ML14175A536: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 202: | Line 202: | ||
: 1. Glossary of Evaluations | : 1. Glossary of Evaluations | ||
: 2. Screening and Prioritization Results 3. List of Licensee March 2014 Re-evaluated Seismic Hazard Submittals | : 2. Screening and Prioritization Results 3. List of Licensee March 2014 Re-evaluated Seismic Hazard Submittals | ||
: 4. List of Addressees Glossary of Evaluations Associated with Near-Term Task Force Recommendation | : 4. List of Addressees Glossary of Evaluations Associated with Near-Term Task Force Recommendation 2.1 Seismic Hazard Re-evaluations Interim Evaluation or Actions-An immediate licensee and NRC review of the re-evaluated hazard to determine whether actions are needed to assure plant safety while further evaluations are ongoing. The staff has completed its review and concluded that, based on the licensees' interim evaluations and actions, all central and eastern United States (CEUS) plants are safe for continued operations. | ||
Hazard Re-evaluations Interim Evaluation or Actions-An immediate licensee and NRC review of the re-evaluated hazard to determine whether actions are needed to assure plant safety while further evaluations are ongoing. The staff has completed its review and concluded that, based on the licensees' interim evaluations and actions, all central and eastern United States (CEUS) plants are safe for continued operations. | |||
Interim evaluations and actions are provided in Section 5.0, "Interim Actions," of the licensee submittals. | Interim evaluations and actions are provided in Section 5.0, "Interim Actions," of the licensee submittals. | ||
Expedited Approach-A near-term licensee evaluation to be completed by December 31, 2014, for CEUS plants whose re-evaluated hazard exceeds the current design basis for the safe shutdown earthquake hazard level. The evaluation looks at the systems and components that can be used to safely shut down a plant under the conditions of a station blackout (i.e., no alternating current power is available) and loss of ultimate heat sink. The expedited approach will either confirm that a plant has sufficient margin to continue with a longer-term evaluation without any modifications, or confirm the need to enhance the seismic capacity to assure they can withstand the re-evaluated hazard. The Expedited Approach guidance document is found in the Agencywide Documents Access and Management System under No. ML 13102A142. | Expedited Approach-A near-term licensee evaluation to be completed by December 31, 2014, for CEUS plants whose re-evaluated hazard exceeds the current design basis for the safe shutdown earthquake hazard level. The evaluation looks at the systems and components that can be used to safely shut down a plant under the conditions of a station blackout (i.e., no alternating current power is available) and loss of ultimate heat sink. The expedited approach will either confirm that a plant has sufficient margin to continue with a longer-term evaluation without any modifications, or confirm the need to enhance the seismic capacity to assure they can withstand the re-evaluated hazard. The Expedited Approach guidance document is found in the Agencywide Documents Access and Management System under No. ML 13102A142. |
Revision as of 10:36, 11 May 2019
ML14175A536 | |
Person / Time | |
---|---|
Site: | Watts Bar |
Issue date: | 06/23/2014 |
From: | Curran D J Harmon, Curran, Harmon, Curran, Spielberg & Eisenberg, LLP, Southern Alliance for Clean Energy |
To: | Macfarlane A M NRC/Chairman |
SECY RAS | |
References | |
50-394-OL, ASLBP 09-893-01OL-BD01, RAS 26115 | |
Download: ML14175A536 (34) | |
Text
June 23, 2014
Allison Macfarlane, Chairman U.S. Nuclear Regulatory Commission Washington, DC 20555 By e-mail to:
CMRMACFARLANE@nrc.gov
SUBJECT:
Watts Bar Unit 2 Operating License Proceeding
Dear Chairman Macfarlane:
On June 19, 2014, the U.S. Nuclear Regulatory Commission ("NRC") posted a notice on the hearing docket for the Watts Bar Unit 2 ("WBN2")
operating license ("OL
") proceeding that on June 24, you plan to tour the WBN2 constructi on site for the purpose of obtaining "a general familiarity with the facility." On behalf of the Southern Alliance for Clean Energy ("SACE"), the admitted Intervenor in the WBN2 OL proceeding, I am writing to ensure that before touring the facility, you are aware of the inconsistency between th e Tennessee Valley Authority's ("TVA's") schedule for resolution of serious seismic design and flood protection issues with the recommendations of the NRC's Near-Term Task Force regarding actions needed to ensure reactor safety in the aftermath of the Fukushima accident. TVA has contradicted a key recommendation by the Fukushima Near-Term Task Force by postponing completion of seismic and flooding investigations until after licensing of WBN2. If the NRC acquiesces to TVA's schedule, it will not only undermine the Task Force recommendations for ensuring reactor safety in the post-Fukushima era, but it will violate the safety requirements of the Atomic Energy Act and the public's right to a hearing on material safety issues.
The Fukushima Task Force Report included recommendation 2.1, which advises the NRC to:
Order licensees to reevaluate the seismic and flooding hazards at their sites against current NRC requirements and guidance, and, if necessary, update the design basis and SSCs [structures, systems and components] important to safety to protect against the updated hazards.
1 The Task Force also recommended that these issues be resolved for WBN2 in the course of the
OL review:
For the two plants with reactivated construction permits (Watts Bar Unit 2 and Bellefonte Unit 1), the Task Force recommends that those operating licen se reviews and the licensing itself include all of the near-term actions and any of the recommended rule changes that have been completed at the time of licensing. Any additional rule changes would be imposed on the plants in the same manner as for other operating reactors.
2 1 Recommendations for Enhancing Reactor Safety in the 21 st Century: the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident at 30 (July 12, 2011), http://www.nrc.gov/reactors/operating/ops-experience/japan-dashboard/ref-library.html. 2 Id. at 72.
Allison Macfarlane, NRC Chairman June 23, 2014 Page 2 SACE is very concerned that TVA does not appear to be following this recommendation with respect to its post-Fukushima seismic and flooding studies. According to a recent NRC chart depicting the WBN OL review schedule, the NRC plans to make a decision on the Watts Bar 2 full-power license in January 2015.
