Line 3: |
Line 3: |
| | issue date = 11/18/2010 | | | issue date = 11/18/2010 |
| | title = MIP- Nasa Plum Brook Reactor Facility FY2011 | | | title = MIP- Nasa Plum Brook Reactor Facility FY2011 |
| | author name = Kemker B J | | | author name = Kemker B |
| | author affiliation = NRC/RGN-III/DNMS/DB | | | author affiliation = NRC/RGN-III/DNMS/DB |
| | addressee name = Lugo R | | | addressee name = Lugo R |
|
---|
Category:Letter
MONTHYEARML17090A5292017-03-31031 March 2017 Independent Spent Fuel Storage Installation (ISFSI) - Transmittal of 10 CFR 50.59, 10 CFR 72.48, and Commitment Change Annual Reports and Notifications ML12326A8732012-11-0202 November 2012 Signed Amendment to Indemnity Agreement No. D-3 (Amendment No. 18) Nasa Pbrf ML12223A2522012-10-10010 October 2012 A. Liang Ltr Termination of Facility License Nos. TR-3 and R-93 for the National Aeronautics and Space Administration Research Reactors at the Plum Brook Reactor Facility, Sandusky, Ohio ML12264A3232012-10-10010 October 2012 Amendment to Indemnity Agreement No. D-3 Amendment No. 18 IR 05000030/20120022012-09-26026 September 2012 IR 05000030-12-002 (DNMS) and 05000185-12-002 (Dnms), on 09/13/2012, Nasa Plum Brook Reactor Facility ML12268A3262012-09-18018 September 2012 Plum Brook Reactor Facility, Request for Termination of Licenses Nos. TR-3 and R-93 ML12264A5592012-09-18018 September 2012 Final Status Survey Report, Main Body of Report, Revision 1, for the Plum Brook Reactor Facility ML12201A1112012-07-13013 July 2012 Revised Final Status Survey Report, Attachment 17 for the Plum Brook Reactor ML12195A2402012-07-12012 July 2012 Response to NRC Staff Comments on Final Status Survey Report Main Body, for the Plum Brook Reactor Facility ML12194A5812012-07-11011 July 2012 Technical Basis Document, TBD-12-002, Rev. 0, Dose Assessment for Miscellaneous and Buried Piping for the Plum Brook Reactor Facility, Licenses ML12153A2792012-06-25025 June 2012 M. Epstein Ltr Decommissioning Status of Nasa Plum Brook Reactor Facility ML12166A1592012-06-22022 June 2012 Letter to EPA Regarding Notification of the Decommissioning of the National Aeronautics and Space Administration Plum Brook Reactor Facility ML12160A3622012-06-0707 June 2012 Response to NRC Staff Comments on Final Status Survey Report Attachments 17, for the Plum Brook Reactor Facility IR 05000030/20110022012-05-11011 May 2012 IR 05000030-11-002(DNMS) and 05000185-11-002(DNMS) on 07/25/2011 - 07/29/2011 and In-office Completed on 05/03/2012, Nasa Plum Brook Reactor Facility ML1212407022012-05-0909 May 2012 P. Kolb Ltr Nasa Response to U.S. Nuclear Regulatory Commission Staff Comments on Final Status Survey Report Attachments for the Plum Brook Reactor Facility ML12100A1232012-04-0505 April 2012 Plum Brook Reactor Facility - Revised Final Status Survey Report, Attachments 7, 8 and 9 ML12095A1562012-03-30030 March 2012 Nasa, Transmittal of Main Body of the Final Status Survey Report to Support Termination of the Licenses for the Plum Brook Reactor Facility ML12090A6002012-03-29029 March 2012 Final Status Survey Report, Attachment 17, Buried and Miscellaneous Piping, for the Plum Brook Reactor Facility ML12068A2612012-03-0606 March 2012 Final Status Survey Report, Attachment 14, Transport Roadways and Parking Lots, for the Plum Brook Reactor Facility ML12059A3332012-02-23023 February 2012 Final Status Survey Report, Attachment 18, Excavated and Backfill Material for the Plum Brook Reactor Facility ML12065A2142012-02-23023 February 2012 Final Status Survey Report, Attachment 15, Open Land Areas within Restricted Area and Outside Buffer Area, for the Plum Brook Reactor Facility ML12034A1392012-02-0202 February 2012 Response to NRC Staff Comments on Final Status Survey Report Attachments 7, 8, 9, 10, 11 and 13 for the Plum Brook Reactor Facility ML12030A2312012-01-25025 January 2012 Transmittal of Final Status Survey Report, Attachment 12 - Reactor (Building 1111), for the Plum Brook Reactor Facility ML12025A0872012-01-23023 January 