ML15240A212: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:1 NRR-PMDAPEm Resource From: Jackson, Diane Sent: Thursday, August 27, 2015 4:39 PM To: Shams, Mohamed Cc: DiFrancesco, Nicholas; Wyman, Stephen; Spenc e, Jane; Devlin-Gill, Stephanie; Roche, Kevin; Yee, On; Candelario, Luissette; Nak anishi, Tony; Lehman, Bryce; Tsirigotis, Alexander; 50.54f_Seismic Resource; RidsNroDsea Resource
{{#Wiki_filter:NRR-PMDAPEm Resource From:                     Jackson, Diane Sent:                     Thursday, August 27, 2015 4:39 PM To:                       Shams, Mohamed Cc:                       DiFrancesco, Nicholas; Wyman, Stephen; Spence, Jane; Devlin-Gill, Stephanie; Roche, Kevin; Yee, On; Candelario, Luissette; Nakanishi, Tony; Lehman, Bryce; Tsirigotis, Alexander; 50.54f_Seismic Resource; RidsNroDsea Resource


==Subject:==
==Subject:==
RESEND: PERRY NUCLEAR POWER PLANT, UNIT 1 - TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM ESEP SUPPORTING IMPL EMENTATION OF NTTF R2.1, SEISMIC (TAC NO. MF5261)
RESEND: PERRY NUCLEAR POWER PLANT, UNIT 1 - TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM ESEP SUPPORTING IMPLEMENTATION OF NTTF R2.1, SEISMIC (TAC NO. MF5261)
Attachments:
Attachments:               Perry R2. 1 Seismic ESEP NRC review(1).docx August 27, 2015 MEMORANDUM TO: Mohamed K. Shams, Chief Hazards Management Branch (JHMB)
Perry R2. 1 Seismic ESEP NRC review(1).docx August 2 7 , 2015 MEMORANDUM TO: Mohamed K. Shams, Chief Hazards Management Branch (JHMB)
Japan Lessons-Learned Division Office of Nuclear Reactor Regulation FROM: Diane T. Jackson, Chief Geosciences and Geotechnical Engineering Branch 2 (RGS2)
Japan Lessons-Learned Division Office of Nuclear Reactor Regulation
 
FROM: Diane T. Jackson, Chief Geosciences and Geotechnical Engineering Branch 2 (RGS2)
Division of Site Safety and Environmental Analysis Office of New Reactors
Division of Site Safety and Environmental Analysis Office of New Reactors


==SUBJECT:==
==SUBJECT:==
PERRY NUCLEAR POWER PLANT - TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM EXPEDITED SEISMIC EVALUATION PROCESS SUPPORTING IMPLEMENTATION OF NTTF RECOMMENDATION 2.1, SEISMIC, RELATED TO THE FUKUSHIMA DAI-ICHI NUCL EAR POWER PLANT ACCIDENT (TAC NO. MF5261)
PERRY NUCLEAR POWER PLANT - TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM EXPEDITED SEISMIC EVALUATION PROCESS SUPPORTING IMPLEMENTATION OF NTTF RECOMMENDATION 2.1, SEISMIC, RELATED TO THE FUKUSHIMA DAI-ICHI NUCLEAR POWER PLANT ACCIDENT (TAC NO. MF5261)
The NRC technical staff working through the Geoscien ces and Geotechnical Engineering Branches 1 and 2 (RGS1 and RGS2) completed the Technical Review Checklist of the PERRY NUCLEAR POWER PLANT, UNIT 1 response to Enclosure 1, Item (6) of the March 12, 2012, request for information letter issued per Title 10 of the Code of Federal Regulations, Subpart 50.54(f), to power reactor licensees and holders of construction permits requesting addressees to provide further information to support the NRC staff's evaluation of regulatory actions to be taken in response to Fukushima Near-Term Ta sk Force (NTTF) Recommendation 2.1:
The NRC technical staff working through the Geosciences and Geotechnical Engineering Branches 1 and 2 (RGS1 and RGS2) completed the Technical Review Checklist of the PERRY NUCLEAR POWER PLANT, UNIT 1 response to Enclosure 1, Item (6) of the March 12, 2012, request for information letter issued per Title 10 of the Code of Federal Regulations, Subpart 50.54(f), to power reactor licensees and holders of construction permits requesting addressees to provide further information to support the NRC staffs evaluation of regulatory actions to be taken in response to Fukushima Near-Term Task Force (NTTF) Recommendation 2.1:
Seismic which implements lessons learned from Japan's March 11, 2011, Great Thoku Earthquake and subsequent tsunami. This addresses the staff review of the interim Expedited Seismic Evaluation Process (ESEP) report in response to Requested Item (6) of Enclosure 1, "Recommendation 2.1: Seismic," of the 50.54(f) letter. Attached is a file containing the technical review checklist to prepare a response letter to the licensee.
Seismic which implements lessons learned from Japans March 11, 2011, Great Thoku Earthquake and subsequent tsunami. This addresses the staff review of the interim Expedited Seismic Evaluation Process (ESEP) report in response to Requested Item (6) of Enclosure 1, Recommendation 2.1: Seismic, of the 50.54(f) letter. Attached is a file containing the technical review checklist to prepare a response letter to the licensee.
The NRC staff reviewed the information provided and, as documented in the enclosed staff checklist, determined that sufficient information was provided to be responsive to this portion of the Enclosure 1 of the 50.54(f) letter. The application of this staff review is lim ited to the interim ESEP as part of NTTF R2.1: Seismic activities.
The NRC staff reviewed the information provided and, as documented in the enclosed staff checklist, determined that sufficient information was provided to be responsive to this portion of the Enclosure 1 of the 50.54(f) letter. The application of this staff review is limited to the interim ESEP as part of NTTF R2.1: Seismic activities.
This electronic memo constitutes the DSEA concurrence provided that only editorial changes are made to the staff assessment that would not affect the technical conclusions or technical context of the assessment.  
This electronic memo constitutes the DSEA concurrence provided that only editorial changes are made to the staff assessment that would not affect the technical conclusions or technical context of the assessment.
 
This memo replaces the memo dated August 25, 2015. This concludes the NRCs efforts associated with TAC NO. MF5261 for the review of the interim ESEP report for the PERRY NUCLEAR POWER PLANT, UNIT 1.
This memo replaces the memo dated August 25, 2015. This concludes the NRC's efforts associated with TAC NO. MF5261 for the review of the interim ESEP re port for the PERRY NUCLEA R POWER PLANT, UNIT 1.
1
 
2 Docket No: 50-440
 
CONTACT: Stephanie Devlin-Gill Office of New Reactors 301-415-5301


Copy: Nicholas DiFrancesco, Steve Wyman, Jane Spence, Stephanie Devlin-Gill, Kevin Roche, On Yee, Mahmoud Jardaneh, Luissette Candelario, Tony Nakanishi, Bryce Lehman, Alexander Tsirigotis, 50.54f Seismic Resource, RidsNroDsea Resource  
Docket No: 50-440 CONTACT: Stephanie Devlin-Gill Office of New Reactors 301-415-5301 Copy: Nicholas DiFrancesco, Steve Wyman, Jane Spence, Stephanie Devlin-Gill, Kevin Roche, On Yee, Mahmoud Jardaneh, Luissette Candelario, Tony Nakanishi, Bryce Lehman, Alexander Tsirigotis, 50.54f Seismic Resource, RidsNroDsea Resource 2


Hearing Identifier: NRR_PMDA Email Number: 2345   Mail Envelope Properties   (70cd86829a844dca851e184f46a2fb6d)
Hearing Identifier:     NRR_PMDA Email Number:           2345 Mail Envelope Properties     (70cd86829a844dca851e184f46a2fb6d)


