ML070390040

From kanterella
Revision as of 05:28, 13 July 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
APS Response to NRC Inspection Report 05000528/2006012; 05000529/2006012; 05000530/2006012
ML070390040
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 01/24/2007
From: James M. Levine
Arizona Public Service Co
To:
Document Control Desk, NRC Region 4
References
102-05636/JML/SAB/TNW/CJS, IR-06-012
Download: ML070390040 (11)


See also: IR 05000528/2006012

Text

LA subsidiary

of Pinnacle West Capital Corporation

James M. Levine Mail Station 7602 Palo Verde Nuclear Executive

Vice President

Tel (623) 393-5300 PO Box 52034 Generating

Station Generation

Fax (623) 393-6077 Phoenix, Arizona 85072-2034

102-05636-JMLJSAB/TNW/CJS

January 24, 2007 U.S. Nuclear Regulatory

Commission

ATTN: Document Control Desk Washington, DC 20555 Dear Sir: Subject: Palo Verde Nuclear Generating

Station (PVNGS)Units 1, 2 and 3 Docket Nos. STN 50-528, 50-529, and 50-530 APS Response to NRC Inspection

Report 05000528/2006012;

0500052912006012;

0500053012006012

In NRC Special Inspection

Report 2006012, dated December 6, 2006, the NRC documented

their examination

of activities

associated

with the PVNGS Unit 3, Train A, emergency

diesel generator (EDG) failures that occurred on July 25 and September

22, 2006. At a January 16, 2007 Regulatory

Conference

in Arlington, Texas, APS provided the NRC its perspective

on the facts and analytical

assumptions

relevant to determining

the safety significance

of the findings, in accordance

with the Inspection

Manual Chapter 0609.The purpose of this letter is to provide the additional

information

requested

by the NRC during the regulatory

conference.

The Enclosure

to this letter contains 7 questions

that were requested

at the close of the conference

and 4 additional

questions

that were part of the conference

general discussion.

There are no regulatory

commitments

in this letter.If you have any questions, please contact Thomas N. Weber at (623) 393-5764.Sincerely, JMLJSABITNW/CJS/gt

U.S. Nuclear Regulatory

Commission

ATTN: Document Control Desk APS Response to NRC Inspection

Report 05000528/2006012;

05000529/2006012;

05000530/2006012

Page 2 Enclosure:

Additional

Information

Requested

at the January 16, 2007 NRC Regulatory

Conference

cc: B. S. Malleft M. B. Fields M. T. Markley G. G. Warnick NRC Region IV Regional Administrator

NRC NRR Project Manager NRC NRR Project Manager NRC Senior Resident Inspector

for PVNGS

ENCLOSURE Additional

Information

Requested

at the January 16, 2007 NRC Regulatory

Conference

NRC Question 1 Is it acceptable

to provide auxiliary

feedwater

to a steam generator

after it has dried out?APS Response 1 Yes. The Unit 3 steam generators

are designed with an allowance

for feeding a hot dry steam generator

with cold feedwater.

APS asked ABB (the design authority

for the PVNGS Steam Generators)

about the maximum allowed flow rate for feedwater

to a hot dry steam generator.

The ABB response stated "the generators

are designed to handle seven cycles of adding 40 degrees F feedwater

at 1750 gpm." The information

was requested

to support development

of the PVNGS Emergency

Operating

Procedures.

This information

is documented

in ABB Inter-Office

Correspondence

V-MPS-91-163, dated, November 14, 1991.NRC Question 2 What reliability/unavailability

for the Gas Turbine Generators (GTGs) was assumed in the Probabilistic

Risk Analysis (PRA)? Provide the data that was used to obtain these values. Please indicate how buried cable reliability

is addressed

in the PRA.APS Response 2 GTG Reliability

Gas Turbine Generator (GTG) fail to start and fail to run probabilities

are Bayesian updated values based on the values in Advanced Light Water Reactor Requirements

Document (ALWR), Volume II, Chapter 1, Appendix A -PRA Key Assumptions

and Groundrules, Electric Power Research Institute, Revision 6, December 1993, pages A.A-67 and A.A-68. The number of GTG demands, accumulated

run time, and failures were collected

for the period of 1/1/1998 to 10/1/2004

and documented

in study 13-NS-C076, Plant Specific Reliability

Data for PRA Model, Revision 0, Appendix C: PRA Final Failures and Demands Report. The values were based on an actual count (they were not estimated).

