ML17349A818: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 3: Line 3:
| issue date = 04/20/1993
| issue date = 04/20/1993
| title = Application for Amends to Licenses DPR-31 & DPR-41,modifying TS Table 2.2-1, Reactor Trip Sys Instrumentation Trip Setpoints to Remove Lead/Lag Compensator Term on Measured Delta T from Overtemp Delta T & Overpower Delta T
| title = Application for Amends to Licenses DPR-31 & DPR-41,modifying TS Table 2.2-1, Reactor Trip Sys Instrumentation Trip Setpoints to Remove Lead/Lag Compensator Term on Measured Delta T from Overtemp Delta T & Overpower Delta T
| author name = PLUNKETT T F
| author name = Plunkett T
| author affiliation = FLORIDA POWER & LIGHT CO.
| author affiliation = FLORIDA POWER & LIGHT CO.
| addressee name =  
| addressee name =  

Revision as of 09:05, 18 June 2019

Application for Amends to Licenses DPR-31 & DPR-41,modifying TS Table 2.2-1, Reactor Trip Sys Instrumentation Trip Setpoints to Remove Lead/Lag Compensator Term on Measured Delta T from Overtemp Delta T & Overpower Delta T
ML17349A818
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 04/20/1993
From: Plunkett T
FLORIDA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML17349A819 List:
References
L-93-081, L-93-81, NUDOCS 9304290160
Download: ML17349A818 (21)


Text

>CCELERATj" 0 DOCUMENT D1ST BUT1ON SYSTEM REGULA-Y INFORMATION DZSTRIBUTIO YSTEM (RIDE)ACCESSIOP NBR:9304290160 DOC.DATE: 93/04/20 NOTARIZED:

YES FACIAL:50-250 Turkey Point Plant, Unit 3, Florida Power and Light C 50-251 Turkey Point Plant, Unit 4, Florida Power and Light C AUTH.NAME AUTHOR AFFILIATION PLUNKETT,T.F.

Florida Power 6 Light Co.RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)

SUBJECT:

Application for amends'o Licenses DPR-31 6 DPR-41,modifying TS Table 2.2-1,"Reactor Trip Sys Instrumentation Trip Setpoints" to remove lead/lag compensator term on measured delta T from overtemp delta T a overpower delta T.DISTRIBUTION CODE: AOOZD COPIES RECEIVED:LTR I ENCL I SIZE: 1 Wg TITLE: OR Submittal:

General Distribution NOTES: DOCKET li 05000250 05000251 D RECIPIENT ID CODE/NAME PD2-2 LA RAGHAVAN,L INTERNAL: NRR/DE/EELB NRR/DRCH/HICB NRR/DSSA/SPLB NUDOCS-ABSTRACT OGC/HDS3 EXTERNAL: NRC PDR COPIES LTTR ENCL 1 1 2 2 1 1 1 1 1'1 1 1 0 1 1 RECIPIENT ID CODE/NAME PD2-2 PD NRR/DORS/OTSB NRR/DSSA/SCSB NRR/DSSA/SRXB.

FMB REG FI 01 NSIC COPIES LTTR ENCL 1 1 1 1 1 0 1 1 1 0 1 1 1 1 D S, D NOTE TO ALL"RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE!CONTACT THE DOCUMENT CONTROL DFDK, ROOM Pl-37 (EXT.504-2065)TO ELIMINATE YOUR NAME FROM DISTRII3UTION LISTS FOR DOCUMENTS YOU DON'7 NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 16 ENCL 13 P.O.Box 029100, Miami, FL, 33102-9100 APR 8 0 1S93 L-93-081 10 CFR 50.90 U.S.Nuclear Regulatory Commission Attn: Document Contzol Desk Washington, D.C.20555 Gentlemen:

Re: Turkey Point'nits 3 and 4 Docket Nos.50-250 and 50-251 Proposed License Amendments-Removal of Lead/Lag Compensator Term on measured aT in Overtem erature wT and Over ower~T Reactor Tzi Functions In accordance with 10 CFR 50'0, Florida Power and Light Company (FPL)requests that Appendix A of Facility Operating Licenses DPR-31 and DPR-41 be amended to modify Turkey Point Units 3 and 4 Technical Specifications Table 2.2-1, Reactor Trip System Instrumentation Trip Setpoints.

The purpose of these amendments is to revise Technical Specification Table 2.2-1, Reactor Trip System Instrumentation Trip Setpoints, to remove the lead/lag compensator term on measured aT from the overtemperature

~T and overpower~T zeactor trip functions.

