{{#Wiki_filter:GTST AP1000-P08-3.5.8, Rev. 1 Advanced Passive 1000 (AP1000)
{{#Wiki_filter:GTST AP1000- P08-3.5.8, Rev. 1
 
Advanced Passive 1000 (AP1000)
Generic Technical Specification Traveler (GTST)
Generic Technical Specification Traveler (GTST)


==Title:==
==Title:==
Changes Related to LCO 3.5.8, In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6 I. Technical Specifications Task Force (TSTF) Travelers, Approved Since Revision 2 of STS NUREG-1431, and Used to Develop this GTST TSTF Number and
Changes Related to LCO 3.5.8, In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6
 
I. Technical Specifications Task Force (TSTF) Travelers, Approved Since Revision 2 of STS NUREG-1431, and Used to Develop this GTST
 
TSTF Number and


==Title:==
==Title:==
TSTF-425, Rev. 3,   Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5b TSTF-523, Rev. 2,   Generic Letter 2008-01, Managing Gas Accumulation STS NUREGs Affected:
TSTF-425, Rev. 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5b TSTF-523, Rev. 2, Generic Letter 2008- 01, Managing Gas Accumulation
TSTF-425, Rev. 3:   NUREG-1430, 1431, 1432, 1433, 1434 TSTF-523, Rev. 2:   NUREG-1430, 1431, 1432, 1433, 1434 NRC Approval Date:
 
TSTF-425, Rev. 3:   06-Jul-09 TSTF-523, Rev. 2:   23-Dec-13 TSTF Classification:
STS NUREGs Affected:
TSTF-425, Rev. 3:   Technical Change TSTF-523, Rev. 2:   Technical Change Date report generated:
 
Monday, April 20, 2015                                                                 Page 1
TSTF-425, Rev. 3: NUREG-1430, 1431, 1432, 1433, 1434 TSTF-523, Rev. 2: NUREG-1430, 1431, 1432, 1433, 1434
 
NRC Approval Date:
 
TSTF-425, Rev. 3: 06-Jul-09 TSTF-523, Rev. 2: 23-Dec-13
 
TSTF Classification:
 
TSTF-425, Rev. 3: Technical Change TSTF-523, Rev. 2: Technical Change
 
Date report generated:
Monday, April 20, 2015 Page 1 GTST AP1000- P08-3.5.8, Rev. 1


GTST AP1000-P08-3.5.8, Rev. 1 II. Reference Combined License (RCOL) Standard Departures (Std. Dep.), RCOL COL Items, and RCOL Plant-Specific Technical Specifications (PTS) Changes Used to Develop this GTST RCOL Std. Dep. Number and
II. Reference Combined License (RCOL) Standard Departures (Std. Dep.), RCOL COL Items, and RCOL Plant-Specific Technical Specifications (PTS) Changes Used to Develop this GTST
 
RCOL Std. Dep. Number and


==Title:==
==Title:==
None RCOL COL Item Number and
None
 
RCOL COL Item Number and


==Title:==
==Title:==
None RCOL PTS Change Number and
None
 
RCOL PTS Change Number and


==Title:==
==Title:==
VEGP LAR DOC A031:     Required Action revision for Condition with single MODE applicability VEGP LAR DOC A078:     Borated water volume designation revision VEGP LAR DOC A079:     IRWST SR Frequency revision VEGP LAR DOC A081:     TS 3.5.8 Condition F revision VEGP LAR DOC L01:       Added SR for valve actuation VEGP LAR DOC L17:       Revisions to Actions and SRs associated with noncondensible gases Date report generated:
VEGP LAR DOC A031: Required Action revision for Condition with single MODE applicability VEGP LAR DOC A078: Borated water volume designation revision VEGP LAR DOC A079: IRWST SR Frequency revision VEGP LAR DOC A081: TS 3.5.8 Condition F revision VEGP LAR DOC L01: Added SR for valve actuation VEGP LAR DOC L17: Revisions to Actions and SRs associated with noncondensible gases
Monday, April 20, 2015                                                               Page 2
 
Date report generated:
Monday, April 20, 2015 Page 2 GTST AP1000- P08-3.5.8, Rev. 1
 
III. Comments on Relations Among TSTFs, RCOL Std. Dep., RCOL COL Items, and RCOL PTS Changes
 
This section discusses the considered changes that are: (1) applicable to operating reactor designs, but not to the AP1000 design; (2) already incorporated in the GTS; or (3) superseded by another change.


GTST AP1000-P08-3.5.8, Rev. 1 III. Comments on Relations Among TSTFs, RCOL Std. Dep., RCOL COL Items, and RCOL PTS Changes This section discusses the considered changes that are: (1) applicable to operating reactor designs, but not to the AP1000 design; (2) already incorporated in the GTS; or (3) superseded by another change.
TSTF-425 is deferred for future consideration.
TSTF-425 is deferred for future consideration.
TSTF-523, Rev. 1 is not applicable to the GTS. The issues of gas accumulation have been addressed by GTS Rev.19.
TSTF-523, Rev. 1 is not applicable to the GTS. The issues of gas accumulation have been addressed by GTS Rev.19.
VEGP LAR DOC A078 revises the third entry statement for Condition D of TS 3.5.8 by changing the IRWST borated water volume from a percent range of < 100% and > 97% to a specific range of 73,100 cu. ft. and > 70,907 cu. ft. A proposed additional change corrects cu. ft. to cu ft.
 
VEGP LAR DOC A078 revises the third entry statement for Condition D of TS 3.5.8 by changing the IRWST borated water volume from a percent range of < 100% and > 97% to a specific range of 73,100 cu. ft. and > 70,907 cu. ft. A proposed additional change corrects cu. ft. to cu ft.
 
Date report generated:
Date report generated:
Monday, April 20, 2015                                                                     Page 3
Monday, April 20, 2015 Page 3 GTST AP1000- P08-3.5.8, Rev. 1
 
IV. Additional Changes Proposed as Part of this GTST (modifications proposed by NRC staff and/or clear editorial changes or deviations identified by preparer of GTST)


GTST AP1000-P08-3.5.8, Rev. 1 IV. Additional Changes Proposed as Part of this GTST (modifications proposed by NRC staff and/or clear editorial changes or deviations identified by preparer of GTST)
The Bases for Required Action B.1 and C.1 of TS 3.5.8 is revised for consistency with VEGP LAR DOC L17 changes to Required Action B.1 and C.1 of TS 3.5.8.
The Bases for Required Action B.1 and C.1 of TS 3.5.8 is revised for consistency with VEGP LAR DOC L17 changes to Required Action B.1 and C.1 of TS 3.5.8.
The Bases for SR 3.5.8.2 is revised by correcting the word intitial to initial.
The Bases for SR 3.5.8.2 is revised by correcting the word intitial to initial.
Condition D and SR 3.5.8.2 are revised to delete the periods from cu. ft.
Condition D and SR 3.5.8.2 are revised to delete the periods from cu. ft.
APOG Recommended Changes to Improve the Bases An editorial change is made to the Actions section of the Bases, under heading A.1. The change clarifies and corrects the first use of the acronym ECCS by using the full phrase emergency core cooling system and deleting system after ECCS.
 
APOG Recommended Changes to Improve the Bases
 
An editorial change is made to the Actions section of the Bases, under heading A.1. The change clarifies and corrects the first use of the acronym ECCS by using the full phrase emergency core cooling system and deleting system after ECCS.
 
An editorial change is made to the Actions section of the Bases, under heading B.1. The change corrects the first use of the acronym DVI by using the full phrase direct vessel injection.
An editorial change is made to the Actions section of the Bases, under heading B.1. The change corrects the first use of the acronym DVI by using the full phrase direct vessel injection.
An editorial change is made to the Actions section of the Bases, under heading D.1. The change corrects the first use of the acronym PRA by using the full phrase probabilistic risk assessment and DBAs by using the full phrase design basis accidents. The change also clarifies the assumed number of failed boron injection sources (CMTs and Accumulators).
An editorial change is made to the Actions section of the Bases, under heading D.1. The change corrects the first use of the acronym PRA by using the full phrase probabilistic risk assessment and DBAs by using the full phrase design basis accidents. The change also clarifies the assumed number of failed boron injection sources (CMTs and Accumulators).
Revise the Actions section of the Bases, under heading F.1 and F.2 statement withdrawal of reactivity control assemblies to withdrawal of control rods for editorial improvement and consistency with other TS Bases discussions.
Revise the Actions section of the Bases, under heading F.1 and F.2 statement withdrawal of reactivity control assemblies to withdrawal of control rods for editorial improvement and consistency with other TS Bases discussions.
In the Surveillance Requirements section of the Bases, under heading SR 3.5.8.3, change
In the Surveillance Requirements section of the Bases, under heading SR 3.5.8.3, change
...solution volume increase 15,000 gal. to ...combined volume increase 15,000 gal. In addition, change the SR 3.5.8.3 Frequency from ...solution volume increase 15,000 gal to
...solution volume increase 15,000 gal. to...combined volume increase 15,000 gal. In addition, change the SR 3.5.8.3 Frequency from...solution volume increase 15,000 gal to
...combined volume increase 15,000 gal.
...combined volume increase 15,000 gal.
 
Date report generated:
Date report generated:
Monday, April 20, 2015                                                                       Page 4
Monday, April 20, 2015 Page 4 GTST AP1000- P08-3.5.8, Rev. 1
 
V. Applicability
 
Affected Generic Technical Specifications and Bases:
 
Section 3.5.8, In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6
 
Changes to the Generic Technical Specifications and Bases:


GTST AP1000-P08-3.5.8, Rev. 1 V. Applicability Affected Generic Technical Specifications and Bases:
Section 3.5.8, In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6 Changes to the Generic Technical Specifications and Bases:
Condition B of TS 3.5.8 is revised from Required IRWST injection line inoperable due to presence of noncondensible gases in one high point vent. to Required IRWST injection flow path with noncondensible gas volume in one squib valve outlet line pipe stub not within limit.
Condition B of TS 3.5.8 is revised from Required IRWST injection line inoperable due to presence of noncondensible gases in one high point vent. to Required IRWST injection flow path with noncondensible gas volume in one squib valve outlet line pipe stub not within limit.
The Required Action B.1 is revised from Vent noncondensible gases. to Restore noncondensible gas volume in squib valve outlet line pipe stub to within limit. (DOC L17)
The Required Action B.1 is revised from Vent noncondensible gases. to Restore noncondensible gas volume in squib valve outlet line pipe stub to within limit. (DOC L17)
Condition C of TS 3.5.8 is revised from Required IRWST injection line inoperable due to presence of noncondensible gases in both high point vents. to Required IRWST injection flow path with noncondensible gas volume in both squib valve outlet line pipe stubs not within limit.
Condition C of TS 3.5.8 is revised from Required IRWST injection line inoperable due to presence of noncondensible gases in both high point vents. to Required IRWST injection flow path with noncondensible gas volume in both squib valve outlet line pipe stubs not within limit.
The Required Action C.1 is revised from Vent noncondensible gases from one high point vent.
The Required Action C.1 is revised from Vent noncondensible gases from one high point vent.
to Restore noncondensible gas volume in one squib valve outlet line pipe stub to within limit.
to Restore noncondensible gas volume in one squib valve outlet line pipe stub to within limit.
(DOC L17)
(DOC L17)
The third entry statement for Condition D of TS 3.5.8 is revised by replacing the IRWST borated water volume specified as a percent with cubic feet. (DOC A078)
The third entry statement for Condition D of TS 3.5.8 is revised by replacing the IRWST borated water volume specified as a percent with cubic feet. (DOC A078)
Condition D and SR 3.5.8.2 of TS 3.5.8 is revised to correct cu. ft. to cu ft. (proposed additional change)
Condition D and SR 3.5.8.2 of TS 3.5.8 is revised to correct cu. ft. to cu ft. (proposed additional change)
The first entry statement for Condition F of TS 3.5.8 is revised by specifying the applicable Conditions. The associated Actions section of the Bases is also revised. (DOC A081)
The first entry statement for Condition F of TS 3.5.8 is revised by specifying the applicable Conditions. The associated Actions section of the Bases is also revised. (DOC A081)
Required Action F.1 of TS 3.5.8 is revised by deleting the requirement to be in MODE 6. (DOC A031)
Required Action F.1 of TS 3.5.8 is revised by deleting the requirement to be in MODE 6. (DOC A031)
SR 3.5.8.3 second Frequency is revised by changing the ...solution volume increase of 15,000 gal to ...solution volume increase of 15,000 gal. The associated Bases for SR 3.5.8.3 is also revised. (DOC A079)
 
SR 3.5.8.3 second Frequency is revised by changing the...solution volume increase of 15,000 gal to...solution volume increase of 15,000 gal. The associated Bases for SR 3.5.8.3 is also revised. (DOC A079)
 
SR 3.5.8.4 is revised to address the new SR 3.5.6.9 by adding the renumbered SR 3.5.6.11.
SR 3.5.8.4 is revised to address the new SR 3.5.6.9 by adding the renumbered SR 3.5.6.11.
The associated Bases for SR 3.5.4.8 are also revised. (DOC L01)
The associated Bases for SR 3.5.4.8 are also revised. (DOC L01)
The LCO section of the Bases of TS 3.5.8 is revised by adding discussion of noncondensible gas accumulation in the injection line high point. (DOC L17)
The LCO section of the Bases of TS 3.5.8 is revised by adding discussion of noncondensible gas accumulation in the injection line high point. (DOC L17)
In the Actions section of the Bases, under heading A.1 the last sentence is revised by changing ECCS system to emergency core cooling system (ECCS). (APOG Comment)
In the Actions section of the Bases, under heading A.1 the last sentence is revised by changing ECCS system to emergency core cooling system (ECCS). (APOG Comment)
In the Actions section of the Bases, under heading B.1 use of the acronym DVI is changed to direct vessel injection (DVI). (APOG Comment)
In the Actions section of the Bases, under heading B.1 use of the acronym DVI is changed to direct vessel injection (DVI). (APOG Comment)
The Bases for Required Action B.1 and C.1 of TS 3.5.8 is revised by changing high point vents to injection flow path squib valve outlet line pipe stubs. (proposed additional change)
The Bases for Required Action B.1 and C.1 of TS 3.5.8 is revised by changing high point vents to injection flow path squib valve outlet line pipe stubs. (proposed additional change)
Date report generated:
Date report generated:
Monday, April 20, 2015                                                                       Page 5
Monday, April 20, 2015 Page 5 GTST AP1000- P08-3.5.8, Rev. 1
 
In the Actions section of the Bases, under heading D.1 the fourth sentence is revised by changing PRA to probabilistic risk assessment (PRA) and clarifying the assumed number of failed boron injection sources (CMTs and Accumulators). Under heading D.1 the last sentence is revised by changing DBAs to design basis accidents (DBAs). (APOG Comment)


GTST AP1000-P08-3.5.8, Rev. 1 In the Actions section of the Bases, under heading D.1 the fourth sentence is revised by changing PRA to probabilistic risk assessment (PRA) and clarifying the assumed number of failed boron injection sources (CMTs and Accumulators). Under heading D.1 the last sentence is revised by changing DBAs to design basis accidents (DBAs). (APOG Comment)
In the Actions section of the Bases, under heading F.1 and F.2, second paragraph, fourth sentence is revised from withdrawal of reactivity control assemblies to withdrawal of control rods. (APOG Comment)
In the Actions section of the Bases, under heading F.1 and F.2, second paragraph, fourth sentence is revised from withdrawal of reactivity control assemblies to withdrawal of control rods. (APOG Comment)
The Bases for SR 3.5.8.2 is revised by correcting intitial to initial. (proposed additional change)
The Bases for SR 3.5.8.2 is revised by correcting intitial to initial. (proposed additional change)
The Surveillance Requirements section of the Bases, under heading SR 3.5.8.3, is revised from ...solution volume increase 15,000 gal. to ...combined volume increase 15,000 gal.
 
In addition, SR 3.5.8.3 Frequency is revised from ...solution volume increase 15,000 gal to
The Surveillance Requirements section of the Bases, under heading SR 3.5.8.3, is revised from...solution volume increase 15,000 gal. to...combined volume increase 15,000 gal.
...combined volume increase 15,000 gal. (APOG Comment)
In addition, SR 3.5.8.3 Frequency is revised from...solution volume increase 15,000 gal to
...combined volume increase 15,000 gal. (APOG Comment)
 
Date report generated:
Date report generated:
Monday, April 20, 2015                                                                         Page 6
Monday, April 20, 2015 Page 6 GTST AP1000- P08-3.5.8, Rev. 1
 
VI. Traveler Information
 
Description of TSTF changes:
 
None
 
Rationale for TSTF changes:
 
None
 
Description of changes in RCOL Std. Dep., RCOL COL Item(s), and RCOL PTS Changes:
 
VEGP LAR DOC A031 revises Required Action F.1 of TS 3.5.8 from Initiate action to be in MODE 6 with the water level 23 feet above the top of the reactor vessel flange. to Initiate action to establish water level 23 feet above the top of the reactor vessel flange.
 
VEGP LAR DOC A078 revises the third entry statement for Condition D of TS 3.5.8 by changing the IRWST borated water volume from a percent range of < 100% and > 97% to a specific range of 73,100 cu. ft. and > 70,907 cu. ft.
 
VEGP LAR DOC A079 revises the second Frequency for SR 3.5.8.3 from...solution volume increase of 15,000 gal to...solution volume increase of 15,000 gal. The associated Bases for SR 3.5.8.3 is also revised.


