{{#Wiki_filter:Keith J. Poison Site Vice President DTE Energy Company 6400 N. Dixie Highway, Newport, M1 48166 Tel: 734.586.4849    Fax: 734.586.4172 Email: polsonk@dteenergy.com DTE Energy-10 CFR 54 July 6, 2016 NRC-16-0045 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D C        20555-0001
 
==References:==
: 1) Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
: 2) DTE Electric Company Letter to NRC, "Fermi 2 License Renewal Application," NRC-14-0028, dated April 24, 2014 (ML14121A554)
: 3) DTE Electric Company Letter to NRC, "Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 15," NRC-15-0009, dated January 15, 2015 (ML15016A063)
 
==Subject:==
Completion of Fermi 2 License Renewal Application Commitment Item 1 In Reference 2, DTE Electric Company (DTE) submitted the License Renewal Application (LRA) for Fermi 2. In Reference 3, DTE provided an updated commitment date of March 31, 2016 for Item 1 in LRA Table A.4. The activities in Item 1 of LRA Table A.4 were completed prior to March 31, 2016. The enclosure to this letter provides a revised version of LRA Table A.4 that shows Item 1 as complete.
No new commitments are being made in this submittal. However, as indicated, the commitment in Item 1 of LRA Table A.4 has been completed.
 
USNRC NRC-16-0045 Page 2 Should you have any questions or require additional information, please contact Lynne Goodman at 734-586-1205.
I declare under penalty of perjury that the foregoing is true and correct.
E ecuted on J    6, 2016 Wayne      Colonnello Director - Nuclear Wor Management For Keith Polson
 
==Enclosure:==
Revision to Fermi 2 License Renewal Commitment List cc: NRC Project Manager NRC License Renewal Project Manager NRC Resident Office Reactor Projects Chief, Branch 5, Region III Regional Administrator, Region III Michigan Public Service Commission, Regulated Energy Division (kindschlamichigan.gov)
 
Enclosure 1 to NRC-16-0045 Fermi 2 NRC Docket No. 50-341 Operating License No. NPF-43 Revision to Fermi 2 License Renewal Commitment List
 
Enclosure to NRC-16-0045 Page 1 A.4      LICENSE RENEWAL COMMITMENT LIST No.      Program or Activity                          Commitment                          Implementation  Source Schedule    Suc 1    Operating Experience  DTE will make the following changes to the process for        Prior-to-March A.1 Review                operating experience review (OER).                            312846.
Complete
: a. Procedures will be revised to add an aging type code to Corrective Action Program documents that describe either plant conditions related to aging or industry operating experience related to aging.
: b. Procedures will be revised to provide for training of personnel responsible for submitting, screening, assigning, evaluating, or otherwise processing plant-specific and industry operating experience concerning age-related degradation and aging management, as well as for personnel responsible for implementing AMPs, based on the complexity of the job performance requirements and assigned responsibilities.
: c. Procedures will be revised to specify that evaluations of operating experience concerning age-related degradation will include consideration of the affected systems, structures or components, the environments, materials, aging effects, aging mechanisms, and aging management programs.}}

Latest revision as of 18:00, 30 October 2019

Completion of Fermi 2 License Renewal Application Commitment Item 1
ML16188A202
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 07/06/2016
From: Colonnello W, Polson K
DTE Energy
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC-16-0045
Download: ML16188A202 (4)


Text

Keith J. Poison Site Vice President DTE Energy Company 6400 N. Dixie Highway, Newport, M1 48166 Tel: 734.586.4849 Fax: 734.586.4172 Email: polsonk@dteenergy.com DTE Energy-10 CFR 54 July 6, 2016 NRC-16-0045 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D C 20555-0001

References:

1) Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
2) DTE Electric Company Letter to NRC, "Fermi 2 License Renewal Application," NRC-14-0028, dated April 24, 2014 (ML14121A554)
3) DTE Electric Company Letter to NRC, "Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 15," NRC-15-0009, dated January 15, 2015 (ML15016A063)

Subject:

Completion of Fermi 2 License Renewal Application Commitment Item 1 In Reference 2, DTE Electric Company (DTE) submitted the License Renewal Application (LRA) for Fermi 2. In Reference 3, DTE provided an updated commitment date of March 31, 2016 for Item 1 in LRA Table A.4. The activities in Item 1 of LRA Table A.4 were completed prior to March 31, 2016. The enclosure to this letter provides a revised version of LRA Table A.4 that shows Item 1 as complete.

No new commitments are being made in this submittal. However, as indicated, the commitment in Item 1 of LRA Table A.4 has been completed.

USNRC NRC-16-0045 Page 2 Should you have any questions or require additional information, please contact Lynne Goodman at 734-586-1205.

I declare under penalty of perjury that the foregoing is true and correct.

E ecuted on J 6, 2016 Wayne Colonnello Director - Nuclear Wor Management For Keith Polson

Enclosure:

Revision to Fermi 2 License Renewal Commitment List cc: NRC Project Manager NRC License Renewal Project Manager NRC Resident Office Reactor Projects Chief, Branch 5, Region III Regional Administrator, Region III Michigan Public Service Commission, Regulated Energy Division (kindschlamichigan.gov)

Enclosure 1 to NRC-16-0045 Fermi 2 NRC Docket No. 50-341 Operating License No. NPF-43 Revision to Fermi 2 License Renewal Commitment List

Enclosure to NRC-16-0045 Page 1 A.4 LICENSE RENEWAL COMMITMENT LIST No. Program or Activity Commitment Implementation Source Schedule Suc 1 Operating Experience DTE will make the following changes to the process for Prior-to-March A.1 Review operating experience review (OER). 312846.

Complete

a. Procedures will be revised to add an aging type code to Corrective Action Program documents that describe either plant conditions related to aging or industry operating experience related to aging.
b. Procedures will be revised to provide for training of personnel responsible for submitting, screening, assigning, evaluating, or otherwise processing plant-specific and industry operating experience concerning age-related degradation and aging management, as well as for personnel responsible for implementing AMPs, based on the complexity of the job performance requirements and assigned responsibilities.
c. Procedures will be revised to specify that evaluations of operating experience concerning age-related degradation will include consideration of the affected systems, structures or components, the environments, materials, aging effects, aging mechanisms, and aging management programs.