This is accomplished by setting the time constants, 9, and 9to zero seconds.FPL has determined that the proposed license amendments do not involve a significant hazard pursuant to 10 CFR 50.92.A description of the amendments request is provided in Attachment 1.The no significant hazards determination in support of the proposed Technical Specification change is provided in Attachment 2~Attachment 3 provides the proposed revised Technical Specification changes.In accordance with 10 CFR 50'1 (b)(1), a copy of these proposed license amendments are being forwarded to the State Designee for the State of Florida.The proposed amendments have been reviewed by the Turkey Point Plant Nuclear Safety Committee and the FPL Company Nuclear Review Board.Should there be any questions on this request, please contact us.Very truly yours, T.F.Plunkett Vice President Turkey Point Nuclear Plant TFP/RJT/rt Attachments cc: Stewart D.Ebneter,, Regional Administrator,'Region II, USNRC R.C.Butcher, Senior Resident Inspector, USNRC, Turkey Point Mr.W.A.Pasetti, Florida Department of Health and Rehabilitative Services 9304290160 930420,,a, PDR ADOCK 05000250,",,y P PDR'n FPL Group company o'

~~I p ()s STATE OF FLORIDA COUNTY OF DADE))ss.)T.F.Plunkett being first duly sworn, deposes and says: That.he is Vice President Turke Point Nuclear Plant, of Florida Power and Light Company, the Licensee herein;That he has executed the foregoing document;that the statements made in this document are true and correct to the best of his knowledge, information and belief, and that he is authorized to execute the document on behalf of said Licensee.T;F.P lunkett Subscribed and sworn to before me this day of f E+, 1993.Name of Notary Public (Type or Print)NOTARY PUBLIC, in Dade, State of Fl My Commission exp;,, CHEAYL A.KE I+r',": MY COMMISSION S CC 22378 I qi EXPQES: SoptNRNf 2T, 1996 g~gg~I goy Pic unauweee Commission No.T.F.Plunkett is personally known to me.

~~~'P I p A~'~

ATTACHMENT 1 DESCRIPTION OF AMENDMENTS REQUEST I w' L-93-081 Attachment 1 Page 1 of 5 DESCRIPTION OF AMENDMENTS RE UEST Introduction To reduce the potential foz a spurious turbine runback or reactor trip, Florida Power and Light Company (FPL)proposes a change to the Technical Specifications reactor trip functions.

The proposed change is requested to alleviate the effects of existing temperature oscillations which became significant when the primary reactor coolant system Resistance Temperature Devices (RTDs)were relocated from the bypass lines to the main loops at Turkey Point.FPL has concluded that this proposed change will not compromise the health and safety of the public.The basis of FPL's conclusion is discussed below.The proposed amendments revise the Turkey Point Units 3 6 4 Technical Specifications Table 2.2-1, Reactor Trip System Instrumentation Setpoints, to remove the lead/lag compensator term on the measured reactor coolant system (RCS)loop temperature difference (aT)from the oveztemperature aT and overpower~T reactor trip functions.

This is accomplished by changing the time constants, 0, and 0from 8 and 3 seconds respectively, to zero seconds each.Issue After experiencing several spurious overtemperatuze

~T turbine runback alarms on the Unit 3 Eagle-21 system, FPL determined that the cause of these alarms was the oscillations of the Loop B reactor coolant system hot leg temperature.

These temperature oscillations reached 2-3'F peak to peak amplitude at a fzequency between.067 Hz and 1 Hz.These oscillations have been experienced at other Westinghouse plants that have eliminated the RTD bypass loops and are attributed to phenomena resulting from such factors as power level, core loading, fuel burnup, hot channel factors (Fq, F,), and coze exit flow characteristics.

Current evidence supported by the Nuclear Steam Supply System vendor, Westinghouse, suggests that the amplitudes of these oscillations decrease with coze burnup.Westinghouse presented a summary of the hot leg streaming issue to the NRC staff on September 17, 1991.Based upon industry information provided by Westinghouse, and a review of Turkey Point's plant data, FPL concluded that the elimination of the lead/lag compensator term on measured~T from the overtemperatuze aT and overpower wT reactor trip functions would reduce the potential for a spurious turbine runback or reactor trip signal.Current Requirements Turkey Point Units 3 and 4 Technical Specification 2.2, LIMITING SAFETY SYSTEM SETTINGS, specifies the REACTOR TRIP SYSTEM INSTRUMENTATION TRIP SETPOINTS for Overtemperature

~T (NOTE 1)and Overpower sT (NOTE 3).Both the Overtemperature aT and the Overpower aT reactor trip functions include a term on the left hand-side of the expression, referred to as the lead/lag compensator term on measured aT.This term is expressed as follows:

l)l I al~