GTST AP1000-P08-3.5.8, Rev. 1 VI. Traveler Information Description of TSTF changes:
None Rationale for TSTF changes:
None Description of changes in RCOL Std. Dep., RCOL COL Item(s), and RCOL PTS Changes:
VEGP LAR DOC A031 revises Required Action F.1 of TS 3.5.8 from Initiate action to be in MODE 6 with the water level  23 feet above the top of the reactor vessel flange. to Initiate action to establish water level  23 feet above the top of the reactor vessel flange.
VEGP LAR DOC A078 revises the third entry statement for Condition D of TS 3.5.8 by changing the IRWST borated water volume from a percent range of < 100% and > 97% to a specific range of  73,100 cu. ft. and > 70,907 cu. ft.
VEGP LAR DOC A079 revises the second Frequency for SR 3.5.8.3 from ...solution volume increase of 15,000 gal to ...solution volume increase of  15,000 gal. The associated Bases for SR 3.5.8.3 is also revised.
VEGP LAR DOC A081 revises Condition F of TS 3.5.8 by specifying the Conditions that are applicable to the first entry statement.
VEGP LAR DOC A081 revises Condition F of TS 3.5.8 by specifying the Conditions that are applicable to the first entry statement.
VEGP LAR DOC L01 revises SR 3.5.8.4 by adding the renumbered SR 3.5.6.11 to the listing of applicable SRs. Also, the Bases for SR 3.5.8.4 is revised.
VEGP LAR DOC L01 revises SR 3.5.8.4 by adding the renumbered SR 3.5.6.11 to the listing of applicable SRs. Also, the Bases for SR 3.5.8.4 is revised.
VEGP LAR DOC L17 revises Condition B of TS 3.5.8 from Required IRWST injection line inoperable due to presence of noncondensible gases in one high point vent. to Required IRWST injection flow path with noncondensible gas volume in one squib valve outlet line pipe stub not within limit. The Required Action B.1 is revised from Vent noncondensible gases. to Restore noncondensible gas volume in squib valve outlet line pipe stub to within limit.
VEGP LAR DOC L17 revises Condition B of TS 3.5.8 from Required IRWST injection line inoperable due to presence of noncondensible gases in one high point vent. to Required IRWST injection flow path with noncondensible gas volume in one squib valve outlet line pipe stub not within limit. The Required Action B.1 is revised from Vent noncondensible gases. to Restore noncondensible gas volume in squib valve outlet line pipe stub to within limit.
Condition C of TS 3.5.8 is revised from Required IRWST injection line inoperable due to presence of noncondensible gases in both high point vents. to Required IRWST injection flow path with noncondensible gas volume in both squib valve outlet line pipe stubs not within limit.
Condition C of TS 3.5.8 is revised from Required IRWST injection line inoperable due to presence of noncondensible gases in both high point vents. to Required IRWST injection flow path with noncondensible gas volume in both squib valve outlet line pipe stubs not within limit.
Line 106: Line 184:
to Restore noncondensible gas volume in one squib valve outlet line pipe stub to within limit.
to Restore noncondensible gas volume in one squib valve outlet line pipe stub to within limit.
The associated Actions section of the Bases is also revised.
The associated Actions section of the Bases is also revised.
Date report generated:
Date report generated:
Monday, April 20, 2015                                                                       Page 7
Monday, April 20, 2015 Page 7 GTST AP1000- P08-3.5.8, Rev. 1
 
Rationale for changes in RCOL Std. Dep., RCOL COL Item(s), and RCOL PTS Changes:


GTST AP1000-P08-3.5.8, Rev. 1 Rationale for changes in RCOL Std. Dep., RCOL COL Item(s), and RCOL PTS Changes:
VEGP LAR DOC A031 changes to Required Action F.1 of TS 3.5.8 enhance TS clarity by deleting the reference to MODE 6 from the Required Action. TS 3.5.8 is applicable only in MODE 6 and is not necessary to refer to that mode in the associated Required Actions.
VEGP LAR DOC A031 changes to Required Action F.1 of TS 3.5.8 enhance TS clarity by deleting the reference to MODE 6 from the Required Action. TS 3.5.8 is applicable only in MODE 6 and is not necessary to refer to that mode in the associated Required Actions.
VEGP LAR DOC A078 changes to the third entry statement for Condition D of TS 3.5.8 and provides clarity by changing the IRWST borated water volume in units of cubic feet. Changing the volume unit of measure to cubic feet aligns with SR 3.5.8.2.
VEGP LAR DOC A078 changes to the third entry statement for Condition D of TS 3.5.8 and provides clarity by changing the IRWST borated water volume in units of cubic feet. Changing the volume unit of measure to cubic feet aligns with SR 3.5.8.2.
VEGP LAR DOC A079 changes to the second Frequency for SR 3.5.8.3 clarifies the requirement is also applicable to solution volume increase greater than 15,000 gallons.
VEGP LAR DOC A079 changes to the second Frequency for SR 3.5.8.3 clarifies the requirement is also applicable to solution volume increase greater than 15,000 gallons.
VEGP LAR DOC A081 changes to the first entry statement for Condition F of TS 3.5.8 provide clarification by specifying the applicable Conditions.
VEGP LAR DOC A081 changes to the first entry statement for Condition F of TS 3.5.8 provide clarification by specifying the applicable Conditions.
VEGP LAR DOC L01 change to SR 3.5.8.4 by adding the renumbered SR 3.5.6.11 to the listing of applicable SRs is an editorial change due to changes to TS 3.5.6.
VEGP LAR DOC L01 change to SR 3.5.8.4 by adding the renumbered SR 3.5.6.11 to the listing of applicable SRs is an editorial change due to changes to TS 3.5.6.
VEGP LAR DOC L17 changes TS 3.5.8 Condition B and C entry statements and LCO section of the Bases for consistency with LCO section of the Bases of TS 3.5.6. The changes to TS 3.5.8 Required Action B.1 and C.1 are for consistency with changes made to the associated entry conditions.
VEGP LAR DOC L17 changes TS 3.5.8 Condition B and C entry statements and LCO section of the Bases for consistency with LCO section of the Bases of TS 3.5.6. The changes to TS 3.5.8 Required Action B.1 and C.1 are for consistency with changes made to the associated entry conditions.
Description of additional changes proposed by NRC staff/preparer of GTST:
Description of additional changes proposed by NRC staff/preparer of GTST:
The Bases for Required Action B.1 and C.1 of TS 3.5.8 is revised by changing high point vents to injection flow path squib valve outlet line pipe stubs.
The Bases for Required Action B.1 and C.1 of TS 3.5.8 is revised by changing high point vents to injection flow path squib valve outlet line pipe stubs.
The Bases for SR 3.5.8.2 is revised by correcting the word intitial to initial.
The Bases for SR 3.5.8.2 is revised by correcting the word intitial to initial.
Condition D and SR 3.5.8.2 of TS 3.5.8 is revised to correct cu. ft. to cu ft.
Condition D and SR 3.5.8.2 of TS 3.5.8 is revised to correct cu. ft. to cu ft.
The phrase ECCS system is clarified and corrected to emergency core cooling system (ECCS) in the Actions section of the Bases, under heading A.1. (APOG Comment)
The phrase ECCS system is clarified and corrected to emergency core cooling system (ECCS) in the Actions section of the Bases, under heading A.1. (APOG Comment)
The first use of acronym DVI is corrected to direct vessel injection (DVI) in the Actions section of the Bases, under heading B.1. (APOG Comment)
The first use of acronym DVI is corrected to direct vessel injection (DVI) in the Actions section of the Bases, under heading B.1. (APOG Comment)
The acronym PRA is corrected to include the phrase probabilistic risk assessment before (PRA) and DBAs is corrected to include the phrase design basis accidents before (DBAs) in the Actions section of the Bases, under heading D.1. In addition, the assumed number of failed boron injection sources (CMTs and Accumulators) is clarified in the Actions section of the Bases, under heading D.1. (APOG Comment)
The acronym PRA is corrected to include the phrase probabilistic risk assessment before (PRA) and DBAs is corrected to include the phrase design basis accidents before (DBAs) in the Actions section of the Bases, under heading D.1. In addition, the assumed number of failed boron injection sources (CMTs and Accumulators) is clarified in the Actions section of the Bases, under heading D.1. (APOG Comment)
In the Actions section of the Bases, under heading F.1 and F.2, second paragraph, fourth sentence is revised from withdrawal of reactivity control assemblies to withdrawal of control rods. (APOG Comment)
In the Actions section of the Bases, under heading F.1 and F.2, second paragraph, fourth sentence is revised from withdrawal of reactivity control assemblies to withdrawal of control rods. (APOG Comment)
The second Frequency for SR 3.5.8.3 and Surveillance Requirements section of the Bases, under heading SR 3.5.8.3, is revised from ...solution volume increase 15,000 gal to
 
...combined volume increase 15,000 gal. (APOG Comment)
The second Frequency for SR 3.5.8.3 and Surveillance Requirements section of the Bases, under heading SR 3.5.8.3, is revised from...solution volume increase 15,000 gal to
...combined volume increase 15,000 gal. (APOG Comment)
 
Date report generated:
Date report generated:
Monday, April 20, 2015                                                                       Page 8
Monday, April 20, 2015 Page 8 GTST AP1000- P08-3.5.8, Rev. 1
 
Rationale for additional changes proposed by NRC staff/preparer of GTST:


GTST AP1000-P08-3.5.8, Rev. 1 Rationale for additional changes proposed by NRC staff/preparer of GTST:
The Bases for Required Action B.1 and C.1 of TS 3.5.8 is changed to provide consistency with VEGP LAR DOC L17 changes to Required Action B.1 and C.1. The change is also consistent with VEGP LAR DOC L17 changes to the Bases for Required Action B.1 and C.1 of TS 3.5.7, which are identical to Required Action B.1 and C.1 of TS 3.5.8.
The Bases for Required Action B.1 and C.1 of TS 3.5.8 is changed to provide consistency with VEGP LAR DOC L17 changes to Required Action B.1 and C.1. The change is also consistent with VEGP LAR DOC L17 changes to the Bases for Required Action B.1 and C.1 of TS 3.5.7, which are identical to Required Action B.1 and C.1 of TS 3.5.8.
Spelling correction in the Bases for SR 3.5.8.2 is an editorial change.
Spelling correction in the Bases for SR 3.5.8.2 is an editorial change.
Changing cu. ft. to cu ft is an editorial correction. The change is in accordance with section 3.3.4.d of writer's guide TST-GG-05-01.
Changing cu. ft. to cu ft is an editorial correction. The change is in accordance with section 3.3.4.d of writer's guide TST-GG-05-01.
The change from ECCS system to emergency core cooling system (ECCS) is an editorial clarification and the correction is in conformance with TSTF-GG-05-01, section 3.2.2.a.
 
The change from DVI to direct vessel injection (DVI) is an editorial correction in conformance with TSTF-GG-05-01, section 3.2.2.a.
The change from ECCS system to emergency core cooling system (ECCS) is an editorial clarification and the correction is in conformance with TSTF-GG 01, section 3.2.2.a.
The change from PRA to probabilistic risk assessment (PRA) and DBAs to design basis accidents (DBAs) are editorial correction in conformance with TSTF-GG-05-01, section 3.2.2.a and the change to the discussion of the assumed number of failed boron injection sources (CMTs and Accumulators) is an editorial clarification.
 
The change from DVI to direct vessel injection (DVI) is an editorial correction in conformance with TSTF-GG 01, section 3.2.2.a.
 
The change from PRA to probabilistic risk assessment (PRA) and DBAs to design basis accidents (DBAs) are editorial correction in conformance with TSTF-GG- 05-01, section 3.2.2.a and the change to the discussion of the assumed number of failed boron injection sources (CMTs and Accumulators) is an editorial clarification.
 
The change from reactivity control assemblies to control rods in the Actions section of the Bases is for editorial improvement and consistency with other TS Bases discussions.
The change from reactivity control assemblies to control rods in the Actions section of the Bases is for editorial improvement and consistency with other TS Bases discussions.
The change from ...solution volume increase 15,000 gal to ...combined volume increase 15,000 gal is a non-technical change that provides improved clarity, consistency, and operator usability.
 
The change from...solution volume increase 15,000 gal to...combined volume increase 15,000 gal is a non-technical change that provides improved clarity, consistency, and operator usability.
 
Date report generated:
Date report generated:
Monday, April 20, 2015                                                                       Page 9
Monday, April 20, 2015 Page 9 GTST AP1000- P08-3.5.8, Rev. 1
 
VII. GTST Safety Evaluation
 
Technical Analysis:


GTST AP1000-P08-3.5.8, Rev. 1 VII. GTST Safety Evaluation Technical Analysis:
VEGP LAR DOC L17: As stated in the associated Bases for the GTS 3.5.8 Actions, the presence of some noncondensible gases does not mean that the CMT is immediately inoperable, but that gases are collecting and should be vented. TS 3.5.8, Condition B and C are revised for consistency.
VEGP LAR DOC L17: As stated in the associated Bases for the GTS 3.5.8 Actions, the presence of some noncondensible gases does not mean that the CMT is immediately inoperable, but that gases are collecting and should be vented. TS 3.5.8, Condition B and C are revised for consistency.
GTS 3.5.8, Required Action B.1 and C.1 are revised to replace a specific method of restoration with a more general action to restore the parameter, in this case noncondensible gas volume, to within its limit. This change is made for consistency with the revised entry conditions associated with the Required Action. Only the specific method is deleted from the action. The associated Bases, both GTS and revised, describe an appropriate method for restoration. The revised Action continues to provide assurance that operation with a noncondensible gas volume that can affect the associated flow path is allowed for only a limited period of time. These changes are designated as less restrictive because the specific method of restoration is deleted and replaced with a more general requirement to restore within the limit.
GTS 3.5.8, Required Action B.1 and C.1 are revised to replace a specific method of restoration with a more general action to restore the parameter, in this case noncondensible gas volume, to within its limit. This change is made for consistency with the revised entry conditions associated with the Required Action. Only the specific method is deleted from the action. The associated Bases, both GTS and revised, describe an appropriate method for restoration. The revised Action continues to provide assurance that operation with a noncondensible gas volume that can affect the associated flow path is allowed for only a limited period of time. These changes are designated as less restrictive because the specific method of restoration is deleted and replaced with a more general requirement to restore within the limit.
Other Changes: The remaining changes are editorial, clarifying, grammatical, or otherwise considered administrative. These changes do not affect the technical content, but improve the readability, implementation, and understanding of the requirements, and are therefore acceptable.
Other Changes: The remaining changes are editorial, clarifying, grammatical, or otherwise considered administrative. These changes do not affect the technical content, but improve the readability, implementation, and understanding of the requirements, and are therefore acceptable.
Having found that this GTSTs proposed changes to the GTS and Bases are acceptable, the NRC staff concludes that AP1000 STS Subsection 3.5.8 is an acceptable model Specification for the AP1000 standard reactor design.
Having found that this GTSTs proposed changes to the GTS and Bases are acceptable, the NRC staff concludes that AP1000 STS Subsection 3.5.8 is an acceptable model Specification for the AP1000 standard reactor design.
References to Previous NRC Safety Evaluation Reports (SERs):
References to Previous NRC Safety Evaluation Reports (SERs):
None Date report generated:
Monday, April 20, 2015                                                                    Page 10


GTST AP1000-P08-3.5.8, Rev. 1 VIII. Review Information Evaluator Comments:
None
None Steve Short Pacific Northwest National Laboratory 509-375-2868 steve.short@pnnl.gov Review Information:
 
Date report generated:
Monday, April 20, 2015 Page 10 GTST AP1000- P08-3.5.8, Rev. 1
 
VIII. Review Information
 
Evaluator Comments:
 
None
 
Steve Short Pacific Northwest National Laboratory 509-375-2868 steve.short@pnnl.gov
 
Review Information:
 
Availability for public review and comment on Revision 0 of this traveler approved by NRC staff on 5/23/2014.
Availability for public review and comment on Revision 0 of this traveler approved by NRC staff on 5/23/2014.
APOG Comments (Ref. 7) and Resolutions:
APOG Comments (Ref. 7) and Resolutions:
: 1.   (Internal #2) Approved TSTF-523 is not dispositioned in the material provided to support the GTSTs. Include TSTF-523 in the reference disposition tables, as TSTF deferred for future consideration. This is resolved by dispositioningTSTF-523, Rev. 1 as not applicable to the GTS and stating that the concerns of the TSTF have been addressed by GTS Rev.19.
: 1. (Internal #2) Approved TSTF-523 is not dispositioned in the material provided to support the GTSTs. Include TSTF-523 in the reference disposition tables, as TSTF deferred for future consideration. This is resolved by dispositioningTSTF-523, Rev. 1 as not applicable to the GTS and stating that the concerns of the TSTF have been addressed by GTS Rev.19.
: 2.   (Internal #6) The GTST sections often repeat VEGP LAR DOCs, which reference existing and current requirements. The inclusion in the GTST of references to existing and current, are not always valid in the context of the GTS. Each occurrence of existing and current should be revised to be clear and specific to GTS, MTS, or VEGP COL TS (or other), as appropriate. This is resolved by making the APOG recommended changes to the GTST.
: 2. (Internal #6) The GTST sections often repeat VEGP LAR DOCs, which reference existing and current requirements. The inclusion in the GTST of references to existing and current, are not always valid in the context of the GTS. Each occurrence of existing and current should be revised to be clear and specific to GTS, MTS, or VEGP COL TS (or other), as appropriate. This is resolved by making the APOG recommended changes to the GTST.
: 3.   (Internal #13) The NRC approval of TSTF-425, and model safety evaluation provided in the CLIIP for TSTF-425, are generically applicable to any designs Technical Specifications. As such, the replacement of certain Frequencies with a Surveillance Frequency Control Program should be included in the GTST for AP1000 STS NUREG.
: 3. (Internal #13) The NRC approval of TSTF-425, and model safety evaluation provided in the CLIIP for TSTF-425, are generically applicable to any designs Technical Specifications. As such, the replacement of certain Frequencies with a Surveillance Frequency Control Program should be included in the GTST for AP1000 STS NUREG.
 
However, implementation in the AP1000 STS should not reflect optional (i.e., bracketed) material showing retention of fixed Surveillance Frequencies where relocation to a Surveillance Frequency Control Program is acceptable. Since each represented AP1000 Utility is committed to maintaining standardization, there is no rationale for an AP1000 STS that includes bracketed options.
However, implementation in the AP1000 STS should not reflect optional (i.e., bracketed) material showing retention of fixed Surveillance Frequencies where relocation to a Surveillance Frequency Control Program is acceptable. Since each represented AP1000 Utility is committed to maintaining standardization, there is no rationale for an AP1000 STS that includes bracketed options.
Consistent with TSTF-425 criteria, replace applicable Surveillance Frequencies with In accordance with the Surveillance Frequency control Program and add that Program as new AP1000 STS Specification 5.5.15. NRC Staff disagrees with implementing TSTF-425. The TSTF is deferred for future consideration.
Consistent with TSTF-425 criteria, replace applicable Surveillance Frequencies with In accordance with the Surveillance Frequency control Program and add that Program as new AP1000 STS Specification 5.5.15. NRC Staff disagrees with implementing TSTF-425. The TSTF is deferred for future consideration.
: 4.   (Internal #295) The SPSB proposed change to correct cu. ft. to cu ft is part of comment
: 4. (Internal #295) The SPSB proposed change to correct cu. ft. to cu ft is part of comment
      #295.
#295.
 
