Category:2.206 Director Decision
MONTHYEARML24136A1622024-05-15015 May 2024 OEDO-24-00083 (E-Mail) 10 CFR 2.206 - Diablo Canyon Power Plant, Unit Nos. 1 and 2 Seismic - Initial Assessment ML17194A8802017-06-0808 June 2017 Letter from Annette L. Vietti-Cook to Mr. David Lochbaum Re DD-17-03 ML17138A3412017-05-17017 May 2017 Letter from Annette Vietti-Cook to Richard Ayres Regarding Director'S Decision - DD-17-02 ML17108A5902017-05-12012 May 2017 OEDO-16-00436 - Final Director's Decision - David Lochbaum, Union of Concerned Scientists, Letter Re: 10 CFR 2.206 Petition on Apparent Violation of 10 CFR 50.9 (CAC Nos. MF8123 and MF8124) ML17090A1822017-04-21021 April 2017 Final Directors Decision Friends of Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 ML17095A9322017-04-21021 April 2017 Final Director'S Decision Under 10 CFR Sec. 2.206 Friends of the Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 ML17011A2052017-02-28028 February 2017 SRM-M150521A - Petitioner Letter Friends of the Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 ML17011A2062017-02-28028 February 2017 SRM-M150521A-2 - Licensee Letter Friends of Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 (CAC Nos. MF6443 and MF6444 ML17011A2042017-02-28028 February 2017 SRM-M150521A - Proposed Director'S Decision Friends of Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 ML13018A2392015-04-0808 April 2015 G20110171 - Letter to Petitioner Saporito on Proposed Director'S Decision Regarding 2.206 Petition Dated: March 12, 2011 CY-92-223, G20110523/LTR-11-0411/EDATS: SECY-2011-0411 - Ltr. from Rep. E.J. Markey to Chairman Jaczko NRC Safety Requirements for Reactors Granted Construction Permits Prior to 19712011-07-14014 July 2011 G20110523/LTR-11-0411/EDATS: SECY-2011-0411 - Ltr. from Rep. E.J. Markey to Chairman Jaczko NRC Safety Requirements for Reactors Granted Construction Permits Prior to 1971 2024-05-15
[Table view] Category:Letter
MONTHYEARDCL-24-103, Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 22024-10-24024 October 2024 Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 2 DCL-24-092, Supplement and Annual Update License Renewal Application, Amendment 12024-10-14014 October 2024 Supplement and Annual Update License Renewal Application, Amendment 1 DCL-24-098, Material Status Report for the Period Ending August 31, 20242024-10-0909 October 2024 Material Status Report for the Period Ending August 31, 2024 IR 05000275/20253012024-10-0303 October 2024 Notification of NRC Initial Operator Licensing Examination 05000275/2025301; 05000323/2025301 DCL-24-091, Response to Request for Additional Information by the Office of Nuclear Reactor Regulation2024-10-0303 October 2024 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation ML24240A0222024-09-20020 September 2024 Letter to A. Peck Environmental Impact Statement Scoping Summary Report for Diablo Canyon Nuclear Power Plant Units 1 and 2 ML24260A1222024-09-14014 September 2024 14 Sept 2024 Ltr - California Coastal Commission to Pg&E, Incomplete Consistency Certification for Requested Nuclear Regulatory Commission License Renewal for Diablo Canyon Power Plant DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) ML24262A2462024-09-11011 September 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Petitioner Response to Acknowledgement Letter - DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - IR 05000275/20243012024-08-26026 August 2024 NRC Examination Report 05000275/2024301; 05000323/2024301 IR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 DCL-24-079, DC-2024-07 Post Exam Comments Analysis2024-08-0202 August 2024 DC-2024-07 Post Exam Comments Analysis DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL ML24155A2182024-06-18018 June 2024 OEDO-23-00350-NRR - (LTR-23-0228-1) - Closure Letter - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24129A1762024-06-14014 June 2024 National Historic Preservation Act Section 106 Consultation – Results of Identification and Evaluation (Docket Number: 72-026) ML24200A2052024-06-0707 June 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project for Diablo Canyon License Renewal ML24099A2192024-05-29029 May 2024 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24117A0132024-05-20020 May 2024 Letter to Paula Gerfen-Diablo Canyon Units 1 and 2-Regulatory Audit Regarding Severe Accident Mitigation Alternatives for the License Renewal Application