L-93-081 Attachment 1 Page 2 of 5 Lead/Lag Compensator term 1+GS 1+O,S where 9,-8 seconds, 0, 3 seconds, and S Laplace transform operator, sec'hese values were chosen based on Westinghouse experience and are typical foz a lead/lag compensator function.The basis for the lead/lag compensatoz term on measured aT in both the overtemperature zT and overpower aT reactor trip functions is discussed below.Discussion Overtem erature aT Reactor Tri Function: The overtemperature aT reactor trip function is defined in NOTE 1 of Turkey Point Technical Specifications Table 2.2-1.This reactor trip function provides core protection to prevent Departure from Nucleate Boiling (DNB)for all combinations of pressure, power, coolant temperature, and axial power distribution, provided the transient is slow with respect to piping transit delays from the core to the temperature detectors and pressure is within the range between the Pressurizer High and Low Pressure trips.The setpoint is automatically varied with: (1)coolant temperature to correct for temperature induced changes in density and heat capacity of water, and includes dynamic compensation for piping delays from the core to the.loop temperature detectors, (2)pressurizer pressure, and (3)axial power distribution.

The measured aT is multiplied by the lead/lag compensator term discussed above, and the product is compared to the continuously calculated oveztemperature aT setpoint.If the product exceeds the calculated setpoint in 2 out of 3 channels, a reactor trip signal is generated.

Over ower aT Reactor Tri Function: The overpower aT reactor trip function is defined in NOTE 3 of Turkey Point Technical Specifications Table 2.2-1.This reactor trip function is designed specifically to ensure operation within the fuel centerline temperature design basis.This is accomplished by controlling the gross core thermal power within a prescribed limit (118 percent of nominal full power).This provides assurance of fuel integrity (i.e., no fuel pellet melting and less than 1%cladding strain)under all creditable overpower conditions, limits the required range for overtemperatuze aT trip, and provides a backup to the High Neutron Flux trip.The setpoint is automatically varied with: (1)coolant temperature to correct for temperature induced changes in density and heat capacity of water, and (2)rate of change of temperature for dynamic compensation of piping delays from the core to the loop temperature detectors to ensure that the allowable heat generation rate (kw/ft)is not exceeded.The measured aT is multiplied by the lead/lag compensator, and the product is compared to the continuously calculated overpower aT setpoint.If the product exceeds the calculated setpoint in 2 out, of 3 channels, a reactor trip signal is generated.

L-93-081 Attachment 1 Page 3 of 5 Lead La Com ensator Term on measured aT in the Overtem erature wT and Over ower~T Reactor Tri Functions:

The function of the lead/lag compensator term is to amplify changes in measured aT for comparison to the overtemperature nT and overpower~T reactor trip functions.

The lead/lag compensator term on measured aT is used at some plants in instances where a faster response to a change in measured aT is required earlier to satisfy the plant's safety analyses.The lead/lag compensator on measured~T was added to FPL'Turkey Point Units 3 and 4 Technical Specifications in Amendments 140 and 135.The Technical Specification change was due to the RTD Bypass Elimination project and the installation of the Eagle-21 digital protection system.The Eagle-21 digital protection system gives Turkey Point the capability to have a lead/lag compensator term on the measured aT signal and is used as input to the overtemperature sT and overpower aT reactor trip functions.

The predecessor to Eagle-21, the Westinghouse Hagan 7100 analog protection system as installed at Turkey Point, did not have a lead/lag compensator term on measured aT.FPL verified that the lead/lag compensator term on measured~T for the oveztempezatuze

~T and overpower~T reactor trip functions are not required or assumed foz accident mitigation in any of the safety analyses that comprise the Turkey Point licensing basis.Other plants of Turkey Point's vintage currently do not have the lead/lag compensator term on measured aT in the overtemperature aT and overpower aT reactor trip functions.

Licensin Basis: During the reload design process, the overtemperature

~T and overpower~T reactor trip setpoints are reverified each cycle based on the reload core and reactor coolant system parameters.

FPL performed a review of the Turkey Point licensing basis accident analyses to determine the analyses in which either oveztemperature aT or overpower aT reactor trips were used as the primary method for system protection.

This review included the following accident analyses: Dropped Rod Cluster Control Assembly (RCCA)with and without Turbine Runback, RCCA Bank Withdrawal at Power, Feedwater Enthalpy Reduction, Boron Dilution Analysis for Density Compensation Correction, Steamline Break for Continued Feedwater Addition from Standby Feedwater Pumps, Loss of Flow, Locked Rotor, Rod Ejection, Loss of Load, and Startup of an Inactive Loop.