2012 Plum Brook Reactor Facility - Technical Basis for Reevaluation of Structural Dcgls and Uranium Activity Fractions ML12025A1282012-01-23023 January 2012 Transmittal of Final Status Survey Report, Attachment 15, Miscellaneous Structures and Pads, for the Plum Brook Reactor Facility ML12020A1002012-01-18018 January 2012 Revised Final Status Survey Report, Attachment 13, Primary Pump House (Building 1134), for the Plum Brook Reactor Facility IR 05000030/20120012011-12-0909 December 2011 IR 05000030-12-001 and 05000185-12-001; National Aeronautics and Space Administration (Nasa); 10/18-20/2011 - 11/22/2011; (DNMS) - Nasa Plum Brook Reactor Facility, Inspection Report ML1132105362011-11-10010 November 2011 Orise Report for Soil Samples at the Nasa Plum Brook Reactor Facility ML11286A0712011-10-0707 October 2011 Submittal of Attachment 9 to Final Status Survey Report Supporting Eventual Termination of Licenses for Plum Brook Reactor Facility ML11280A2942011-10-0606 October 2011 Notification of Staff Changes Update at the Plum Brook Reactor Facility ML11273A0542011-09-29029 September 2011 Fy 2012 Nasa Plum Brook Reactor Facility Master Inspection Plan ML11262A2872011-09-15015 September 2011 Final Status Survey Report, Attachment 11, Reactor Containment Vessel, for the Plum Brook Reactor Facility ML11243A1832011-08-29029 August 2011 Final Status Survey Report, Attachment 10, Emergency Retention Basin, for the Plum Brook Reactor Facility ML11228A0242011-08-11011 August 2011 Nasa - Final Status Survey Report, Attachment 13, Primary Pump House (Building 1134), for the Plum Brook Reactor Facility ML11203A3602011-07-19019 July 2011 Final Status Survey Report, Attachment 8, Hot Laboratory (Building 1112), for the Plum Brook Reactor Facility, Licenses Nos. TR-3, Docket No. 50-30 and R-93, Docket No. 50-185 ML1107402272011-03-11011 March 2011 Nasa - Final Status Survey Report, Attachment 7, Storm Drains, Pipe Trenches & Other Sub-Surface Excavations, for the Plum Brook Reactor Facility IR 05000030/20110012011-03-0707 March 2011 IR 05000030-11-001(DNMS) and 05000185-11-001(DNMS), on 01/26/2011 - 01/27/2011 and In-office Review Completed on 02/10/2011, Nasa Plum Brook Reactor Facility and NOV ML1032302522010-11-18018 November 2010 MIP- Nasa Plum Brook Reactor Facility FY2011 ML1031902172010-11-15015 November 2010 K. Peecook Ltr Nasa Response to NRC Staff Comments on Final Status Survey Report, Attachments 1 Through 5, for the Plum Brook Reactor Facility ML1031907082010-11-12012 November 2010 Nasa Technical Basis Document PBRF-TBD-10-001, Supplemental Radiological Characterization of Plum Brook Section 2 ML1030603242010-10-27027 October 2010 Revised Final Status Survey Report, Attachments 1, 2, 3, 5, and 6, for the Plum Brook Reactor Facility ML1029903352010-10-25025 October 2010 Response to NRC Staff Comments on Final Status Survey Report Attachments 1 Through 5, for the Plum Brook Reactor Facility, Licenses Nos. TR-3, Docket No. 50-30 and R-93, Docket No, 50-185 ML1027200312010-09-24024 September 2010 Letter from National Aeronautics and Space Administration Staff Changes, at the Plum Brook Reactor Facility IR 05000030/20100012010-09-14014 September 2010 IR 05000030-10-001 (DNMS) & 05000185-10-001, 08/16/2010, On-site 07/12-14/2010, In-office 08/16/2010, Nasa Plum Brook Reactor Facility ML1025803342010-09-13013 September 2010 Nasa - Final Status Survey Report, Attachment 6, Rev. 0, Waste Handling Building (Building 1133), for the Plum Brook Reactor Facility ML1023904082010-08-26026 August 2010 Submittal of Final Status Survey Report, Amendment 4, Pentolite Ditch, for Plum Brook Reactor Facility ML1021501862010-07-29029 July 2010 Orise Report for Five Soil Samples from Nasa Plum Brook (IR 05000030-10-001, 05000185-10-001) ML1018304142010-06-30030 June 2010 Notice of Change of Decommissioning Schedule for Nasa Plum Brook Reactor Facility ML1020302792010-05-27027 May 2010 Final Status Survey Report, Attachment 5, Hot Retention Area, for the Plum Brook Reactor Facility ML1020302802010-05-27027 May 2010 Final Status Survey Report, Attachment 3, Fan House Building, for the Plum Brook Reactor Facility 2017-03-31