DCL-24-054, LCO 3.0.3 Completion Time Limits2024-05-17017 May 2024 LCO 3.0.3 Completion Time Limits DCL-24-052, Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report2024-05-16016 May 2024 Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report DCL-24-051, One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage2024-05-0808 May 2024 One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage ML24127A2042024-05-0202 May 2024 02May2024 Ltr - California Coastal Commission to Pg&E, Coastal Development Permit Needed for Pg&E’S Proposed Relicensing of Diablo Canyon Nuclear Power Plant DCL-24-047, 2023 Annual Non-radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Non-radiological Environmental Operating Report DCL-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Radiological Environmental Operating Report L-24-004, Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007)2024-04-30030 April 2024 Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007) DCL-24-048, O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 20232024-04-30030 April 2024 O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 2023 DCL-24-027, 2023 Annual Radioactive Effluent Release Report2024-04-28028 April 2024 2023 Annual Radioactive Effluent Release Report DCL-24-045, Annual Report of Occupational Radiation Exposure for 20232024-04-24024 April 2024 Annual Report of Occupational Radiation Exposure for 2023 IR 05000275/20240012024-04-23023 April 2024 Integrated Inspection Report 05000275/2024001 and 05000323/2024001 ML24114A2032024-04-22022 April 2024 Request for Information for EP Program and Performance Indicator Verification Inspection (Wolf Creek Nuclear Generating Station) Inspection Report 05000482/2024003 ML24106A2882024-04-18018 April 2024 License Renewal Application Environmental Review RCIs and RAIs ML24106A2892024-04-18018 April 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of March 2024 Audit Regarding the Environmental Review of the License Renewal Application DCL-24-042, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-04-17017 April 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24108A1122024-04-15015 April 2024 License Amendment Request 24-02 Request for Approval of DCPP Early Warning System to Meet 10 CFR 73.55(i)(2) and 10 CFR 73.55(e)(9)(vi)(A) DCL-24-023, Revised Certification of Permanent Cessation of Power Operations2024-04-0202 April 2024 Revised Certification of Permanent Cessation of Power Operations 2024-09-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON , D.C. 20555-0001 May 17, 2017 SECRETARY Mr. Richard Ayres Attorney for Friends of the Earth Ayres Law Group, LLP 1707 L Street NW, Suite 850 Washington, DC 20036 Re: Director's Decision DD-17-02 Pacific Gas and Electric Company Diablo Canyon Power Plant, Units 1 and 2 Docket No. 50-275 and 50-323
Dear Mr. Ayres :
This is to inform you that the Commission has declined to review Director's Decision (DD-17-02). Accordingly, the decision became a final agency action on May 16, 2017.
Sincerely, Annette L. Vietti-Cook cc: Service list
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )
)
PACIFIC GAS AND ELECTRIC COMPANY )
) Docket Nos. 50-247 and 50-286
)
)
(Diablo Canyon Power Plant, Units 1 and 2) )
)
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing LETTER FROM ANNETTE L. VIETTI-COOK TO MR. RICHARD AYRES RE: DD-17-02 have been served upon the following persons by U.S.
mail, first class, or through NRC internal distribution.
Mr. Richard Ayres Marian L. Zobler, Esq.
Attorney for Friends of the Earth Office of the General Counsel Ayres Law Group, LLP Mail Stop - O-14 A44 1707 L Street NW, Suite 850 U.S. Nuclear Regulatory Commission Washington, DC 20036 Washington, DC 20555-0001 Mr. Edward D. Halpin Merrilee J. Banic, Sr. Project Manager Senior Vice-President, Generation 2.206 Coordinator & Generic Communications And Chief Nuclear Officer Program Manager Pacific Gas and Electric Company Division of Policy and Rulemaking Diablo Canyon Power Plant Office of Nuclear Reactor Regulation P.O. Box 56, Mail Code 104/6 Mail Stop - O-12 D20 Avila Beach, CA 93424 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 William Dean, Director Office of Nuclear Reactor Regulation Mail Stop - O-13H16 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
[Original signed by Clara Sola ]
Office of the Secretary of the Commission Dated at Rockville, Maryland this 17th day of May, 2017