Date report generated:
Date report generated:
Monday, April 20, 2015                                                                       Page 11
Monday, April 20, 2015 Page 11 GTST AP1000- P08-3.5.8, Rev. 1
: 5. (Internal #330) APOG recommends making the editorial changes in the Actions section of the Bases, under heading A.1. These non-technical changes provide improved clarity, consistency, and operator usability. This is resolved by making the suggested changes and adding a comma after (ECCS) as follows:


GTST AP1000-P08-3.5.8, Rev. 1
: 5.  (Internal #330) APOG recommends making the editorial changes in the Actions section of the Bases, under heading A.1. These non-technical changes provide improved clarity, consistency, and operator usability. This is resolved by making the suggested changes and adding a comma after (ECCS) as follows:
The 72 hour Completion Time is consistent with times normally applied to a degraded two train emergency core cooling system (ECCS), systems which can provide 100% of the required flow without a single failure.
The 72 hour Completion Time is consistent with times normally applied to a degraded two train emergency core cooling system (ECCS), systems which can provide 100% of the required flow without a single failure.
: 6.   (Internal #331) APOG recommends making the editorial changes in the Actions section of the Bases, under heading B.1. These non-technical changes provide improved clarity, consistency, and operator usability. This is resolved by making the suggested changes as follows:
: 6. (Internal #331) APOG recommends making the editorial changes in the Actions section of the Bases, under heading B.1. These non-technical changes provide improved clarity, consistency, and operator usability. This is resolved by making the suggested changes as follows:
 
A direct vessel injection (DVI) line break is not postulated in MODE 6.
A direct vessel injection (DVI) line break is not postulated in MODE 6.
: 7.   (Internal #332) Editorial change is recommended to the Actions section of the Bases, under heading D.1. These non-technical changes provide improved clarity, consistency, and operator usability. This is resolved by making the suggested changes and additional changes to the assumed multiple failures of the boron injection sources statement as follows:
: 7. (Internal #332) Editorial change is recommended to the Actions section of the Bases, under heading D.1. These non-technical changes provide improved clarity, consistency, and operator usability. This is resolved by making the suggested changes and additional changes to the assumed multiple failures of the boron injection sources statement as follows:
This limit prevents a significant change in boron concentration and is consistent with the long-term cooling analysis performed to justify probabilistic risk assessment (PRA) success criteria (Ref. 3), which assumed multiple failures with as many as three of the four boron injection sources (two CMTs and two Accumulators)3 CMTs/Accum not injecting.The 8-hour Completion Time is acceptable, considering that the IRWST will be fully capable of performing its assumed safety function in response to design basis accidents (DBAs) with slight deviations in these parameters.
 
: 8.   (Internal #328) Revise various TS Bases stating withdrawal of reactivity control assemblies to withdrawal of control rods for editorial improvement and consistency with other TS Bases discussions. This is resolved by making the suggested changes in the Actions section of the Bases, under heading F.1 and F.2 as follows:
This limit prevents a significant change in boron concentration and is consistent with the long-term cooling analysis performed to justify probabilistic risk assessment (PRA) success criteria (Ref. 3), which assumed multiple failures with as many as three of the four boron injection sources (two CMTs and two Accumulators) 3 CMTs/Accum not injecting.The 8 -hour Completion Time is acceptable, considering that the IRWST will be fully capable of performing its assumed safety function in response to design basis accidents (DBAs) with slight deviations in these parameters.
: 8. (Internal #328) Revise various TS Bases stating withdrawal of reactivity control assemblies to withdrawal of control rods for editorial improvement and consistency with other TS Bases discussions. This is resolved by making the suggested changes in the Actions section of the Bases, under heading F.1 and F.2 as follows:
 
Sources of positive reactivity addition include boron dilution, withdrawal of reactivity control assembliesrods, and excessive cooling of the RCS.
Sources of positive reactivity addition include boron dilution, withdrawal of reactivity control assembliesrods, and excessive cooling of the RCS.
: 9.   (Internal #334) Editorial change is recommended to the Surveillance Requirements section of the Bases, under heading SR 3.5.8.3. These non-technical changes provide improved clarity, consistency, and operator usability. This is resolved by making the suggested change and additional change to the second Frequency for SR 3.5.8.3 as follows:
: 9. (Internal #334) Editorial change is recommended to the Surveillance Requirements section of the Bases, under heading SR 3.5.8.3. These non-technical changes provide improved clarity, consistency, and operator usability. This is resolved by making the suggested change and additional change to the second Frequency for SR 3.5.8.3 as follows:
            ...solutioncombined volume increase  15,000 gal Date report generated:
Monday, April 20, 2015                                                                      Page 12


GTST AP1000-P08-3.5.8, Rev. 1 NRC Final Approval Date: 4/20/2015 NRC
...solutioncombined volume increase 15,000 gal
 
Date report generated:
Monday, April 20, 2015 Page 12 GTST AP1000- P08-3.5.8, Rev. 1
 
NRC Final Approval Date: 4/20/2015
 
NRC


==Contact:==
==Contact:==
Derek Scully United States Nuclear Regulatory Commission 301-415-6972 Derek.Scully@nrc.gov Date report generated:
Derek Scully United States Nuclear Regulatory Commission 301-415-6972 Derek.Scully@nrc.gov
Monday, April 20, 2015                                      Page 13


GTST AP1000-P08-3.5.8, Rev. 1 IX. Evaluator Comments for Consideration in Finalizing Technical Specifications and Bases None Date report generated:
Date report generated:
Monday, April 20, 2015                                                          Page 14
Monday, April 20, 2015 Page 13 GTST AP1000- P08-3.5.8, Rev. 1
 
IX. Evaluator Comments for Consideration in Finalizing Technical Specifications and Bases
 
None


GTST AP1000-P08-3.5.8, Rev. 1 X. References Used in GTST
Date report generated:
Monday, April 20, 2015 Page 14 GTST AP1000- P08-3.5.8, Rev. 1
 
X. References Used in GTST
: 1. AP1000 DCD, Revision 19, Section 16, Technical Specifications, June 2011 (ML11171A500).
: 1. AP1000 DCD, Revision 19, Section 16, Technical Specifications, June 2011 (ML11171A500).
: 2. Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Units 3 and 4, Technical Specifications Upgrade License Amendment Request, February 24, 2011 (ML12065A057).
: 2. Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Units 3 and 4, Technical Specifications Upgrade License Amendment Request, February 24, 2011 (ML12065A057).
: 3. TSTF-GG-05-01, Writer's Guide for Plant-Specific Improved Technical Specifications, June 2005 (ML070660229).
: 3. TSTF-GG-05-01, Writer's Guide for Plant-Specific Improved Technical Specifications, June 2005 (ML070660229).
: 4. Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Units 3 and 4, Response to Request for Additional Information Letter No. 01 Related to License Amendment Request LAR-12-002, ND-12-2015, October 04, 2012 (ML12286A363 and ML12286A360).
: 4. Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Units 3 and 4, Response to Request for Additional Information Letter No. 01 Related to License Amendment Request LAR 002, ND 2015, October 04, 2012 (ML12286A363 and ML12286A360).
: 5. NRC Safety Evaluation (SE) for Amendment No. 13 to Combined License (COL) No. NPF-91 for Vogtle Electric Generating Plant (VEGP) Unit 3, and Amendment No. 13 to COL No.
: 5. NRC Safety Evaluation (SE) for Amendment No. 13 to Combined License (COL) No. NPF-91 for Vogtle Electric Generating Plant (VEGP) Unit 3, and Amendment No. 13 to COL No.
NPF-92 for VEGP Unit 4, September 9, 2013, ADAMS Package Accession No. ML13238A337, which contains:
NPF-92 for VEGP Unit 4, September 9, 2013, ADAMS Package Accession No. ML13238A337, which contains:
ML13238A355           Cover Letter - Issuance of License Amendment No. 13 for Vogtle Units 3 and 4 (LAR 12-002).
 
ML13238A359           Enclosure 1 - Amendment No. 13 to COL No. NPF-91 ML13239A256           Enclosure 2 - Amendment No. 13 to COL No. NPF-92 ML13239A284           Enclosure 3 - Revised plant-specific TS pages (Attachment to Amendment No. 13)
ML13238A355 Cover Letter - Issuance of License Amendment No. 13 for Vogtle Units 3 and 4 (LAR 12-002).
ML13239A287           Enclosure 4 - Safety Evaluation (SE), and Attachment 1 - Acronyms ML13239A288           SE Attachment 2 - Table A - Administrative Changes ML13239A319           SE Attachment 3 - Table M - More Restrictive Changes ML13239A333           SE Attachment 4 - Table R - Relocated Specifications ML13239A331           SE Attachment 5 - Table D - Detail Removed Changes ML13239A316           SE Attachment 6 - Table L - Less Restrictive Changes The following documents were subsequently issued to correct an administrative error in Enclosure 3:
ML13238A359 Enclosure 1 - Amendment No. 13 to COL No. NPF-91 ML13239A256 Enclosure 2 - Amendment No. 13 to COL No. NPF-92 ML13239A284 Enclosure 3 - Revised plant-specific TS pages (Attachment to Amendment No. 13)
ML13277A616           Letter - Correction To The Attachment (Replacement Pages) - Vogtle Electric Generating Plant Units 3 and 4-Issuance of Amendment Re:
ML13239A287 Enclosure 4 - Safety Evaluation (SE), and Attachment 1 - Acronyms ML13239A288 SE Attachment 2 - Table A - Administrative Changes ML13239A319 SE Attachment 3 - Table M - More Restrictive Changes ML13239A333 SE Attachment 4 - Table R - Relocated Specifications ML13239A331 SE Attachment 5 - Table D - Detail Removed Changes ML13239A316 SE Attachment 6 - Table L - Less Restrictive Changes
Technical Specifications Upgrade (LAR 12-002) (TAC No. RP9402)
 
ML13277A637           Enclosure 3 - Revised plant-specific TS pages (Attachment to Amendment No. 13) (corrected)
The following documents were subsequently issued to correct an administrative error in Enclosure 3:
: 6. RAI Letter No. 01 Related to License Amendment Request (LAR) 12-002 for the Vogtle Electric Generating Plant Units 3 and 4 Combined Licenses, September 7, 2012 (ML12251A355).
 
: 7. APOG-2014-008, APOG (AP1000 Utilities) Comments on AP1000 Standardized Technical Specifications (STS) Generic Technical Specification Travelers (GTSTs), Docket ID NRC-2014-0147, September 22, 2014 (ML14265A493).
ML13277A616 Letter - Correction To The Attachment (Replacement Pages) - Vogtle Electric Generating Plant Units 3 and 4-Issuance of Amendment Re:
Technical Specifications Upgrade (LAR 12- 002) (TAC No. RP9402)
ML13277A637 Enclosure 3 - Revised plant-specific TS pages (Attachment to Amendment No. 13) (corrected)
: 6. RAI Letter No. 01 Related to License Amendment Request (LAR) 12- 002 for the Vogtle Electric Generating Plant Units 3 and 4 Combined Licenses, September 7, 2012 (ML12251A355).
: 7. APOG-2014- 008, APOG (AP1000 Utilities) Comments on AP1000 Standardized Technical Specifications (STS) Generic Technical Specification Travelers (GTSTs), Docket ID NRC-2014- 0147, September 22, 2014 (ML14265A493).
 
Date report generated:
Monday, April 20, 2015 Page 15 GTST AP1000- P08-3.5.8, Rev. 1
 
Date report generated:
Date report generated:
Monday, April 20, 2015                                                                   Page 15
Monday, April 20, 2015 Page 16 GTST AP1000- P08-3.5.8, Rev. 1


GTST AP1000-P08-3.5.8, Rev. 1 Date report generated:
XI. MARKUP of the Applicable GTS Subsection for Preparation of the STS NUREG
Monday, April 20, 2015                              Page 16
 
The entire section of the Specifications and the Bases associated with this GTST is presented next.


GTST AP1000-P08-3.5.8, Rev. 1 XI. MARKUP of the Applicable GTS Subsection for Preparation of the STS NUREG The entire section of the Specifications and the Bases associated with this GTST is presented next.
Changes to the Specifications and Bases are denoted as follows: Deleted portions are marked in strikethrough red font, and inserted portions in bold blue font.
Changes to the Specifications and Bases are denoted as follows: Deleted portions are marked in strikethrough red font, and inserted portions in bold blue font.
Date report generated:
Date report generated:
Monday, April 20, 2015                                                                 Page 17
Monday, April 20, 2015 Page 17 GTST AP1000- P08-3.5.8, Rev. 1


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 3.5.8 3.5 PASSIVE CORE COOLING SYSTEM (PXS) 3.5.8 In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6 LCO 3.5.8               The IRWST, with one injection flow path and one containment recirculation flow path, shall be OPERABLE.
IRWST - Shutdown, MODE 6 3.5.8
APPLICABILITY:           MODE 6.
 
ACTIONS CONDITION                         REQUIRED ACTION                 COMPLETION TIME A. Required motor                   A.1     Open required motor           72 hours operated containment                   operated containment recirculation isolation               recirculation isolation valve.
3.5 PASSIVE CORE COOLING SYSTEM (PXS)
 
3.5.8 In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6
 
LCO 3.5.8 The IRWST, with one injection flow path and one containment recirculation flow path, shall be OPERABLE.
 
APPLICABILITY: MODE 6.
 
ACTIONS
 
CONDITION REQUIRED ACTION COMPLETION TIME
 
A. Required motor A.1 Open required motor 72 hours operated containment operated containment recirculation isolation recirculation isolation valve.
valve not fully open.
valve not fully open.
B. Required IRWST                   B.1     Vent noncondensible           72 hours injection flow path                   gasesRestore withline inoperable due               noncondensible gas to presence of                         volume in squib valve noncondensible gases in               outlet line pipe stub to one high point vent                   within limit.
 
B. Required IRWST B.1 Vent noncondensible 72 hours injection flow path gasesRestore withline inoperable due noncondensible gas to presence of volume in squib valve noncondensible gases in outlet line pipe stub to one high point vent within limit.
volume in one squib valve outlet line pipe stub not within limit.
volume in one squib valve outlet line pipe stub not within limit.
C. Required IRWST                   C.1     Vent noncondensible gases     8 hours injection flow path                   from one high point withline inoperable due               ventRestore to presence of                         noncondensible gas noncondensible gases in               volume in one squib both high point vents                 valve outlet line pipe stub volume in both squib                   to within limit.
 
C. Required IRWST C.1 Vent noncondensible gases 8 hours injection flow path from one high point withline inoperable due ventRestore to presence of noncondensible gas noncondensible gases in volume in one squib both high point vents valve outlet line pipe stub volume in both squib to within limit.
valve outlet line pipe stubs not within limit.
valve outlet line pipe stubs not within limit.
AP1000 STS                                      3.5.8-1                      Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015                                                                    Page 18


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 3.5.8 ACTIONS (continued)
AP1000 STS 3.5.8-1 Amendment 0Rev. 0 Revision 19 Date report generated:
CONDITION                   REQUIRED ACTION               COMPLETION TIME D. IRWST and refueling         D.1   Restore IRWST to             8 hours cavity boron concentra-         OPERABLE status.
Monday, April 20, 2015 Page 18 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 3.5.8
 
ACTIONS (continued)
 
CONDITION REQUIRED ACTION COMPLETION TIME
 
D. IRWST and refueling D.1 Restore IRWST to 8 hours cavity boron concentra-OPERABLE status.
tion not within limits.
tion not within limits.
OR IRWST and refueling cavity borated water temperature not within limits.
 
OR IRWST and refueling cavity borated water volume 73,100 cu. ft.
OR
 
IRWST and refueling cavity borated water temperature not within limits.
 
OR
 
IRWST and refueling cavity borated water volume 73,100 cu. ft.
and > 70,907 cu. ft.<
and > 70,907 cu. ft.<
100% and > 97% of limit.
100% and > 97% of limit.
E. Required motor              E.1  Restore required motor        1 hour operated IRWST                  operated IRWST isolation isolation valve not fully        valve to fully open condition open.                            with power removed.
OR Power is not removed from required motor operated IRWST isolation valve.
AP1000 STS                                3.5.8-2                      Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015                                                            Page 19


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 3.5.8 ACTIONS (continued)
E. Required motor E.1 Restore required motor 1 hour operated IRWST operated IRWST isolation isolation valve not fully valve to fully open condition open. with power removed.
CONDITION                      REQUIRED ACTION                COMPLETION TIME F. Required Action and            F.1     Initiate action to            Immediately associated Completion                establishbe in MODE 6 Time of Condition A, B,              with the water level  23 C, D, or E not met.                  feet above the top of the reactor vessel flange.
OR AND LCO not met for reasons other than Condition A,      F.2    Suspend positive reactivity  Immediately B, C, D, or E.                      additions.
SURVEILLANCE REQUIREMENTS SURVEILLANCE                                    FREQUENCY SR 3.5.8.1         Verify the IRWST and refueling cavity water              24 hours temperature is < 120&deg;F.
SR 3.5.8.2        Verify the IRWST and refueling cavity water total        24 hours borated water volume is > 73,100 cu. ft.
SR 3.5.8.3        Verify the IRWST and refueling cavity boron              31 days concentration is  2600 ppm and  2900 ppm.
AND Once within 6 hours after each solutioncombined volume increase of  15,000 gal AP1000 STS                                    3.5.8-3                      Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015                                                                  Page 20


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 3.5.8 SURVEILLANCE REQUIREMENTS (continued)
OR
SURVEILLANCE                                FREQUENCY SR 3.5.8.4        For the IRWST and flow paths required to be          In accordance OPERABLE, the following SRs of Specification 3.5.6,  with applicable In-containment Refueling Water Storage Tank        SRs (IRWST) - Operating are applicable:
SR 3.5.6.3 SR 3.5.6.6 SR 3.5.6.8 SR 3.5.6.10 SR 3.5.6.5 SR 3.5.6.7 SR 3.5.6.9 SR 3.5.6.11 AP1000 STS                                  3.5.8-4                    Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015                                                              Page 21


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 B 3.5.8 B 3.5 PASSIVE CORE COOLING SYSTEM (PXS)
Power is not removed from required motor operated IRWST isolation valve.
B 3.5.8 In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6 BASES BACKGROUND             A description of the IRWST is provided in LCO 3.5.6, In-containment Refueling Water Storage Tank (IRWST) - Operating.
 
APPLICABLE             For MODE 6, heat removal is provided by IRWST injection and SAFETY                 containment sump recirculation.
AP1000 STS 3.5.8-2 Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015 Page 19 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 3.5.8
 
ACTIONS (continued)
 
CONDITION REQUIRED ACTION COMPLETION TIME
 
F. Required Action and F.1 Initiate action to Immediately associated Completion establishbe in MODE 6 Ti m e of Condition A, B, with the water level 23 C, D, or E not met. feet above the top of the reactor vessel flange.
OR AND LCO not met for reasons other than Condition A, F.2 Suspend positive reactivity Immediately B, C, D, or E. additions.
 
