ML19093A391: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:. & a
{{#Wiki_filter:.&   a*
* VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND,VIRGIN.IA 23261 January 24, 1978 Mr. James P. O'Reilly, Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Region II -Suite 818 230 Peachtree Street, Northwest Atlanta, Georgia 30303  
VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND,VIRGIN.IA 23261 January 24, 1978 Mr. James P. O'Reilly, Director                         Serial No. 023/011078 Office of Inspection and Enforcement                   PO&l'f/DLB:das U.S. Nuclear Regulatory Commission                     Docket N o ~
Region II - Suite 818                                             ~
230 Peachtree Street, Northwest                       License Nos. DPR-32 Atlanta, Georgia 30303                                                 DPR-37


==Dear Mr. O'Reilly:==
==Dear Mr. O'Reilly:==


Serial No. 023/011078 PO&l'f/DLB:das Docket No~ License Nos. DPR-32 DPR-37 This is in response to your letter of January 10, 1978, in reference to the inspection conducted at Surry Power Station on November 29-December 2, 1977 and reported in Inspection Report Nos. 50-280/77-35 and 50-281/77-35.
This is in response to your letter of January 10, 1978, in reference to the inspection conducted at Surry Power Station on November 29-December 2, 1977 and reported in Inspection Report Nos. 50-280/77-35 and 50-281/77-35.
We have reviewed the subject inspection report and have determined that no proprietary information is contained therein. Accordingly, the Virginia Electric and Power Company interposes no objection to this inspection report being made a matter of public disclosure.
We have reviewed the subject inspection report and have determined that no proprietary information is contained therein. Accordingly, the Virginia Electric and Power Company interposes no objection to this inspection report being made a matter of public disclosure.
e cc: Mr. Robert W. Reid, Chief Very truly yours, C. }f. Stallings Vice President  
e                                                       Very truly yours, C. }f. Stallings Vice President - Power Supply and Production Operations cc:  Mr. Robert W. Reid, Chief}}
-Power Supply and Production Operations}}

Latest revision as of 23:05, 19 October 2019

Response of Letter of 01/10/1978 in Reference to Inspection Conducted on 11/29-12/02/1977 and Reported in Inspection Report Nos. 05000280/1977035 & 05000281/1977035
ML19093A391
Person / Time
Site: Surry  Dominion icon.png
Issue date: 01/24/1978
From: Stallings C
Virginia Electric & Power Co (VEPCO)
To: O'Reilly J
NRC/IE, NRC/RGN-II
References
IR 1977035
Download: ML19093A391 (1)


Text

.& a*

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND,VIRGIN.IA 23261 January 24, 1978 Mr. James P. O'Reilly, Director Serial No. 023/011078 Office of Inspection and Enforcement PO&l'f/DLB:das U.S. Nuclear Regulatory Commission Docket N o ~

Region II - Suite 818 ~

230 Peachtree Street, Northwest License Nos. DPR-32 Atlanta, Georgia 30303 DPR-37

Dear Mr. O'Reilly:

This is in response to your letter of January 10, 1978, in reference to the inspection conducted at Surry Power Station on November 29-December 2, 1977 and reported in Inspection Report Nos. 50-280/77-35 and 50-281/77-35.

We have reviewed the subject inspection report and have determined that no proprietary information is contained therein. Accordingly, the Virginia Electric and Power Company interposes no objection to this inspection report being made a matter of public disclosure.

e Very truly yours, C. }f. Stallings Vice President - Power Supply and Production Operations cc: Mr. Robert W. Reid, Chief