'~+~a L-93-081 Attachment 1 Page 4 of 5 The overtempezature aT reactor trip is used as the primary protection for three Updated Final Safety Analysis Report (UFSAR)Chapter 14 accident scenarios:

Rod Withdrawal at Power (UFSAR Chapter 14.1.2), Dropped Rod at Power (UFSAR Chapter 14.1.3), and Boron Dilution Mode 1 (UFSAR Chapter 14.1.5).The overpower aT reactor trip is not used as the primary protection for any UFSAR Chapter 14 accident scenario;however it is assumed in the overpower.kw/ft analysis performed by Westinghouse for each fuel cycle.This review verified that the lead/lag compensator term on measured aT for the overtemperature

~T and overpower~T reactor trip functions are not required or assumed for accident mitigation in any of the safety analyses that comprise the Turkey Point licensing basis.The proposed amendments will not change the trip setpoints for the overpower aT and overtemperature

~T reactor trip functions.

Proposed Technical Specification Changes FPL proposes to change the values in the Overtempezature

~T reactor trip function in Technical Specification Table 2.2-1, REACTOR TRIP SYSTEM INSTRUMENTATION TRIP SETPOINTS, NOTE l.Specifically, the proposed change involves changing the time constants 9, and 9from 8 and 3 seconds respectively, to 0 seconds each.Justification:

The lead/lag compensator term on measured~T in the overtemperature aT reactor trip function serves to amplify a change in measured aT.By setting the time constants 9, and 9, equal to zero, this amplifier term (lead/lag compensator term)is removed while still maintaining the ability to trip prior to exceeding the Departure from Nucleate Boiling Ratio (DNBR)limit.FPL's safety analyses for UFSAR Chapter 14 events do not require the lead/lag compensator term on measured~T in the oveztempezature aT reactor trip function.Within the results of the UFSAR Chapter 14 safety analyses, FPL can change the lead/lag compensator term on measured aT as long as the reactor is tripped prior to zeaching the DNBR and fuel centerline temperature limits.Changing the time constants 9, and 9, to 0 seconds, provides a gain of unity and thus ensures the reactor will trip on a valid input signal, while reducing the potential for a turbine runback or reactor trip on a spurious (invalid)input signal.

f" L-93-081 Attachment 1 Page 5 of 5 2.FPL proposes to change the values in the Overpower aT reactor trip function in Technical Specification Table 2.2-1, REACTOR TRIP SYSTEM INSTRUMENTATION TRIP SETPOINTS, NOTE 3.Specifically, the proposed change involves changing the time constants 9, and 9values from 8 and 3 seconds respectively, to 0 seconds each.Justification:

The lead/lag compensator term on measured aT in the overpower~T reactor trip function serves to amplify a change in measured aT.By setting the time constants 9, and 9, equal to zero, this amplifier term (lead/lag compensator term)is removed while still maintaining the ability to trip prior to exceeding the fuel centerline temperature limit.Turkey Point's safety analyses for UFSAR Chapter 14 events does not require the lead/lag compensator term on measured aT in the overpower u,T reactor trip function.Within the results of the UFSAR Chapter 14 safety analyses, FPL can change the lead/lag compensator term on measured~T as long as the reactor is tripped prior to exceeding the DNBR and fuel centerline temperature limits.Changing the time constants 9, and 9, to 0 seconds, provides a gain of unity and thus ensures the reactor will trip on a valid input signal, while reducing the potential for a turbine runback or reactor trip on a spurious (invalid)input signal.FPL has confirmed that the lead/lag compensatoz tezm on the measured~T in the overtemperature

~T and overpower~T reactor trip functions are not required oz assumed as a basis for the Turkey Point UFSAR safety analyses.As a result, this proposed amendment does not either create the possibility of a new or different kind of accident from any accident previously evaluated, or impact the margin of safety as'alculated in the licensing basis analyses.FPL proposes to remove the lead/lag compensatoz term on measured aT from the overtemperature aT and overpower aT'eactor trip functions by setting the time constants 9, and 9, to zero seconds each, from 8 and 3 seconds, respectively.

ATTACHMENT 2 DETERMINATION OF NO SZGNIFZCANT HAZARDS CONSIDERATION L-93-081 Attachment 2 Page 1 of 2 DETERMINATION OF NO SIGNIFICANT HAZARDS CONSIDERATION Description of Proposed License Amendments Turkey Point Units 3 and 4 Technical Specification Table 2.2-1, Reactor Trip System Instrumentation Trip Setpoints, specifies the overtemperature

~T and overpower~T reactor trip functions.