==Subject:==
==Subject:==
RESEND: PERRY NUCLEAR POWER PLANT, UNIT 1 - TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM ESEP SUPPORTING IMPLEMENTATION OF NTTF R2.1, SEISMIC (TAC NO. MF5261)
RESEND: PERRY NUCLEAR POWER PLANT, UNIT 1 - TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM ESEP SUPPORTING IMPLEMENTATION OF NTTF R2.1, SEISMIC (TAC NO. MF5261)
Sent Date:   8/27/2015 4:38:58 PM Received Date: 8/27/2015 4:39:00 PM From:   Jackson, Diane Created By:   Diane.Jackson@nrc.gov  
Sent Date:               8/27/2015 4:38:58 PM Received Date:           8/27/2015 4:39:00 PM From:                   Jackson, Diane Created By:             Diane.Jackson@nrc.gov Recipients:
 
"DiFrancesco, Nicholas" <Nicholas.DiFrancesco@nrc.gov>
Recipients:     "DiFrancesco, Nicholas" <Nicholas.DiFrancesco@nrc.gov> Tracking Status: None "Wyman, Stephen" <Stephen.Wyman@nrc.gov> Tracking Status: None "Spence, Jane" <Jane.Spence@nrc.gov> Tracking Status: None "Devlin-Gill, Stephanie" <Stephanie.Devlin-Gill@nrc.gov> Tracking Status: None "Roche, Kevin" <Kevin.Roche@nrc.gov> Tracking Status: None "Yee, On" <On.Yee@nrc.gov> Tracking Status: None "Candelario, Luissette" <Luissette.Candelario@nrc.gov>
Tracking Status: None "Wyman, Stephen" <Stephen.Wyman@nrc.gov>
Tracking Status: None "Nakanishi, Tony" <Tony.Nakanishi@nrc.gov> Tracking Status: None "Lehman, Bryce" <Bryce.Lehman@nrc.gov> Tracking Status: None "Tsirigotis, Alexander" <Alexander.Tsirigotis@nrc.gov> Tracking Status: None "50.54f_Seismic Resource" <50.54f_Seismic.Resource@nrc.gov> Tracking Status: None "RidsNroDsea Resource" <RidsNroDsea.Resource@nrc.gov> Tracking Status: None "Shams, Mohamed" <Mohamed.Shams@nrc.gov> Tracking Status: None  
Tracking Status: None "Spence, Jane" <Jane.Spence@nrc.gov>
Tracking Status: None "Devlin-Gill, Stephanie" <Stephanie.Devlin-Gill@nrc.gov>
Tracking Status: None "Roche, Kevin" <Kevin.Roche@nrc.gov>
Tracking Status: None "Yee, On" <On.Yee@nrc.gov>
Tracking Status: None "Candelario, Luissette" <Luissette.Candelario@nrc.gov>
Tracking Status: None "Nakanishi, Tony" <Tony.Nakanishi@nrc.gov>
Tracking Status: None "Lehman, Bryce" <Bryce.Lehman@nrc.gov>
Tracking Status: None "Tsirigotis, Alexander" <Alexander.Tsirigotis@nrc.gov>
Tracking Status: None "50.54f_Seismic Resource" <50.54f_Seismic.Resource@nrc.gov>
Tracking Status: None "RidsNroDsea Resource" <RidsNroDsea.Resource@nrc.gov>
Tracking Status: None "Shams, Mohamed" <Mohamed.Shams@nrc.gov>
Tracking Status: None Post Office:            HQPWMSMRS08.nrc.gov Files                            Size                    Date & Time MESSAGE                          3194                    8/27/2015 4:39:00 PM Perry R2. 1 Seismic ESEP NRC review(1).docx                    52320 Options Priority:                        Standard Return Notification:            No Reply Requested:                No Sensitivity:                    Normal Expiration Date:


Post Office:  HQPWMSMRS08.nrc.gov Files    Size      Date & Time MESSAGE    3194      8/27/2015 4:39:00 PM Perry R2. 1 Seismic ESEP NRC review(1).docx    52320 Options  Priority:    Standard  Return Notification:    No  Reply Requested:    No  Sensitivity:    Normal  Expiration Date:
Recipients Received:
Recipients Received:
TECHNICAL REVIEW CHECKLIST BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO EXPEDITED SEISMIC EVALUATION PROCESSINTERIM EVALUATION IMPLEMENTING NTTF RECOMMENDATION 2.1 SEISMIC PERRY NUCLEAR POWER PLANT DOCKET NO. 50-440  
TECHNICAL REVIEW CHECKLIST BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO EXPEDITED SEISMIC EVALUATION PROCESSINTERIM EVALUATION IMPLEMENTING NTTF RECOMMENDATION 2.1 SEISMIC PERRY NUCLEAR POWER PLANT DOCKET NO. 50-440 By letter dated March 12, 2012 (USNRC, 2012a), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(f) Conditions of License (hereafter referred to as the 50.54(f) letter). Enclosure 1 of the 50.54(f) letter requests addressees to reevaluate the seismic hazard at their site using present-day methods and guidance for licensing new nuclear power plants, and identify actions to address or modify, as necessary, plant components affected with the reevaluated seismic hazards. Requested Information Item (6) in Enclosure 1 to the 50.54(f) letter requests addressees to provide an interim evaluation and actions taken or planned to address a higher seismic hazard relative to the design basis, as appropriate, prior to completion and submission of the seismic risk evaluation.
Additionally, by letter dated April 12, 20131, the Electric Power Research Institute (EPRI) staff submitted EPRI TR 3002000704 Seismic Evaluation Guidance: Augmented Approach for the Resolution of Fukushima Near-Term Task Force (NTTF) Recommendation 2.1: Seismic (hereafter referred to as the guidance). The Augmented Approach proposed that licensees would use an Expedited Seismic Evaluation Process (ESEP) to address the interim actions as requested by Information Item (6) in the 50.54(f) letter. The ESEP is a simplified seismic capacity evaluation with a focused scope of certain key installed Mitigating Strategies equipment that is used for core cooling and containment functions to cope with scenarios that involve a loss of all AC power and loss of access to the ultimate heat sink to withstand the Review Level Ground Motion, which is up to two times the safe shutdown earthquake (SSE).
Due to the expedited and interim nature of the ESEP, the assessment does not include many considerations that are part of a normal risk evaluation.These deferred items, include but are not limited to, structures, piping, non-seismic failures, and operator actions, as well scenarios such as addressing loss of coolant accidents. By letter dated May 7, 20132, the NRC staff endorsed the guidance. Central and eastern United States licensees with a reevaluated seismic hazard exceeding the SSE submitted an ESEP interim evaluation in December 2014.
Consistent with the interim nature of this activity, the staff performed the review of the licensees submittal to assess whether the intent of the guidance was implemented. A multi-disciplined team checked whether the identified methods were consistent with the guidance. A senior expert panel reviewed the teams questions, if any, and checklist for consistency and scope.
New or updated parameters (e.g., In-Structure Response Spectra, High Confidence of Low Probability of Failure calculations) presented by the licensees were assessed only based on licensee statements for acceptability for the Item (6) response. The application of this staff review is limited to the ESEP interim evaluation as part of NTTF R2.1: Seismic activities.
1 ADAMS Accession No. ML13102A142 2 ADAMS Accession No. ML13106A331


