ENCLOSURE 1 REVISED PAGES OF FACILITY OPERATING LICENSE NOS. DPR-80 AND DPR-82 DOCKET NOS. 50-275 AND 50-323 DIABLO CANYON POWER PLANT, UNITS 1 AND 2 Replace the following pages of the Facility Operating Licenses. The revised pages are identified by the date of the letter issuing these pages and contain marginal lines indicating the areas of change.
REMOVE INSERT License DPR-80 License DPR-80 Page 9 Page 9 Page 10 License DPR-82 License DPR-82 Page 7 Page 7 Page 8
E. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans Including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p).
The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled: "Diablo Canyon Power Plant, Units 1 and 2 Physical Security Plan, by Training and Qualification Plan, and Safeguards Contingency Plan," submitted by letter dated May 16, 2006.
F. Deleted.
G. Deleted.
H. Financial Protection PG&E shall have and maintain financial protection of such type and in such amounts as the Commission shall require In accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.
I. Mitigation Strategy License Condition l l
Develop and maintain strategies for addressing large fires and explosions and that l include the following key areas: l l
(a) Fire fighting response strategy with the following elements: l
- 1. Pre-defined coordinated fire response strategy and guidance l
- 2. Assessment of mutual aid fire fighting assets l
- 3. Designated staging areas for equipment and materials l
- 4. Command and control l
- 5. Training of response personnel l l
(b) Operations to mitigate fuel damage considering the following: l
- 1. Protection and use of personnel assets l
- 2. Communications l
- 3. Minimizing fire spread l
- 4. Procedures for implementing integrated fire response strategy l
- 5. Identification of readily-available pre-staged equipment l
- 6. Training on integrated fire response strategy l
- 7. Spent fuel pool mitigation measures l l
(c) Actions to minimize release to include consideration of: l
- 1. Water spray scrubbing l
- 2. Dose to onsite responders l Revised by letter dated December 11, 2006 Revised by letter dated July 11, 2007
l J. Term of License This License is effective as of the date of Issuance and shall expire at midnight on November 2, 2024.
FOR THE NUCLEAR REGULATORY COMMISSION Original Signed by:
Edson G. Case for Harold R. Denton, Director Office of Nuclear Reactor Regulation Attachments:
- 1. Appendix A - Technical Specifications
- 2. Appendix B - Environmental Protection Plan
- 3. Appendix C - Deleted
- 4. Appendix D - Additional Conditions Date of Issuance: November 2, 1984 Amendment No. 82, 75, 97, 129, 188, 189, 193 Revised by letter dated July 11, 2007
F. Deleted.
G. Deleted.
H. Financial Protection PG&E shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.
I. Mitigation Strategy l l
Develop and maintain strategies for addressing large fires and explosions and that include the l following key areas: l l
(a) Fire fighting response strategy with the following elements: l
- 1. Pre-defined coordinated fire response strategy and guidance l
- 2. Assessment of mutual aid fire fighting assets l
- 3. Designated staging areas for equipment and materials l
- 4. Command and control l
- 5. Training of response personnel l l
(b) Operations to mitigate fuel damage considering the following: l
- 1. Protection and use of personnel assets l
- 2. Communications l
- 3. Minimizing fire spread l
- 4. Procedures for implementing integrated fire response strategy l
- 5. Identification of readily-available pre-staged equipment l
- 6. Training on integrated fire response strategy l
- 7. Spent fuel pool mitigation measures l l
(c) Actions to minimize release to include consideration of: l
- 1. Water spray scrubbing l
- 2. Dose to onsite responders l l
Revised by letter dated December 11, 2006 Revised by letter dated July 11, 2007
l J. Term of License This License is effective as of the date of issuance and shall expire at midnight on August 26, 2025.
FOR THE NUCLEAR REGULATORY COMMISSION Original Signed by:
Harold R. Denton Harold R. Denton, Director Office of Nuclear Reactor Regulation Attachments:
- 1. Appendix A Technical Specifications (NUREG-1151)
- 2. Appendix B - Environmental Protection Plan
- 3. Appendix C - Deleted
- 4. Appendix D - Additional Conditions Date of Issuance: August 26, 1985 Amendment No. 96, 118, 190, 191, 194 Revised by letter dated December 11, 2006 Revised by letter dated July 11, 2007