3 But TVA recently told th e Securities and Exchange Commission ("SEC") that it does not plan to finish its post-Fukushima seismic and flooding studies until mid-2015. TVA's 10-K report for FY 2013 states:
Since the Fukushima events, the NRC has also issued and adopted additional detailed guidance on the expected response capability to be developed by each nuclear plant site. TVA has developed plans and schedules for the development and implementation of strategies and physical plant modifications to address the actions outlined in this guidance for all of its plants, including Watts Bar Unit 2.
The initial studies, including the required plant walkdowns, are expected to be complete in the first quarter of 2014. Flooding and seismic re-evaluations to determine any further plant modifications are scheduled for completion in mid 2015.4 TVA's 10-K report also states that: "In addition to the actions described above, TVA may be required to take further actions to comply with any additional regulatory action that the NRC takes in response to the Fukushima events."
5 It is already clear, however, that TVA needs to take further actions to ensure the safety of WBN from earthquakes and floods.
The NRC has placed WBN2 in "Category 1" for earthquakes, i.e., reactors for which the predicted ground motion exceeds the design basis.
6 With respect to flood risks, TVA has found it necessary to embark on a plan for mitigating flood risks with an improved flood mitigation system.
7 Based on other statements made by TVA on page 16 of its 10-K report, it appears that TVA does not believe it is necessary to resolve the seismic design and flood protection deficiencies in the OL proceeding for WBN2. But Recommendation 2.1 is not included in the set of Fukushima Task Force recommendations that may be put off for consideration at some time in the future if the NRC deemed a rulemaking to be necessary. Instead, the Task Force included Recommendation 2.1 in the set of recommended "near-term actions."
8 3 Watts Bar Nuclear Plan Licensing Schedule (April 3, 2014) (Attachment A).
4 TVA Form 10-K for year ending September 30, 2013 at 16 (emphasis added) (Attachment B (excerpt)).
5 Id. 6 Letter from Eric J. Leeds, NRC, to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status on the Enclosed List re: Screening and Prioritization Results Regarding Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Seismic Hazard Re-evaluations of the Near-Term Task Force Review of Insights from the Fukushima Dai-chi Accident (May 9, 2014) (Attachment C).
7 Letter from J.W. Shea, TVA, to NRC, re: Fourth Progress Update on Improved Flood Mitigation System Project (Mar. 31, 2014) (Attachment D).
8 See id.at 74.
Allison Macfarlane, NRC Chairman June 23, 2014 Page 3 Equally importantly, for NRC to license WBN2 despite known deficiencies in the designs for earthquake and flood protection would violate the Atomic Energy Act's prohibition against licensing reactors if it would be "ini mical" to public health and safety.
9 And for the NRC to postpone resolution of these serious safety issues until after issuance of an OL would violate the public's right to a hearing on whether the application satisfies NRC safety requirements.
10 In your meeting with TVA, we urge you to confirm that the NRC will not issue an OL for WBN2 until it has received and reviewed the results of TVA's seismic investigation and flood mitigation design. In addition, please provide SACE with your assurance that (a) TVA will be required to amend its operating license application with the results of the seismic investigation and flood mitigation design and (b) SACE and other interested members of the public will be given the opportunity to request a hearing on those aspects of TVA's OL application, in compliance with the Atomic Energy Act.
Sincerely,
[Electronically signed by]
Diane Curran Counsel to SACE Cc: Watts Bar operating license proceeding service list 9 42 U.S.C. § 2133(d).
10 42 U.S.C. § 2239(a);
Union of Concerned Scientists v. NRC, 735 F.2d 1437 (D.C. Cir. 1984).
ACRS Full CommitteeMeetingSep-14Aug-14Advisory CommitteeOn Reactor Safeguards(ACRS)SubcommitteeDec-14Atomic Safety Licensing Board Decision Feb-15Pre-Operational, Start-up Oversight Activities Inspection Manual Chapters 2513, 2514, 2517Jan-15Decision Full Power License(NRR)Jan-15Fuel LoadDec-14TVA Letter to CertifyReadiness forFuel LoadDec-14IP94300 30 Day Status ReportCommission Notation Vote PaperNov-14TVA SubstantiallyComplete LetterOct-14Oct-14IP9430090 Day Status Report Oct-14Operational Readiness Assessment(R-II)Sep-14Complete Hot Functional TestingJun-14Supplement 27 SafetyEvaluation ReportSep-14CommissionBriefingon StatusWatts Bar Nuclear Plant Licensing ScheduleU.S. Nuclear Regulatory CommissionOffice of Nuclear Reactor RegulationApr 14 May 14Jun 14 Jul 14 Aug 14 Sep 14 Oct 14Nov 14Dec 14Jan 15 Feb 15 Mar 15 Apr 15May 15 Jun 15As of April 3, 2014TVA to begin Watts Bar Nuclear Plant Unit 2 Commercial Operation approximately 6-8 months after Issuance of Operating License and Initial Fuel LoadingDates are subject to change NRC Milestones TVA MilestonesNov-14IP94300Updated Status Report NRC/TVA Site Management MeetingOct-14Reviews, Hearings, and Briefings Supporting Oper ating License Issuance Operating LicenseOversight Prior to Commercial Operation Table of Contents
UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C. 20549 FORM 10-K (MARK ONE)
ANNUAL REPORT PURSUANT TO SECTION 13, 15(d), OR 37 OF THE SECURITIES EXCHANGE ACT OF 1934 For the fiscal year ended September30, 2013 OR TRANSITION REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934 For the transition period from _____ to _____
Commission file number 000
-52313 TENNESSEE VALLEY AUTHORITY (Exact name of registrant as specified in its charter)
(865) 632-2101 (Registrant
's telephone number, including area code)
Securities registered pursuant to Section 12(b) of the Act:None Securities registered pursuant to Section 12(g) of the Act:None Indicate by check mark if the registrant is a well
-known seasoned issuer, as defined in Rule 405 of the Securities Act.