SURVEILLANCE REQUIREMENTS
 
SURVEILLANCE FREQUENCY
 
SR 3.5.8.1 Verify the IRWST and refueling cavity water 24 hours temperature is < 120&deg;F.
 
SR 3.5.8.2 Verify the IRWST and refueling cavity water total 24 hours borated water volume is > 73,100 cu. ft.
 
SR 3.5.8.3 Verify the IRWST and refueling cavity boron s concentration is 2600 ppm and.
A
 
lnceh 6 s afth sicombined volume increase of 15,000 gal
 
AP1000 STS 3.5.8-3 Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015 Page 20 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 3.5.8
 
SURVEILLANCE REQUIREMENTS (continued)
 
SURVEILLANCE FREQUENCY
 
SR 3.5.8.4 For the IRWST and flow paths required to be In accordance OPERABLE, the following SRs of Specification 3.5.6, with applicable In-containment Refueling Water Storage Tank SRs
( I RW ST) - Operating are applicable:
 
SR 3.5.6.3 SR 3.5.6.6 SR 3.5.6.8 SR 3.5.6.10 SR 3.5.6.5 SR 3.5.6.7 SR 3.5.6.9 SR 3.5.6.11
 
AP1000 STS 3.5.8-4 Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015 Page 21 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 B 3.5.8
 
B 3.5 PASSIVE CORE COOLING SYSTEM (PXS)
 
B 3.5.8 In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6
 
BASES
 
BACKGROUND A description of the IRWST is provided in LCO 3.5.6, In-containment Refueling Water Storage Tank (IRWST) - Operating.
 
APPLICABLE For MODE 6, heat removal is provided by IRWST injection and SAFETY containment sump recirculation.
ANALYSES IRWST injection could be required to mitigate some events by providing RCS inventory makeup.
ANALYSES IRWST injection could be required to mitigate some events by providing RCS inventory makeup.
One line with redundant, parallel valves is required to accommodate a single failure (to open) of an isolation valve.
One line with redundant, parallel valves is required to accommodate a single failure (to open) of an isolation valve.
The IRWST satisfies Criteria 2 and 3 of 10 CFR 50.36(c)(2)(ii).
The IRWST satisfies Criteria 2 and 3 of 10 CFR 50.36(c)(2)(ii).
LCO                    The IRWST requirements ensure that an adequate supply of borated water is available to supply the required volume of borated water as safety injection for core cooling and reactivity control.
To be considered OPERABLE, the IRWST in combination with the refueling cavity must meet the water volume, boron concentration, and temperature limits defined in the Surveillance Requirements, and one path of injection and recirculation must be OPERABLE. The motor operated injection isolation valve must be open and power removed, and the motor operated sump recirculation isolation valves must be open and OPERABLE. Any cavity leakage should be estimated and made up with borated water such that the volume in the IRWST plus the refueling cavity will meet the IRWST volume requirement. The absence of noncondensible gases in the high point vents is necessary for system OPERABILITY.OPERABILITY is not expected to be challenged due to small gas accumulations in the high point, and rapid gas accumulations are not expected during plant operation. However, a relatively small gas volume was incorporated into the design for alerting operators to provide sufficient time to initiate venting operations before the gas volume would be expected to increase to a sufficient volume that might potentially challenge the OPERABILITY of passive safety injection flow. Noncondensible gas accumulation in the injection line high point that causes the water AP1000 STS                                    B 3.5.8-1                        Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015                                                                  Page 22


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 B 3.5.8 BASES LCO (continued) level to drop below the sensor will require operator action to investigate the cause of the gas accumulation and to vent the associated high point(s).
LCO The IRWST requirements ensure that an adequate supply of borated water is available to supply the required volume of borated water as safety injection for core cooling and reactivity control.
APPLICABILITY         In MODE 6, the IRWST is an Reactor Coolant System (RCS) injection source of borated water for core cooling and reactivity control.
 
To be considered OPERABLE, the IRWST in combination with the refueling cavity must meet the water volume, boron concentration, and temperature limits defined in the Surveillance Requirements, and one path of injection and recirculation must be OPERABLE. The motor operated injection isolation valve must be open and power removed, and the motor operated sump recirculation isolation valves must be open and OPERABLE. Any cavity leakage should be estimated and made up with borated water such that the volume in the IRWST plus the refueling cavity will meet the IRWST volume requirement. The absence of noncondensible gases in the high point vents is necessary for system OPERABILITY.OPERABILITY is not expected to be challenged due to small gas accumulations in the high point, and rapid gas accumulations are not expected during plant operation. However, a relatively small gas volume was incorporated into the design for alerting operators to provide sufficient time to initiate venting operations before the gas volume would be expected to increase to a sufficient volume that might potentially challenge the OPERABILITY of passive safety injection flow. Noncondensible gas accumulation in the injection line high point that causes the water
 
AP1000 STS B 3.5.8-1 Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015 Page 22 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 B 3.5.8
 
BASES
 
LCO (continued)
 
level to drop below the sensor will require operator action to investigate the cause of the gas accumulation and to vent the associated high point(s).
 
APPLICABILITY In MODE 6, the IRWST is an Reactor Coolant System (RCS) injection source of borated water for core cooling and reactivity control.
 
The requirements for the IRWST in MODES 1, 2, 3, and 4 are specified in LCO 3.5.6, In-containment Refueling Water Storage Tank (IRWST) -
The requirements for the IRWST in MODES 1, 2, 3, and 4 are specified in LCO 3.5.6, In-containment Refueling Water Storage Tank (IRWST) -
Operating. The requirements for the IRWST in MODE 5 are specified in LCO 3.5.7, In-containment Refueling Water Storage Tank (IRWST) -
Operating. The requirements for the IRWST in MODE 5 are specified in LCO 3.5.7, In-containment Refueling Water Storage Tank (IRWST) -
Shutdown, MODE 5.
Shutdown, MODE 5.
ACTIONS                A.1 With the required motor operated containment sump isolation valve not fully open, the valve must be fully opened within 72 hours. The 72 hour Completion Time is consistent with times normally applied to a degraded two train emergency core cooling system (ECCS), systems which can provide 100% of the required flow without a single failure.
B.1 Excessive amounts of noncondensible gases in one of the injection flow path squib valve outlet line pipe stubshigh point vents in the required IRWST injection line may interfere with the passive injection of IRWST water into the reactor vessel from the associated parallel flow path in the affected injection line. Analyses have shown that with enough noncondensible gas accumulation, IRWST injection through the affected flow path could be delayed. However, the presence of some noncondensible gases does not mean that the IRWST injection capability is immediately inoperable, but that gases are collecting and should be vented. Venting of these gases requires containment entry to manually operate the vent valves. In this Condition, the parallel flow path in the affected injection line is capable of providing 100% of the required injection. A direct vessel injection (DVI) line break is not postulated in MODE 6. A Completion Time of 72 hours is acceptable since the IRWST is capable of performing the safety function without a single failure of the remaining parallel isolation valve. In addition, the 72-hour Completion Time is consistent with the time normally applicable to one inoperable train in a two train ECCS system.
AP1000 STS                                    B 3.5.8-2                      Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015                                                                      Page 23


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 B 3.5.8 BASES ACTIONS (continued)
ACTIONS A.1
C.1 Excessive amounts of noncondensible gases in both of the injection flow path squib valve outlet line pipe stubshigh point vents in the required IRWST injection line may interfere with the passive injection of IRWST water into the reactor vessel from the affected injection line.
 
With the required motor operated containment sump isolation valve not fully open, the valve must be fully opened within 72 hours. The 72 hour Completion Time is consistent with times normally applied to a degraded two train emergency core cooling system (ECCS), systems which can provide 100% of the required flow without a single failure.
 
B.1
 
Excessive amounts of noncondensible gases in one of the injection flow path squib valve outlet line pipe stubshigh point vents in the required IRWST injection line may interfere with the passive injection of IRWST water into the reactor vessel from the associated parallel flow path in the affected injection line. Analyses have shown that with enough noncondensible gas accumulation, IRWST injection through the affected flow path could be delayed. However, the presence of some noncondensible gases does not mean that the IRWST injection capability is immediately inoperable, but that gases are collecting and should be vented. Venting of these gases requires containment entry to manually operate the vent valves. In this Condition, the parallel flow path in the affected injection line is capable of providing 100% of the required injection. A direct vessel injection (DVI) line break is not postulated in MODE 6. A Completion Time of 72 hours is acceptable since the IRWST is capable of performing the safety function without a single failure of the remaining parallel isolation valve. In addition, the 72-hour Completion Time is consistent with the time normally applicable to one inoperable train in a two train ECCS system.
 
AP1000 STS B 3.5.8-2 Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015 Page 23 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 B 3.5.8
 
BASES
 
ACTIONS (continued)
 
C.1
 
Excessive amounts of noncondensible gases in both of the injection flow path squib valve outlet line pipe stubshigh point vents in the required IRWST injection line may interfere with the passive injection of IRWST water into the reactor vessel from the affected injection line.
Analyses have shown that with enough noncondensible gas accumulation, IRWST injection could be delayed long enough to cause core uncover. However, the presence of some noncondensible gases does not mean that the IRWST injection capability is immediately inoperable, but that gases are collecting and should be vented. Venting of these gases requires containment entry to manually operate the vent valves. Considering the slow rate of gas accumulation, venting within 8 hours should normally prevent accumulation of amounts of noncondensible gases that could interfere with IRWST injection. A Completion Time of 8 hours is permitted for venting noncondensible gases and is acceptable since the injection capability is not significantly affected. If only one of the affected injection flow path squib valve outlet line pipe stubshigh point vents is vented, then Condition B will apply to the remaining high point vent with noncondensible gas accumulation.
Analyses have shown that with enough noncondensible gas accumulation, IRWST injection could be delayed long enough to cause core uncover. However, the presence of some noncondensible gases does not mean that the IRWST injection capability is immediately inoperable, but that gases are collecting and should be vented. Venting of these gases requires containment entry to manually operate the vent valves. Considering the slow rate of gas accumulation, venting within 8 hours should normally prevent accumulation of amounts of noncondensible gases that could interfere with IRWST injection. A Completion Time of 8 hours is permitted for venting noncondensible gases and is acceptable since the injection capability is not significantly affected. If only one of the affected injection flow path squib valve outlet line pipe stubshigh point vents is vented, then Condition B will apply to the remaining high point vent with noncondensible gas accumulation.
D.1 If the IRWST and refueling cavity water volume, boron concentration, or temperature are not within limits, the core cooling capability from injection or PRHR HX heat transfer and the reactivity benefit of injection assumed in safety analyses may not be available. Due to the large volume of the IRWST, online monitoring of volume and temperature, and frequent surveillances, the deviation of these parameters is expected to be minor.
 
D.1
 
If the IRWST and refueling cavity water volume, boron concentration, or temperature are not within limits, the core cooling capability from injection or PRHR HX heat transfer and the reactivity benefit of injection assumed in safety analyses may not be available. Due to the large volume of the IRWST, online monitoring of volume and temperature, and frequent surveillances, the deviation of these parameters is expected to be minor.
The allowable deviation of the water volume is limited to 3%. This limit prevents a significant change in boron concentration and is consistent with the long-term cooling analysis performed to justify probabilistic risk assessment (PRA) success criteria (Ref. 3), which assumed multiple failures with as many as three of the four boron injection sources (two CMTs and two Accumulators)3 CMTs/Accum not injecting. This analysis shows that there is significant margin with respect to the water supplies that support containment recirculation operation. The 8-hour Completion Time is acceptable, considering that the IRWST will be fully capable of performing its assumed safety function in response to design basis accidents (DBAs) with slight deviations in these parameters.
The allowable deviation of the water volume is limited to 3%. This limit prevents a significant change in boron concentration and is consistent with the long-term cooling analysis performed to justify probabilistic risk assessment (PRA) success criteria (Ref. 3), which assumed multiple failures with as many as three of the four boron injection sources (two CMTs and two Accumulators)3 CMTs/Accum not injecting. This analysis shows that there is significant margin with respect to the water supplies that support containment recirculation operation. The 8-hour Completion Time is acceptable, considering that the IRWST will be fully capable of performing its assumed safety function in response to design basis accidents (DBAs) with slight deviations in these parameters.
AP1000 STS                                  B 3.5.8-3                        Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015                                                                      Page 24


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 B 3.5.8 BASES ACTIONS (continued)
AP1000 STS B 3.5.8-3 Amendment 0Rev. 0 Revision 19 Date report generated:
E.1 If the required motor operated IRWST isolation valve is not fully open or valve power is not removed, injection flow from the IRWST may be less than assumed in the safety analysis. In this situation, the valve must be restored to fully open with valve power removed in 1 hour. This Completion Time is acceptable based on risk considerations.
Monday, April 20, 2015 Page 24 GTST AP1000- P08-3.5.8, Rev. 1
F.1 and F.2 If the IRWST cannot be returned to OPERABLE status within the associated Completion Times or the LCO is not met for reasons other than Conditions A, B, C, D, or E, the plant must be placed in a Condition in which the probability and consequences of an event are minimized to the extent possible. In MODE 6, action must be immediately initiated to be in MODE 6 with the cavity water level  23 feet above the top of the reactor vessel flange.
The time to RCS boiling is maximized by maximizing the RCS inventory and maintaining RCS temperature as low as practical. With the RCS intact, another means of removing decay heat is available (the PRHR HX). Additionally, action to suspend positive reactivity additions is required to ensure that the SDM is maintained. Sources of positive reactivity addition include boron dilution, withdrawal of reactivity control rodsassemblies, and excessive cooling of the RCS. These Actions place the plant in a condition which maximizes the time to IRWST injection, thus providing time for repairs or application of alternative cooling capabilities.
SURVEILLANCE          SR 3.5.8.1 REQUIREMENTS The IRWST and refueling cavity borated water temperature must be verified every 24 hours to ensure that the temperature is within the limit assumed in accident analysis. This Frequency is sufficient to identify a temperature change that would approach the limit and has been shown to be acceptable through operating experience.
AP1000 STS                                   B 3.5.8-4                      Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015                                                                   Page 25


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 B 3.5.8 BASES SURVEILLANCE REQUIREMENTS (continued)
IRWST - Shutdown, MODE 6 B 3.5.8
SR 3.5.8.2 Verification every 24 hours that the IRWST and refueling cavity borated water volume is above the required minimum level will ensure that a sufficient initialintitial supply is available for safety injection and floodup volume for recirculation and as the heat sink for PRHR. During shutdown with the refueling cavity flooded with water from the IRWST, the Surveillance requires that the combined volume of borated water in the IRWST and refueling cavity meets the specified limit. Since the IRWST volume is normally stable, and is monitored by redundant main control indication and alarm, a 24 hour Frequency is appropriate.
 
SR 3.5.8.3 Verification every 31 days that the boron concentration of the IRWST and refueling cavity is greater than the required limit ensures that the reactor will remain subcritical following shutdown events. Since the IRWST volume is large and normally stable, the 31 day Frequency is acceptable, considering additional verifications are required within 6 hours after each solutioncombined volume increase of 15,000 gal.
BASES
SR 3.5.8.4 LCO 3.5.6 Surveillance Requirements and Frequencies SR 3.5.6.3 and 3.5.6.5 through 3.5.6.1110 are applicable to the IRWST and the flow paths required to be OPERABLE. Refer to the corresponding Bases for LCO 3.5.6 for a discussion of each SR.
 
REFERENCES             None.
ACTIONS (continued)
AP1000 STS                                     B 3.5.8-5                         Amendment 0Rev. 0 Revision 19 Date report generated:
 
Monday, April 20, 2015                                                                           Page 26
E.1
 
If the required motor operated IRWST isolation valve is not fully open or valve power is not removed, injection flow from the IRWST may be less than assumed in the safety analysis. In this situation, the valve must be restored to fully open with valve power removed in 1 hour. This Completion Time is acceptable based on risk considerations.
 
F.1 and F.2
 
If the IRWST cannot be returned to OPERABLE status within the associated Completion Times or the LCO is not met for reasons other than Conditions A, B, C, D, or E, the plant must be placed in a Condition in which the probability and consequences of an event are minimized to the extent possible. In MODE 6, action must be immediately initiated to be in MODE 6 with the cavity water level 23 feet above the top of the reactoressl.
 
The timeoCplisaximized byaximiziCpenty and mCp temperate assractic. ithCp it,ther m of ring dectsvlable Ethe moeo eu). Adtily, tioto sus pitive retivity tions is ruiretensth thpaM is maiai poces sitiv rctivity aitioilu bodilio withdral reacti vy contr rodsassemblies, and excessive cooling of the RCS. These Actions place the plant in a condition which maximizes the time to IRWST injection, thus providing time for repairs or application of alternative cooling capabilities.
 
SURVEILLANCE SR 3.5.8.1 REQUIREMENTS The IRWST and refueling cavity borated water temperature must be verified every 24 hours to ensure that the temperature is within the limit assumed in accident analysis. This Frequency is sufficient to identify a temperature change that would approach the limit and has been shown to be acceptable through operating experience.
 
AP1000 STS B 3.5.8-4 Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015 Page 25 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 B 3.5.8
 
BASES
 
SURVEILLANCE REQUIREMENTS (continued)
 
SR 3.5.8.2
 
Verification every 24 hours that the IRWST and refueling cavity borated water volume is above the required minimum level will ensure that a sufficient initialintitial supply is available for safety injection and floodup volume for recirculation and as the heat sink for PRHR. During shutdown with the refueling cavity flooded with water from the IRWST, the Surveillance requires that the combined volume of borated water in the IRWST and refueling cavity meets the specified limit. Since the IRWST volume is normally stable, and is monitored by redundant main control indication and alarm, a 24 hour Frequency is appropriate.
 
SR 3.5.8.3
 
Verification every 31 days that the boron concentration of the IRWST and refueling cavity is greater than the required limit ensures that the reactor will remain subcritical following shutdown events. Since the IRWST volume is large and normally stable, the 31 day Frequency is acceptable, considering additional verifications are required within 6 hours after each solutioncombined volume increase of 15,000 gal.
 
SR 3.5.8.4
 
LCO 3.5.6 Surveillance Requirements and Frequencies SR 3.5.6.3 and 3.5.6.5 through 3.5.6.1110 are applicable to the IRWST and the flow paths required to be OPERABLE. Refer to the corresponding Bases for LCO 3.5.6 for a discussion of each SR.
 
REFERENCES None.
 