By letter dated March 12, 2012 (USNRC, 2012a), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(f) "Conditions of License" (hereafter referred to as the "50.54(f) letter"). Enclosure 1 of the 50.54(f) letter requests addressees to reevaluate the seismic hazard at their site using present-day methods and guidance for licensing new nuclear power plants, and identify actions to address or modify, as necessary, plant components affected with the reevaluated seismic hazards. Requested Information Item (6) in Enclosure 1 to the 50.54(f) letter requests addressees to provide an interim evaluation and actions taken or planned to address a higher seismic hazard relative to the design basis, as appropriate, prior to completion and submission of the seismic risk evaluation. Additionally, by letter dated April 12, 2013 1, the Electric Power Research Institute (EPRI) staff submitted EPRI TR 3002000704 "Seismic Evaluat ion Guidance: Augmented Approach for the Resolution of Fukushima Near-Term Task Force (NTTF) Recommendation 2.1: Seismic" (hereafter referred to as the guidance). The Augmented Approach proposed that licensees would use an Expedited Seismic Evaluation Process (ESEP) to address the interim actions as requested by Information Item (6) in the 50.54(f) letter. The ESEP is a simplified seismic capacity evaluation with a focused scope of certain key installed Mitigating Strategies equipment that is used for core cooling and containment functions to cope with scenarios that involve a loss of all AC power and loss of access to the ultimate heat sink to withstand the Review Level Ground Motion, which is up to two times the safe shutdown earthquake (SSE).
NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant By letter dated November 3, 20143, First Energy Nuclear Operating Company provided an Expedited Seismic Evaluation Process (ESEP) report in a response to Enclosure 1, Requested Information Item (6) of the 50.54(f) letter, for the Perry Nuclear Power Plant (Perry).
I.      Review Level Ground Motion The licensee:
* described the determination of the review level ground motion                      Yes (RLGM) using one of the means acceptable by the guidance
* identified location of the control point and is consistent with March              Yes 2014 Seismic Hazard and Screening Report submittal
* compared the site ground motion response spectra used to select                    Yes the ESEP RLGM to the safe shutdown earthquake (SSE).
Perryused a used a new Seismic Probabilistic Risk Analysis (SPRA)
Ground Motion Response Spectra(GMRS).(1)
Notes from the Reviewer:
: 1. The licensee used a new GMRS rather than its seismic hazard reevaluation GMRS documented in its March 2014 Seismic Hazard and Screening Report (SHSR)4, which was found acceptable for use in Recommendation 2.1 seismic activities by the staff.
Because the new GMRS is similar to and bounds the SHSR GMRS, the staff judged that this GMRS is acceptable for the purposes of this interim evaluation.
Deviation(s) or Deficiency(ies), and Resolution:
No deviation or deficiencies were found in the review of this particular section.
The NRC staff concludes:
* the licensees RLGM meets the intent of the guidance                              Yes
* the RLGM is reasonable for use in the interim evaluation.                         Yes II.     Selection of the Success Path The licensee:
* described the success path                                                        Yes
* described normal and desired state of the equipment for the                      Yes success path
* ensured that the success path is consistent with the plants overall              Yes mitigating strategies approach or provided a justification for an alternate path
* stated that the selection process was in accordance with the guidance or meets the intent of the guidance                                    Yes
* used installed FLEX Phase 1 equipment as part of the success path                                                                            Yes
* included FLEX Phase 2 and/or 3 connections                                        Yes
* considered installed FLEX Phase 2 and/or 3 equipment                              Yes 3 ADAMS Accession No. ML14353A058 4 ADAMS Accession No. ML14092A203 Page 2


Due to the expedited and interim nature of t he ESEP, the assessment does not include many considerations that are part of a normal risk evaluation.These deferred items, include but are not limited to, structures, piping, non-seismic failures, and operator actions, as well scenarios such as addressing loss of coolant accidents. By letter dated May 7, 2013 2 , the NRC staff endorsed the guidance. Central and eastern United States licensees with a reevaluated seismic hazard exceeding the SSE submitted an ESEP interim evaluation in December 2014.
NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant Notes from the Reviewer: None Deviation(s) or Deficiency(ies), and Resolution:
 
No deviation or deficiencies were found in the review of this particular section.
Consistent with the interim nature of this activity, the staff performed the review of the licensee's submittal to assess whether the intent of the guidance was implemented. A multi-disciplined team checked whether the identified methods were consistent with the guidance. A senior expert panel reviewed the team's questions, if any, and checklist for consistency and scope.
The NRC staff concludes that:
New or updated parameters (e.g., In-Structure Response Spectra, High Confidence of Low Probability of Failure calculations) presented by the licensees were assessed only based on licensee statements for acceptability for the Item (6) response. The application of this staff review is limited to the ESEP interim evaluati on as part of NTTF R2.1: Seismic activities.
* the selected success path is reasonable for use in the interim             Yes evaluation
1 ADAMS Accession No. ML13102A142 2 ADAMS Accession No. ML13106A331 NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant Page 2      By letter dated November 3, 2014 3, First Energy Nuclear Operating Company provided an Expedited Seismic Evaluation Process (ESEP) report in a response to Enclosure 1, Requested Information Item (6) of the 50.54(f) letter, for the Perry Nuclear Power Plant (Perry).
* the licensee considered installed Phase 2 and 3 connections or             Yes equipment in the interim evaluation.
 
III. Selection of the Expedited Seismic Equipment List (ESEL)
I. Review Level Ground Motion The licensee:
The licensee:
* described the determination of the review level ground motion (RLGM) using one of the means acceptable by the guidance
* developed and provided the ESEL by applying the ESEP                         Yes
* identified location of the control point and is consistent with March 2014 Seismic Hazard and Screening Report submittal
* compared the site ground motion response spectra used to select the ESEP RLGM to the safe shutdown earthquake (SSE).
Yes  Yes  Yes Perryused a used a new Seismic Probabilistic Risk Analysis (SPRA) Ground Motion Response Spectra(GMRS).(1)  Notes from the Reviewer:
: 1. The licensee used a new GMRS rather than its seismic hazard reevaluation GMRS documented in its March 2014 Seismic Hazard and Screening Report (SHSR) 4 , which was found acceptable for use in Recommendation 2.1 seismic activities by the staff. Because the new GMRS is similar to and bounds the SHSR GMRS, the staff judged that this GMRS is acceptable for the purposes of this interim evaluation.
Deviation(s) or Deficiency(ies), and Resolution: No deviation or deficiencies were found in the review of this particular section. The NRC staff concludes:
* the licensee's RLGM meets the intent of the guidance
* the RLGM is reasonable for use in the interim evaluation.
Yes Yes  II. Selection of the Success Path The licensee:
* described the success path
* described normal and desired state of the equipment for the success path
* ensured that the success path is consistent with the plant's overall mitigating strategies approach or provided a justification for an alternate path
* stated that the selection process was in accordance with the guidance or meets the intent of the guidance
* used installed FLEX Phase 1 equipment as part of the success path
* included FLEX Phase 2 and/or 3 connections
* considered installed FLEX Phase 2 and/or 3 equipment Yes Yes  Yes 
 
Yes  Yes Yes Yes 3 ADAMS Accession No. ML14353A058 4 ADAMS Accession No. ML14092A203 NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant Page 3      Notes from the Reviewer: None Deviation(s) or Deficiency(ies), and Resolution:  No deviation or deficiencies were found in the review of this particular section. The NRC staff concludes that:
* the selected success path is reasonable for use in the interim evaluation
* the licensee considered installed Phase 2 and 3 connections or equipment in the interim evaluation.
Yes  Yes  III. Selection of the Expedited Seismic Equipment List (ESEL) The licensee:
* developed and provided the ESEL by applying the ESEP
* identified equipment considering the following functions:
* identified equipment considering the following functions:
o Core cooling (with focus on Mode 1) function o Available, sustainable water source o Containment function and integrity Yes  Yes Yes Yes Notes from the reviewer: None Deviation(s) or Deficiency(ies), and Resolution: No deviation or deficiencies were found in the review of this particular section. For PWR Plants ONLY
o Core cooling (with focus on Mode 1) function                       Yes o Available, sustainable water source                               Yes o Containment function and integrity                                 Yes Notes from the reviewer: None Deviation(s) or Deficiency(ies), and Resolution:
No deviation or deficiencies were found in the review of this particular section.
For PWR Plants ONLY The licenseeincluded indicators / instrumentation for the following functions:
level, pressure, temperature, that would be indicative of (but not explicitly      N/A identified to specific instruments): water level of a steam generator (SG),
pressure of SG, containment, and reactor coolant system (RCS); and temperature of the RCS.
For BWR Plants ONLY The licenseeconsidered indicators for the following functions:level, pressure, temperature that would be indicative of (but not explicitly identified to          Yes specific instruments): Temperature of suppression pool, RCS, containment; Pressure of suppression pool, RCS, and drywell; water level of the suppression pool.
Notes from the Reviewer: None Deviation(s) or Deficiency(ies), and Resolution:
No deviation or deficiencies were found in the review of this particular section.
Page 3