For the given time period and system boundary, there were 6 failures (3 on GTG 1 and 3 on GTG 2) in 267 demands and 0 failures in 283 hours0.00328 days <br />0.0786 hours <br />4.679233e-4 weeks <br />1.076815e-4 months <br />. The final failure probabilities

were 2.5E-2 per demand and 4.2E-5 per hour.1

GTG Unavailability

GTG unavailability

is based on an actual count of unavailable

hours during the period 1/1/1999 through 12/31/2001

as documented

in study 13-NS-C064, Plant Specific Unavailability

Data for PRA Model, Revision 0, Appendix A: Individual

Parameter Unavailability

Listings Gas Turbine Generator.

There were 954.68 hours7.87037e-4 days <br />0.0189 hours <br />1.124339e-4 weeks <br />2.5874e-5 months <br /> unavailable

in the 26304 hour period for a probability

of 1.81 E-2.GTG UnderQround

Cable Reliability

The underground

cables between the GTGs and the units are modeled separately

from the GTGs. The cable is not direct buried but runs in an underground

conduit. Two three phase cables are used to supply power to each unit. The failure probability

is a Bayesian updated value based on the value in IEEE Standard 500-1984, IEEE Guide to the Collection

and Presentation

of Electrical, Electronic, Sensing Component

and Mechanical

Equipment

Reliability

Data for Nuclear-Power

Generating

Stations, Institute of Electrical

and Electronics

Engineers, Inc., December 13, 1983, Reaffirmed

1991, page 770. This value is multiplied

by the length of the cable (3475' for Unit 1, See note below) obtained from the Plant Data Management

System EDB Electrical

Database, since the IEEE value is given per 1000' cable length. Based on a search of EPIX/NPRDS, Failure Data Trending, and CRDRs, there were zero cable failures since the GTGs were installed.

In the search, 4 instances

were identified (CRDRs 2559098, 2564721, 2580013, and 2843631) where the results of megger testing was less than the service criteria but greater than the emergency

criteria.

These tests had been evaluated by Maintenance

Engineering

and it was determined

that since the as-found readings were greater than the emergency

allowed value, the cables would have been able to perform their function.

Appropriate

corrective

actions were taken in each case to restore the cables such that the service criteria were met.Engineering

Support provided a Maintenance

Rule Hours in Mode Summary Report for the date range of 9/27/1993 (date of first GTG isochronous

test) through 11/30/2006.

The exposure time was taken as the time spent in Modes 1 through 6 in each unit, for an exposure time of 334,836 hours0.00968 days <br />0.232 hours <br />0.00138 weeks <br />3.18098e-4 months <br /> for the 3 units. Since there are two cables per unit, the total exposure time is 669,672 hours0.00778 days <br />0.187 hours <br />0.00111 weeks <br />2.55696e-4 months <br />. From a unit perspective, a load test powering that unit's cables from the GTGs is performed

every 18 months per 40DP-9OP06, Operations

Department

Repetitive

Task Program, Task GT002. The Bayesian updated failure rate for one cable was 1.46E-2 per hour, for a failure probability

of a standby component

of 9.59E-3. Since there are two cables, the final probability

for the underground

GTG cable was 1.91 E-2 (equivalent

to an "OR" gate).Note: A single PRA model based on Unit 1 is used at PVNGS. Plant differences

are accounted

for when performing

specific applications.

Since a continuously

energized failure rate is being applied to a cable energized

only a very short period of its exposed life, the value is very conservative

and bounds all three units.2

NRC Question 3 Describe how the PRA handles the recovery of the Auxiliary

Feedwater (AF) Train "N" pump once the GTG is on line. What dependency

exists between getting GTG alignment

and AF "N" alignment?

APS Response 3 In a Station Blackout, restoration

of a motor-driven

AFW pump after alignment

of the GTGs is required if auxiliary

feedwater

from the turbine driven pump is lost to the SGs and power is not available.

This scenario involves failure of both the Maintenance

of Vital Auxiliaries

and RCS Heat Removal safety functions.

As such, Operations

would be directed to the Functional

Recovery procedure

40EP-9EO09

for this condition.

The Control Room Supervisor

retains the option to proceed with the Blackout procedure

with the understanding

that the mitigating

strategy (restoration

of power) will resolve both failed safety functions.