Yes No Indicate by check mark if the registrant is not required to file reports pursuant to Section 13, Section 15(d), or Section 37 of the Act.Yes No Indicate by check mark whether the registrant (1) has filed all reports required to be filed by Section 13, 15(d), or 37 of the Securities Exchange Act of 1934 during the preceding 12 months (or for such shorter period that the registrant was required to file such reports), and (2) has been subject to such filing requirements for the past 90 days.
Yes No Indicate by check mark whether the registrant has submitted electronically and posted on its corporate Web site, if any, every Interactive Data File required to be submitted and posted pursuant to Rule 405 of Regulation S
-T (§232.405 of this chapter) during the preceding 12 months (or for such shorter period that the registrant was required to submit and post such files).
Yes No Indicate by check mark if disclosure of delinquent filers pursuant to Item 405 of Regulation S
-K (§229.405 of this chapter) is not contained herein and will not be contained, to the best of registrant
's knowledge, in definitive proxy or information statements incorporated by reference in Part III of this Form 10
-K or any amendment to this Form 10
-K. Indicate by check mark whether the registrant is a large accelerated filer, an accelerated filer, a non
-accelerated filer, or a smaller reporting company.See the definitions of "large accelerated filer," "accelerated filer," and "smaller reporting company
" in Rule 12b
-2 of the Exchange Act.
Tennessee+Valley+Authority 10
-K 9/30/2013 Section 1: 10
-K (10-K) A corporate agency of the United States created by an act of Congress (State or other jurisdiction of incorporation or organization) 62-0474417 (IRS Employer Identification No.)
400 W. Summit Hill Drive Knoxville, Tennessee (Address of principal executive offices) 37902 (Zip Code)
Table of Contents
As of September 30, 2010, TVA had 14,573 MW (Summer Net Capability) of coal
-fired generation. After these planned actions TVA will have 9,098 MW (Summer Net Capability) of coal
-fired generation.
TVA is planning to balance its coal
-fired generation with lower
-cost and cleaner energy generation technologies.
TVA's long-range plans will continue to attempt to balance the costs and benefits of significant environmental investments at its remaining coal
-fired plants that do not have scrubbers and/or SCRs. TVA expects to decide whether to control, convert, or retire its remaining coal
-fired capacity on a unit
-by-unit schedule. Transmission upgrades may be required to maintain reliability when some coal
-fired units become inactive. TVA invested $130 million in such upgrades between 2011 and 2013, and estimates future expenditures for transmission upgrades to accommodate inactive coal
-fired units to be approximately $350 million for 2014 to 2020. Upgrades may include enhancements to existing lines and substations or new installations as necessary to provide adequate power transmission capacity, maintain voltage support, and ensure generating plant and transmission system stability.
Nuclear TVA has three nuclear sites consisting of six units in operation.The units at Browns Ferry Nuclear Plant ("Browns Ferry")
are boiling water reactor units, and the units at Sequoyah Nuclear Plant ("Sequoyah")
and Watts Bar Nuclear Plant ("Watts Bar")
are pressurized water reactor units.Statistics for each of these units are included in the table below.
- An extension request has been submitted to the Nuclear Regulatory Commission. See Sequoyah License Renewal and Nuclear Reactor Licensing below. Nuclear Regulatory Commission Safety Improvements Orders and Other Guidance. In March 2012, the Nuclear Regulatory Commission ("NRC")
issued three new safety orders stemming from lessons learned from the events that occurred in 2011 at the Fukushima Daiichi Nuclear Power Plant ("Fukushima events"). The orders require (1) the development of strategies for responding to an interruption of off
-site power, (2) the addition of more reliable instruments to measure water levels in cooling pools where spent nuclear fuel is stored, and (3) the installation of more robust containment venting systems to prevent containment failure due to overpressurization. The first two orders apply to every nuclear reactor in the U.S., including Watts Bar Unit 2, which will be required to comply prior to issuance of its operating license. The third order applies only to certain U.S. boiling water reactors, including Browns Ferry. These reactors are required to improve their containment venting systems to prevent over
-pressurization due to the buildup of non
-condensable gases such as hydrogen. TVA plans to fully implement the requirements of these three orders which were submitted to the NRC on February 28, 2013. TVA expects to complete the implementation of these orders by 2019, and the cost to comply with these orders is not expected to exceed $220 million.
In addition to these orders, the NRC issued requests for information from U.S. nuclear operators regarding earthquake and flood risks and emergency planning. Based on the information provided in response to these requests, the NRC will determine if additional regulatory requirements are needed for these subjects. At this time, TVA is not able to predict the final outcome of these potential requirements or the associated costs; however, these amounts could be significant.
Since the Fukushima events, the NRC has also issued and adopted additional detailed guidance on the expected response capability to be developed by each nuclear plant site. TVA has developed plans and schedules for the development and implementation of strategies and physical plant modifications to address the actions outlined in this guidance for all of its plants, including Watts Bar Unit 2. The initial studies, including the required plant walkdowns, are expected to be complete in the first quarter of 2014. Flooding and seismic re
-evaluations to determine any further plant modifications are scheduled for completion in mid 2015. In addition to the actions described above, TVA may be required to take further actions to comply with any additional regulatory action that the NRC takes in response to the Fukushima events.
Sequoyah License Renewal.
TVA submitted the license renewal applications for both Sequoyah units to the NRC on January 7, 2013. If approved, the licenses for both units would be extended by an additional 20 years to 2040 for Unit 1 and 16 TVA Nuclear Power At September 30, 2013 Nuclear Unit Status Nameplate Capacity (MW)
Net Capacity Factor for 2013 Date of Expiration of Operating License Date of Expiration of Construction Permits Sequoyah Unit 1 Operating 1,221 97.0 2020* - Sequoyah Unit 2 Operating 1,221 73.7 2021* - Browns Ferry Unit 1 Operating 1,264 82.9 2033 - Browns Ferry Unit 2 Operating 1,190 80.6 2034 - Browns Ferry Unit 3 Operating 1,190 93.1 2036 - Watts Bar Unit 1 Operating 1,270 88.7 2035 - Watts Bar Unit 2 Under construction 1,220 - - 2013*
Table of Contents
2041 for Unit 2. The NRC's review of the applications is expected to take up to three years after their submission. It is possible that the timing of approval of the final license renewal applications could be impacted by the NRC suspension of final decisions on nuclear reactor licensing discussed below.