AP1000 STS B 3.5.8-5 Amendment 0Rev. 0 Revision 19 Date report generated:
Monday, April 20, 2015 Page 26 GTST AP1000- P08-3.5.8, Rev. 1
 
XII. Applicable STS Subsection After Incorporation of this GTSTs Modifications
 
The entire subsection of the Specifications and the Bases associated with this GTST, following incorporation of the modifications, is presented next.


GTST AP1000-P08-3.5.8, Rev. 1 XII. Applicable STS Subsection After Incorporation of this GTSTs Modifications The entire subsection of the Specifications and the Bases associated with this GTST, following incorporation of the modifications, is presented next.
Date report generated:
Date report generated:
Monday, April 20, 2015                                                                 Page 27
Monday, April 20, 2015 Page 27 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 3.5.8
 
3.5 PASSIVE CORE COOLING SYSTEM (PXS)
 
3.5.8 In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6
 
LCO 3.5.8 The IRWST, with one injection flow path and one containment recirculation flow path, shall be OPERABLE.


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 3.5.8 3.5 PASSIVE CORE COOLING SYSTEM (PXS) 3.5.8 In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6 LCO 3.5.8                The IRWST, with one injection flow path and one containment recirculation flow path, shall be OPERABLE.
APPLICABILITY: MODE 6.
APPLICABILITY:           MODE 6.
 
ACTIONS CONDITION                         REQUIRED ACTION                 COMPLETION TIME A. Required motor                   A.1     Open required motor           72 hours operated containment                   operated containment recirculation isolation               recirculation isolation valve.
ACTIONS
 
CONDITION REQUIRED ACTION COMPLETION TIME
 
A. Required motor A.1 Open required motor 72 hours operated containment operated containment recirculation isolation recirculation isolation valve.
valve not fully open.
valve not fully open.
B. Required IRWST                   B.1     Restore noncondensible         72 hours injection flow path with               gas volume in squib valve noncondensible gas                     outlet line pipe stub to volume in one squib                   within limit.
 
B. Required IRWST B.1 Restore noncondensible 72 hours injection flow path with gas volume in squib valve noncondensible gas outlet line pipe stub to volume in one squib within limit.
valve outlet line pipe stub not within limit.
valve outlet line pipe stub not within limit.
C. Required IRWST                   C.1     Restore noncondensible         8 hours injection flow path with               gas volume in one squib noncondensible gas                     valve outlet line pipe stub to volume in both squib                   within limit.
 
C. Required IRWST C.1 Restore noncondensible 8 hours injection flow path with gas volume in one squib noncondensible gas valve outlet line pipe stub to volume in both squib within limit.
valve outlet line pipe stubs not within limit.
valve outlet line pipe stubs not within limit.
AP1000 STS                                      3.5.8-1                                  Rev. 0 Date report generated:
Monday, April 20, 2015                                                                    Page 28


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 3.5.8 ACTIONS (continued)
AP1000 STS 3.5.8-1 Rev. 0
CONDITION                   REQUIRED ACTION               COMPLETION TIME D. IRWST and refueling         D.1   Restore IRWST to             8 hours cavity boron concentra-         OPERABLE status.
 
Date report generated:
Monday, April 20, 2015 Page 28 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 3.5.8
 
ACTIONS (continued)
 
CONDITION REQUIRED ACTION COMPLETION TIME
 
D. IRWST and refueling D.1 Restore IRWST to 8 hours cavity boron concentra-OPERABLE status.
tion not within limits.
tion not within limits.
OR IRWST and refueling cavity borated water temperature not within limits.
OR IRWST and refueling cavity borated water volume  73,100 cu ft and > 70,907 cu ft.
E. Required motor              E.1  Restore required motor        1 hour operated IRWST                  operated IRWST isolation isolation valve not fully        valve to fully open condition open.                            with power removed.
OR Power is not removed from required motor operated IRWST isolation valve.
AP1000 STS                                3.5.8-2                                  Rev. 0 Date report generated:
Monday, April 20, 2015                                                            Page 29


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 3.5.8 ACTIONS (continued)
OR
CONDITION                       REQUIRED ACTION                   COMPLETION TIME F. Required Action and           F.1     Initiate action to establish   Immediately associated Completion               water level 23 feet above Time of Condition A, B,             the top of the reactor vessel C, D, or E not met.                 flange.
 
OR                           AND LCO not met for reasons     F.2     Suspend positive reactivity     Immediately other than Condition A,             additions.
IRWST and refueling cavity borated water temperature not within limits.
 
OR
 
IRWST and refueling cavity borated water volume 73,100 cu ft and > 70,907 cu ft.
 
E. Required motor E.1 Restore required motor 1 hour operated IRWST operated IRWST isolation isolation valve not fully valve to fully open condition open. with power removed.
 
OR
 
Power is not removed from required motor operated IRWST isolation valve.
 
AP1000 STS 3.5.8-2 Rev. 0
 
Date report generated:
Monday, April 20, 2015 Page 29 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 3.5.8
 
ACTIONS (continued)
 
CONDITION REQUIRED ACTION COMPLETION TIME
 
F. Required Action and F.1 Initiate action to establish Immediately associated Completion water level 23 feet above Ti m e of Condition A, B, the top of the reactor vessel C, D, or E not met. flange.
 
OR AND
 
LCO not met for reasons F.2 Suspend positive reactivity Immediately other than Condition A, additions.
B, C, D, or E.
B, C, D, or E.
SURVEILLANCE REQUIREMENTS SURVEILLANCE                                      FREQUENCY SR 3.5.8.1        Verify the IRWST and refueling cavity water                24 hours temperature is < 120&deg;F.
SR 3.5.8.2        Verify the IRWST and refueling cavity water total          24 hours borated water volume is > 73,100 cu ft.
SR 3.5.8.3        Verify the IRWST and refueling cavity boron                31 days concentration is  2600 ppm and  2900 ppm.
AND Once within 6 hours after each combined volume increase of 15,000 gal AP1000 STS                                    3.5.8-3                                      Rev. 0 Date report generated:
Monday, April 20, 2015                                                                    Page 30


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 3.5.8 SURVEILLANCE REQUIREMENTS (continued)
SURVEILLANCE REQUIREMENTS
SURVEILLANCE                                 FREQUENCY SR 3.5.8.4        For the IRWST and flow paths required to be          In accordance OPERABLE, the following SRs are applicable:          with applicable SRs SR 3.5.6.3 SR 3.5.6.6 SR 3.5.6.8 SR 3.5.6.10 SR 3.5.6.5 SR 3.5.6.7 SR 3.5.6.9 SR 3.5.6.11 AP1000 STS                                   3.5.8-4                                  Rev. 0 Date report generated:
 
Monday, April 20, 2015                                                               Page 31
SURVEILLANCE FREQUENCY
 
SR 3.5.8.1 Verify the IRWST and refueling cavity water 24 hours temperature is < 120&deg;F.
 
SR 3.5.8.2 Verify the IRWST and refueling cavity water total 24 hours borated water volume is > 73,100 cu ft.
 
SR 3.5.8.3 Verify the IRWST and refueling cavity boron s concentration is 2600 ppm and.
A
 
lnceh 6 s afth cned v irease of 15,000 gal
 
AP1000 STS 3.5.8-3 Rev. 0
 
Date report generated:
Monday, April 20, 2015 Page 30 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 3.5.8


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 B 3.5.8 B 3.5 PASSIVE CORE COOLING SYSTEM (PXS)
SURVEILLANCE REQUIREMENTS (continued)
B 3.5.8 In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6 BASES BACKGROUND             A description of the IRWST is provided in LCO 3.5.6, In-containment Refueling Water Storage Tank (IRWST) - Operating.
 
APPLICABLE             For MODE 6, heat removal is provided by IRWST injection and SAFETY                 containment sump recirculation.
SURVEILLANCE FREQUENCY
 
SR 3.5.8.4 For the IRWST and flow paths required to be In accordance OPERABLE, the following SRs are applicable: with applicable SRs SR 3.5.6.3 SR 3.5.6.6 SR 3.5.6.8 SR 3.5.6.10 SR 3.5.6.5 SR 3.5.6.7 SR 3.5.6.9 SR 3.5.6.11
 
AP1000 STS 3.5.8-4 Rev. 0
 
Date report generated:
Monday, April 20, 2015 Page 31 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 B 3.5.8
 
B 3.5 PASSIVE CORE COOLING SYSTEM (PXS)
 
B 3.5.8 In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6
 
BASES
 
BACKGROUND A description of the IRWST is provided in LCO 3.5.6, In-containment Refueling Water Storage Tank (IRWST) - Operating.
 
APPLICABLE For MODE 6, heat removal is provided by IRWST injection and SAFETY containment sump recirculation.
ANALYSES IRWST injection could be required to mitigate some events by providing RCS inventory makeup.
ANALYSES IRWST injection could be required to mitigate some events by providing RCS inventory makeup.
One line with redundant, parallel valves is required to accommodate a single failure (to open) of an isolation valve.
One line with redundant, parallel valves is required to accommodate a single failure (to open) of an isolation valve.
The IRWST satisfies Criteria 2 and 3 of 10 CFR 50.36(c)(2)(ii).
The IRWST satisfies Criteria 2 and 3 of 10 CFR 50.36(c)(2)(ii).
LCO                    The IRWST requirements ensure that an adequate supply of borated water is available to supply the required volume of borated water as safety injection for core cooling and reactivity control.
To be considered OPERABLE, the IRWST in combination with the refueling cavity must meet the water volume, boron concentration, and temperature limits defined in the Surveillance Requirements, and one path of injection and recirculation must be OPERABLE. The motor operated injection isolation valve must be open and power removed, and the motor operated sump recirculation isolation valves must be open and OPERABLE. Any cavity leakage should be estimated and made up with borated water such that the volume in the IRWST plus the refueling cavity will meet the IRWST volume requirement. OPERABILITY is not expected to be challenged due to small gas accumulations in the high point, and rapid gas accumulations are not expected during plant operation. However, a relatively small gas volume was incorporated into the design for alerting operators to provide sufficient time to initiate venting operations before the gas volume would be expected to increase to a sufficient volume that might potentially challenge the OPERABILITY of passive safety injection flow. Noncondensible gas accumulation in the injection line high point that causes the water level to drop below the sensor will require operator action to investigate the cause of the gas accumulation and to vent the associated high point(s).
AP1000 STS                                    B 3.5.8-1                                        Rev. 0 Date report generated:
Monday, April 20, 2015                                                                        Page 32


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 B 3.5.8 BASES APPLICABILITY         In MODE 6, the IRWST is an Reactor Coolant System (RCS) injection source of borated water for core cooling and reactivity control.
LCO The IRWST requirements ensure that an adequate supply of borated water is available to supply the required volume of borated water as safety injection for core cooling and reactivity control.
 
To be considered OPERABLE, the IRWST in combination with the refueling cavity must meet the water volume, boron concentration, and temperature limits defined in the Surveillance Requirements, and one path of injection and recirculation must be OPERABLE. The motor operated injection isolation valve must be open and power removed, and the motor operated sump recirculation isolation valves must be open and OPERABLE. Any cavity leakage should be estimated and made up with borated water such that the volume in the IRWST plus the refueling cavity will meet the IRWST volume requirement. OPERABILITY is not expected to be challenged due to small gas accumulations in the high point, and rapid gas accumulations are not expected during plant operation. However, a relatively small gas volume was incorporated into the design for alerting operators to provide sufficient time to initiate venting operations before the gas volume would be expected to increase to a sufficient volume that might potentially challenge the OPERABILITY of passive safety injection flow. Noncondensible gas accumulation in the injection line high point that causes the water level to drop below the sensor will require operator action to inve stigate the cause of the gas accumulation and to vent the associated high point(s).
 
AP1000 STS B 3.5.8-1 Rev. 0
 
Date report generated:
Monday, April 20, 2015 Page 32 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 B 3.5.8
 
BASES
 
APPLICABILITY In MODE 6, the IRWST is an Reactor Coolant System (RCS) injection source of borated water for core cooling and reactivity control.
 
The requirements for the IRWST in MODES 1, 2, 3, and 4 are specified in LCO 3.5.6, In-containment Refueling Water Storage Tank (IRWST) -
The requirements for the IRWST in MODES 1, 2, 3, and 4 are specified in LCO 3.5.6, In-containment Refueling Water Storage Tank (IRWST) -
Operating. The requirements for the IRWST in MODE 5 are specified in LCO 3.5.7, In-containment Refueling Water Storage Tank (IRWST) -
Operating. The requirements for the IRWST in MODE 5 are specified in LCO 3.5.7, In-containment Refueling Water Storage Tank (IRWST) -
Shutdown, MODE 5.
Shutdown, MODE 5.
ACTIONS                A.1 With the required motor operated containment sump isolation valve not fully open, the valve must be fully opened within 72 hours. The 72 hour Completion Time is consistent with times normally applied to a degraded two train emergency core cooling system (ECCS), which can provide 100% of the required flow without a single failure.
B.1 Excessive amounts of noncondensible gases in one of the injection flow path squib valve outlet line pipe stubs in the required IRWST injection line may interfere with the passive injection of IRWST water into the reactor vessel from the associated parallel flow path in the affected injection line. Analyses have shown that with enough noncondensible gas accumulation, IRWST injection through the affected flow path could be delayed. However, the presence of some noncondensible gases does not mean that the IRWST injection capability is immediately inoperable, but that gases are collecting and should be vented. Venting of these gases requires containment entry to manually operate the vent valves. In this Condition, the parallel flow path in the affected injection line is capable of providing 100% of the required injection. A direct vessel injection (DVI) line break is not postulated in MODE 6. A Completion Time of 72 hours is acceptable since the IRWST is capable of performing the safety function without a single failure of the remaining parallel isolation valve. In addition, the 72-hour Completion Time is consistent with the time normally applicable to one inoperable train in a two train ECCS system.
AP1000 STS                                    B 3.5.8-2                                        Rev. 0 Date report generated:
Monday, April 20, 2015                                                                        Page 33


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 B 3.5.8 BASES ACTIONS (continued)
ACTIONS A.1
C.1 Excessive amounts of noncondensible gases in both of the injection flow path squib valve outlet line pipe stubs in the required IRWST injection line may interfere with the passive injection of IRWST water into the reactor vessel from the affected injection line. Analyses have shown that with enough noncondensible gas accumulation, IRWST injection could be delayed long enough to cause core uncover. However, the presence of some noncondensible gases does not mean that the IRWST injection capability is immediately inoperable, but that gases are collecting and should be vented. Venting of these gases requires containment entry to manually operate the vent valves. Considering the slow rate of gas accumulation, venting within 8 hours should normally prevent accumulation of amounts of noncondensible gases that could interfere with IRWST injection. A Completion Time of 8 hours is permitted for venting noncondensible gases and is acceptable since the injection capability is not significantly affected. If only one of the affected injection flow path squib valve outlet line pipe stubs is vented, then Condition B will apply to the remaining high point vent with noncondensible gas accumulation.
 
D.1 If the IRWST and refueling cavity water volume, boron concentration, or temperature are not within limits, the core cooling capability from injection or PRHR HX heat transfer and the reactivity benefit of injection assumed in safety analyses may not be available. Due to the large volume of the IRWST, online monitoring of volume and temperature, and frequent surveillances, the deviation of these parameters is expected to be minor.
With the required motor operated containment sump isolation valve not fully open, the valve must be fully opened within 72 hours. The 72 hour Completion Time is consistent with times normally applied to a degraded two train emergency core cooling system (ECCS), which can provide 100% of the required flow without a single failure.
 
B.1
 
Excessive amounts of noncondensible gases in one of the injection flow path squib valve outlet line pipe stubs in the required IRWST injection line may interfere with the passive injection of IRWST water into the reactor vessel from the associated parallel flow path in the affected injection line. Analyses have shown that with enough noncondensible gas accumulation, IRWST injection through the affected flow path could be delayed. However, the presence of some noncondensible gases does not mean that the IRWST injection capability is immediately inoperable, but that gases are collecting and should be vented. Venting of these gases requires containment entry to manually operate the vent valves. In this Condition, the parallel flow path in the affected injection line is capable of providing 100% of the required injection. A direct vessel injection (DVI) line break is not postulated in MODE 6. A Completion Time of 72 hours is acceptable since the IRWST is capable of performing the safety function without a single failure of the remaining parallel isolation valve. In addition, the 72-hour Completion Time is consistent with the time normally applicable to one inoperable train in a two train ECCS system.
 
AP1000 STS B 3.5.8-2 Rev. 0
 
Date report generated:
Monday, April 20, 2015 Page 33 GTST AP1000- P08-3.5.8, Rev. 1
 
IRWST - Shutdown, MODE 6 B 3.5.8
 
BASES
 
ACTIONS (continued)
 
C.1
 
Excessive amounts of noncondensible gases in both of the injection flow path squib valve outlet line pipe stubs in the required IRWST injection line may interfere with the passive injection of IRWST water into the reactor vessel from the affected injection line. Analyses have shown that with enough noncondensible gas accumulation, IRWST injection could be delayed long enough to cause core uncover. However, the presence of some noncondensible gases does not mean that the IRWST injection capability is immediately inoperable, but that gases are collecting and should be vented. Venting of these gases requires containment entry to manually operate the vent valves. Considering the slow rate of gas accumulation, venting within 8 hours should normally prevent accumulation of amounts of noncondensible gases that could interfere with IRWST injection. A Completion Time of 8 hours is permitted for venting noncondensible gases and is acceptable since the injection capability is not significantly affected. If only one of the affected injection flow path squib valve outlet line pipe stubs is vented, then Condition B will apply to the remaining high point vent with noncondensible gas accumulation.
 
D.1
 
If the IRWST and refueling cavity water volume, boron concentration, or temperature are not within limits, the core cooling capability from injection or PRHR HX heat transfer and the reactivity benefit of injection assumed in safety analyses may not be available. Due to the large volume of the IRWST, online monitoring of volume and temperature, and frequent surveillances, the deviation of these parameters is expected to be minor.
The allowable deviation of the water volume is limited to 3%. This limit prevents a significant change in boron concentration and is consistent with the long-term cooling analysis performed to justify probabilistic risk assessment (PRA) success criteria (Ref. 3), which assumed multiple failures with as many as three of the four boron injection sources (two CMTs and two Accumulators) not injecting. This analysis shows that there is significant margin with respect to the water supplies that support containment recirculation operation. The 8-hour Completion Time is acceptable, considering that the IRWST will be fully capable of performing its assumed safety function in response to design basis accidents (DBAs) with slight deviations in these parameters.
The allowable deviation of the water volume is limited to 3%. This limit prevents a significant change in boron concentration and is consistent with the long-term cooling analysis performed to justify probabilistic risk assessment (PRA) success criteria (Ref. 3), which assumed multiple failures with as many as three of the four boron injection sources (two CMTs and two Accumulators) not injecting. This analysis shows that there is significant margin with respect to the water supplies that support containment recirculation operation. The 8-hour Completion Time is acceptable, considering that the IRWST will be fully capable of performing its assumed safety function in response to design basis accidents (DBAs) with slight deviations in these parameters.
AP1000 STS                                    B 3.5.8-3                                        Rev. 0 Date report generated:
Monday, April 20, 2015                                                                        Page 34


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 B 3.5.8 BASES ACTIONS (continued)
AP1000 STS B 3.5.8-3 Rev. 0
E.1 If the required motor operated IRWST isolation valve is not fully open or valve power is not removed, injection flow from the IRWST may be less than assumed in the safety analysis. In this situation, the valve must be restored to fully open with valve power removed in 1 hour. This Completion Time is acceptable based on risk considerations.
 