The licenseeincluded indicators / instrumentation for the following functions:
NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant Through a sampling of the ESEP key components, the NRC staff concludes that:
level, pressure, temperature, that would be indicative of (but not explicitly identified to specific instruments): water level of a steam generator (SG),
* the licensees process to develop the ESEL meets the intent of the                Yes guidance for the interim evaluation
pressure of SG, containment, and reactor coolant system (RCS); and temperature of the RCS. N/A For BWR Plants ONLY
* the desired equipment state for the success path were identified                  Yes
* the licensee considered the support equipment for the ESEL                        Yes
* both front-line and support systems appeared to be included in the ESEL as evidenced by inclusion of SSCs on the success path and of                Yes support systems (e.g., batteries, motor control center,inverters).
IV. Walkdown Approach The licensee:
* described the walkdown screening approach, including walkbys                    Yes and walkdowns performed exclusively for the ESEP, in accordance with the guidance
* credited previous walkdown results, including a description of                   Yes current action(s) to verify the present equipment condition and/or configuration (e.g., walk-bys), in accordance with the guidance
* stated seismic walkdown training of walkdown personnel(1)                       Yes Notes from the Reviewer:
: 1. In response to a staff question (ML15212A955), the licensee provided the training credentials for personnel involved in the walkdown. The staff finds that the response adequately addresses the question and therefore,it is acceptable.
Deviation(s) or Deficiency(ies), and Resolution:
No deviation or deficiencies were found in the review of this particular section.
The licensee:
* described, if needed, adverse material condition of the equipment                N/A (e.g., material degradation)
* credited previous walkdown results, included a description of current action(s) to verify the present equipment condition                    Yes (e.g., walk-bys), meeting the intent of the guidance The licensee:
* described the conditions of structural items considered for the interim evaluation, including:
o spatial interactions (i.e. interaction between block walls and          Yes other items/components) o anchorage                                                                Yes o piping connected to tanks (i.e. differential movement between pipes and tanks at connections)                                Yes Notes from the Reviewer: None Deviation(s) or Deficiency(ies), and Resolution:
No deviation or deficiencies were found in the review of this particular section.
Page 4


The licenseeconsidered indicators for the following functions:level, pressure, temperature that would be indicative of (but not explicitly identified to specific instruments): Temperature of suppression pool, RCS, containment; Pressure of suppression pool, RCS, and drywell; water level of the suppression pool.
NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant The licensee reported deviations for Perry.                                          No If deviations wereidentified, there is a discussion of how the deficiencies were or will be addressed in the ESEP submittal report.                            N/A The NRC staff concludes that:
Yes Notes from the Reviewer
* the licensee described the performed walkdown approach,                      Yes including any credited previous efforts (e.g., Individual Plant Examination of External Events(IPEEE)) consistent with the guidance
: None  Deviation(s) or Deficiency(ies), and Resolution:  No deviation or deficiencies were found in the review of this particular section.
* the licensee addressed identified deviations consistent with the             N/A guidance, if any V.      Capacity Screening Approach and High Confidence/Low Probability of Failure (HCLPF) Calculation Results The licensee:
NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant Page 4      Through a sampling of the ESEP key components, the NRC staff concludes that:
* described the capacity screening process for the ESEL items,                   N/A consistent with the guidance (e.g., use of EPRI NP-6041 screening table).
* the licensee's process to develop the ESEL meets the intent of the guidance for the interim evaluation
* presented the results of the screened-out ESEL items in the ESEP                N/A report
* the desired equipment state for the success path were identified
* described the development of in-structure response                              N/A spectra(ISRS)based on scaling
* the licensee considered the support equipment for the ESEL
* described the development of ISRS based on new analysis                        Yes (1) consistent with the guidance
* both front-line and support systems appeared to be included in the ESEL as evidenced by inclusion of SSCs on the success path and of support systems (e.g., batteries, motor control center,inverters).
* described the method for estimating HCLPF capacity of screened-in ESEL items, including both structural and functional failure modes consistent with the guidance: (2) (3) o use of Conservative Deterministic Failure Margin (CDFM)                Yes o use of fragility analysis (FA)                                         N/A o use of experience data or generic information                          Yes
Yes  Yes Yes  Yes  IV. Walkdown Approach  The licensee:
* credited IPEEE spectral shape for HCLPF capacity estimates is similar to or envelopes the RLGM, and anchored at the same                    N/A control point
* described the walkdown screening approach, including walkbys and walkdowns performed exclusively for the ESEP, in accordance with the guidance
* presented the results of HCLPF capacities including associated failure modes for screened-in ESEL items (4)                                 Yes
* credited previous walkdown results, including a description of current action(s) to verify the present equipment condition and/or configuration (e.g., walk-bys), in accordance with the guidance
* reviewed the ESEL items with the lowest HCLPF values to ensure Yes that their capacities are equal or greater than the RLGM Notes from the Reviewer:
* stated seismic walkdown training of walkdown personnel (1) Yes   Yes Yes Notes from the Reviewer
: 1. The licensee did not use a scaled ISRS. As allowed by guidance, the licensee calculated a new GMRS-based ISRS. The new GMRS was developed to be used in an upcoming SPRA, which at the time of the Perry ESEP submittal was underway (see Perry ESEP Submittal page 40 of 42). The staff ESEP review for the GMRS is in Section I of this checklist.Based on the above, the Perry ESEP new GMRS-based ISRS is judged by the staff to be acceptable for this interim evaluation only.
1. In response to a staff question (ML15212A955), the licensee provided the training credentials for personnel involved in the walkdown. The staff finds that the response adequately addresses the question and therefore,it is acceptable.
: 2. The staff asked several questions to the licensee regarding the HCLPF calculations methodologyto include: thefunctional evaluation of relays and treatment of valves that did not meet the valve operator caveats necessary to use a generic approach for estimating Page 5
Deviation(s) or Deficiency(ies), and Resolution: No deviation or deficiencies were found in the review of this particular section. The licensee:
* described, if needed, adverse  material condition of the equipment (e.g., material degradation)
* credited previous walkdown results, included a description of current action(s) to verify the present equipment condition (e.g., walk-bys), meeting the intent of the guidance N/A   Yes  The licensee:
* described the conditions of structural items considered for the interim evaluation, including:
o spatial interactions (i.e. interaction between block walls and other items/components) o anchorage o piping connected to tanks (i.e. differential movement between pipes and tanks at connections)
Yes   Yes  Yes  Notes from the Reviewer
: None  Deviation(s) or Deficiency(ies), and Resolution: No deviation or deficiencies were found in the review of this particular section.
NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant Page 5      The licensee reported deviations for Perry.
If deviations wereidentified, there is a discussion of how the deficiencies were or will be addressed in the ESEP submittal report.
No  N/A The NRC staff concludes that:
* the licensee described the performed walkdown approach, including any credited previous efforts (e.g., Individual Plant Examination of External Events(IPEEE)) consistent with the guidance
* the licensee addressed identified deviations consistent with the guidance, if any Yes 