Nuclear Reactor Licensing
. On August 7, 2012, the NRC suspended final decisions on nuclear reactor licensing in response to a ruling by the the U.S. Court of Appeals for the District of Columbia Circuit ("D.C. Circuit")
that vacated the NRC's Waste Confidence Decision ("WCD")
relating to the environmental impact of the long
-term storage of nuclear waste. On September 6, 2012, in response to the ruling, the NRC directed the NRC staff to develop a generic Environmental Impact Statement ("EIS")
to support an updated WCD rule, maintaining the option for the staff to conduct some analyses of waste confidence issues on a site
-specific basis, if necessary. Licensing reviews and proceedings may currently continue, but final licenses will not be issued until the NRC completes its reassessment of the environmental impacts of the storage of nuclear waste. The delay of licensing decisions by the NRC could affect the unit currently under construction at Watts Bar Unit 2, the proposed construction of Bellefonte Unit 1, and the renewal of the licenses for the two units at Sequoyah. All of the procedures and inspections that happen prior to licensing will continue as usual.
Operational Challenges
. See Item 7, Management's Discussion and Analysis of Financial Condition and Results of Operations
- Liquidity and Capital Resources
- Liquidity Challenges Related to Generation Resources, which discussion is incorporated herein by reference.
Other Nuclear Matters.
See Fuel Supply
- Nuclear Fuel below for a discussion of spent nuclear fuel and low
-level radioactive waste, Item 7, Management's Discussion and Analysis of Financial Condition and Results of Operations
- Liquidity and Capital Resources
- Liquidity Challenges Related to Generation Resources for a discussion of challenges associated with the nuclear program, Note 20 - Contingencies for a discussion of TVA's nuclear decommissioning liabilities and the related trust and nuclear insurance, and Note 20 - Legal Proceedings for a discussion of legal and administrative proceedings related to TVA's nuclear program, which discussions are incorporated herein by reference.
Hydroelectric and Other Renewable Energy Resources Conventional Hydroelectric Dams. TVA maintains 29 conventional hydroelectric dams with 109 generating units throughout the Tennessee River system and one pumped
-storage facility for the production of electricity.At September30, 2013 , these units accounted for 5,433 MW of summer net capability.The amount of electricity that TVA is able to generate from its hydroelectric plants depends on a number of factors, including the amount of precipitation and runoff, initial water levels, and the need for water for competing water management objectives.The amount of electricity generated also depends on the availability of TVA's hydroelectric generation plants.When these factors are unfavorable, TVA must increase its reliance on higher cost generation plants and purchased power.In addition, four hydroelectric dams owned by a third party on the Little Tennessee River and eight U.S. Army Corps of Engineers dams on the Cumberland River contribute to the TVA power system.See Weather and Seasonality.
In 1992, TVA began a Hydro Modernization Program to address reliability issues on its conventional hydroelectric units and on Raccoon Mountain Pumped
-Storage Plant ("Raccoon Mountain"). At September30, 2013 , modernization had been completed on 55 conventional hydroelectric units and four pumped
-storage units. These modernization projects resulted in 422 MW of increased capacity on the conventional units, with an average efficiency gain of approximately five percent. Hydroelectric generation will continue to be an important part of TVA's energy mix. TVA, through its Hydro Modernization Program, continues to assess its remaining conventional hydroelectric units for opportunities to improve reliability and increase capacity.
Raccoon Mountain Pumped
-Storage Plant
. The four units at Raccoon Mountain were placed in service during 1978 and 1979. The units, with a total net summer capability of 1,616 MW, are utilized to balance the transmission system as well as generate power.
Inspections of the turbines in the four units of Raccoon Mountain during 2012 found cracking in the rotor poles and the rotor rims.
Because the same type of cracking led to the catastrophic failure of a similar unit in Europe, the Raccoon Mountain units were taken out of service. Raccoon Mountain Unit 2 returned to limited service with a partially restacked rotor in October 2012, but was taken out of service again on January 3, 2013, due to a failed rotor pole clamp. All units are undergoing a maintenance overhaul and are expected to be returned to service in 2014. TVA is dispatching generation from other TVA units and purchasing power if needed to compensate for the loss in generating capacity.
Other Renewable Energy Resources. TVA's renewable energy portfolio includes both TVA owned assets and renewable energy purchases. TVA has 16 solar sites, capability for digester gas and biomass cofiring, and three wind turbines. At September 30, 2013, the wind turbines did not provide any summer net capability because they were not operational, and they do not appear to be economical for returning to operation. The digester gas cofiring capability is accounted for as coal
-fired generation summer net capability. The solar sites provide less than one MW of summer net capability. See Power Supply
- Purchased Power and Other Agreements for information on renewable energy power purchase contracts.
17 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 9, 2014 All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status on the Enclosed List
SUBJECT:
SCREENING AND PRIORITIZATION RESULTS REGARDING INFORMATION PURSUANT TO TITLE 10 OF THE CODE OF FEDERAL REGULATIONS 50.54(f) REGARDING SEISMIC HAZARD RE-EVALUATIONS FOR RECOMMENDATION 2.1 OF THE NEAR-TERM TASK FORCE REVIEW OF INSIGHTS FROM THE FUKUSHIMA DAI-ICHI ACCIDENT On March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued a request for information pursuant to Title 10 of the Code of Federal Regulations, Part 50 (1 0 CFR), Section 50.54(f) (hereafter referred to as the 50.54 (f) letter) (Agencywide Document Access and Management System (ADAMS) Accession No. ML 12053A340).