F.1 and F.2 If the IRWST cannot be returned to OPERABLE status within the associated Completion Times or the LCO is not met for reasons other than Conditions A, B, C, D, or E, the plant must be placed in a Condition in which the probability and consequences of an event are minimized to the extent possible. In MODE 6, action must be immediately initiated to be in MODE 6 with the cavity water level 23 feet above the top of the reactor vessel flange.
Date report generated:
The time to RCS boiling is maximized by maximizing the RCS inventory and maintaining RCS temperature as low as practical. With the RCS intact, another means of removing decay heat is available (the PRHR HX). Additionally, action to suspend positive reactivity additions is required to ensure that the SDM is maintained. Sources of positive reactivity addition include boron dilution, withdrawal of control rods, and excessive cooling of the RCS. These Actions place the plant in a condition which maximizes the time to IRWST injection, thus providing time for repairs or application of alternative cooling capabilities.
Monday, April 20, 2015 Page 34 GTST AP1000- P08-3.5.8, Rev. 1
SURVEILLANCE          SR 3.5.8.1 REQUIREMENTS The IRWST and refueling cavity borated water temperature must be verified every 24 hours to ensure that the temperature is within the limit assumed in accident analysis. This Frequency is sufficient to identify a temperature change that would approach the limit and has been shown to be acceptable through operating experience.
 
AP1000 STS                                   B 3.5.8-4                                       Rev. 0 Date report generated:
IRWST - Shutdown, MODE 6 B 3.5.8
Monday, April 20, 2015                                                                     Page 35
 
BASES
 
ACTIONS (continued)
 
E.1
 
If the required motor operated IRWST isolation valve is not fully open or valve power is not removed, injection flow from the IRWST may be less than assumed in the safety analysis. In this situation, the valve must be restored to fully open with valve power removed in 1 hour. This Completion Time is acceptable based on risk considerations.
 
F.1 and F.2
 
If the IRWST cannot be returned to OPERABLE status within the associated Completion Times or the LCO is not met for reasons other than Conditions A, B, C, D, or E, the plant must be placed in a Condition in which the probability and consequences of an event are minimized to the extent possible. In MODE 6, action must be immediately initiated to be in MODE 6 with the cavity water level 23 feet above the top of the reactoressl.
 
The timeoCplisaximized byaximiziCpenty and mCp temperate assractic. ithCp it,ther of ring dectsvlable Ethe moeo eu). Adtily, tioto sus pitive retivity tions is ruiretensth thpaM is maiai poces sitiv rctivity aitioilu bodilio withdr al contr rods csiveooling ofCp.ThesActions ple t plant ctich maximizimtfotpTtion, thus pring timfrsr applicion of altnivcooliapabiliti.
 
osbfiiC po 3 nMbp The fotpTefueliityatatemperateust vified every O4 hours to enset the temperesittimit scilysis.Thisrys sficient tidentify a trure cthatouloachimitshow t acctable thr operating experience.
 
AP1000 STS B 3.5.8-4 Rev. 0
 
Date report generated:
Monday, April 20, 2015 Page 35 GTST AP1000- P08-3.5.8, Rev. 1


GTST AP1000-P08-3.5.8, Rev. 1 IRWST - Shutdown, MODE 6 B 3.5.8 BASES SURVEILLANCE REQUIREMENTS (continued)
IRWST - Shutdown, MODE 6 B 3.5.8
SR 3.5.8.2 Verification every 24 hours that the IRWST and refueling cavity borated water volume is above the required minimum level will ensure that a sufficient initial supply is available for safety injection and floodup volume for recirculation and as the heat sink for PRHR. During shutdown with the refueling cavity flooded with water from the IRWST, the Surveillance requires that the combined volume of borated water in the IRWST and refueling cavity meets the specified limit. Since the IRWST volume is normally stable, and is monitored by redundant main control indication and alarm, a 24 hour Frequency is appropriate.
 
SR 3.5.8.3 Verification every 31 days that the boron concentration of the IRWST and refueling cavity is greater than the required limit ensures that the reactor will remain subcritical following shutdown events. Since the IRWST volume is large and normally stable, the 31 day Frequency is acceptable, considering additional verifications are required within 6 hours after each combined volume increase of 15,000 gal.
BASES
SR 3.5.8.4 LCO 3.5.6 Surveillance Requirements and Frequencies SR 3.5.6.3 and 3.5.6.5 through 3.5.6.11 are applicable to the IRWST and the flow paths required to be OPERABLE. Refer to the corresponding Bases for LCO 3.5.6 for a discussion of each SR.
 
REFERENCES             None.
SURVEILLANCE REQUIREMENTS (continued)
AP1000 STS                                     B 3.5.8-5                                       Rev. 0 Date report generated:
 
Monday, April 20, 2015                                                                         Page 36}}
SR 3.5.8.2
 
Verification every 24 hours that the IRWST and refueling cavity borated water volume is above the required minimum level will ensure that a sufficient initial supply is available for safety injection and floodup volume for recirculation and as the heat sink for PRHR. During shutdown with the refueling cavity flooded with water from the IRWST, the Surveillance requires that the combined volume of borated water in the IRWST and refueling cavity meets the specified limit. Since the IRWST volume is normally stable, and is monitored by redundant main control indication and alarm, a 24 hour Frequency is appropriate.
 
SR 3.5.8.3
 
Verification every 31 days that the boron concentration of the IRWST and refueling cavity is greater than the required limit ensures that the reactor will remain subcritical following shutdown events. Since the IRWST volume is large and normally stable, the 31 day Frequency is acceptable, considering additional verifications are required within 6 hours after each combined volume increase of 15,000 gal.
 
SR 3.5.8.4
 
LCO 3.5.6 Surveillance Requirements and Frequencies SR 3.5.6.3 and 3.5.6.5 through 3.5.6.11 are applicable to the IRWST and the flow paths required to be OPERABLE. Refer to the corresponding Bases for LCO 3.5.6 for a discussion of each SR.
 
REFERENCES None.
 
AP1000 STS B 3.5.8-5 Rev. 0
 
Date report generated:
Monday, April 20, 2015 Page 36}}

Revision as of 04:39, 16 November 2024

Changes Related to AP1000 Gts Subsection 3.5.8, IRWST Shutdown, Mode 6
ML22240A080
Person / Time
Issue date: 04/20/2015
From:
NRC/NRR/DSS/STSB
To:
Craig Harbuck NRR/DSS 301-415-3140
Shared Package
ML22240A001 List: ... further results
References
Download: ML22240A080 (36)


Text

GTST AP1000- P08-3.5.8, Rev. 1

Advanced Passive 1000 (AP1000)

Generic Technical Specification Traveler (GTST)

Title:

Changes Related to LCO 3.5.8, In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6

I. Technical Specifications Task Force (TSTF) Travelers, Approved Since Revision 2 of STS NUREG-1431, and Used to Develop this GTST

TSTF Number and

Title:

TSTF-425, Rev. 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5b TSTF-523, Rev. 2, Generic Letter 2008- 01, Managing Gas Accumulation

STS NUREGs Affected:

TSTF-425, Rev. 3: NUREG-1430, 1431, 1432, 1433, 1434 TSTF-523, Rev. 2: NUREG-1430, 1431, 1432, 1433, 1434

NRC Approval Date:

TSTF-425, Rev. 3: 06-Jul-09 TSTF-523, Rev. 2: 23-Dec-13

TSTF Classification:

TSTF-425, Rev. 3: Technical Change TSTF-523, Rev. 2: Technical Change

Date report generated:

Monday, April 20, 2015 Page 1 GTST AP1000- P08-3.5.8, Rev. 1

II. Reference Combined License (RCOL) Standard Departures (Std. Dep.), RCOL COL Items, and RCOL Plant-Specific Technical Specifications (PTS) Changes Used to Develop this GTST

RCOL Std. Dep. Number and

Title:

None

RCOL COL Item Number and

Title:

None

RCOL PTS Change Number and

Title:

VEGP LAR DOC A031: Required Action revision for Condition with single MODE applicability VEGP LAR DOC A078: Borated water volume designation revision VEGP LAR DOC A079: IRWST SR Frequency revision VEGP LAR DOC A081: TS 3.5.8 Condition F revision VEGP LAR DOC L01: Added SR for valve actuation VEGP LAR DOC L17: Revisions to Actions and SRs associated with noncondensible gases

Date report generated:

Monday, April 20, 2015 Page 2 GTST AP1000- P08-3.5.8, Rev. 1

III. Comments on Relations Among TSTFs, RCOL Std. Dep., RCOL COL Items, and RCOL PTS Changes

This section discusses the considered changes that are: (1) applicable to operating reactor designs, but not to the AP1000 design; (2) already incorporated in the GTS; or (3) superseded by another change.

TSTF-425 is deferred for future consideration.

TSTF-523, Rev. 1 is not applicable to the GTS. The issues of gas accumulation have been addressed by GTS Rev.19.

VEGP LAR DOC A078 revises the third entry statement for Condition D of TS 3.5.8 by changing the IRWST borated water volume from a percent range of < 100% and > 97% to a specific range of 73,100 cu. ft. and > 70,907 cu. ft. A proposed additional change corrects cu. ft. to cu ft.

Date report generated:

Monday, April 20, 2015 Page 3 GTST AP1000- P08-3.5.8, Rev. 1

IV. Additional Changes Proposed as Part of this GTST (modifications proposed by NRC staff and/or clear editorial changes or deviations identified by preparer of GTST)

The Bases for Required Action B.1 and C.1 of TS 3.5.8 is revised for consistency with VEGP LAR DOC L17 changes to Required Action B.1 and C.1 of TS 3.5.8.

The Bases for SR 3.5.8.2 is revised by correcting the word intitial to initial.

Condition D and SR 3.5.8.2 are revised to delete the periods from cu. ft.

APOG Recommended Changes to Improve the Bases

An editorial change is made to the Actions section of the Bases, under heading A.1. The change clarifies and corrects the first use of the acronym ECCS by using the full phrase emergency core cooling system and deleting system after ECCS.

An editorial change is made to the Actions section of the Bases, under heading B.1. The change corrects the first use of the acronym DVI by using the full phrase direct vessel injection.

An editorial change is made to the Actions section of the Bases, under heading D.1. The change corrects the first use of the acronym PRA by using the full phrase probabilistic risk assessment and DBAs by using the full phrase design basis accidents. The change also clarifies the assumed number of failed boron injection sources (CMTs and Accumulators).

Revise the Actions section of the Bases, under heading F.1 and F.2 statement withdrawal of reactivity control assemblies to withdrawal of control rods for editorial improvement and consistency with other TS Bases discussions.

In the Surveillance Requirements section of the Bases, under heading SR 3.5.8.3, change

...solution volume increase 15,000 gal. to...combined volume increase 15,000 gal. In addition, change the SR 3.5.8.3 Frequency from...solution volume increase 15,000 gal to

...combined volume increase 15,000 gal.

Date report generated:

Monday, April 20, 2015 Page 4 GTST AP1000- P08-3.5.8, Rev. 1

V. Applicability

Affected Generic Technical Specifications and Bases:

Section 3.5.8, In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6

Changes to the Generic Technical Specifications and Bases:

Condition B of TS 3.5.8 is revised from Required IRWST injection line inoperable due to presence of noncondensible gases in one high point vent. to Required IRWST injection flow path with noncondensible gas volume in one squib valve outlet line pipe stub not within limit.

The Required Action B.1 is revised from Vent noncondensible gases. to Restore noncondensible gas volume in squib valve outlet line pipe stub to within limit. (DOC L17)

Condition C of TS 3.5.8 is revised from Required IRWST injection line inoperable due to presence of noncondensible gases in both high point vents. to Required IRWST injection flow path with noncondensible gas volume in both squib valve outlet line pipe stubs not within limit.

The Required Action C.1 is revised from Vent noncondensible gases from one high point vent.

to Restore noncondensible gas volume in one squib valve outlet line pipe stub to within limit.

(DOC L17)

The third entry statement for Condition D of TS 3.5.8 is revised by replacing the IRWST borated water volume specified as a percent with cubic feet. (DOC A078)

Condition D and SR 3.5.8.2 of TS 3.5.8 is revised to correct cu. ft. to cu ft. (proposed additional change)

The first entry statement for Condition F of TS 3.5.8 is revised by specifying the applicable Conditions. The associated Actions section of the Bases is also revised. (DOC A081)

Required Action F.1 of TS 3.5.8 is revised by deleting the requirement to be in MODE 6. (DOC A031)

SR 3.5.8.3 second Frequency is revised by changing the...solution volume increase of 15,000 gal to...solution volume increase of 15,000 gal. The associated Bases for SR 3.5.8.3 is also revised. (DOC A079)

SR 3.5.8.4 is revised to address the new SR 3.5.6.9 by adding the renumbered SR 3.5.6.11.

The associated Bases for SR 3.5.4.8 are also revised. (DOC L01)

The LCO section of the Bases of TS 3.5.8 is revised by adding discussion of noncondensible gas accumulation in the injection line high point. (DOC L17)

In the Actions section of the Bases, under heading A.1 the last sentence is revised by changing ECCS system to emergency core cooling system (ECCS). (APOG Comment)

In the Actions section of the Bases, under heading B.1 use of the acronym DVI is changed to direct vessel injection (DVI). (APOG Comment)

The Bases for Required Action B.1 and C.1 of TS 3.5.8 is revised by changing high point vents to injection flow path squib valve outlet line pipe stubs. (proposed additional change)

Date report generated:

Monday, April 20, 2015 Page 5 GTST AP1000- P08-3.5.8, Rev. 1

In the Actions section of the Bases, under heading D.1 the fourth sentence is revised by changing PRA to probabilistic risk assessment (PRA) and clarifying the assumed number of failed boron injection sources (CMTs and Accumulators). Under heading D.1 the last sentence is revised by changing DBAs to design basis accidents (DBAs). (APOG Comment)

In the Actions section of the Bases, under heading F.1 and F.2, second paragraph, fourth sentence is revised from withdrawal of reactivity control assemblies to withdrawal of control rods. (APOG Comment)

The Bases for SR 3.5.8.2 is revised by correcting intitial to initial. (proposed additional change)

The Surveillance Requirements section of the Bases, under heading SR 3.5.8.3, is revised from...solution volume increase 15,000 gal. to...combined volume increase 15,000 gal.

In addition, SR 3.5.8.3 Frequency is revised from...solution volume increase 15,000 gal to

...combined volume increase 15,000 gal. (APOG Comment)

Date report generated:

Monday, April 20, 2015 Page 6 GTST AP1000- P08-3.5.8, Rev. 1

VI. Traveler Information

Description of TSTF changes:

None

Rationale for TSTF changes:

None

Description of changes in RCOL Std. Dep., RCOL COL Item(s), and RCOL PTS Changes:

VEGP LAR DOC A031 revises Required Action F.1 of TS 3.5.8 from Initiate action to be in MODE 6 with the water level 23 feet above the top of the reactor vessel flange. to Initiate action to establish water level 23 feet above the top of the reactor vessel flange.

VEGP LAR DOC A078 revises the third entry statement for Condition D of TS 3.5.8 by changing the IRWST borated water volume from a percent range of < 100% and > 97% to a specific range of 73,100 cu. ft. and > 70,907 cu. ft.

VEGP LAR DOC A079 revises the second Frequency for SR 3.5.8.3 from...solution volume increase of 15,000 gal to...solution volume increase of 15,000 gal. The associated Bases for SR 3.5.8.3 is also revised.

VEGP LAR DOC A081 revises Condition F of TS 3.5.8 by specifying the Conditions that are applicable to the first entry statement.

VEGP LAR DOC L01 revises SR 3.5.8.4 by adding the renumbered SR 3.5.6.11 to the listing of applicable SRs. Also, the Bases for SR 3.5.8.4 is revised.

VEGP LAR DOC L17 revises Condition B of TS 3.5.8 from Required IRWST injection line inoperable due to presence of noncondensible gases in one high point vent. to Required IRWST injection flow path with noncondensible gas volume in one squib valve outlet line pipe stub not within limit. The Required Action B.1 is revised from Vent noncondensible gases. to Restore noncondensible gas volume in squib valve outlet line pipe stub to within limit.

Condition C of TS 3.5.8 is revised from Required IRWST injection line inoperable due to presence of noncondensible gases in both high point vents. to Required IRWST injection flow path with noncondensible gas volume in both squib valve outlet line pipe stubs not within limit.

The Required Action C.1 is revised from Vent noncondensible gases from one high point vent.

to Restore noncondensible gas volume in one squib valve outlet line pipe stub to within limit.

The associated Actions section of the Bases is also revised.

Date report generated:

Monday, April 20, 2015 Page 7 GTST AP1000- P08-3.5.8, Rev. 1

Rationale for changes in RCOL Std. Dep., RCOL COL Item(s), and RCOL PTS Changes:

VEGP LAR DOC A031 changes to Required Action F.1 of TS 3.5.8 enhance TS clarity by deleting the reference to MODE 6 from the Required Action. TS 3.5.8 is applicable only in MODE 6 and is not necessary to refer to that mode in the associated Required Actions.

VEGP LAR DOC A078 changes to the third entry statement for Condition D of TS 3.5.8 and provides clarity by changing the IRWST borated water volume in units of cubic feet. Changing the volume unit of measure to cubic feet aligns with SR 3.5.8.2.

VEGP LAR DOC A079 changes to the second Frequency for SR 3.5.8.3 clarifies the requirement is also applicable to solution volume increase greater than 15,000 gallons.

VEGP LAR DOC A081 changes to the first entry statement for Condition F of TS 3.5.8 provide clarification by specifying the applicable Conditions.

VEGP LAR DOC L01 change to SR 3.5.8.4 by adding the renumbered SR 3.5.6.11 to the listing of applicable SRs is an editorial change due to changes to TS 3.5.6.