N/A  V. Capacity Screening Approach and High Confidence/Low Probability of Failure (HCLPF) Calculation Results  The licensee:
NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant HCLPF capacity.The licensee stated that CDFM methodology has been used for all calculations, including the relay capacity evaluations. The licensee provided detailed information,consistent with the ESEP guidance, about the treatment of valves that do not meet the valve operator caveatsnecessary to use a generic approach for estimating HCLPF capacity. The staff finds that the licensee responses (ML15212A955) adequately addressed the concerns and met the intent of the guidance for this interim evaluation.
* described the capacity screening process for the ESEL items, consistent with the guidance (e.g., use of EPRI NP-6041 screening table).
: 3. The staff asked the licenseesabout the implementation of the rule-of-the-box, as discussed in Sections 3.1.5 and 6.1 of the ESEP submittal. In its response (ML15212A955),the licensee clarified its implementation of the rule-of-the-box and stated that when an ESEL item is identified to be mounted on a parent component, the HCLPF of the parent component is assigned to the item. Thestaff finds that the method used is consistent with the ESEP guidance and therefore, is acceptable.
* presented the results of the screened-out ESEL items in the ESEP report
: 4. As a result of a question from the staff, the licensee provided a roadmap between the entries in the ESEL (Attachment A) and the entries in HCLPF Capacity Table (Attachment B). The staff finds the licensee response (ML15212A955) adequately addressed the question.
* described the development of in-structure response spectra(ISRS)based on scaling
* described the development of ISRS based on new analysis consistent with the guidance (1)
* described the method for estimating HCLPF capacity of screened-in ESEL items, including both structural and functional failure modes consistent with the guidance:
(2) (3) o use of Conservative Deterministic Failure Margin (CDFM) o use of fragility analysis (FA) o use of experience data or generic information
* credited IPEEE spectral shape for HCLPF capacity estimates is similar to or envelopes the RLGM, and anchored at the same control point
* presented the results of HCLPF capacities including associated failure modes for screened-in ESEL items (4)
* reviewed the ESEL items with the lowest HCLPF values to ensure that their capacities are equal or greater than the RLGM N/A  N/A  N/A  Yes Yes  N/A Yes    N/A  Yes  Yes Notes from the Reviewer
: 1. The licensee did not use a scaled ISRS. As allowed by guidance, the licensee calculated a new GMRS-based ISRS. The new GMRS was developed to be used in an upcoming SPRA, which at the time of the Perry ESEP submittal was underway (see Perry ESEP Submittal page 40 of 42). The staff ESEP review for the GMRS is in Section I of this checklist.Based on the above, the Perry ESEP new GMRS-based ISRS is judged by the staff to be acceptable for this interim evaluation only. 2. The staff asked several questions to the licensee regarding the HCLPF calculations methodologyto include: thefunctional evaluation of relays and treatment of valves that did not meet the valve operator caveats necessary to use a generic approach for estimating NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant Page 6      HCLPF capacity.The licensee stated that CDFM methodology has been used for all calculations, including the relay capacity evaluations. The licensee provided detailed information,consistent with the ESEP guidance, about the treatment of valves that do not meet the valve operator caveatsnecessary to use a generic approach for estimating HCLPF capacity. The staff finds that the licensee responses (ML15212A955) adequately addressed the concerns and met the intent of the guidance for this interim evaluation. 3. The staff asked the licensee'sabout the implementation of the "rule-of-the-box", as discussed in Sections 3.1.5 and 6.1 of the ESEP submittal. In its response (ML15212A955),the licensee clarified its implementation of the "rule-of-the-box" and stated that when an ESEL item is identified to be mounted on a parent component, the HCLPF of the parent component is assigned to the item. Thestaff finds that the method used is consistent with the ESEP guidance and therefore, is acceptable. 4. As a result of a question from the staff, the licensee provided a roadmap between the entries in the ESEL (Attachment A) and the entries in HCLPF Capacity Table (Attachment B). The staff finds the licensee response (ML15212A955) adequately addressed the question.
Deviation(s) or Deficiency(ies), and Resolution:
Deviation(s) or Deficiency(ies), and Resolution:
* No deviation or deficiencies were found in the review of this particular section. The NRC staff concludes that:
* No deviation or deficiencies were found in the review of this particular section.
* the licensee described the implementation of the capacity screening process consistent with the intent of the guidance
The NRC staff concludes that:
* the licensee presented capacity screening and calculation results, as appropriate, in the ESEP report
* the licensee described the implementation of the capacity                         N/A screening process consistent with the intent of the guidance
* the method used to develop the ISRS is consistent with guidance for use in the ESEP
* the licensee presented capacity screening and calculation results,               Yes as appropriate, in the ESEP report
* for HCLPF calculations, the licensee used HCLPF calculation methods as endorsed in the guidance
* the method used to develop the ISRS is consistent with guidance                   Yes for use in the ESEP
* no anomalies were noted in the reported HCLPF N/A  Yes  Yes   Yes  Yes  VI. Inaccessible Items The licensee:
* for HCLPF calculations, the licensee used HCLPF calculation                       Yes methods as endorsed in the guidance
* provided a list of inaccessible items (1)
* no anomalies were noted in the reported HCLPF                                     Yes VI.     Inaccessible Items The licensee:
* provided a schedule of the planned walkdown and evaluation for all inaccessible items
* provided a list of inaccessible items(1)                                         Yes
* provided Regulatory Commitment to complete walkdowns.
* provided a schedule of the planned walkdown and evaluation for all               N/A inaccessible items
Yes  N/A  N/A Perrywill provide results or complete walkdown by:N/A N/A Notes from the Reviewer: 1. The licensee identified twelve components as inaccessible due to their location in confined spaces and high radiation areas. The licensee used plant drawings to asses design parameters and similarity with anevaluated representative component of the same class. The reviewer finds this acceptable for the purpose of this interim evaluation.
* provided Regulatory Commitment to complete walkdowns.                             N/A Perrywill provide results or complete walkdown by:N/A                                 N/A Notes from the Reviewer:
Deviation(s) or Deficiency(ies), and Resolution: No deviation or deficiencies were found in the review of this particular section.
: 1. The licensee identified twelve components as inaccessible due to their location in confined spaces and high radiation areas. The licensee used plant drawings to asses design parameters and similarity with anevaluated representative component of the same class. The reviewer finds this acceptable for the purpose of this interim evaluation.
NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant Page 7      The NRC staff concludes that the licensee:
Deviation(s) or Deficiency(ies), and Resolution:
* listed inaccessible items
No deviation or deficiencies were found in the review of this particular section.
* committed to provide the results (e.g. walkdowns, walkbys, etc.) of the remaining inaccessible items consistent with the guidance
Page 6
* substitutions, if needed, were appropriately justified Yes N/A  Yes  VII. Modifications The licensee:
 
* identified modifications for ESEL items necessary to achieve HCLPF values that bound the RLGM, as specified in the guidance
NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant The NRC staff concludes that the licensee:
* provided a schedule to implement such modifications (if any), consistent with the intent of the guidance
* listed inaccessible items                                                       Yes
* provided Regulatory Commitment to complete modifications
* committed to provide the results (e.g. walkdowns, walkbys, etc.) of             N/A the remaining inaccessible items consistent with the guidance
* provided Regulatory Commitment to report completion of modifications.
* substitutions, if needed, were appropriately justified                         Yes VII. Modifications The licensee:
N/A N/A  N/A  N/A Perry will:
* identified modifications for ESEL items necessary to achieve HCLPF               N/A values that bound the RLGM, as specified in the guidance
* provided a schedule to implement such modifications (if any),                   N/A consistent with the intent of the guidance
* provided Regulatory Commitment to complete modifications                         N/A
* provided Regulatory Commitment to report completion of modifications.                                                               N/A Perrywill:
* complete modifications by:N/A
* complete modifications by:N/A
* report completion of modifications by:N/A Notes from the Reviewer: None Deviation(s) or Deficiency(ies), and Resolution: No deviation or deficiencies were found in the review of this particular section. The NRC staff concludes that the licensee:
* report completion of modifications by:N/A Notes from the Reviewer: None Deviation(s) or Deficiency(ies), and Resolution:
* identified plant modifications necessary to achieve the target seismic capacity
No deviation or deficiencies were found in the review of this particular section.
* provided a schedule to implement the modifications (if any) consistent with the guidance N/A  N/A  VII. Conclusions  
The NRC staff concludes that the licensee:
 
