAILURE 1-9 500KV 4 Exhibit G -Instructions for Preparation of Data Entry Sheets for Licensee Event Report CLER) File (NUREG-0161) 5 Exhibit 1 -Same Source --

lOCFRS0.59 EVALUATIONS MONTH: AUGUST 1995 DOCKET NO: UNIT NAME: DATE: COMPLETED BY: TELEPHONE:

50-311 SALEM2 09/10/95 R. HELLER 609-339-5162 The following items were evaluated in accordance with the provisions of the Code of Federal Regulations 10CFR50.59.

The Station Operations Review Committee has reviewed and concurs with these evaluations.

1. Design Change Packages (DCP) The reporting ofDCP related 10CFR50.59 evaluations is being modified to address these items only after they have been implemented and turned over to Operations.

For the next several months, during this transition phase, we anticipate few new DCPs to report. 2EC-3372, Pkg. 1 "Enhance 2 RMS Computer Alarm Reliability" Rev. 0 -The purpose of this design change is to implement corrections to the Interdata 7/32 assembly language software used to drive the annunciator.

Changes are to assure messages defining changes in RMS status will be provided to the Met Package, driving the RIS reflash relays, providing inputs to the 2RP 1 RMS annunciator, and thus to the A6 window on the overhead annunciator.

The RMS computers have no effect on any physical parameters relating to the fission product barriers.

There is no reduction in the margin of safety relating to any fuel cladding, RCS boundary pressures or stresses, or containment pressure boundary. (SORC 95-082)

, . . .. REFUELING INFORMATION . MONTH: AUGUST 1995 MONTH: AUGUST 1995 DOCKET NO: UNIT NAME: DATE: COMPLETED BY: TELEPHONE:

50-311 SALEM2 09/10/95 R.HELLER 609-339-5162

1. Refueling information has changed from last month: YES ____ NO __ 2. Scheduled date for next refueling: (to be determined)

Scheduled date for restart following refueling:

2nd quarter 1996 3. a. Will Technical Specification changes or other license amendments be required?

YES_ NO NOT DETERMINED TO DATE X b. Has the reload fuel design been reviewed by the Station Operating Review Committee?

YES NO X If no, when is it scheduled? (to be determined)

5. Scheduled date(s) for submitting proposed licensing action:
6. Important licensing considerations associated with refueling:
7. Number of Fuel Assemblies:
a. lncore b. In Spent Fuel Storage 8. Present licensed spent fuel storage capacity:

Future spent fuel storage capacity:

9. Date of last refueling that can be discharged to the spent fuel pool assuming the present licensed capacity:

8-1-7.R4 _193_ 556 1632 1632 March 2012

..... SALEM GENERATING STATION MONTHLY OPERATING

SUMMARY

-UNIT 2 AUGUST 1995 SALEM UNIT NO. 2 The Unit remained shutdown for the entire period. According to commitments from PSE&G and a subsequent confirmatory action letter from the NRC, both Units will remain shutdown pending completion of the following actions:

  • Appropriately address long standing equipment reliability and operability issues
  • After the work is completed, conduct a restart readiness review to determine for ourselves the ability of each Unit to operate in a safe, event free manner
  • After the restart review, meet with the NRC and communicate the results of that review I I J