VEGP LAR DOC L17 changes TS 3.5.8 Condition B and C entry statements and LCO section of the Bases for consistency with LCO section of the Bases of TS 3.5.6. The changes to TS 3.5.8 Required Action B.1 and C.1 are for consistency with changes made to the associated entry conditions.

Description of additional changes proposed by NRC staff/preparer of GTST:

The Bases for Required Action B.1 and C.1 of TS 3.5.8 is revised by changing high point vents to injection flow path squib valve outlet line pipe stubs.

The Bases for SR 3.5.8.2 is revised by correcting the word intitial to initial.

Condition D and SR 3.5.8.2 of TS 3.5.8 is revised to correct cu. ft. to cu ft.

The phrase ECCS system is clarified and corrected to emergency core cooling system (ECCS) in the Actions section of the Bases, under heading A.1. (APOG Comment)

The first use of acronym DVI is corrected to direct vessel injection (DVI) in the Actions section of the Bases, under heading B.1. (APOG Comment)

The acronym PRA is corrected to include the phrase probabilistic risk assessment before (PRA) and DBAs is corrected to include the phrase design basis accidents before (DBAs) in the Actions section of the Bases, under heading D.1. In addition, the assumed number of failed boron injection sources (CMTs and Accumulators) is clarified in the Actions section of the Bases, under heading D.1. (APOG Comment)

In the Actions section of the Bases, under heading F.1 and F.2, second paragraph, fourth sentence is revised from withdrawal of reactivity control assemblies to withdrawal of control rods. (APOG Comment)

The second Frequency for SR 3.5.8.3 and Surveillance Requirements section of the Bases, under heading SR 3.5.8.3, is revised from...solution volume increase 15,000 gal to

...combined volume increase 15,000 gal. (APOG Comment)

Date report generated:

Monday, April 20, 2015 Page 8 GTST AP1000- P08-3.5.8, Rev. 1

Rationale for additional changes proposed by NRC staff/preparer of GTST:

The Bases for Required Action B.1 and C.1 of TS 3.5.8 is changed to provide consistency with VEGP LAR DOC L17 changes to Required Action B.1 and C.1. The change is also consistent with VEGP LAR DOC L17 changes to the Bases for Required Action B.1 and C.1 of TS 3.5.7, which are identical to Required Action B.1 and C.1 of TS 3.5.8.

Spelling correction in the Bases for SR 3.5.8.2 is an editorial change.

Changing cu. ft. to cu ft is an editorial correction. The change is in accordance with section 3.3.4.d of writer's guide TST-GG-05-01.

The change from ECCS system to emergency core cooling system (ECCS) is an editorial clarification and the correction is in conformance with TSTF-GG 01, section 3.2.2.a.

The change from DVI to direct vessel injection (DVI) is an editorial correction in conformance with TSTF-GG 01, section 3.2.2.a.

The change from PRA to probabilistic risk assessment (PRA) and DBAs to design basis accidents (DBAs) are editorial correction in conformance with TSTF-GG- 05-01, section 3.2.2.a and the change to the discussion of the assumed number of failed boron injection sources (CMTs and Accumulators) is an editorial clarification.

The change from reactivity control assemblies to control rods in the Actions section of the Bases is for editorial improvement and consistency with other TS Bases discussions.

The change from...solution volume increase 15,000 gal to...combined volume increase 15,000 gal is a non-technical change that provides improved clarity, consistency, and operator usability.

Date report generated:

Monday, April 20, 2015 Page 9 GTST AP1000- P08-3.5.8, Rev. 1

VII. GTST Safety Evaluation

Technical Analysis:

VEGP LAR DOC L17: As stated in the associated Bases for the GTS 3.5.8 Actions, the presence of some noncondensible gases does not mean that the CMT is immediately inoperable, but that gases are collecting and should be vented. TS 3.5.8, Condition B and C are revised for consistency.

GTS 3.5.8, Required Action B.1 and C.1 are revised to replace a specific method of restoration with a more general action to restore the parameter, in this case noncondensible gas volume, to within its limit. This change is made for consistency with the revised entry conditions associated with the Required Action. Only the specific method is deleted from the action. The associated Bases, both GTS and revised, describe an appropriate method for restoration. The revised Action continues to provide assurance that operation with a noncondensible gas volume that can affect the associated flow path is allowed for only a limited period of time. These changes are designated as less restrictive because the specific method of restoration is deleted and replaced with a more general requirement to restore within the limit.

Other Changes: The remaining changes are editorial, clarifying, grammatical, or otherwise considered administrative. These changes do not affect the technical content, but improve the readability, implementation, and understanding of the requirements, and are therefore acceptable.

Having found that this GTSTs proposed changes to the GTS and Bases are acceptable, the NRC staff concludes that AP1000 STS Subsection 3.5.8 is an acceptable model Specification for the AP1000 standard reactor design.

References to Previous NRC Safety Evaluation Reports (SERs):

None

Date report generated:

Monday, April 20, 2015 Page 10 GTST AP1000- P08-3.5.8, Rev. 1

VIII. Review Information

Evaluator Comments:

None

Steve Short Pacific Northwest National Laboratory 509-375-2868 steve.short@pnnl.gov

Review Information:

Availability for public review and comment on Revision 0 of this traveler approved by NRC staff on 5/23/2014.

APOG Comments (Ref. 7) and Resolutions:

1. (Internal #2) Approved TSTF-523 is not dispositioned in the material provided to support the GTSTs. Include TSTF-523 in the reference disposition tables, as TSTF deferred for future consideration. This is resolved by dispositioningTSTF-523, Rev. 1 as not applicable to the GTS and stating that the concerns of the TSTF have been addressed by GTS Rev.19.
2. (Internal #6) The GTST sections often repeat VEGP LAR DOCs, which reference existing and current requirements. The inclusion in the GTST of references to existing and current, are not always valid in the context of the GTS. Each occurrence of existing and current should be revised to be clear and specific to GTS, MTS, or VEGP COL TS (or other), as appropriate. This is resolved by making the APOG recommended changes to the GTST.
3. (Internal #13) The NRC approval of TSTF-425, and model safety evaluation provided in the CLIIP for TSTF-425, are generically applicable to any designs Technical Specifications. As such, the replacement of certain Frequencies with a Surveillance Frequency Control Program should be included in the GTST for AP1000 STS NUREG.

However, implementation in the AP1000 STS should not reflect optional (i.e., bracketed) material showing retention of fixed Surveillance Frequencies where relocation to a Surveillance Frequency Control Program is acceptable. Since each represented AP1000 Utility is committed to maintaining standardization, there is no rationale for an AP1000 STS that includes bracketed options.

Consistent with TSTF-425 criteria, replace applicable Surveillance Frequencies with In accordance with the Surveillance Frequency control Program and add that Program as new AP1000 STS Specification 5.5.15. NRC Staff disagrees with implementing TSTF-425. The TSTF is deferred for future consideration.

4. (Internal #295) The SPSB proposed change to correct cu. ft. to cu ft is part of comment
  1. 295.

Date report generated:

Monday, April 20, 2015 Page 11 GTST AP1000- P08-3.5.8, Rev. 1

5. (Internal #330) APOG recommends making the editorial changes in the Actions section of the Bases, under heading A.1. These non-technical changes provide improved clarity, consistency, and operator usability. This is resolved by making the suggested changes and adding a comma after (ECCS) as follows:

The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time is consistent with times normally applied to a degraded two train emergency core cooling system (ECCS), systems which can provide 100% of the required flow without a single failure.

6. (Internal #331) APOG recommends making the editorial changes in the Actions section of the Bases, under heading B.1. These non-technical changes provide improved clarity, consistency, and operator usability. This is resolved by making the suggested changes as follows:

A direct vessel injection (DVI) line break is not postulated in MODE 6.

7. (Internal #332) Editorial change is recommended to the Actions section of the Bases, under heading D.1. These non-technical changes provide improved clarity, consistency, and operator usability. This is resolved by making the suggested changes and additional changes to the assumed multiple failures of the boron injection sources statement as follows:

This limit prevents a significant change in boron concentration and is consistent with the long-term cooling analysis performed to justify probabilistic risk assessment (PRA) success criteria (Ref. 3), which assumed multiple failures with as many as three of the four boron injection sources (two CMTs and two Accumulators) 3 CMTs/Accum not injecting.The 8 -hour Completion Time is acceptable, considering that the IRWST will be fully capable of performing its assumed safety function in response to design basis accidents (DBAs) with slight deviations in these parameters.

8. (Internal #328) Revise various TS Bases stating withdrawal of reactivity control assemblies to withdrawal of control rods for editorial improvement and consistency with other TS Bases discussions. This is resolved by making the suggested changes in the Actions section of the Bases, under heading F.1 and F.2 as follows:

Sources of positive reactivity addition include boron dilution, withdrawal of reactivity control assembliesrods, and excessive cooling of the RCS.

9. (Internal #334) Editorial change is recommended to the Surveillance Requirements section of the Bases, under heading SR 3.5.8.3. These non-technical changes provide improved clarity, consistency, and operator usability. This is resolved by making the suggested change and additional change to the second Frequency for SR 3.5.8.3 as follows:

...solutioncombined volume increase 15,000 gal

Date report generated:

Monday, April 20, 2015 Page 12 GTST AP1000- P08-3.5.8, Rev. 1

NRC Final Approval Date: 4/20/2015

NRC

Contact:

Derek Scully United States Nuclear Regulatory Commission 301-415-6972 Derek.Scully@nrc.gov

Date report generated:

Monday, April 20, 2015 Page 13 GTST AP1000- P08-3.5.8, Rev. 1

IX. Evaluator Comments for Consideration in Finalizing Technical Specifications and Bases

None

Date report generated:

Monday, April 20, 2015 Page 14 GTST AP1000- P08-3.5.8, Rev. 1

X. References Used in GTST

1. AP1000 DCD, Revision 19, Section 16, Technical Specifications, June 2011 (ML11171A500).
2. Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Units 3 and 4, Technical Specifications Upgrade License Amendment Request, February 24, 2011 (ML12065A057).
3. TSTF-GG-05-01, Writer's Guide for Plant-Specific Improved Technical Specifications, June 2005 (ML070660229).
4. Southern Nuclear Operating Company, Vogtle Electric Generating Plant, Units 3 and 4, Response to Request for Additional Information Letter No. 01 Related to License Amendment Request LAR 002, ND 2015, October 04, 2012 (ML12286A363 and ML12286A360).
5. NRC Safety Evaluation (SE) for Amendment No. 13 to Combined License (COL) No. NPF-91 for Vogtle Electric Generating Plant (VEGP) Unit 3, and Amendment No. 13 to COL No.

NPF-92 for VEGP Unit 4, September 9, 2013, ADAMS Package Accession No. ML13238A337, which contains:

ML13238A355 Cover Letter - Issuance of License Amendment No. 13 for Vogtle Units 3 and 4 (LAR 12-002).

ML13238A359 Enclosure 1 - Amendment No. 13 to COL No. NPF-91 ML13239A256 Enclosure 2 - Amendment No. 13 to COL No. NPF-92 ML13239A284 Enclosure 3 - Revised plant-specific TS pages (Attachment to Amendment No. 13)

ML13239A287 Enclosure 4 - Safety Evaluation (SE), and Attachment 1 - Acronyms ML13239A288 SE Attachment 2 - Table A - Administrative Changes ML13239A319 SE Attachment 3 - Table M - More Restrictive Changes ML13239A333 SE Attachment 4 - Table R - Relocated Specifications ML13239A331 SE Attachment 5 - Table D - Detail Removed Changes ML13239A316 SE Attachment 6 - Table L - Less Restrictive Changes

The following documents were subsequently issued to correct an administrative error in Enclosure 3:

ML13277A616 Letter - Correction To The Attachment (Replacement Pages) - Vogtle Electric Generating Plant Units 3 and 4-Issuance of Amendment Re:

Technical Specifications Upgrade (LAR 12- 002) (TAC No. RP9402)

ML13277A637 Enclosure 3 - Revised plant-specific TS pages (Attachment to Amendment No. 13) (corrected)

6. RAI Letter No. 01 Related to License Amendment Request (LAR) 12- 002 for the Vogtle Electric Generating Plant Units 3 and 4 Combined Licenses, September 7, 2012 (ML12251A355).
7. APOG-2014- 008, APOG (AP1000 Utilities) Comments on AP1000 Standardized Technical Specifications (STS) Generic Technical Specification Travelers (GTSTs), Docket ID NRC-2014- 0147, September 22, 2014 (ML14265A493).

Date report generated:

Monday, April 20, 2015 Page 15 GTST AP1000- P08-3.5.8, Rev. 1

Date report generated:

Monday, April 20, 2015 Page 16 GTST AP1000- P08-3.5.8, Rev. 1

XI. MARKUP of the Applicable GTS Subsection for Preparation of the STS NUREG

The entire section of the Specifications and the Bases associated with this GTST is presented next.

Changes to the Specifications and Bases are denoted as follows: Deleted portions are marked in strikethrough red font, and inserted portions in bold blue font.

Date report generated:

Monday, April 20, 2015 Page 17 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 3.5.8

3.5 PASSIVE CORE COOLING SYSTEM (PXS)

3.5.8 In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6

LCO 3.5.8 The IRWST, with one injection flow path and one containment recirculation flow path, shall be OPERABLE.

APPLICABILITY: MODE 6.

ACTIONS

CONDITION REQUIRED ACTION COMPLETION TIME

A. Required motor A.1 Open required motor 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> operated containment operated containment recirculation isolation recirculation isolation valve.

valve not fully open.

B. Required IRWST B.1 Vent noncondensible 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> injection flow path gasesRestore withline inoperable due noncondensible gas to presence of volume in squib valve noncondensible gases in outlet line pipe stub to one high point vent within limit.

volume in one squib valve outlet line pipe stub not within limit.

C. Required IRWST C.1 Vent noncondensible gases 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> injection flow path from one high point withline inoperable due ventRestore to presence of noncondensible gas noncondensible gases in volume in one squib both high point vents valve outlet line pipe stub volume in both squib to within limit.

valve outlet line pipe stubs not within limit.

AP1000 STS 3.5.8-1 Amendment 0Rev. 0 Revision 19 Date report generated:

Monday, April 20, 2015 Page 18 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 3.5.8

ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME

D. IRWST and refueling D.1 Restore IRWST to 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> cavity boron concentra-OPERABLE status.

tion not within limits.

OR

IRWST and refueling cavity borated water temperature not within limits.

OR

IRWST and refueling cavity borated water volume 73,100 cu. ft.

and > 70,907 cu. ft.<

100% and > 97% of limit.

E. Required motor E.1 Restore required motor 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> operated IRWST operated IRWST isolation isolation valve not fully valve to fully open condition open. with power removed.

OR

Power is not removed from required motor operated IRWST isolation valve.

AP1000 STS 3.5.8-2 Amendment 0Rev. 0 Revision 19 Date report generated:

Monday, April 20, 2015 Page 19 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 3.5.8

ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME

F. Required Action and F.1 Initiate action to Immediately associated Completion establishbe in MODE 6 Ti m e of Condition A, B, with the water level 23 C, D, or E not met. feet above the top of the reactor vessel flange.

OR AND LCO not met for reasons other than Condition A, F.2 Suspend positive reactivity Immediately B, C, D, or E. additions.

SURVEILLANCE REQUIREMENTS

SURVEILLANCE FREQUENCY

SR 3.5.8.1 Verify the IRWST and refueling cavity water 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> temperature is < 120°F.

SR 3.5.8.2 Verify the IRWST and refueling cavity water total 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> borated water volume is > 73,100 cu. ft.

SR 3.5.8.3 Verify the IRWST and refueling cavity boron s concentration is 2600 ppm and.

A

lnceh 6 s afth sicombined volume increase of 15,000 gal

AP1000 STS 3.5.8-3 Amendment 0Rev. 0 Revision 19 Date report generated:

Monday, April 20, 2015 Page 20 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 3.5.8

SURVEILLANCE REQUIREMENTS (continued)

SURVEILLANCE FREQUENCY

SR 3.5.8.4 For the IRWST and flow paths required to be In accordance OPERABLE, the following SRs of Specification 3.5.6, with applicable In-containment Refueling Water Storage Tank SRs

( I RW ST) - Operating are applicable:

SR 3.5.6.3 SR 3.5.6.6 SR 3.5.6.8 SR 3.5.6.10 SR 3.5.6.5 SR 3.5.6.7 SR 3.5.6.9 SR 3.5.6.11

AP1000 STS 3.5.8-4 Amendment 0Rev. 0 Revision 19 Date report generated:

Monday, April 20, 2015 Page 21 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 B 3.5.8

B 3.5 PASSIVE CORE COOLING SYSTEM (PXS)

B 3.5.8 In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6

BASES

BACKGROUND A description of the IRWST is provided in LCO 3.5.6, In-containment Refueling Water Storage Tank (IRWST) - Operating.

APPLICABLE For MODE 6, heat removal is provided by IRWST injection and SAFETY containment sump recirculation.

ANALYSES IRWST injection could be required to mitigate some events by providing RCS inventory makeup.

One line with redundant, parallel valves is required to accommodate a single failure (to open) of an isolation valve.

The IRWST satisfies Criteria 2 and 3 of 10 CFR 50.36(c)(2)(ii).

LCO The IRWST requirements ensure that an adequate supply of borated water is available to supply the required volume of borated water as safety injection for core cooling and reactivity control.

To be considered OPERABLE, the IRWST in combination with the refueling cavity must meet the water volume, boron concentration, and temperature limits defined in the Surveillance Requirements, and one path of injection and recirculation must be OPERABLE. The motor operated injection isolation valve must be open and power removed, and the motor operated sump recirculation isolation valves must be open and OPERABLE. Any cavity leakage should be estimated and made up with borated water such that the volume in the IRWST plus the refueling cavity will meet the IRWST volume requirement. The absence of noncondensible gases in the high point vents is necessary for system OPERABILITY.OPERABILITY is not expected to be challenged due to small gas accumulations in the high point, and rapid gas accumulations are not expected during plant operation. However, a relatively small gas volume was incorporated into the design for alerting operators to provide sufficient time to initiate venting operations before the gas volume would be expected to increase to a sufficient volume that might potentially challenge the OPERABILITY of passive safety injection flow. Noncondensible gas accumulation in the injection line high point that causes the water

AP1000 STS B 3.5.8-1 Amendment 0Rev. 0 Revision 19 Date report generated:

Monday, April 20, 2015 Page 22 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 B 3.5.8

BASES

LCO (continued)

level to drop below the sensor will require operator action to investigate the cause of the gas accumulation and to vent the associated high point(s).