* identified plant modifications necessary to achieve the target seismic           N/A capacity
The NRC staff assessed the licensee's implementation of the ESEP guidance. Due to the interim applicability of the ESEP evaluations,use of the information for another application would require a separate NRC review and approval.Based on its review, the NRC staff concludes that the licensee's implementation of the interim evaluation meets the intent of the guidance. The staff concludes that, through the implementati on of the ESEP guidance, the licensee identified and evaluated the seismic capacity of certain key installed Mitigating Strategies equipment that is used for core cooling and containment functions to cope with scenarios that involvea loss of all AC power and loss of access to the ultimate heat sink to withstand a seismic event up to the Review Level Ground Motion (RLGM) and thus, provides additional assurance while the plant seismic risk evaluation is being conducted. In the case of Perry, the RLGM used the SPRA GMRS.The application of this staff review is limited to the ESEP interim evaluation as part of the  
* provided a schedule to implement the modifications (if any)                     N/A consistent with the guidance VII. Conclusions The NRC staff assessed the licensees implementation of the ESEP guidance. Due to the interim applicability of the ESEP evaluations,use of the information for another application would require a separate NRC review and approval.Based on its review, the NRC staff concludes that the licensees implementation of the interim evaluation meets the intent of the guidance. The staff concludes that, through the implementation of the ESEP guidance, the licensee identified and evaluated the seismic capacity of certain key installed Mitigating Strategies equipment that is used for core cooling and containment functions to cope with scenarios that involvea loss of all AC power and loss of access to the ultimate heat sink to withstand a seismic event up to the Review Level Ground Motion (RLGM) and thus, provides additional assurance while the plant seismic risk evaluation is being conducted. In the case of Perry, the RLGM used the SPRA GMRS.The application of this staff review is limited to the ESEP interim evaluation as part of the NTTF R2.1: Seismic activities. The staff did not identify deviations or exceptions from the guidance for the purposes this interim evaluation. The licensee found all equipment evaluated for the ESEP to have adequate capacity for the required demand. Therefore, no modification of equipment was required.
 
Page 7
NTTF R2.1: Seismic activities. The staff did not identify deviations or exceptions from the guidance for the purposes this interim evaluation. The licensee found all equipment evaluated for the ESEP to have adequate capacity for the requi red demand. Therefore, no modification of equipment was required.  
 
NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant Page 8      In summary, by implementing the ESEP interim evaluation, the licensee demonstrated that additional assurance exists which supports continued plant safety and confirms that sufficient
 
time exists to allow the completion of longer-term seismic evaluations to support regulatory decision making. The NRC staff concludes that the licensee responded appropriately to  , Item (6) of the 50.54(f) letter, dated March 12, 2012, for Perry Nuclear Power


Plant.
NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant In summary, by implementing the ESEP interim evaluation, the licensee demonstrated that additional assurance exists which supports continued plant safety and confirms that sufficient time exists to allow the completion of longer-term seismic evaluations to support regulatory decision making. The NRC staff concludes that the licensee responded appropriately to , Item (6) of the 50.54(f) letter, dated March 12, 2012, for Perry Nuclear Power Plant.
Principle Contributors:
Principle Contributors:
Stephanie Devlin-Gill, On Yee, Tony Nakanishi, Bryce Lehman, Alexander Tsirigotis, , Luissette Candelario, Richard Morante (NRC consultant)}}
Stephanie Devlin-Gill, On Yee, Tony Nakanishi, Bryce Lehman, Alexander Tsirigotis, , Luissette Candelario, Richard Morante (NRC consultant)
Page 8}}

Revision as of 08:13, 31 October 2019

Resend: Perry Nuclear Power Plant, Unit 1 - Technical Review Checklist Related to Interim ESEP Supporting Implementation of NTTF R2.1, Seismic
ML15240A212
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 08/27/2015
From: Diane Jackson
Office of New Reactors
To: Mohamed Shams
Japan Lessons-Learned Division
References
TAC MF5261
Download: ML15240A212 (12)


Text

NRR-PMDAPEm Resource From: Jackson, Diane Sent: Thursday, August 27, 2015 4:39 PM To: Shams, Mohamed Cc: DiFrancesco, Nicholas; Wyman, Stephen; Spence, Jane; Devlin-Gill, Stephanie; Roche, Kevin; Yee, On; Candelario, Luissette; Nakanishi, Tony; Lehman, Bryce; Tsirigotis, Alexander; 50.54f_Seismic Resource; RidsNroDsea Resource

Subject:

RESEND: PERRY NUCLEAR POWER PLANT, UNIT 1 - TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM ESEP SUPPORTING IMPLEMENTATION OF NTTF R2.1, SEISMIC (TAC NO. MF5261)

Attachments: Perry R2. 1 Seismic ESEP NRC review(1).docx August 27, 2015 MEMORANDUM TO: Mohamed K. Shams, Chief Hazards Management Branch (JHMB)

Japan Lessons-Learned Division Office of Nuclear Reactor Regulation FROM: Diane T. Jackson, Chief Geosciences and Geotechnical Engineering Branch 2 (RGS2)

Division of Site Safety and Environmental Analysis Office of New Reactors

SUBJECT:

PERRY NUCLEAR POWER PLANT - TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM EXPEDITED SEISMIC EVALUATION PROCESS SUPPORTING IMPLEMENTATION OF NTTF RECOMMENDATION 2.1, SEISMIC, RELATED TO THE FUKUSHIMA DAI-ICHI NUCLEAR POWER PLANT ACCIDENT (TAC NO. MF5261)

The NRC technical staff working through the Geosciences and Geotechnical Engineering Branches 1 and 2 (RGS1 and RGS2) completed the Technical Review Checklist of the PERRY NUCLEAR POWER PLANT, UNIT 1 response to Enclosure 1, Item (6) of the March 12, 2012, request for information letter issued per Title 10 of the Code of Federal Regulations, Subpart 50.54(f), to power reactor licensees and holders of construction permits requesting addressees to provide further information to support the NRC staffs evaluation of regulatory actions to be taken in response to Fukushima Near-Term Task Force (NTTF) Recommendation 2.1:

Seismic which implements lessons learned from Japans March 11, 2011, Great Thoku Earthquake and subsequent tsunami. This addresses the staff review of the interim Expedited Seismic Evaluation Process (ESEP) report in response to Requested Item (6) of Enclosure 1, Recommendation 2.1: Seismic, of the 50.54(f) letter. Attached is a file containing the technical review checklist to prepare a response letter to the licensee.

The NRC staff reviewed the information provided and, as documented in the enclosed staff checklist, determined that sufficient information was provided to be responsive to this portion of the Enclosure 1 of the 50.54(f) letter. The application of this staff review is limited to the interim ESEP as part of NTTF R2.1: Seismic activities.

This electronic memo constitutes the DSEA concurrence provided that only editorial changes are made to the staff assessment that would not affect the technical conclusions or technical context of the assessment.

This memo replaces the memo dated August 25, 2015. This concludes the NRCs efforts associated with TAC NO. MF5261 for the review of the interim ESEP report for the PERRY NUCLEAR POWER PLANT, UNIT 1.

1

Docket No: 50-440 CONTACT: Stephanie Devlin-Gill Office of New Reactors 301-415-5301 Copy: Nicholas DiFrancesco, Steve Wyman, Jane Spence, Stephanie Devlin-Gill, Kevin Roche, On Yee, Mahmoud Jardaneh, Luissette Candelario, Tony Nakanishi, Bryce Lehman, Alexander Tsirigotis, 50.54f Seismic Resource, RidsNroDsea Resource 2

Hearing Identifier: NRR_PMDA Email Number: 2345 Mail Envelope Properties (70cd86829a844dca851e184f46a2fb6d)

Subject:

RESEND: PERRY NUCLEAR POWER PLANT, UNIT 1 - TECHNICAL REVIEW CHECKLIST RELATED TO INTERIM ESEP SUPPORTING IMPLEMENTATION OF NTTF R2.1, SEISMIC (TAC NO. MF5261)

Sent Date: 8/27/2015 4:38:58 PM Received Date: 8/27/2015 4:39:00 PM From: Jackson, Diane Created By: Diane.Jackson@nrc.gov Recipients:

"DiFrancesco, Nicholas" <Nicholas.DiFrancesco@nrc.gov>

Tracking Status: None "Wyman, Stephen" <Stephen.Wyman@nrc.gov>

Tracking Status: None "Spence, Jane" <Jane.Spence@nrc.gov>

Tracking Status: None "Devlin-Gill, Stephanie" <Stephanie.Devlin-Gill@nrc.gov>

Tracking Status: None "Roche, Kevin" <Kevin.Roche@nrc.gov>

Tracking Status: None "Yee, On" <On.Yee@nrc.gov>

Tracking Status: None "Candelario, Luissette" <Luissette.Candelario@nrc.gov>

Tracking Status: None "Nakanishi, Tony" <Tony.Nakanishi@nrc.gov>

Tracking Status: None "Lehman, Bryce" <Bryce.Lehman@nrc.gov>

Tracking Status: None "Tsirigotis, Alexander" <Alexander.Tsirigotis@nrc.gov>

Tracking Status: None "50.54f_Seismic Resource" <50.54f_Seismic.Resource@nrc.gov>