Both the overtemperature aT and overpower~T reactor trip functions include terms on the left hand-side of the expression, referred to as the lead/lag compensatoz term on measured~T.The lead/lag compensator term is expressed as (1+9, times S)divided by (1+9, times S)where 9, and 9, are time constants (seconds)and S is the Laplace transform operator (seconds').Currently in Turkey Point's Units 3 and 4 Technical Specifications, the time constants 9, and 9, are set to 8 and 3 seconds, respectively.

Florida Power and Light Company (FPL)proposes to revise the lead/lag compensator term on the measured~T in the overtemperature aT and overpower aT reactor trip functions by setting the time constants, 9, and 9equal to zero seconds.Introduction The NRC has provided standards foz determining whether a significant hazards consideration exists (10 CFR 50.92(c)).A proposed amendment to an operating license for a facility involves no significant hazards consideration, if operation of the facility in accordance with the proposed amendment would not (1)involve a significant increase in the probability or consequences of an accident previously evaluated; oz (2)create the possibility of a new or different kind of accident from any accident previously evaluated; or (3)involve a significant reduction in a margin of safety.Each standard is discussed below for the proposed license amendments.

Discussion (l)Operation of the facility in accordance with the proposed amendment would not involve a significant increase in the probability or consequences of an accident previously evaluated.

The amendment will not increase the probability oz consequences of an accident previously evaluated since the lead/lag compensator term on measured aT in the oveztemperature aT and overpower aT reactor trip functions are not required or assumed for accident mitigation in any of the UFSAR safety analyses that comprise the Turkey Point licensing basis.In addition, the reactor protection system will continue to perform its intended design function of ensuring that the core and reactor coolant system do not exceed their safety limits during normal operation or design basis anticipated operational occurrences.

,I~

L-93-081 Attachment 2 Page 2 of 2 (2)Operation of the facility in accordance with the proposed amendment would not create the possibility of a new or different kind of accident from any accident previously evaluated.

The overtemperature aT reactor trip function is used as the primary protection for three UFSAR Chapter 14 accident scenarios:

Rod Withdrawal at Power (UFSAR Chapter 14.1.2), Dropped Rod at Power (UFSAR Chapter 14.1.3), and Boron Dilution Mode 1 (UFSAR Chapter 14.1.5).The overpower sT reactor trip function is not used as the primary protection for any UFSAR Chapter 14 accident scenario;however it is assumed in the overpower kw/ft analysis performed by Westinghouse for each fuel zeload.The lead/lag compensator term on measured aT in the overtemperature

~T and overpower~T reactor trip functions are not required or assumed for accident mitigation in any of the UFSAR safety analyses that comprise the Turkey Point licensing basis.The proposed amendments will not create the possibility of a new oz different kind of accident from any accident previously analyzed, since the operating modes, plant configuration and safety analysis assumptions will not be changed from those previously analyzed in the UFSAR.(3)Operation of the facility in accordance with the proposed amendment would not involve a significant reduction in a margin of safety.The margin of safety for the proposed-amendment is defined in the licensing basis safety analysis.The oveztemperature

~T reactor trip function is used as the primary protection for three UFSAR Chapter 14 accident scenarios:

Rod Withdrawal at Power (UFSAR Chapter 14.1.2), Dropped Rod at Power (UFSAR Chapter 14.1.3), and Boron Dilution Mode 1 (UFSAR Chapter 14.1.5).The overpower aT reactor trip is not used as the primary protection for any UFSAR Chapter 14 accident scenario;however it is assumed in the overpower kw/ft analysis performed by Westinghouse for each fuel reload.The lead/lag compensator term on measured~T for the overtemperature aT and overpower~T reactor trip functions are not required or assumed for accident mitigation in any of the safety analyses that comprise the Turkey Point licensing basis.The proposed amendments will not reduce the margin.of safety since the plant operating and safety limits, the input assumptions to the safety analyses and the plant response to transients as analyzed in the Turkey Points Units 3&4 licensing basis will not be changed from those previously analyzed in the UFSAR.Based on the above, FPL has determined that the amendment request does not (1)involve a significant increase in the probability or consequences of an accident previously evaluated, (2)create the possibility of a new or different kind of accident fzom any accident previously evaluated, or (3)involve a significant reduction in a margin of safety;and therefore the proposed changes do not involve a significant hazards consideration as defined in 10 CFR 50.92.