MONTHYEARET 06-0004, Revision to Technical Specification 5.5.9, Steam Generator Tube Surveillance Program2006-02-21021 February 2006 Revision to Technical Specification 5.5.9, Steam Generator Tube Surveillance Program Project stage: Request ML0605204202006-02-23023 February 2006 Draft RAI, Re to Be Discussed in an Upcoming Conference Call (Tac No. MC8554) Project stage: Draft RAI SBK-L-06064, License Amendment Request 06-02, Application for Technical Specification Improvement Regarding Steam Generator Integrity Using the Consolidated Line Item Improvement Process2006-03-23023 March 2006 License Amendment Request 06-02, Application for Technical Specification Improvement Regarding Steam Generator Integrity Using the Consolidated Line Item Improvement Process Project stage: Request SBK-L-06157, Response to Request for Additional Information Regarding License Amendment Request 05-08 Limited Inspection of the Steam Generator Tube Portion within the Tubesheet.2006-08-0808 August 2006 Response to Request for Additional Information Regarding License Amendment Request 05-08 Limited Inspection of the Steam Generator Tube Portion within the Tubesheet. Project stage: Response to RAI SBK-L-06166, Proprietary Information to Support Response to Request for Additional Information Re License Amendment Request 05-08, Limited Inspection of Steam Generator Tube Portion within the Tubesheet.2006-08-0808 August 2006 Proprietary Information to Support Response to Request for Additional Information Re License Amendment Request 05-08, Limited Inspection of Steam Generator Tube Portion within the Tubesheet. Project stage: Response to RAI SBK-L-06183, Revision to License Amendment Request 05-08, Limited Inspection of the Steam Generator Tube Portion within the Tubesheet, to Narrow the Scope to a One-Time Allowance2006-09-18018 September 2006 Revision to License Amendment Request 05-08, Limited Inspection of the Steam Generator Tube Portion within the Tubesheet, to Narrow the Scope to a One-Time Allowance Project stage: Request ML0625100622006-09-19019 September 2006 Westinghouse Electric Company, LLC - Request for Withholding Information from Public Disclosure for Seabrook Station, Unit No. 1 Project stage: Withholding Request Acceptance ML0627200062006-09-28028 September 2006 E-Mail, O'Keefe, Fple, to Miller, NRR, Seabrook License Amendment 05-08 Project stage: Other ML0627200042006-09-28028 September 2006 E-mail, Miller, NRR, to O'Keefe, Fple, Seabrook License Amendment Request 05-08 Project stage: Other ML0626304502006-09-29029 September 2006 Issuance of Amendment Limited Inspection of the Steam Generator Tube Portion within the Tubesheet Project stage: Approval ML0627501812006-09-29029 September 2006 Technical Specifications, Limited Inspection of the Steam Generator Tube Portion within the Tubesheet Project stage: Other ML0626502572006-10-15015 October 2006 Receipt of Draft Response to NRC Staff Clarifying Questions Related to a Request for Additional Information Project stage: Draft RAI 2006-08-08
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23156A3042023-05-31031 May 2023 Acceptance of Requested Licensing Action Amendment Request to Remove Period of Applicability from Pressure Temperature Limits and Low Temperature Over Pressure Protection Curves ML23109A1862023-04-19019 April 2023 and Turkey Point Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23066A1892023-03-0303 March 2023 OEDO-22-00419: Email Dated 3-3-2023 to Petitioner on Seabrook ASR Petition ML23066A0892023-02-24024 February 2023 OEDO-22-00419 - Email Dated 02/24/2023 to Petitioner on Seabrook Unit 1 ASR Petition ML23020A9392023-01-19019 January 2023 Acceptance of Requested Licensing Action Amendment Request to Revise Cooling Tower Service Water Loop or Cell Requirements (EPID L-2022-LLA-0183) (Email) ML23011A3082023-01-11011 January 2023 Request for Additional Information Regarding Relief Request 4RA-22-001 (L-2022-LLR-0074) ML22341A0012022-12-0606 December 2022 Acceptance of Requested Licensing Action Relief Request 4RA-22-001, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) ML22333A7452022-11-22022 November 2022 OEDO-22-00419 - Email: C-10 Response on PRB Initial Assessment - C-10 Petition on Seabrook ASR Concrete Degradation ML22287A1472022-10-13013 October 2022 