The purpose of that request was to gather information concerning, in part, the seismic hazards at operating reactor sites and to enable the NRC staff to determine whether licenses should be modified, suspended, or revoked. The "Required Response" section of Enclosure 1 indicated that licensees and construction permit holders should provide a Seismic Hazard Evaluation and Screening report within 1.5 years from the date of the letter for central and eastern United States (CEUS) nuclear power plants, and within 3 years for western United States (WUS) plants. For CEUS plants, the date to submit the report was extended to March 31, 2014, by NRC letter dated May 7, 2013.1 Further, the 50.54(f) letter stated that NRC would provide the results of the screening and prioritization indicating deadlines for individual plants to complete seismic risk evaluations to assess the total plant response to the re-evaluated seismic hazard. Additionally, by dated February 20, 2014, the NRC provided supplemental information on the content of the seismic re-evaluated hazard submittals including guidance on reportability and operability.
The purpose of this letter is to inform licensees of the NRC's screening and prioritization and to allow licensees to appropriately plan the completion of further seismic risk evaluations described in Enclosure 1 of the 50.54(f) letter. To respond to the 50.54(f) letter, all addressees committed to follow the Electric Power Research Institute (EPRI) Report, "Seismic Evaluation Guidance:
Screening, Prioritization and Implementation Details (SPID) for the Resolution of Fukushima Near-Term Task Force Recommendation 2.1: Seismic, " 3 as supplemented by the EPRI Report, "Seismic Evaluation Guidance:
Augmented Approach for the Resolution of Fukushima Near-Term Task Force (NTTF) Recommendation 2.1: Seismic" 4 (referred to as the Expedited Approach).
The NRC held multiple public meetings and teleconferences with industry and the public leading to the development of the guidance documents supporting review of re-evaluated seismic hazards. 1 The May 7, 2013, endorsement letter is available in ADAMS under Accession No. ML 131 06A331. 2 The February 20, 2014, supplemental information letter is available in ADAMS under Accession No. ML 14030A046 3 The SPID guidance document is found in ADAMS under Accession No. ML 12333A170.
The staff endorsement letter for the SPID guidance is found in ADAMS under Accession No. ML 12319A074.
4 The Expedited Approach guidance document is found in ADAMS under Accession No. ML 13102A142. Licensees submitted the re-evaluated seismic hazards or letter of intent to provide the hazard for their sites by letters dated March 2014 (references are provided in Enclosure 3 of this letter). The NRC staff conducted the screening and prioritization review of the submittals by assessing each licensee's screening evaluation and hazard analysis utilizing the endorsed SPID guidance.
INTERIM EVALUATIONS 5 The 50.54(f) letter requested that licensees provide "interim evaluations and actions taken or planned to address the higher seismic hazard relative to the design basis, as appropriate, prior to completion of the risk evaluation." For those plants where the re-evaluated seismic hazard exceeds the seismic design basis, licensees stated they will provide interim evaluations to demonstrate that the plant can cope with the higher re-evaluated seismic hazard while the longer term seismic risk evaluations are ongoing. In support of licensee interim evaluations, the Nuclear Energy Institute (NEI) by letter' dated March 12, 2014, provided an EPRI study that estimated fleetwide seismic risk and provided a discussion of the inherent seismic design margins for structures, systems, and components (SSCs). The March 12, 2014, EPRI fleetwide study calculated seismic risk following the approach the NRC staff used in 2010 for the Safety/Risk Assessment conducted as part of Generic Issue (GI)-199, "Implications of Updated Probabilistic Seismic Hazard Estimates in Central and Eastern United States on Existing Plants" 7. The EPRI study concluded that "site-specific seismic hazards show that there [ ... ] has not been an overall increase in seismic risk for the fleet of U.S. plants" based on the re-evaluated seismic hazards. As such, the "current seismic design of operating reactors continues to provide a safety margin to withstand potential earthquakes exceeding the seismic design basis." Lastly, the March 12, 2014, NEIIetter provided "Perspectives on the Seismic Capacity of Operating Plants," which (1) assessed a number of qualitative reasons why the design of SSCs inherently contain margin beyond their design level, (2) discussed industrial seismic experience databases of performance of industry facility components similar to nuclear SSCs, and (3) discussed earthquake experience at operating plants. In their March 2014 submittals, licensees confirmed that the conclusions of the EPRI fleetwide study apply to their plants. The submittals also discussed completing plant seismic walkdowns as part of NTTF Recommendation 2.3 in order to verify that the current plant configuration is consistent with the licensing basis. In addition, licensees described any insights gained from previous seismic evaluations.
To assess each licensee's interim evaluations, the NRC staff reviewed the fleetwide study as well as each licensee's plant-specific discussion.
The results of the staff's independent review confirm that fleetwide seismic risk estimates are consistent with the approach and results used in the Gl-199 safety/risk assessment.
As a result, the staff has confirmed that the conclusions reached in Gl-199 safety/risk assessment remain valid and that the plants can continue to operate while additional evaluations are conducted.
5 Enclosure 1 of this letter provides a Glossary of Seismic Evaluations 6 Industry-issued letter on seismic risk evaluations for plants in the Central and Eastern United States is available in ADAMS under Accession No. ML 14083A596.
7 Results of Safety/Risk Assessment of Gl-199 is available in ADAMS under Accession No. ML 100270582. The interim evaluation is a first step in the near-term assessment of the plant's capacity to withstand the re-evaluated hazard. Also in the near-term, by December 2014, plants with a higher re-evaluated hazard will complete an "Expedited Approach" to evaluate and identify reinforcements, if necessary, for certain equipment to ensure a safe shutdown pathway can withstand the higher seismic ground motion. SCREENING PROCESS As defined in the 50.54(f) letter and the SPID guidance, the seismic hazard re-evaluations were conducted using current analysis methods and guidance.
The licensees' responses to the 50.54(f) letter provided seismic hazard re-evaluation results, which were the focus of the NRC staff's initial screening and prioritization review. Although the safe shutdown earthquake (SSE) is commonly referred to as a single number, this number represents a distribution of ground motions that occur over a range of spectral frequencies.
