ML22242A299: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:August 30, 2022 FS-M-22-0026 ATTN: Pierre M. Saverot, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Orano Federal Services LLC 505 South 336th Street    
{{#Wiki_filter:August 30, 2022 FS-M-22-0026
 
ATTN: Pierre M. Saverot, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards
 
Orano Federal Services LLC
 
505 South 336th Street  


==SUBJECT:==
==SUBJECT:==
Schedule Update Needed for Response to RAIs on CR3MP Suite 400 Federal Way WA 98003 Tel: +1 253-552-1322
Schedule Update Needed for Response to RAIs on CR3MP Suite 400 Federal Way WA 98003
 
Tel: +1 253-552-1322  


==References:==
==References:==
Line 24: Line 32:


==SUBJECT:==
==SUBJECT:==
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE MODEL NO. CR3MP PACKAGE, dated June 24, 2022.
REQUEST FOR ADDITIONAL INFORMAT ION FOR THE REVIEW OF THE MODEL NO. CR3MP PACKAGE, dated June 24, 2022.


==Dear Mr. Saverot:==
==Dear Mr. Saverot:==
This letter regards Docket No. 71-9393 Crystal River 3 Middle Package (CR3MP) and Enterprise Project Identifier (EPID) No. L2021-NEW- 0003.


This letter regards Docket No. 71-9393 Crystal River 3 Middle Package (CR3MP) and Enterprise Project Identifier (EPID) No. L2021-NEW- 0003.
We have received and reviewed the RAIs sent to us by {{letter dated|date=June 24, 2022|text=letter dated June 24, 2022}} (Reference 1) on the CR3MP license application. After reviewing the amount of calculation work that must be performed, we have determined that we will be unable to meet the proposed schedule submittal of responses date of October 15, 2022. Due to resource constraints, we need to delay our response due date to November 21, 2022.
We have received and reviewed the RAIs sent to us by {{letter dated|date=June 24, 2022|text=letter dated June 24, 2022}} (Reference 1) on the CR3MP license application. After reviewing the amount of calculation work that must be performed, we have determined that we will be unable to meet the proposed schedule submittal of responses date of October 15, 2022. Due to resource constraints, we need to delay our response due date to November 21, 2022.
Should you have any questions regarding this letter, please dont hesitate to contact me at: (253) 552-1322 or via email (chris.backus@orano.group).
Should you have any questions regarding this letter, please dont hesitate to contact me at: (253) 552-1322 or via email (chris.backus@orano.group).
Yours Truly, Digitally signed by BACKUS BACKUS Christopher Christopher Date: 2022.08.30 13:53:25 -07'00' Chris Backus Orano Federal Services LLC Copies (per email):
 
Phil Noss, Licensing Manager, Orano Federal Services LLC Scott Edwards, Project Manager, Orano Decommissioning Services LLC Tom Criddle, Project Manager, Orano Federal Services LLC Armando Merlin, Project Technical Lead, Orano Federal Services LLC www.orano.group                                                                                       1}}
Yours Truly,
 
Chris Backus Orano Federal Services LLC
 
Copies (per email):
Phil Noss, Licensing Manager, Orano Federal Services LLC Scott Edwards, Project Manager, Orano Decommissioning Services LLC Tom Criddle, Project Manager, Orano Federal Services LLC Armando Merlin, Project Technical Lead, Orano Federal Services LLC
 
www.orano.group 1}}

Revision as of 04:29, 16 November 2024

Orano Federal Services, LLC - Schedule Update Needed for Response to RAIs on Crystal River 3 Middle Package (CR3MP)
ML22242A299
Person / Time
Site: 07109393
Issue date: 08/30/2022
From: Backus C
Orano Federal Services
To: Pierre Saverot
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
Download: ML22242A299 (1)


Text

August 30, 2022 FS-M-22-0026

ATTN: Pierre M. Saverot, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards

Orano Federal Services LLC

505 South 336th Street

SUBJECT:

Schedule Update Needed for Response to RAIs on CR3MP Suite 400 Federal Way WA 98003

Tel: +1 253-552-1322

References:

1) NRC Letter from Mr. Pierre M. Saverot to Mr. Philip Noss,

SUBJECT:

REQUEST FOR ADDITIONAL INFORMAT ION FOR THE REVIEW OF THE MODEL NO. CR3MP PACKAGE, dated June 24, 2022.

Dear Mr. Saverot:

This letter regards Docket No. 71-9393 Crystal River 3 Middle Package (CR3MP) and Enterprise Project Identifier (EPID) No. L2021-NEW- 0003.

We have received and reviewed the RAIs sent to us by letter dated June 24, 2022 (Reference 1) on the CR3MP license application. After reviewing the amount of calculation work that must be performed, we have determined that we will be unable to meet the proposed schedule submittal of responses date of October 15, 2022. Due to resource constraints, we need to delay our response due date to November 21, 2022.

Should you have any questions regarding this letter, please dont hesitate to contact me at: (253) 552-1322 or via email (chris.backus@orano.group).

Yours Truly,

Chris Backus Orano Federal Services LLC

Copies (per email):

Phil Noss, Licensing Manager, Orano Federal Services LLC Scott Edwards, Project Manager, Orano Decommissioning Services LLC Tom Criddle, Project Manager, Orano Federal Services LLC Armando Merlin, Project Technical Lead, Orano Federal Services LLC

www.orano.group 1