The procedure

actions are similar, and both direct Operations

to initially

restore power to PBA-S03 from a GTG, after determination

that offsite power and EDGs can not be restored within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.Procedure

40EP-9EO09, Functional

Recovery, Section 8.0, Maintenance

of Vital Auxiliaries, Success path MVAC 3: GTGs, provides the instructions

to start and load the GTGs onto a Class 1E 4.16kV AC Bus. Step 8.7 directs performance

of Appendix 80"When NAN-S07 is energized, align GTG to PBA-S03 (BO)". Alternately

available

to Operations

is step 8.7.1 which directs performance

of Appendix 81 "When NAN-S07 is energized, Align GTGs to PBB-S04 (BO)". The equivalent

steps to align a GTG to a Class 1 E 4.16kV AC bus are provided in the Blackout procedure

40EP-9EO08, in steps 13 and 13.1.Standard Appendix 80 [81] (40EP-9EO10)

step 7 [9] completes

the actions necessary

to energize the Class 1 E 4.16kV AC bus PBA-S03 [PBB-S04].

At this time power is available

to start an AFW pump and initiate AFW flow to a SG. Step 9, of Appendix 80, directs an Operator [Licensed

Control Room Operator]

to check that AFA is being used to maintain at least one SG at 45%-60% NR level, else if the AFA pump is not available, then align and start AFN-P01 to restore SG level. Step 11, of Appendix 81, directs the Operator to start AFB-P01 to restore SG level.The Control Room Supervisor (CRS) has the responsibility

to manage the operator resources

during the event. The description

below reflects what would typically

be the assignments

made for power recovery and AFW recovery.

Specific assignments

may vary, but there are always two licensed control room operators

available

to perform the two main functions

of power recovery and AFW recovery without dependency

between the tasks. The tasks are also separated

in time, with power recovery required prior to AFW recovery for this scenario.

The same is true of the 4 Auxiliary

Operators.

The specific operator assigned to a task may vary, but sufficient

resources

exist to perform all the tasks without any dependency.

3

Actions necessary

to start and align the AFN-P01 pump or AFB-P01 pump are typically performed

by the Controls Operator from the Control Room. To initiate flow from the AFN-P01 pump, the Controls Operator must open the two (2) suction MOVs, open a Downcomer

Bypass MOV (one per SG), open the Downcomer

Isolation

valves (2 per SG), and start the pump. To initiate flow from the AFB-P01 pump, the Controls Operator must only start the pump, given the discharge

isolation

and regulation

valves are open due to the AFAS actuation.

The time to take these actions is less than 5 minutes.The Licensed Operators

are extensively

trained on these actions during various simulator

events. The detailed actions are not prescriptively

described

in the Emergency Operating

Procedures, but are simple and easily accomplished

by any control room operator as a result of their training.

Failure of the Controls Operator to initiate AFW flow to at least one SG would be immediately

recovered

by the Control Room Supervisor

and/or the STA. The Controls Operator typically

has no other dependent

responsibilities

for power restoration.

Initiation

of AFW for restoration

of the RCS Heat Removal safety function is the Control Operator's

primary focus, thus ample time is available

for proper diagnosis

and recovery.

The PRA does not model a specific HRA for failure to establish AFW flow after power is restored to a Class 1 E 4.16kV AC bus because the failure probability

for the AFW restoration

action is so low it is negligible

compared to the action to restore power.Recovery of the 4.16KV AC bus from a GTG is typically

performed

bythe Reactor Operator [Licensed

Control Room Operator]

with assistance

from an assigned Auxiliary Operator (AO), typically

the Area 4 AO and the Water Reclamation

Facility Operator.The assigned AO would have no responsibilities

for assisting

with the recovery of the assumed failed AFA-P01 pump, which is typically

assigned to a different

AO (Area 1).There are no required actions of the Controls Operator to support the power recovery actions, nor any actions of the Reactor Operator to support the AFW recovery actions, other than the standard actions to maintain cognizance

of critical system parameters.

No Auxiliary

Operators

are required for recovery of AFW after power has been restored to a 4.16kV AC bus. Actions to restore power and initiate AFW are considered

to have zero dependency.

NRC Question 4 Which EOP covers overriding

automatic

control (AFAS) and taking manual control of AF"A"? How soon does this happen based on simulator

experience?

This relates to the battery analysis assumption

that the AF isolation

valves do not continuously

cycle, as assumed in the design calculation.

APS Response 4 Procedure

40EP-9EO01, Standard Post Trip Actions, has the Secondary

Operator override AFAS valves to ensure feed flow is not excessive.

Operators

are trained to take manual control of the feed rate to preclude a SIAS, which would likely follow an AFAS, due to overcooling.

The operator will typically

initiate this action by starting AFA-4

P01 from control room panel B06, and establish

feed by opening the block valves and throttling

the regulation

valves. This would normally occur (assuming

a Station Blackout)

prior to an AFAS actuation.

The isolation

valves are left open and are not cycled and the only valve manipulations

are adjustments

to feed rate using the regulation

valves.In the event of an AFAS automatic

actuation, the operator will take control of feed rate, and not allow the regulation

valves to control level. The specific feed rate is not scripted, but the safety function is met when level in at least one steam generator

is increasing

towards its normal band as required by Procedure

40EP-9EO01.