Tracking Status: None "RidsNroDsea Resource" <RidsNroDsea.Resource@nrc.gov>

Tracking Status: None "Shams, Mohamed" <Mohamed.Shams@nrc.gov>

Tracking Status: None Post Office: HQPWMSMRS08.nrc.gov Files Size Date & Time MESSAGE 3194 8/27/2015 4:39:00 PM Perry R2. 1 Seismic ESEP NRC review(1).docx 52320 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received:

TECHNICAL REVIEW CHECKLIST BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO EXPEDITED SEISMIC EVALUATION PROCESSINTERIM EVALUATION IMPLEMENTING NTTF RECOMMENDATION 2.1 SEISMIC PERRY NUCLEAR POWER PLANT DOCKET NO. 50-440 By letter dated March 12, 2012 (USNRC, 2012a), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(f) Conditions of License (hereafter referred to as the 50.54(f) letter). Enclosure 1 of the 50.54(f) letter requests addressees to reevaluate the seismic hazard at their site using present-day methods and guidance for licensing new nuclear power plants, and identify actions to address or modify, as necessary, plant components affected with the reevaluated seismic hazards. Requested Information Item (6) in Enclosure 1 to the 50.54(f) letter requests addressees to provide an interim evaluation and actions taken or planned to address a higher seismic hazard relative to the design basis, as appropriate, prior to completion and submission of the seismic risk evaluation.

Additionally, by letter dated April 12, 20131, the Electric Power Research Institute (EPRI) staff submitted EPRI TR 3002000704 Seismic Evaluation Guidance: Augmented Approach for the Resolution of Fukushima Near-Term Task Force (NTTF) Recommendation 2.1: Seismic (hereafter referred to as the guidance). The Augmented Approach proposed that licensees would use an Expedited Seismic Evaluation Process (ESEP) to address the interim actions as requested by Information Item (6) in the 50.54(f) letter. The ESEP is a simplified seismic capacity evaluation with a focused scope of certain key installed Mitigating Strategies equipment that is used for core cooling and containment functions to cope with scenarios that involve a loss of all AC power and loss of access to the ultimate heat sink to withstand the Review Level Ground Motion, which is up to two times the safe shutdown earthquake (SSE).

Due to the expedited and interim nature of the ESEP, the assessment does not include many considerations that are part of a normal risk evaluation.These deferred items, include but are not limited to, structures, piping, non-seismic failures, and operator actions, as well scenarios such as addressing loss of coolant accidents. By letter dated May 7, 20132, the NRC staff endorsed the guidance. Central and eastern United States licensees with a reevaluated seismic hazard exceeding the SSE submitted an ESEP interim evaluation in December 2014.

Consistent with the interim nature of this activity, the staff performed the review of the licensees submittal to assess whether the intent of the guidance was implemented. A multi-disciplined team checked whether the identified methods were consistent with the guidance. A senior expert panel reviewed the teams questions, if any, and checklist for consistency and scope.

New or updated parameters (e.g., In-Structure Response Spectra, High Confidence of Low Probability of Failure calculations) presented by the licensees were assessed only based on licensee statements for acceptability for the Item (6) response. The application of this staff review is limited to the ESEP interim evaluation as part of NTTF R2.1: Seismic activities.

1 ADAMS Accession No. ML13102A142 2 ADAMS Accession No. ML13106A331

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant By letter dated November 3, 20143, First Energy Nuclear Operating Company provided an Expedited Seismic Evaluation Process (ESEP) report in a response to Enclosure 1, Requested Information Item (6) of the 50.54(f) letter, for the Perry Nuclear Power Plant (Perry).

I. Review Level Ground Motion The licensee:

  • described the determination of the review level ground motion Yes (RLGM) using one of the means acceptable by the guidance
  • identified location of the control point and is consistent with March Yes 2014 Seismic Hazard and Screening Report submittal

Perryused a used a new Seismic Probabilistic Risk Analysis (SPRA)

Ground Motion Response Spectra(GMRS).(1)

Notes from the Reviewer:

1. The licensee used a new GMRS rather than its seismic hazard reevaluation GMRS documented in its March 2014 Seismic Hazard and Screening Report (SHSR)4, which was found acceptable for use in Recommendation 2.1 seismic activities by the staff.

Because the new GMRS is similar to and bounds the SHSR GMRS, the staff judged that this GMRS is acceptable for the purposes of this interim evaluation.

Deviation(s) or Deficiency(ies), and Resolution:

No deviation or deficiencies were found in the review of this particular section.

The NRC staff concludes:

  • the licensees RLGM meets the intent of the guidance Yes
  • the RLGM is reasonable for use in the interim evaluation. Yes II. Selection of the Success Path The licensee:
  • described the success path Yes
  • described normal and desired state of the equipment for the Yes success path
  • ensured that the success path is consistent with the plants overall Yes mitigating strategies approach or provided a justification for an alternate path
  • stated that the selection process was in accordance with the guidance or meets the intent of the guidance Yes
  • used installed FLEX Phase 1 equipment as part of the success path Yes
  • included FLEX Phase 2 and/or 3 connections Yes

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant Notes from the Reviewer: None Deviation(s) or Deficiency(ies), and Resolution:

No deviation or deficiencies were found in the review of this particular section.

The NRC staff concludes that:

  • the selected success path is reasonable for use in the interim Yes evaluation
  • the licensee considered installed Phase 2 and 3 connections or Yes equipment in the interim evaluation.

III. Selection of the Expedited Seismic Equipment List (ESEL)

The licensee:

  • developed and provided the ESEL by applying the ESEP Yes
  • identified equipment considering the following functions:

o Core cooling (with focus on Mode 1) function Yes o Available, sustainable water source Yes o Containment function and integrity Yes Notes from the reviewer: None Deviation(s) or Deficiency(ies), and Resolution:

No deviation or deficiencies were found in the review of this particular section.

For PWR Plants ONLY The licenseeincluded indicators / instrumentation for the following functions:

level, pressure, temperature, that would be indicative of (but not explicitly N/A identified to specific instruments): water level of a steam generator (SG),

pressure of SG, containment, and reactor coolant system (RCS); and temperature of the RCS.

For BWR Plants ONLY The licenseeconsidered indicators for the following functions:level, pressure, temperature that would be indicative of (but not explicitly identified to Yes specific instruments): Temperature of suppression pool, RCS, containment; Pressure of suppression pool, RCS, and drywell; water level of the suppression pool.

Notes from the Reviewer: None Deviation(s) or Deficiency(ies), and Resolution:

No deviation or deficiencies were found in the review of this particular section.

Page 3

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant Through a sampling of the ESEP key components, the NRC staff concludes that:

  • the licensees process to develop the ESEL meets the intent of the Yes guidance for the interim evaluation
  • the desired equipment state for the success path were identified Yes
  • the licensee considered the support equipment for the ESEL Yes
  • both front-line and support systems appeared to be included in the ESEL as evidenced by inclusion of SSCs on the success path and of Yes support systems (e.g., batteries, motor control center,inverters).

IV. Walkdown Approach The licensee:

  • described the walkdown screening approach, including walkbys Yes and walkdowns performed exclusively for the ESEP, in accordance with the guidance
  • credited previous walkdown results, including a description of Yes current action(s) to verify the present equipment condition and/or configuration (e.g., walk-bys), in accordance with the guidance
  • stated seismic walkdown training of walkdown personnel(1) Yes Notes from the Reviewer:
1. In response to a staff question (ML15212A955), the licensee provided the training credentials for personnel involved in the walkdown. The staff finds that the response adequately addresses the question and therefore,it is acceptable.

