Letter Sequence Other |
---|
EPID:L-2021-LLA-0067, Enclosure a - Evaluation Attachment 2 - Proposed Updated Final Safety Analysis Report Tables and Figures, Part 2 of 2 (Approved, Closed) |
|
MONTHYEARL-21-002, Enclosure a - Evaluation Attachment 2 - Proposed Updated Final Safety Analysis Report Tables and Figures, Part 2 of 22021-04-0707 April 2021 Enclosure a - Evaluation Attachment 2 - Proposed Updated Final Safety Analysis Report Tables and Figures, Part 2 of 2 Project stage: Request ML21140A2802021-05-20020 May 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment and Exemptions Regarding Revising the Methodology Used for Flood Hazard Analysis (Epids: L-2021-LLA-0067, L-2021-LLE-0022, L-2021-LLE-0023) Project stage: Acceptance Review ML21165A0012021-07-0909 July 2021 Regulatory Audit for the Review of License Amendment Regarding Revising the Flood Hazard Protection Scheme Project stage: Approval L-21-206, Regulatory Audit for Review of License Amendment Regarding Revising the Flood Hazard Protection Scheme2021-08-17017 August 2021 Regulatory Audit for Review of License Amendment Regarding Revising the Flood Hazard Protection Scheme Project stage: Other ML22101A2822022-05-0606 May 2022 Regulatory Audit Summary Related to the Review of License Amendment Regarding Revising the Flood Hazard Protection Scheme Project stage: Approval L-22-099, Supplement to License Amendment Request to Revise the Methodology Used for Flood Hazard Analysis2022-06-0101 June 2022 Supplement to License Amendment Request to Revise the Methodology Used for Flood Hazard Analysis Project stage: Supplement ML22167A1002022-06-16016 June 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Delay in Issuance of License Amendment and Exemptions Regarding Revising the Methodology Used for Flood Hazard Analysis (EPIDs No.L-2021-LLA-0067, L-2021-LLE-0022, L-2021-LLE-0023) Project stage: Approval L-22-272, Supplement to License Amendment Request to Revise the Methodology Used for Flood Hazard Analysis (EPID L-2021-LLA-0067) and Withdrawal of Exemption Requests (EPIDs L-2021-LLE-0022 and L-2021-LLE-0023)2022-12-16016 December 2022 Supplement to License Amendment Request to Revise the Methodology Used for Flood Hazard Analysis (EPID L-2021-LLA-0067) and Withdrawal of Exemption Requests (EPIDs L-2021-LLE-0022 and L-2021-LLE-0023) Project stage: Withdrawal ML22356A0012023-01-0303 January 2023 Withdrawal of Exemptions Supporting Flooding Scheme (L-2021-LLA-0067, L-2021-LLE-0022, L-2021-LLE-0023) Project stage: Withdrawal ML23010A2892023-01-10010 January 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Delay in Issuance of License Amendment Regarding Revising the Methodology Used for Flood Hazard Analysis Project stage: Approval ML22284A1442023-02-0303 February 2023 Issuance of Amendment No. 200 Regarding the Revision of Methodology Used for Flood Hazard Analysis Project stage: Approval 2022-05-06
[Table View] |
Similar Documents at Perry |
---|
Category:Letter type:L
MONTHYEARL-24-226, License Renewal Application for the Perry Nuclear Power Plant Revision O - Response to Requests for Confirmatory Information (Rcls) - Set 12024-10-31031 October 2024 License Renewal Application for the Perry Nuclear Power Plant Revision O - Response to Requests for Confirmatory Information (Rcls) - Set 1 L-24-179, License Renewal Application for the Perry Nuclear Power Plant Revision 0 - Supplement 52024-10-21021 October 2024 License Renewal Application for the Perry Nuclear Power Plant Revision 0 - Supplement 5 L-24-208, License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2)2024-10-0202 October 2024 License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2) L-24-207, License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 12024-09-16016 September 2024 License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 1 L-24-201, Spent Fuel Storage Cask Registration2024-09-0909 September 2024 Spent Fuel Storage Cask Registration L-24-200, License Renewal Application for Revision to Supplement 4 for Editorial Corrections2024-09-0505 September 2024 License Renewal Application for Revision to Supplement 4 for Editorial Corrections L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 L-24-190, Spent Fuel Storage Cask Registration2024-08-26026 August 2024 Spent Fuel Storage Cask Registration L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule L-24-174, Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information2024-08-15015 August 2024 Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information L-24-178, License Renewal Application Revision O - Supplement 42024-08-0808 August 2024 License Renewal Application Revision O - Supplement 4 L-24-189, License Renewal Application for Revision O - Supplement 12024-08-0707 August 2024 License Renewal Application for Revision O - Supplement 1 L-24-171, Spent Fuel Storage Cask Registration2024-07-30030 July 2024 Spent Fuel Storage Cask Registration L-24-108, License Renewal Application, Revision 0 - Supplement 32024-07-24024 July 2024 License Renewal Application, Revision 0 - Supplement 3 L-24-036, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-27027 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-24-020, License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 22024-06-27027 June 2024 License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 2 L-24-116, Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification2024-05-16016 May 2024 Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification L-24-085, Nudear Power Plant, Submittal of Emergency Plan, Revision 622024-05-0606 May 2024 Nudear Power Plant, Submittal of Emergency Plan, Revision 62 L-24-103, Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams2024-05-0202 May 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams L-24-097, Submittal of 2023 Annual Radiological Effluent Release Report2024-04-22022 April 2024 Submittal of 2023 Annual Radiological Effluent Release Report L-24-096, Submittal of Annual Radiological Environmental Operating Report2024-04-22022 April 2024 Submittal of Annual Radiological Environmental Operating Report L-24-083, Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification2024-04-15015 April 2024 Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification L-24-066, Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency2024-04-15015 April 2024 Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency L-24-057, Submittal of the Decommissioning Funding Status Report2024-03-28028 