APPLICABILITY In MODE 6, the IRWST is an Reactor Coolant System (RCS) injection source of borated water for core cooling and reactivity control.

The requirements for the IRWST in MODES 1, 2, 3, and 4 are specified in LCO 3.5.6, In-containment Refueling Water Storage Tank (IRWST) -

Operating. The requirements for the IRWST in MODE 5 are specified in LCO 3.5.7, In-containment Refueling Water Storage Tank (IRWST) -

Shutdown, MODE 5.

ACTIONS A.1

With the required motor operated containment sump isolation valve not fully open, the valve must be fully opened within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time is consistent with times normally applied to a degraded two train emergency core cooling system (ECCS), systems which can provide 100% of the required flow without a single failure.

B.1

Excessive amounts of noncondensible gases in one of the injection flow path squib valve outlet line pipe stubshigh point vents in the required IRWST injection line may interfere with the passive injection of IRWST water into the reactor vessel from the associated parallel flow path in the affected injection line. Analyses have shown that with enough noncondensible gas accumulation, IRWST injection through the affected flow path could be delayed. However, the presence of some noncondensible gases does not mean that the IRWST injection capability is immediately inoperable, but that gases are collecting and should be vented. Venting of these gases requires containment entry to manually operate the vent valves. In this Condition, the parallel flow path in the affected injection line is capable of providing 100% of the required injection. A direct vessel injection (DVI) line break is not postulated in MODE 6. A Completion Time of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> is acceptable since the IRWST is capable of performing the safety function without a single failure of the remaining parallel isolation valve. In addition, the 72-hour Completion Time is consistent with the time normally applicable to one inoperable train in a two train ECCS system.

AP1000 STS B 3.5.8-2 Amendment 0Rev. 0 Revision 19 Date report generated:

Monday, April 20, 2015 Page 23 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 B 3.5.8

BASES

ACTIONS (continued)

C.1

Excessive amounts of noncondensible gases in both of the injection flow path squib valve outlet line pipe stubshigh point vents in the required IRWST injection line may interfere with the passive injection of IRWST water into the reactor vessel from the affected injection line.

Analyses have shown that with enough noncondensible gas accumulation, IRWST injection could be delayed long enough to cause core uncover. However, the presence of some noncondensible gases does not mean that the IRWST injection capability is immediately inoperable, but that gases are collecting and should be vented. Venting of these gases requires containment entry to manually operate the vent valves. Considering the slow rate of gas accumulation, venting within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> should normally prevent accumulation of amounts of noncondensible gases that could interfere with IRWST injection. A Completion Time of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> is permitted for venting noncondensible gases and is acceptable since the injection capability is not significantly affected. If only one of the affected injection flow path squib valve outlet line pipe stubshigh point vents is vented, then Condition B will apply to the remaining high point vent with noncondensible gas accumulation.

D.1

If the IRWST and refueling cavity water volume, boron concentration, or temperature are not within limits, the core cooling capability from injection or PRHR HX heat transfer and the reactivity benefit of injection assumed in safety analyses may not be available. Due to the large volume of the IRWST, online monitoring of volume and temperature, and frequent surveillances, the deviation of these parameters is expected to be minor.

The allowable deviation of the water volume is limited to 3%. This limit prevents a significant change in boron concentration and is consistent with the long-term cooling analysis performed to justify probabilistic risk assessment (PRA) success criteria (Ref. 3), which assumed multiple failures with as many as three of the four boron injection sources (two CMTs and two Accumulators)3 CMTs/Accum not injecting. This analysis shows that there is significant margin with respect to the water supplies that support containment recirculation operation. The 8-hour Completion Time is acceptable, considering that the IRWST will be fully capable of performing its assumed safety function in response to design basis accidents (DBAs) with slight deviations in these parameters.

AP1000 STS B 3.5.8-3 Amendment 0Rev. 0 Revision 19 Date report generated:

Monday, April 20, 2015 Page 24 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 B 3.5.8

BASES

ACTIONS (continued)

E.1

If the required motor operated IRWST isolation valve is not fully open or valve power is not removed, injection flow from the IRWST may be less than assumed in the safety analysis. In this situation, the valve must be restored to fully open with valve power removed in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This Completion Time is acceptable based on risk considerations.

F.1 and F.2

If the IRWST cannot be returned to OPERABLE status within the associated Completion Times or the LCO is not met for reasons other than Conditions A, B, C, D, or E, the plant must be placed in a Condition in which the probability and consequences of an event are minimized to the extent possible. In MODE 6, action must be immediately initiated to be in MODE 6 with the cavity water level 23 feet above the top of the reactoressl.

The timeoCplisaximized byaximiziCpenty and mCp temperate assractic. ithCp it,ther m of ring dectsvlable Ethe moeo eu). Adtily, tioto sus pitive retivity tions is ruiretensth thpaM is maiai poces sitiv rctivity aitioilu bodilio withdral reacti vy contr rodsassemblies, and excessive cooling of the RCS. These Actions place the plant in a condition which maximizes the time to IRWST injection, thus providing time for repairs or application of alternative cooling capabilities.

SURVEILLANCE SR 3.5.8.1 REQUIREMENTS The IRWST and refueling cavity borated water temperature must be verified every 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to ensure that the temperature is within the limit assumed in accident analysis. This Frequency is sufficient to identify a temperature change that would approach the limit and has been shown to be acceptable through operating experience.

AP1000 STS B 3.5.8-4 Amendment 0Rev. 0 Revision 19 Date report generated:

Monday, April 20, 2015 Page 25 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 B 3.5.8

BASES

SURVEILLANCE REQUIREMENTS (continued)

SR 3.5.8.2

Verification every 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> that the IRWST and refueling cavity borated water volume is above the required minimum level will ensure that a sufficient initialintitial supply is available for safety injection and floodup volume for recirculation and as the heat sink for PRHR. During shutdown with the refueling cavity flooded with water from the IRWST, the Surveillance requires that the combined volume of borated water in the IRWST and refueling cavity meets the specified limit. Since the IRWST volume is normally stable, and is monitored by redundant main control indication and alarm, a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is appropriate.

SR 3.5.8.3

Verification every 31 days that the boron concentration of the IRWST and refueling cavity is greater than the required limit ensures that the reactor will remain subcritical following shutdown events. Since the IRWST volume is large and normally stable, the 31 day Frequency is acceptable, considering additional verifications are required within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> after each solutioncombined volume increase of 15,000 gal.

SR 3.5.8.4

LCO 3.5.6 Surveillance Requirements and Frequencies SR 3.5.6.3 and 3.5.6.5 through 3.5.6.1110 are applicable to the IRWST and the flow paths required to be OPERABLE. Refer to the corresponding Bases for LCO 3.5.6 for a discussion of each SR.

REFERENCES None.

AP1000 STS B 3.5.8-5 Amendment 0Rev. 0 Revision 19 Date report generated:

Monday, April 20, 2015 Page 26 GTST AP1000- P08-3.5.8, Rev. 1

XII. Applicable STS Subsection After Incorporation of this GTSTs Modifications

The entire subsection of the Specifications and the Bases associated with this GTST, following incorporation of the modifications, is presented next.

Date report generated:

Monday, April 20, 2015 Page 27 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 3.5.8

3.5 PASSIVE CORE COOLING SYSTEM (PXS)

3.5.8 In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6

LCO 3.5.8 The IRWST, with one injection flow path and one containment recirculation flow path, shall be OPERABLE.

APPLICABILITY: MODE 6.

ACTIONS

CONDITION REQUIRED ACTION COMPLETION TIME

A. Required motor A.1 Open required motor 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> operated containment operated containment recirculation isolation recirculation isolation valve.

valve not fully open.

B. Required IRWST B.1 Restore noncondensible 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> injection flow path with gas volume in squib valve noncondensible gas outlet line pipe stub to volume in one squib within limit.

valve outlet line pipe stub not within limit.

C. Required IRWST C.1 Restore noncondensible 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> injection flow path with gas volume in one squib noncondensible gas valve outlet line pipe stub to volume in both squib within limit.

valve outlet line pipe stubs not within limit.

AP1000 STS 3.5.8-1 Rev. 0

Date report generated:

Monday, April 20, 2015 Page 28 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 3.5.8

ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME

D. IRWST and refueling D.1 Restore IRWST to 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> cavity boron concentra-OPERABLE status.

tion not within limits.

OR

IRWST and refueling cavity borated water temperature not within limits.

OR

IRWST and refueling cavity borated water volume 73,100 cu ft and > 70,907 cu ft.

E. Required motor E.1 Restore required motor 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> operated IRWST operated IRWST isolation isolation valve not fully valve to fully open condition open. with power removed.

OR

Power is not removed from required motor operated IRWST isolation valve.

AP1000 STS 3.5.8-2 Rev. 0

Date report generated:

Monday, April 20, 2015 Page 29 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 3.5.8

ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME

F. Required Action and F.1 Initiate action to establish Immediately associated Completion water level 23 feet above Ti m e of Condition A, B, the top of the reactor vessel C, D, or E not met. flange.

OR AND

LCO not met for reasons F.2 Suspend positive reactivity Immediately other than Condition A, additions.

B, C, D, or E.

SURVEILLANCE REQUIREMENTS

SURVEILLANCE FREQUENCY

SR 3.5.8.1 Verify the IRWST and refueling cavity water 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> temperature is < 120°F.

SR 3.5.8.2 Verify the IRWST and refueling cavity water total 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> borated water volume is > 73,100 cu ft.

SR 3.5.8.3 Verify the IRWST and refueling cavity boron s concentration is 2600 ppm and.

A

lnceh 6 s afth cned v irease of 15,000 gal

AP1000 STS 3.5.8-3 Rev. 0

Date report generated:

Monday, April 20, 2015 Page 30 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 3.5.8

SURVEILLANCE REQUIREMENTS (continued)

SURVEILLANCE FREQUENCY

SR 3.5.8.4 For the IRWST and flow paths required to be In accordance OPERABLE, the following SRs are applicable: with applicable SRs SR 3.5.6.3 SR 3.5.6.6 SR 3.5.6.8 SR 3.5.6.10 SR 3.5.6.5 SR 3.5.6.7 SR 3.5.6.9 SR 3.5.6.11

AP1000 STS 3.5.8-4 Rev. 0

Date report generated:

Monday, April 20, 2015 Page 31 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 B 3.5.8

B 3.5 PASSIVE CORE COOLING SYSTEM (PXS)

B 3.5.8 In-containment Refueling Water Storage Tank (IRWST) - Shutdown, MODE 6

BASES

BACKGROUND A description of the IRWST is provided in LCO 3.5.6, In-containment Refueling Water Storage Tank (IRWST) - Operating.

APPLICABLE For MODE 6, heat removal is provided by IRWST injection and SAFETY containment sump recirculation.

ANALYSES IRWST injection could be required to mitigate some events by providing RCS inventory makeup.

One line with redundant, parallel valves is required to accommodate a single failure (to open) of an isolation valve.

The IRWST satisfies Criteria 2 and 3 of 10 CFR 50.36(c)(2)(ii).

LCO The IRWST requirements ensure that an adequate supply of borated water is available to supply the required volume of borated water as safety injection for core cooling and reactivity control.

To be considered OPERABLE, the IRWST in combination with the refueling cavity must meet the water volume, boron concentration, and temperature limits defined in the Surveillance Requirements, and one path of injection and recirculation must be OPERABLE. The motor operated injection isolation valve must be open and power removed, and the motor operated sump recirculation isolation valves must be open and OPERABLE. Any cavity leakage should be estimated and made up with borated water such that the volume in the IRWST plus the refueling cavity will meet the IRWST volume requirement. OPERABILITY is not expected to be challenged due to small gas accumulations in the high point, and rapid gas accumulations are not expected during plant operation. However, a relatively small gas volume was incorporated into the design for alerting operators to provide sufficient time to initiate venting operations before the gas volume would be expected to increase to a sufficient volume that might potentially challenge the OPERABILITY of passive safety injection flow. Noncondensible gas accumulation in the injection line high point that causes the water level to drop below the sensor will require operator action to inve stigate the cause of the gas accumulation and to vent the associated high point(s).

AP1000 STS B 3.5.8-1 Rev. 0

Date report generated:

Monday, April 20, 2015 Page 32 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 B 3.5.8

BASES

APPLICABILITY In MODE 6, the IRWST is an Reactor Coolant System (RCS) injection source of borated water for core cooling and reactivity control.

The requirements for the IRWST in MODES 1, 2, 3, and 4 are specified in LCO 3.5.6, In-containment Refueling Water Storage Tank (IRWST) -

Operating. The requirements for the IRWST in MODE 5 are specified in LCO 3.5.7, In-containment Refueling Water Storage Tank (IRWST) -

Shutdown, MODE 5.

ACTIONS A.1

With the required motor operated containment sump isolation valve not fully open, the valve must be fully opened within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time is consistent with times normally applied to a degraded two train emergency core cooling system (ECCS), which can provide 100% of the required flow without a single failure.

B.1

Excessive amounts of noncondensible gases in one of the injection flow path squib valve outlet line pipe stubs in the required IRWST injection line may interfere with the passive injection of IRWST water into the reactor vessel from the associated parallel flow path in the affected injection line. Analyses have shown that with enough noncondensible gas accumulation, IRWST injection through the affected flow path could be delayed. However, the presence of some noncondensible gases does not mean that the IRWST injection capability is immediately inoperable, but that gases are collecting and should be vented. Venting of these gases requires containment entry to manually operate the vent valves. In this Condition, the parallel flow path in the affected injection line is capable of providing 100% of the required injection. A direct vessel injection (DVI) line break is not postulated in MODE 6. A Completion Time of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> is acceptable since the IRWST is capable of performing the safety function without a single failure of the remaining parallel isolation valve. In addition, the 72-hour Completion Time is consistent with the time normally applicable to one inoperable train in a two train ECCS system.

AP1000 STS B 3.5.8-2 Rev. 0

Date report generated:

Monday, April 20, 2015 Page 33 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 B 3.5.8

BASES

ACTIONS (continued)

C.1

Excessive amounts of noncondensible gases in both of the injection flow path squib valve outlet line pipe stubs in the required IRWST injection line may interfere with the passive injection of IRWST water into the reactor vessel from the affected injection line. Analyses have shown that with enough noncondensible gas accumulation, IRWST injection could be delayed long enough to cause core uncover. However, the presence of some noncondensible gases does not mean that the IRWST injection capability is immediately inoperable, but that gases are collecting and should be vented. Venting of these gases requires containment entry to manually operate the vent valves. Considering the slow rate of gas accumulation, venting within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> should normally prevent accumulation of amounts of noncondensible gases that could interfere with IRWST injection. A Completion Time of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> is permitted for venting noncondensible gases and is acceptable since the injection capability is not significantly affected. If only one of the affected injection flow path squib valve outlet line pipe stubs is vented, then Condition B will apply to the remaining high point vent with noncondensible gas accumulation.

D.1

If the IRWST and refueling cavity water volume, boron concentration, or temperature are not within limits, the core cooling capability from injection or PRHR HX heat transfer and the reactivity benefit of injection assumed in safety analyses may not be available. Due to the large volume of the IRWST, online monitoring of volume and temperature, and frequent surveillances, the deviation of these parameters is expected to be minor.

The allowable deviation of the water volume is limited to 3%. This limit prevents a significant change in boron concentration and is consistent with the long-term cooling analysis performed to justify probabilistic risk assessment (PRA) success criteria (Ref. 3), which assumed multiple failures with as many as three of the four boron injection sources (two CMTs and two Accumulators) not injecting. This analysis shows that there is significant margin with respect to the water supplies that support containment recirculation operation. The 8-hour Completion Time is acceptable, considering that the IRWST will be fully capable of performing its assumed safety function in response to design basis accidents (DBAs) with slight deviations in these parameters.

AP1000 STS B 3.5.8-3 Rev. 0

Date report generated:

Monday, April 20, 2015 Page 34 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 B 3.5.8

BASES

ACTIONS (continued)

E.1

If the required motor operated IRWST isolation valve is not fully open or valve power is not removed, injection flow from the IRWST may be less than assumed in the safety analysis. In this situation, the valve must be restored to fully open with valve power removed in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This Completion Time is acceptable based on risk considerations.

F.1 and F.2

If the IRWST cannot be returned to OPERABLE status within the associated Completion Times or the LCO is not met for reasons other than Conditions A, B, C, D, or E, the plant must be placed in a Condition in which the probability and consequences of an event are minimized to the extent possible. In MODE 6, action must be immediately initiated to be in MODE 6 with the cavity water level 23 feet above the top of the reactoressl.

The timeoCplisaximized byaximiziCpenty and mCp temperate assractic. ithCp it,ther of ring dectsvlable Ethe moeo eu). Adtily, tioto sus pitive retivity tions is ruiretensth thpaM is maiai poces sitiv rctivity aitioilu bodilio withdr al contr rods csiveooling ofCp.ThesActions ple t plant ctich maximizimtfotpTtion, thus pring timfrsr applicion of altnivcooliapabiliti.

osbfiiC po 3 nMbp The fotpTefueliityatatemperateust vified every O4 hours to enset the temperesittimit scilysis.Thisrys sficient tidentify a trure cthatouloachimitshow t acctable thr operating experience.

AP1000 STS B 3.5.8-4 Rev. 0

Date report generated:

Monday, April 20, 2015 Page 35 GTST AP1000- P08-3.5.8, Rev. 1

IRWST - Shutdown, MODE 6 B 3.5.8

BASES

SURVEILLANCE REQUIREMENTS (continued)

SR 3.5.8.2

Verification every 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> that the IRWST and refueling cavity borated water volume is above the required minimum level will ensure that a sufficient initial supply is available for safety injection and floodup volume for recirculation and as the heat sink for PRHR. During shutdown with the refueling cavity flooded with water from the IRWST, the Surveillance requires that the combined volume of borated water in the IRWST and refueling cavity meets the specified limit. Since the IRWST volume is normally stable, and is monitored by redundant main control indication and alarm, a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is appropriate.

SR 3.5.8.3

Verification every 31 days that the boron concentration of the IRWST and refueling cavity is greater than the required limit ensures that the reactor will remain subcritical following shutdown events. Since the IRWST volume is large and normally stable, the 31 day Frequency is acceptable, considering additional verifications are required within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> after each combined volume increase of 15,000 gal.

SR 3.5.8.4

LCO 3.5.6 Surveillance Requirements and Frequencies SR 3.5.6.3 and 3.5.6.5 through 3.5.6.11 are applicable to the IRWST and the flow paths required to be OPERABLE. Refer to the corresponding Bases for LCO 3.5.6 for a discussion of each SR.

REFERENCES None.

AP1000 STS B 3.5.8-5 Rev. 0