This results in a curve of ground acceleration over frequency.
The ability of equipment and structures in the plant to withstand the effects of ground motions is frequency specific.
For the purposes of the licensees' analyses and NRC staff's review, the SPID guidance identifies three frequency ranges that are of particular interest:
1-10 Hz, a low frequency range of <2.5 Hz, and a high frequency range of >1 0 Hz. The different ranges have been identified due to the different types of structures and equipment that may be impacted by ground motions in that range. For example, large components generally are not affected significantly by high frequencies (i.e., >10Hz). The frequency range 1-10Hz is the focus for this portion of the risk evaluation, as this range has the greatest potential effect on the performance of equipment and structures important to safety. For other frequency ranges, discussed below, limited-scope evaluations will be conducted, when appropriate.
In accordance with the SPID and Expedited Approach guidance, the re-evaluated seismic hazard determines if additional seismic risk evaluations are warranted for a plant. Specifically, the re-evaluated ground motion response spectra (GMRS) in the 1-10Hz frequency range is compared to the existing SSE:
- If the re-evaluated GMRS, in the 1-10 Hz range, is less than the plant's existing SSE, then the plant screens out of conducting further seismic risk evaluations.
- If the GMRS, in the 1-10 Hz range, is greater than the existing SSE, then the plant will complete the Expedited Approach (including the Interim Evaluation).
Most plants that meet this criterion also screen in to conduct a seismic risk evaluation and have committed to conduct high frequency and spent fuel pool evaluations.
- The SPID guidance provides criteria for a plant with a GMRS above the SSE, but bounded by the Individual Plant Examination for External Events (I PEE E) capacity spectrum.
To use the IPEEE capacity spectrum to screen out of conducting a seismic risk evaluation, the licensee needed to demonstrate the adequacy of the plant's IPEEE evaluation by meeting the criteria in the SPID. If the IPEEE capacity is greater than the GMRS in the 1-10Hz range, the plant screens out of conducting a seismic risk evaluation.
However, these plants have committed to evaluate the spent fuel pool at the re-evaluated hazard level, as spent fuel pools were not analyzed in the IPEEE program. In addition, if the GMRS meets the low hazard threshold, which is described in the SPID, and only exceeds the SSE below 2.5 Hz, the licensee will perform a limited evaluation of equipment potentially susceptible to low frequency motions. Similarly, if the GMRS exceeds the SSE only above 10 Hz, then the licensee will perform an evaluation of the equipment or structures susceptible to that specific range of ground motion. Enclosure 2 provides the staff's determination of priority for plants that screen in to conduct a seismic risk evaluation, and identification of plants to complete limited-scope evaluations (i.e., spent fuel pool, high frequency, or low frequency).
Additionally, the enclosure identifies plants that screen out of any further evaluations.
CONDITIONAL SCREENING As discussed in public meetings 8 and a February 20, 2014 letter, the staff anticipated the possibility of not being able to complete the determination for conducting a seismic risk evaluation for some plants in the 30-day review period under certain circumstances.
For example, if a licensee provided a unique submittal or deviated from the SPID guidance, additional time for the review might be needed. For other submittals, the staff's independent GMRS assessment could differ from the GMRS provided in the March 2014 submittals, and these differences need to be better understood before determining if a plant would screen out from further evaluation.
Accordingly, during the NRC screening and prioritization process, the staff did identify some plants for which a determination could not be made and interactions with the licensees are needed to reach resolution.
The staff determined these plants are "conditionally screened-in" for the purposes of prioritizing and conducting additional evaluations.
Plants identified as "conditional screen-in" should submit the Expedited Approach by December 31, 2014 and, until a final determination is made, conduct a seismic risk evaluation as prioritized in Enclosure
- 2. Those plants identified as "conditional screen-in," which based on their screening assessment, did not submit an interim evaluation in the March 2014 submittal, should complete the interim evaluations, identify any associated actions, and submit the results to the NRC by no later than June 6, 2014. For plants identified as "conditional screen-in", after interactions with licensees have occurred, the staff will make a final screening and prioritization determination and provide a letter to each impacted licensee.
If the plant remains screened in, the final screening letter also will affirm or update the plant priority for further evaluations.
If the plant screens out, the final screening letter also will determine if the plant needs to complete limited-scope evaluations (i.e., spent fuel pool, high frequency, or low frequency).
8 Discussion as part of public meetings dated January 23, February 5, February 10, and March 25, 2014 (ADAMS Accession Nos. ML14028A062, ML14050A055, ML 14050A084, and ML 14091A102, respectively) PLANT PRIORITIZATION The NRC grouped the "screened in" (including those conditionally screened in) plants into three groups, which (i) reflects the relative priority for conducting a seismic risk evaluation that compares each plant's current capabilities to the re-evaluated seismic hazard, and (ii) accounts for the appropriate allocation of limited staff and available expertise for reviewing and conducting seismic risk evaluations.
During the prioritization review, the staff considered each licensee's re-evaluated hazard submittals, seismic risk insights from Gl 199 "Implications of Updated Probabilistic Seismic Hazard Estimates in Central and Eastern United States on Existing Plants," and the staff's confirmatory analysis of the seismic hazard. Enclosure 2 provides the plant prioritizations for completing the seismic risk evaluations.
To prioritize the plants, staff examined certain key parameters such as (1) the maximum ratio of the new re-evaluated hazard (GMRS) to the SSE in the 1-10Hz range; (2) the maximum ground motion in the 1-10Hz range; and (3) insights from previous seismic risk evaluations.
As such, Group 1 plants are generally those that have the highest re-evaluated hazard relative to the original plant seismic design basis (GMRS to SSE) as well as ground motions in the 1-10Hz range that are generally higher in absolute magnitude.
