UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION

In the Matter of

VIRGINIA ELECTRIC AND POWER Docket Nos. 50-338-SLR-2 COMPANY 50-339-SLR-2

(North Anna Power Station, Units 1 and 2)

ORDER

On February 21, 2024, I issued an order in this proceeding holding in abeyance two

motions filed by Beyond Nuclear and the Sierra Club (together, Petitioners). 1 As explained in

that order, these motions seek (1) withdrawal of the notice of opportunity for hearing on the draft

site-specific environmental impact statement (EIS) concerning the North Anna subsequent

license renewal (SLR) application 2 or, in the alternative, (2) suspension of the deadline to

request a hearing.3 These motions were held in abeyance because the question they raised

whether the NRC staffs issuance of the hearing no tice in this proceeding was consistent with

the Commissions direction in CLI-22-3was identical to the question an Atomic Safety and

Licensing Board certified to the Commission in a separate proceeding concerning the SLR

application for Turkey Point Nuclear Generating Units 3 and 4. 4

1 Order of the Secretary, at 3 (Feb. 21, 2024) (ADAMS Accession No. ML24052A386).

2 Motion by Beyond Nuclear and Sierra Club for Withdrawal of Premature Hearing Notice (Jan.

18, 2024) (ML24018A150) (Withdrawal Motion); Errata to Motion by Beyond Nuclear and Sierra Club for Withdrawal of Premature Hearing Notice (Jan. 22, 2024) (ML24022A066).

3 Notification of Relevance of LBP-24-01 to This Proceeding and Request to Immediately Suspend Hearing Request Deadline Pending Resolution of Certified Question Raised in LBP-24-01 (Feb. 12, 2024) (ML24043A036) (Suspension Motion).

4 See Florida Power & Light Co. (Turkey Point Nuclear Generating Units 3 and 4), LBP-24-1, 99 NRC __, __ (Jan. 31, 2024) (slip op. at 4).

In CLI-24-1 the Commission accepted the Boards certification and found that the NRC

staff reasonably interpreted CLI-22-3 when it published the notice of opportunity for hearing on

the Turkey Point SLR application upon issuance of the draft EIS. 5

Therefore, consistent with CLI-24-1 and pursuant to my authority under 10 C.F.R.

§ 2.346(j), I deny the Petitioners Withdrawal Motion and Suspension Motion.

IT IS SO ORDERED.

For the Commission

Carrie M. Safford Secretary of the Commission

Dated at Rockville, Maryland, this 13th day of March 2024.

5 CLI-24-1, 99 NRC __, __ (Mar. 7, 2024) (slip op. at 6).

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION

In the Matter of )

)

VIRGINIA ELECTRIC AND POWER COMPANY ) Docket Nos. 50-338-SLR-2

) 50-339-SLR-2 (North Anna Power Station, Units 1 and 3) )

CERTIFICATE OF SERVICE

I hereby certify that copies of the foregoing ORDER OF THE SECRETARY OF THE COMMISSION have been served upon the following persons by Electronic Information Exchange.

U.S. Nuclear Regulatory Commission Office of Commission Appellate Adjudication Morgan, Lewis & Bockius LLP Mail Stop: O-16B33 1111 Pennsylvania Ave., N.W.

Washington, DC 20555-0001 Washington, DC 20004 E-mail: ocaamail.resource@nrc.gov Scott D. Clausen, Esq.

Paul M. Bessette, Esq.

U.S. Nuclear Regulatory Commission Ryan K. Lighty, Esq.

Office of the Secretary of the Commission E-mail: Paul.Bessette@morganlewis.com Mail Stop: O-16B33 Ryan.Lighty@morganlewis.com Washington, DC 20555-0001 E-mail: hearingdocket@nrc.gov Harmon, Curran, Spielberg, & Eisenberg, LLP 1725 DeSales Street, N.W., Suite 500 Atomic Safety and Licensing Board Panel Washington, DC 20036 U.S. Nuclear Regulatory Commission Diane Curran, Esq.

Washington, DC 20555-0001 E-mail: dcurran@harmoncurran.com E. Roy Hawkens, Chief Administrative Judge E-mail: Roy.Hawkens@nrc.gov Beyond Nuclear Reactor Oversight Project U.S. Nuclear Regulatory Commission 7304 Carroll Avenue #182 Office of the General Counsel Takoma Park, MD 20912 Mail Stop - O-14A44 Paul Gunter Washington, DC 20555-0001 E-mail: paul@beyondnuclear.org David E. Roth, Esq.

Sherwin E. Turk, Esq.

Susan H. Vrahoretis, Esq.

Georgiann E. Hampton, Paralegal Caitlin R. Byrd, Paralegal E-mail: David.Roth@nrc.gov Sherwin.Turk@nrc.gov Blake.Vaisey@nrc.gov Georgiann.Hampton@nrc.gov Caitlin.Byrd@nrc.gov

Office of the Secretary of the Commission

Dated at Rockville, Maryland, this 13th day of March 2024.