Experience

in the simulator

is that operators~will

take manual control of AF in no longer than 10 minutes during a station blackout (SBO) event.Once level is recovered, the operator feeds at a rate sufficient

to makeup for level lost due to steaming out the Atmospheric

Dump Valves (ADVs).NRC Question 5 In the lower recovery path of the "Event Timelines

for Station Blackout @ t=0" slide of the presentation, APS provided times of 58 and 95 minutes for 'steam generator (SG)dryout' and 'latest SG makeup can be initiated'.

How does the PRA use these two values? What importance

is given to each value?APS Response 5 The 58 minute time is used in Loss of Offsite Power accident sequences

as the basis for the time to start and align the gas turbine generators.

The 95 minute time is not used for Loss of Offsite Power accident sequences.

The 95 minute time is used as the time available

for providing

feed to the steam generators

using the condensate

pumps for sequences

that do not include a Loss of Offsite Power. Thus the 95 minute time has no importance

in the K-1 relay significance

determination.

NRC Question 6 Provide the analysis that was done to extend the battery life from the 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> design requirement

to 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> for the PRA.APS Response 6 NUS-5058, Analysis of Station Blackout Accidents

at PVNGS-1, Yovan Lukic, NUS Corporation, November 1987, Section 4.1, "Description

of Top Events within the SBO event tree", subsection "Failure to Restore Power within 3 Hours", is the basis document for the 3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> battery life in the PVNGS PRA model. This source states: 5

Based on a review of 125 VDC bus loads typical to an SBO event and the 18 month and 60 months test of the DC batteries (Refs. 6 and 7), it is assessed that DC batteries

will last for at least 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> into an SBO event. The 60 month test established

that 1200 amp-hours

can be provided by each DC battery (PKA and PKB) before the 105 VDC battery under-voltage

condition is reached. Given a conservative

estimate of the battery loads during SBO, each battery would have to provide on the order of 1000 amp-hours

during the first 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> into an SBO event. This 20% excess in battery capacity is sufficient

to cover the power requirements

when the battery is operated at near 80% capacity (end-of-life).

It should be noted that batteries

with larger capacity (2415 amp-hours)

were installed since this change was implemented

in the PRA model.NRC Question 7 Provide updated analysis for seven hour battery capacity.APS Response 7 The updated analysis for seven hour battery capacity was provided to the NRC on January 19, 2007. This updated analysis reflects additional

capacity loss for the 'A'battery, which was recognized

following

the January 16, 2007 Regulatory

Conference.

This additional

battery capacity loss resulted in the total capacity loss being greater than 10 percent, which placed the 'A' battery in Technical

Specification

3.8.4.8, requiring

a 12 month surveillance

test, like the 'C' battery. This surveillance

test will be performed along with the 'C' battery test in the upcoming Unit 3 mid-cycle

outage. The updated analysis demonstrates

that the assumptions

for the risk significance

evaluation

remain valid, with margin.NRC Question 8 Did operator failure probabilities

for restoration

of the Emergency

Diesel Generator (EDG) include the potential

that operations

would fail to shut down the EDG as required if it started but the field did not flash, because of the lack of jacket cooling water?APS Response 8 Yes. APS considered

the operator failing to stop the EDG after the field did not flash.The step was not identified

as critical because the failure contribution

(-2E-4) was not a significant

contribution

to the total value of the HRA value for recovery of the EDG. HRA quantification

4DG-RECVR-KI-1-HR

has a value of 5.8E-2 and 4DG-RECVR-K1-7-HR

has a value of 3.2E-3 (reference

13-NS-C081, App D).6

NRC Question 9 Who is relied upon to actually recover the EDG (maintenance, operations

or engineering

personnel)?

How is that accounted

for in your results?APS Response 9 The associated

HRA credited the recovery of K-1 relay contactor

by Electrical

Maintenance

personnel

with technical

support from Electrical

Maintenance

Engineering

personnel.

Operations

would immediately

know of the EDG output failure after the engine start by control room indication/alarms

as well as by Emergency

Response Facility Data Acquisition

Display System (ERFDADS)

flat line output. Operations

would not attempt to correct this condition

since no specific proceduralized

instructions

are readily available

to them. Electrical

Maintenance

personnel

and Electrical

Maintenance

Engineering

would be immediately

called (Maintenance

onsite 24/7). Maintenance

and Engineering

would have the primary responsibility

for recovery of the affected EDG after a loss of generator

output. If not onsite, Electrical

Maintenance

Engineering

personnel would be contacted

immediately

for technical

assistance

by phone or pager. Although the faulted EDG may not be running at the time when Maintenance

and/or Engineering

become involved, Maintenance

and Engineering

personnel

would be informed that the EDG started and ran without power output. Prior plant experience

is that it takes 2-3 hours to replace the K-1 contactor.