Group 1 plants are expected to conduct a seismic risk evaluation and submit it by June 30, 2017. Group 2 plants are also expected to conduct a seismic risk evaluation, which should be submitted by December 31, 2019. Enclosure 2 also provides a list of Group 3 plants. Group 3 plants have GMRS to SSE ratios that are greater than 1, but the amount of exceedance in the 1-10 Hz range is relatively small, and the maximum ground motion in the 1-10Hz range is also not high. Given the limited level of exceedance of the Group 3 plants, staff is evaluating the need for licensees to conduct a seismic risk evaluation in order for the staff to complete its regulatory decision making. However, the staff has had insufficient review time with the recently submitted seismic hazard submittals to reach a conclusion.
After further review of the seismic hazard re-evaluations and the Expedited Approach submittals, the staff will decide which Group 3 plants need to complete a risk evaluation.
Risk evaluations for Group 3 plants are due by December 31, 2020. NEXT STEPS For plants that screen in to conduct a risk evaluation, the licensees should finalize and submit each plant's Expedited Approach no later than December 31, 2014. In accordance with the endorsed guidance, the staff acknowledges that the December 2014 Expedited Approach submittal will focus on plant equipment (i.e. safe shutdown pathwal) evaluations and modifications, as necessary, prior to submitting the plant seismic risk evaluations.
Additionally, the schedule milestones and content of limited-scope evaluations will require additional development and coordination with stakeholders.
For example, for the high frequency evaluation, an industry study of the effects for sensitive equipment is currently in progress.
Furthermore, recent assessments by the NRC staff and related decisions by the Commission may justify revisions to the existing guidance regarding the limited-scope evaluations of spent fuel pools at some sites. As needed, the NRC staff will initiate discussions 9 Section 3 of the Expedited Approach guidance (ADAMS No. ML 13102A142) provides a process to identify a single seismically robust success path using a subset of installed plant equipment, FLEX equipment and connection points. with stakeholders in the near future as part of the development of any revised guidance documents.
Given the generic nature of the limited-scope evaluations, it is expected that these evaluations will be completed for plants within the next two years. This letter transmits the NRC staff's results of the seismic hazard submittals for the purposes of screening and prioritizing the plants. It does not convey the staff's final determination regarding the adequacy of any plant's calculated hazard. As such, the NRC staff will continue its review of the submitted seismic hazard re-evaluations, and may request additional plant-specific information to support this review. The staff has placed a high priority on this review for the early identification of issues that might adversely affect each licensee's seismic risk evaluations.
Initial interactions with licensees will occur as soon as practicable.
The NRC staff plans to issue a staff assessment on the re-evaluated seismic hazard once each review is completed in approximately 12 to 18 months. If you have any questions on this matter, please contact your NRC licensing Project Manager. Sincerely, Eric J. Leeds, Director Office of Nuclear Reactor Regulation
Enclosures:
- 1. Glossary of Evaluations
- 2. Screening and Prioritization Results 3. List of Licensee March 2014 Re-evaluated Seismic Hazard Submittals
- 4. List of Addressees Glossary of Evaluations Associated with Near-Term Task Force Recommendation 2.1 Seismic Hazard Re-evaluations Interim Evaluation or Actions-An immediate licensee and NRC review of the re-evaluated hazard to determine whether actions are needed to assure plant safety while further evaluations are ongoing. The staff has completed its review and concluded that, based on the licensees' interim evaluations and actions, all central and eastern United States (CEUS) plants are safe for continued operations.
Interim evaluations and actions are provided in Section 5.0, "Interim Actions," of the licensee submittals.
Expedited Approach-A near-term licensee evaluation to be completed by December 31, 2014, for CEUS plants whose re-evaluated hazard exceeds the current design basis for the safe shutdown earthquake hazard level. The evaluation looks at the systems and components that can be used to safely shut down a plant under the conditions of a station blackout (i.e., no alternating current power is available) and loss of ultimate heat sink. The expedited approach will either confirm that a plant has sufficient margin to continue with a longer-term evaluation without any modifications, or confirm the need to enhance the seismic capacity to assure they can withstand the re-evaluated hazard. The Expedited Approach guidance document is found in the Agencywide Documents Access and Management System under No. ML 13102A142.
Seismic Risk Evaluation
-Longer-term seismic risk evaluation provides the most comprehensive information to make regulatory decisions, such as whether to amend a plant's design or licensing basis or make additional safety enhancements.
These evaluations provide information to make risk-informed decisions.
The staff will use this information in conjunction with the existing regulatory tools, such as backfit analysis, to decide on further regulatory actions. The longer-term seismic risk evaluations could be either a Seismic Margins Analysis or a Seismic Probabilistic Risk Assessment, depending on the magnitude of the exceedance.
Limited-Scope Evaluations
-These include i) Spent Fuel Pool Evaluation, ii) High Frequency Evaluation, and iii) Low Frequency Evaluation.