[Table view] |
Text
November 18, 2010
Mr. Ramon Lugo, III Director NASA Glenn Research Center at Lewis Field 21000 Brookpark Road M.S. 3-2 Cleveland, OH 44135
SUBJECT:
NASA PLUM BROOK REACTOR FACILITY MASTER INSPECTION PLAN - FISCAL YEAR 2011
Dear Mr. Lugo:
In accordance with the U.S. Nuclear Regulatory Commission (NRC) Inspection Manual, Chapter 2545, "Research and Test Reactor Inspection Program," the NRC Region III staff and management have developed a Master Inspection Plan (MIP) for the Plum Brook Reactor. The plan is based on your current performance and schedule of significant decommissioning activities planned for the site for fiscal year (FY) 2011, which is from October 2010 through September 2011. The plan outlines how we intend to focus our regional inspection resources to address significant ongoing decommissioning activities.
Because the FY 2011 MIP is based, in part, on your proposed schedule of significant decommissioning activities for FY 2011, the plan and the focus of NRC inspection activities may change to reflect a change in your planned decommissioning activities or your performance. In order to ensure that the FY 2011 MIP remains current, we request that you keep the Materials Control, ISFSI, and Decommissioning Branch staff informed of any significant changes in your proposed schedule of decommissioning activities. You will be informed of any significant changes to the Plum Brook Reactor FY 2011 MIP.
We currently project the region will conduct two inspections at the Plum Brook Reactor during FY 2011. We are planning the inspections to coincide with the decontamination activities and final status surveys related to the reactor building, hot lab, primary pump house and remaining open land areas. Additional inspections may be warranted, depending on decommissioning activities. The following is a list of the inspection procedures we expect to use during our inspections. The specific procedures used during each inspection will depend on the specific decommissioning activities being conducted.
Inspection Procedure Inspection Procedure Title IP 69013 Research and Test Reactor Decommissioning IP 83801 Inspection of Final Surveys of Permanently Shutdown Reactors
R. Lugo
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.
We will gladly discuss any questions you may have regarding these inspection plans. If you have questions, please contact Mr. Jeremy Tapp of my staff at (630) 829-9862.
Sincerely,
/RA/
Brian J. Kemker, Acting Chief Materials Control, ISFSI, and Decommissioning Branch
Docket Nos.: 50-30 and 50-185 License Nos.: TR-3 and R-93
cc: Radiation Health Program Director, Ohio Department of Health (ODH)
S. Helmer, ODH M. Rubadue, ODH Ohio Environmental Protection Agency, Division of Planning K. Peecook, NASA, Plum Brook Station R. Lugo
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.
We will gladly discuss any questions you may have regarding these inspection plans. If you have questions, please contact Mr. Jeremy Tapp of my staff at (630) 829-9862.
Sincerely,
/RA/
Brian J. Kemker, Acting Chief Materials Control, ISFSI, and Decommissioning Branch
Docket Nos.: 50-30 and 50-185 License Nos.: TR-3 and R-93
cc: Radiation Health Program Director, Ohio Department of Health (ODH)
S. Helmer, ODH M. Rubadue, ODH Ohio Environmental Protection Agency, Division of Planning K. Peecook, NASA, Plum Brook Station
DISTRIBUTION
- P. Michalak, FSME C. Glenn, FSME N. Orlando, FSME S. West, RIII S. Reynolds, RIII C. Lipa, RIII A. Barker, RIII H. Logaras, RIII V. Mitlyng, RIII P. Chandrathil, RIII MCID Distribution
DOCUMENT NAME: G:\DNMSIII\Work in progress\MI P - NASA Plum Brook Reactor Facility FY2011.doc X Publicly Available Non-Publicly Available Sensitive X Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII E RIII E NAME JTapp BKemker DATE 11/17/2010 11/18/10 OFFICIAL RECORD COPY