That repair action, however, is not required because recovery can be easily accomplished

by manual bypass (opening)

of the K-1 relay contactor.

Following

the involvement

of Electrical

Maintenance

personnel

and their Engineering

support, the time required for EDG 3A loss of output diagnosis

is estimated

at 5 to 10 minutes. It is based on operating

experience

at PVNGS (including

a recent failure in Unit 3) and engineering

knowledge

that when there is no voltage buildup at all by the generator

immediately

after an engine start, the most likely cause would be a failure of the field shorting (K-1) contactor.

No immediate

indications

of a K-1 problem would exist at the EDG with it in a shutdown condition, however, the plant ERFDADS computer (powered by uninterruptible

power supply E-NQN-D01)

monitors and records the voltage and frequency

buildup for each EDG start. Those records are preserved

for several hours. A data flat line showing no attempt at all to build up generator

output voltage would be a strong indicator

of a K-1 contactor

problem. In contrast, if the generator

rotor is spinning, the K-1 has dropped out properly and field flashing fails to occur, then generator

output voltage would still build up slowly due to its residual magnetism.

With the engine in a shutdown condition, Engineering

may advise Maintenance

to functionally

test the K-1 and field flash (FF) contactors

using the Manual Field Flash 7

(MFFPB) push button on the generator

control panel as long as 135 VDC control power was still available.

One wire inside the cabinet would have to be lifted and the 135 VDC FF breaker would have to be opened prior to the manual field flash test. This functional

test was recently used (7/26/2006

3A loss of output event) to verify that a newly installed

spare K-1 was working properly.The task of establishing

EDG 3A output is considered

a recovery action consistent

with RG 1.200, Table A-1. The following

justifications

are provided:* The failed K-1 relay would very likely be bypassed rather than repaired.

Bypass is particularly

easy to perform. The fault is recoverable

by a simple manual action of releasing

the K-1 contactor

reset latch after an engine start. After the 2nd EDG 3A no output failure (9/22/06), no equipment

was required to be replaced." Ease of diagnosis

is supported

by recent similar incidents

and adequate personnel

training, which includes K-1 relays." Responsible

plant personnel

are easily accessible

by pager or telephone." Ample time is available

for diagnosis

and action to bypass the failed relay contactor." No special tools are required for diagnosis

or relay bypass manual action, and there are no issues with accessibility.

  • Plant personnel

responsible

for diagnosis

and bypass would not be subjected

to the potentially

high stress level facing the control room personnel." Flat line data for EDG voltage and frequency

on ERFDADS computer would quickly lead to the determination

that K-1 relay has malfunctioned.

NRC Question 10 Why did we not use the Unit 3 battery design calculation?

How does that affect the applicability

of the results to the Unit 3 battery?APS Response 10 The Unit 2 calculation

was used because it had been updated to reflect a number of implemented

design changes, which the existing Unit 3 calculation

had not yet incorporated.

The designs of the DC systems are quite similar in all three units, and one model was originally

used to represent

any of the units. Due to a desire to improve accuracy and the availability

of more powerful modeling tools, Palo Verde converted

the Class 1E DC system calculation

to unitized models in the mid-1 990's.A comparison

between the Unit 2 calculation

results to an updated Unit 3 computerized

model, which reflects the current configuration (though not yet finalized), was performed.

The load profiles are comparable

with only minor variations

due to nameplate

voltage ratings of motor operated valves and variations

due to differences

in cable lengths. Two of the auxiliary

feed water valves on Unit 3 were found to have lower voltages than the same valves in Unit 2, however, the valves have adequate 8

margin to accommodate

these voltage differences.

In light of the considerable

margins between the battery capacities

and the load demands of a 7-hour station blackout event (27 and 60 percent for the 'A' and 'C' batteries

respectively), the differences

between the designs of Unit 2 and 3 are insignificant

to the conclusions

of the evaluation

of the K-1 relay issue.NRC Question 11 Do the spikes in battery 'E' graph in presentation

slide "Empirical

Data 'E' Battery" correlate

with battery recharging?

APS Response 11 Yes. The first spike shown on the graph (November

7, 2004) is a result of the recharge of the battery under PMWO 2647054 and the second recharge was performed

under PMWO 2794319, on May 5, 2006.9