2.026 Petition Screen-in Email ML22228A0552022-08-15015 August 2022 Request for Additional Information Steam Generator Tube Inspection Report Review ML22200A1082022-07-19019 July 2022 Acceptance Review for TSTF-577 Amendment ML22153A4152022-05-31031 May 2022 Request for Additional Information Re 120V Inverter LAR from TS Branch - Final ML22116A2442022-04-26026 April 2022 Acceptance of Requested Licensing Action Relief Request 3IR-18 and 3IR-19 for End of Third 10-Year ISI Interval for Examinations with Limited Coverage ML22048B5522022-02-17017 February 2022 LTR-22-0010 Reply to Geoff Gilbert Email Concern About Seabrook Station Concrete Degradation ML22062B6642022-02-0707 February 2022 Request for Additional Information 120V Inverter LAR from the Electrical Branch ML22063A0002022-01-25025 January 2022 Requests for Additional Information from Risk Branch Regarding 120V Inverter LAR ML22020A2542022-01-20020 January 2022 LTR-22-0010 Geoff Gilbert, E-mail Concern About Seabrook Station Concrete Degradation ML21097A2512021-04-0707 April 2021 Request for Additional Information Regarding Steam Generator Tube Inspection Report Review for RFO 20 (EPID L-2020-LRO-0066) (Email) ML21054A0482021-02-23023 February 2021 Request for Additional Information Regarding Heat Flux Hot Channel Requirement Amendment Request ML20343A0942020-12-0303 December 2020 Request for Additional Information Regarding Seabrook (COVID-19) Part 73 Force-on-Force Exemption Request (L-2020-LLE-0219) ML20273A2812020-09-22022 September 2020 Acceptance of Requested Licensing Action License Amendment Request to Resolve Non-Conservative Heat Flux Hot Channel Factor Requiments ML20258A1502020-09-14014 September 2020 Request for Additional Information Related to Seabrook License Amendment Request Regarding One-Time Change to the AC Sources Operating TS ML20260H4932020-09-11011 September 2020 NRR E-mail Capture - Comanche Peak - Acceptance of Requested Licensing Action - Request to Use Later Code Edition of ASME OM Code ML20230A2962020-08-14014 August 2020 Acceptance of Requested Licensing Action License Amendment Request to Allow a One-Time Change to the AC Sources Operating TS ML20167A1842020-06-11011 June 2020 Request for Additional Information Related to Seabrook License Amendment Request Regarding TSTF-411 and TSTF-418 (L-2019-LLA-0237) ML20124A0012020-05-0101 May 2020 Cancellation of Call with Seabrook on Steam Generator Tube Inspections ML20114E1592020-04-23023 April 2020 Email and Request for Additional Information Related to Seabrook License Amendment Request to Degraded Voltage Time Delay Setpoint (L-2020-LLA-0012) ML20101N0932020-04-10010 April 2020 Acceptance of Requested Licensing Action Re Relief Request to Defer ASME Inspections Due COVID-19 (EPIDs L-2020-LLR-0055, -56, and -57) ML20101L0402020-04-10010 April 2020 Acceptance of Requested Licensing Action Relief Request to Use Code Case OMN-13 with 2012 Edition of the OM Code ML20101H3912020-04-0808 April 2020 Verbal Authorization for Seabrook Relief Request 3IIR-7 ML20087K8262020-03-27027 March 2020 Upcoming Steam Generator Tube Inservice Inspection ML20063J9792020-02-28028 February 2020 Acceptance of Requested Licensing Action Amendment Request to Revise Degraded Voltage Time Delay Setpoint ML19347C6732019-12-13013 December 2019 Acceptance of Requested Licensing Action Amendment Request to Adopt TSTF-418 ML19296D9122019-10-23023 October 2019 NRR E-mail Capture - Request for Additional Information Related to Seabrook Inverter Amendment (L-2019-LLA-0216) ML19295F5422019-10-15015 October 2019 NRR E-mail Capture - Seabrook Station, Unit No. 1 - Acceptance of Requested Licensing Action Amendment Request to Revise Onsite Power Distribution Requirements ML19275G7832019-10-0101 October 2019 Limited Appearance Statement from New Hampshire State Representative, Robert Harb Regarding the Seabrook Station Unit 1 License Amendment Application ML19270E6512019-09-27027 September 2019 Limited Appearance Statement from Joanna Hammond Regarding the Seabrook Station Unit 1 License Amendment Application ML19270E6542019-09-26026 September 2019 Limited Appearance Statement from Brian Campbell Regarding the Seabrook Station Unit 1 License Amendment Application ML19196A3592019-07-15015 July 2019 NRR E-mail Capture - Seabrook