March 2024 Submittal of the Decommissioning Funding Status Report L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage L-24-076, Independent Spent Fuel Storage Installation - Supplemental Information for Request for Specific Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.2142024-03-22022 March 2024 Independent Spent Fuel Storage Installation - Supplemental Information for Request for Specific Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 L-24-053, Independent Spent Fuel Storage Installation, Request for Specific Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.2142024-02-27027 February 2024 Independent Spent Fuel Storage Installation, Request for Specific Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee L-24-017, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2024-01-24024 January 2024 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative L-23-207, License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2024-01-24024 January 2024 License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs L-23-171, CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency2023-12-0808 December 2023 CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency L-23-244, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation L-23-238, Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 202023-11-10010 November 2023 Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 20 L-23-206, Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD2023-09-12012 September 2023 Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-001, License Amendment Request to Remove the Table of Contents from the Technical Specifications2023-08-0707 August 2023 License Amendment Request to Remove the Table of Contents from the Technical Specifications L-23-174, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2023-07-19019 July 2023 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative L-23-146, License Renewal Application for the Perry Nuclear Power Plant2023-07-0303 July 2023 License Renewal Application for the Perry Nuclear Power Plant L-23-051, Plan, Nineteenth Inservice Inspection Summary Report2023-06-22022 June 2023 Plan, Nineteenth Inservice Inspection Summary Report L-23-050, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-22022 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-22-249, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener2023-06-0505 June 2023 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener L-23-134, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-23023 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report L-23-122, Annual Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Radiological Environmental Operating Report L-23-121, Annual Radiological Effluent Release Report2023-04-26026 April 2023 Annual Radiological Effluent Release Report L-23-061, Submittal of the Decommissioning Funding Status Reports2023-03-31031 March 2023 Submittal of the Decommissioning Funding Status Reports L-23-049, Core Operating Limits Report for Operating Cycle 202023-03-30030 March 2023 Core Operating Limits Report for Operating Cycle 20 2024-09-09
[Table view] |
Text
energy Energy Harbor Nuclear Corp.
harbor Perry Nuclear Power Plant 10 Center Road P.O. Box 97 Perry, Ohio 44081
Rod L. Penfield 440-280-5382 Site Vice President, Perry Nuclear
August 17, 2021 L-21-206 10 CFR 50.90 10 CFR 50.12
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
Perry Nuclear Power Plant, Unit No. 1 Docket No. 50-440, License No. NPF-58 Regulatory Audit for Review of License Amendment Regarding Revising the Flood Hazard Protection Scheme (EPID L-2021-LLA-0067)
By letter dated April 7, 2021 [Agencywide Documents Access and Management System (ADAMS) Accession No. ML21106A027], Energy Harbor Nuclear Corp. submitted to the Nuclear Regulatory Commission (NRC) a license amendment request for the Perry Nuclear Power Plant (PNPP) to revise the Updated Safety Analysis Report (USAR) to change the methodology used for analysis of flooding hazards and drainage within the local intense precipitation (LIP) domain and reflect the results from the new analysis.
Based on the new analysis, a new flood hazard protection scheme is also proposed for PNPP. In addition, Energy Harbor Nuclear Corp. requested exemptions in accordance with 10 CFR 50.12 to credit non-safety related protection features including: (1) permanent (passive) and temporary (deployable) flood barriers, and (2) the plant storm drain system in mitigation of flood levels during a LIP event.
By letter dated July 9, 2021 (ADAMS Accession No. ML21165A001), the NRC staff described the terms and conditions of using a regulatory audit to support review of these requests and provided a regulatory audit plan. Energy Harbor Nuclear Corp.
agrees to the terms and conditions set forth in the letter.
As part of the NRC audit, the NRC staff requested that executable electronic versions of the input and output files for key scenarios and final selected ones used in the license amendment request to simulate (i) FLO-2D LIP flooding, and (ii) inflows and streams course models for the two streams "Major" and "Diversion" be made available. These files should also be submitted for docketing.
Perry Nuclear Power Plant, Unit No. 1 L-21-206 Page2
The requested input/output files are provided in their native file format on the enclosed hard drives. Each hard drive contains one copy of the electronic information for the following calculations.
- 50:64.000, PNPP Site Modifications Local Intense Precipitation (Design Basis),
Revision 1
- 50:72.000, Design Basis Major Stream Probable Maximum Flood (PMF),
Revision 0
- 50:73.000, Design Basis Diversion Stream Probable Maximum Flood (PMF),
Revision 0
There are no regulatory commitments contained in this letter. If there are any questions or if additional information is required, please contact Mr. Phil H. Lashley, Manager Fleet Licensing, at 330-696-7208.
I declare under penalty of perjury that the foregoing is true and correct. Executed on August_IL, 2021.
i?&rf?r{)
Rod L. Penfield ~
Enclosure:
Hard drive with electronic information (2 hard drives provided)
cc: NRC Region Ill Administrator (w/o Enclosure)
NRC Resident Inspector (w/o Enclosure)
NRR Project Manager (w/o Enclosure)
Executive Director, Ohio Emergency Management Agency, State of Ohio (NRC Liaison) (w/o Enclosure)
Utility Radiological Review Board (w/o Enclosure)
Enclosure L-21-206
Hard drive with electronic information (2 hard drives provided)