Deviation(s) or Deficiency(ies), and Resolution:

No deviation or deficiencies were found in the review of this particular section.

The licensee:

  • described, if needed, adverse material condition of the equipment N/A (e.g., material degradation)
  • credited previous walkdown results, included a description of current action(s) to verify the present equipment condition Yes (e.g., walk-bys), meeting the intent of the guidance The licensee:
  • described the conditions of structural items considered for the interim evaluation, including:

o spatial interactions (i.e. interaction between block walls and Yes other items/components) o anchorage Yes o piping connected to tanks (i.e. differential movement between pipes and tanks at connections) Yes Notes from the Reviewer: None Deviation(s) or Deficiency(ies), and Resolution:

No deviation or deficiencies were found in the review of this particular section.

Page 4

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant The licensee reported deviations for Perry. No If deviations wereidentified, there is a discussion of how the deficiencies were or will be addressed in the ESEP submittal report. N/A The NRC staff concludes that:

  • the licensee described the performed walkdown approach, Yes including any credited previous efforts (e.g., Individual Plant Examination of External Events(IPEEE)) consistent with the guidance
  • the licensee addressed identified deviations consistent with the N/A guidance, if any V. Capacity Screening Approach and High Confidence/Low Probability of Failure (HCLPF) Calculation Results The licensee:
  • described the capacity screening process for the ESEL items, N/A consistent with the guidance (e.g., use of EPRI NP-6041 screening table).
  • presented the results of the screened-out ESEL items in the ESEP N/A report
  • described the development of in-structure response N/A spectra(ISRS)based on scaling
  • described the development of ISRS based on new analysis Yes (1) consistent with the guidance
  • described the method for estimating HCLPF capacity of screened-in ESEL items, including both structural and functional failure modes consistent with the guidance: (2) (3) o use of Conservative Deterministic Failure Margin (CDFM) Yes o use of fragility analysis (FA) N/A o use of experience data or generic information Yes
  • credited IPEEE spectral shape for HCLPF capacity estimates is similar to or envelopes the RLGM, and anchored at the same N/A control point
  • presented the results of HCLPF capacities including associated failure modes for screened-in ESEL items (4) Yes
  • reviewed the ESEL items with the lowest HCLPF values to ensure Yes that their capacities are equal or greater than the RLGM Notes from the Reviewer:
1. The licensee did not use a scaled ISRS. As allowed by guidance, the licensee calculated a new GMRS-based ISRS. The new GMRS was developed to be used in an upcoming SPRA, which at the time of the Perry ESEP submittal was underway (see Perry ESEP Submittal page 40 of 42). The staff ESEP review for the GMRS is in Section I of this checklist.Based on the above, the Perry ESEP new GMRS-based ISRS is judged by the staff to be acceptable for this interim evaluation only.
2. The staff asked several questions to the licensee regarding the HCLPF calculations methodologyto include: thefunctional evaluation of relays and treatment of valves that did not meet the valve operator caveats necessary to use a generic approach for estimating Page 5

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant HCLPF capacity.The licensee stated that CDFM methodology has been used for all calculations, including the relay capacity evaluations. The licensee provided detailed information,consistent with the ESEP guidance, about the treatment of valves that do not meet the valve operator caveatsnecessary to use a generic approach for estimating HCLPF capacity. The staff finds that the licensee responses (ML15212A955) adequately addressed the concerns and met the intent of the guidance for this interim evaluation.

3. The staff asked the licenseesabout the implementation of the rule-of-the-box, as discussed in Sections 3.1.5 and 6.1 of the ESEP submittal. In its response (ML15212A955),the licensee clarified its implementation of the rule-of-the-box and stated that when an ESEL item is identified to be mounted on a parent component, the HCLPF of the parent component is assigned to the item. Thestaff finds that the method used is consistent with the ESEP guidance and therefore, is acceptable.
4. As a result of a question from the staff, the licensee provided a roadmap between the entries in the ESEL (Attachment A) and the entries in HCLPF Capacity Table (Attachment B). The staff finds the licensee response (ML15212A955) adequately addressed the question.

Deviation(s) or Deficiency(ies), and Resolution:

  • No deviation or deficiencies were found in the review of this particular section.

The NRC staff concludes that:

  • the licensee described the implementation of the capacity N/A screening process consistent with the intent of the guidance
  • the licensee presented capacity screening and calculation results, Yes as appropriate, in the ESEP report
  • the method used to develop the ISRS is consistent with guidance Yes for use in the ESEP
  • for HCLPF calculations, the licensee used HCLPF calculation Yes methods as endorsed in the guidance
  • no anomalies were noted in the reported HCLPF Yes VI. Inaccessible Items The licensee:
  • provided a list of inaccessible items(1) Yes
  • provided a schedule of the planned walkdown and evaluation for all N/A inaccessible items
  • provided Regulatory Commitment to complete walkdowns. N/A Perrywill provide results or complete walkdown by:N/A N/A Notes from the Reviewer:
1. The licensee identified twelve components as inaccessible due to their location in confined spaces and high radiation areas. The licensee used plant drawings to asses design parameters and similarity with anevaluated representative component of the same class. The reviewer finds this acceptable for the purpose of this interim evaluation.

Deviation(s) or Deficiency(ies), and Resolution:

No deviation or deficiencies were found in the review of this particular section.

Page 6

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant The NRC staff concludes that the licensee:

  • listed inaccessible items Yes
  • committed to provide the results (e.g. walkdowns, walkbys, etc.) of N/A the remaining inaccessible items consistent with the guidance
  • substitutions, if needed, were appropriately justified Yes VII. Modifications The licensee:
  • identified modifications for ESEL items necessary to achieve HCLPF N/A values that bound the RLGM, as specified in the guidance
  • provided a schedule to implement such modifications (if any), N/A consistent with the intent of the guidance
  • provided Regulatory Commitment to complete modifications N/A
  • provided Regulatory Commitment to report completion of modifications. N/A Perrywill:
  • complete modifications by:N/A
  • report completion of modifications by:N/A Notes from the Reviewer: None Deviation(s) or Deficiency(ies), and Resolution:

No deviation or deficiencies were found in the review of this particular section.

The NRC staff concludes that the licensee:

  • identified plant modifications necessary to achieve the target seismic N/A capacity
  • provided a schedule to implement the modifications (if any) N/A consistent with the guidance VII. Conclusions The NRC staff assessed the licensees implementation of the ESEP guidance. Due to the interim applicability of the ESEP evaluations,use of the information for another application would require a separate NRC review and approval.Based on its review, the NRC staff concludes that the licensees implementation of the interim evaluation meets the intent of the guidance. The staff concludes that, through the implementation of the ESEP guidance, the licensee identified and evaluated the seismic capacity of certain key installed Mitigating Strategies equipment that is used for core cooling and containment functions to cope with scenarios that involvea loss of all AC power and loss of access to the ultimate heat sink to withstand a seismic event up to the Review Level Ground Motion (RLGM) and thus, provides additional assurance while the plant seismic risk evaluation is being conducted. In the case of Perry, the RLGM used the SPRA GMRS.The application of this staff review is limited to the ESEP interim evaluation as part of the NTTF R2.1: Seismic activities. The staff did not identify deviations or exceptions from the guidance for the purposes this interim evaluation. The licensee found all equipment evaluated for the ESEP to have adequate capacity for the required demand. Therefore, no modification of equipment was required.

Page 7

NTTF Recommendation 2.1 Expedited Seismic Evaluation Process Technical Review Checklist for Perry Nuclear Power Plant In summary, by implementing the ESEP interim evaluation, the licensee demonstrated that additional assurance exists which supports continued plant safety and confirms that sufficient time exists to allow the completion of longer-term seismic evaluations to support regulatory decision making. The NRC staff concludes that the licensee responded appropriately to , Item (6) of the 50.54(f) letter, dated March 12, 2012, for Perry Nuclear Power Plant.

Principle Contributors:

Stephanie Devlin-Gill, On Yee, Tony Nakanishi, Bryce Lehman, Alexander Tsirigotis, , Luissette Candelario, Richard Morante (NRC consultant)

Page 8