Station, Unit No. 1 - Acceptance of Requested Licensing Action Amendment Request to Revise the Emergency Core Cooling System Accumulator Technical Specifications ML19169A2412019-06-13013 June 2019 NRR E-mail Capture - Seabrook Station, Unit No. 1 - Acceptance of Requested Licensing Action Relief Requests for the Containment Building Spray Pump Flow and Vibration Testing (Epids L-2019-LLR-00 and L-2019-LLR-00) ML19162A0662019-06-0404 June 2019 Reply to Mr. Rick Jakious'S E-mail of 5-29-2019 to Stephen B. Comley Sr., We the People with Attachments ML19112A1782019-04-22022 April 2019 NRR E-mail Capture - Point Beach; Seabrook; Turkey Point - Acceptance of Requested Licensing Action Amendment Request to Revise Technical Specifications to Adopt TSTF-563 ML19101A4042019-04-11011 April 2019 NRR E-mail Capture - Point Beach; Seabrook; St. Lucie; Turkey Point - Acceptance of Licensing Action Relief Request to Use Encoded Phased Array Ultrasonic Examination Techniques for Ferritic and Austenitic Welds ML19070A2382019-03-10010 March 2019 LTR-19-0088 Maura Healey, Attorney General, the Commonwealth of Massachusetts, Ltr NextEras Requests for a License Amendment and Twenty-year Extension Prior to Issuance of a Final Decision in Adjudicatory Hearing on Concrete Degradation at ML19056A4522019-02-25025 February 2019 Comment from Philip Hurzeler Regarding the Emergency Petition Filed by C-10 on February 13, 2019 ML19056A4582019-02-25025 February 2019 Comment from Deborah A. Jones Regarding the Emergency Petition Filed by C-10 on February 13, 2019 ML19056A4602019-02-25025 February 2019 Comment from Lisa Conti Regarding the Emergency Petition Filed by C-10 on February 13, 2019 ML19050A2212019-02-19019 February 2019 NRR E-mail Capture - Seabrook Station, Unit No. 1 - Acceptance of Requested Licensing Action Relief Request Proposed Alternative 3IR-17 Implementation of an Extended Reactor Vessel Inservice Inspection Interval ML19050A3202019-02-13013 February 2019 Package from Stephen B. Comley, Sr. at February 13, 2019 Seabrook Station, Unit 1, Public Meeting 2023-06-22
[Table view] |
Text
From: <michael_okeefe@fpl.com>To:<GXM@nrc.gov>Date: 09/28/2006 4:24:13 PM
Subject:
Re: LAR 05-08 Ed, FPL Energy Seabrook LLC concurs with the proposed license condition tolimit primary-to-secondary leakage to 150 gallons per day per steam generator and if the limit is exceeded to take appropriate action in accordance with Technical Specification 3.4.6.2, Reactor Coolant SystemLeakage."Mike O'KeefeFPLE Seabrook Regulatory Compliance Supervisor 603-773-7745 (office) 603-771-7939 (pager) 765-6319 (cell)
"Ed Miller"
<GXM@nrc.gov> To: michael_okeefe@fpl.com
cc:
09/28/2006 03:04
Subject:
LAR 05-08
PM
Mike, Currently, FPLE procedurally limits operational primary-to-secondary leakage to 150 gallons per day (gpd) per Steam Generator (SG) compared to the Technical Specification (TS) limit of 500 gpd per SG. Upon further review, the staff determined that this procedural restriction needs to be contained in a license condition stating that FPLE will maintain theoperational limit of primary-to-secondary leakage at 150 gpd per SG and if this limit is exceeded, Seabrook will take the appropriate actions inaccordance with TS 3.4.6.2, "Reactor Coolant System Leakage." An e-mail, to be docketed, confirming the acceptability of this condition will besufficient.G. Edward MillerProject Manager Division of Operating Reactor Licensing U.S. Nuclear Regulatory Commission (301) 415-2481 Mail Envelope Properties(451C2F61.42C : 22 : 21548)
Subject:
Re: LAR 05-08Creation Date 09/28/2006 4:25:39 PMFrom: <michael_okeefe@fpl.com>Created By:michael_okeefe@fpl.comRecipientsnrc.gov TWGWPO01.HQGWDO01 GXM (Ed Miller)Post OfficeRoute TWGWPO01.HQGWDO01nrc.govFilesSizeDate & Time MESSAGE230609/28/2006 4:25:39 PM Mime.8223683Options Expiration Date:None Priority:Standard ReplyRequested:
No Return Notification:None Concealed
Subject:
No Security:StandardJunk Mail Handling Evaluation Results Message is eligible for Junk Mail handling This message was not classified as Junk MailJunk Mail settings when this message was delivered Junk Mail handling disabled by User Junk Mail handling disabled by Administrator Junk List is not enabled Junk Mail using personal address books is not enabled Block List is not enabled