Respectively, these evaluations are focused on the following:
i) spent fuel pool components and systems capable of draining water inventory to the level of the spent fuel, ii) a review of components susceptible to high frequency accelerations (e.g. electrical relays), and iii) a review of components susceptible to low frequency accelerations (e.g. water storage tanks). Enclosure 1
Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident Seismic Risk Evaluations Screening and Prioritization Results for Central and Eastern Reactor Sites Seismic Risk Limited-scope Evaluations Screening Expedited Evaluation High Low Spent Fuel Plant Name Result Approach (Prioritization Frequency Frequency Pool Evaluation Group) Evaluation Evaluation Evaluation Callaway Plant, Unit 1 In X 1 X X Donald C. Cook Nuclear Plant, In X 1 X X Units 1 and 2 Indian Point Nuclear Generating In X 1 X X Unit Nos. 2 and 3 North Anna Power Station, Units 1 In X 1 X X and 2 Oconee Nuclear Station, Units 1, In X 1 X X 2, and 3 Peach Bottom Atomic Power In X 1 X X Station Units 2 and 3 Pilgrim Nuclear Power Station, In X 1 X X Unit No. 1 H. B Robinson Steam Electric In X 1 X X Plant, Unit No. 2 Vogtle Electric Generating Plant, In X 1 X X Units 1 and 2 Watts Bar Nuclear Plant, Units 1 In X 1 X X and 2 Beaver Valley Power Station, In X 2 X X Units 1 and 2 Enclosure 2 I Expedited Seismic Risk Limited-scope Evaluations Plant Name Screening Approach Evaluation High Low Spent Fuel Result Evaluation (Prioritization Frequency Frequency Pool Group) Evaluation Evaluation Evaluation Browns Ferry Nuclear Plant, Units In X 2 X X 1, 2, and 3 Dresden Nuclear Power Station, In X 2 X X Units 2 and 3 Fermi, Unit 2 In X 2 X X Edwin I. Hatch Nuclear Plant, In X 2 X X Units 1 and 2 LaSalle County Station, Units 1 In X 2 X X and 2 Oyster Creek Nuclear Generating Conditional In X 2 X X Station Palisades Nuclear Plant In X 2 X X Virgil C. Summer Nuclear Station, In X 2 X X Unit 1 Catawba Nuclear Station, Units 1 In X 2 X X and 2 Sequoyah Nuclear Plant, Units 1 In X 2 X X and 2 Arkansas Nuclear One, Units 1 Conditional In X 3 X X and 2 Bellefonte Nuclear Plant, Units 1 In X 3 X X and 2 Brunswick Steam Electric Plant, Conditional In X 3 X X Units 1 and 2 Calvert Cliffs Nuclear Power Plant, In X 3 X X Units 1 and 2 Clinton Power Station, Unit 1 Conditional In X 3 X X Cooper Nuclear Station Conditional In X 3 X X --------**-- Seismic Risk Limited-scope Evaluations Screening Expedited Evaluation High Low Spent Fuel Plant Name Result Approach (Prioritization Frequency Frequency Pool Evaluation Group) Evaluation Evaluation Evaluation Davis-Besse Nuclear Power In 3 X X Station, Unit 1 X I Duane Arnold Energy Center Conditional In X 3 X X James A. FitzPatrick Nuclear Conditional In 3 X X I Power Plant X Fort Calhoun Station, Unit 1 Conditional In X 3 X X Limerick Generating Station, Units Conditional In X 3 X X 1 and 2 William B. McGuire Nuclear In 3 X X Station, Units 1 and 2 X Millstone Power Station, Unit 2 Conditional In X 3 X X Monticello Nuclear Generating Conditional In X 3 X X Plant Perry Nuclear Power Plant, Unit 1 In X 3 X X Point Beach Nuclear Plant, Units 1 In X 3 X X and 2 Quad Cities Nuclear Power Conditional In 3 X X Station, Units 1 and 2 X Salem Nuclear Generating Station, Conditional In X 3 X X Units 1 and 2 Seabrook, Unit 1 In X 3 X X Surry Power Station, Unit Nos. 1 Conditional In X 3 X X and 2 Three Mile Island Nuclear Station, In X 3 X X Unit 1 Wolf Creek Generating Station, In X 3 X X Unit 1 Expedited Risk Limited-scope Evaluations Screening Evaluation High Low Spent Fuel Plant Name Result Approach (Prioritization Frequency Frequency Pool Evaluation Group) Evaluation Evaluation Evaluation Vermont Yankee Nuclear Power Conditional In Station X 3 X X Braidwood Station, Units 1 and 2 Out X Byron Station, Units 1 and 2 Out X, X X Comanche Peak Nuclear Power Out Plant, Units 1 and 2 Joseph M. Farley Nuclear Plant, Out X X Units 1 and 2 R.E. Ginna Nuclear Power Plant Out X Grand Gulf Nuclear Station, Unit 1 Out Shearon Harris Nuclear Power Out Plant, Unit 1 X Hope Creek Generating Station Out X Millstone Power Station, Unit 3 Out x1 X X Nine Mile Point Nuclear Station, Out X Units 1 and 2 Prairie Island Nuclear Generating Out X Plant, Units 1 and 2 River Bend Station Out X St. Lucie Plant, Units 1 and 2 Out South Texas Project, Units 1 and 2 Out Susquehanna Steam Electric Out x1 X Station, Units 1 and 2 Turkey Point, Units 3 and 4 Out Waterford Steam Electric Station, Out X Unit 3 ------------1 Re-evaluated hazard is greater than plant licensing basis safe shutdown earthquake.
Licensee has demonstrated IPEEE plant capacity consistent with endorsed guidance bounds the re-evaluated hazard. Expedited approach evaluation will provide a demonstration of safe shutdown capability at a greater hazard level.
March 2014 Re-evaluated Seismic Hazard Submittals for Central and Eastern United States Reactor Sites Licensee Facili_!}f_
Date of letter (ADAMS Accession Nos.) Arkansas Nuclear One, Units 1 and 2 March 28, 2014 (M L 14092A021 ) Beaver Valley Power Station, Units 1 and 2 March 31, 2014 (ML 14090A143)
Bellefonte Nuclear Plant, Units 1 and 2 March 31, 2014 (ML 14098A478)
Braidwood Station, Units 1 and 2 March 31, 2014 (ML 14091A243)
Browns Ferry Nuclear Plant, Units 1, 2, and 3 March 31, 2014 (ML 14098A478l Brunswick Steam Electric Plant, Units 1 and 2 March 31,2014 (ML14106A461)
Byron Station, Units 1 and 2 March 31, 2014 (ML 14091A010)
Callaway Plant, Unit 1 March 28, 2014 (ML 14090A446)
Calvert Cliffs Nuclear Power Plant, Units 1 and March 31, 2014 (ML 14099A196) 2 Catawba Nuclear Station, Units 1 and 2 March 31, 2014 (ML 14099A184)
Clinton Power Station, Unit 1 March 31, 2014 (ML 14091A011l Comanche Peak Nuclear Power Plant, Units 1 March 27, 2014 (ML 14099A197) and 2 CooQ_er Nuclear Station March 31, 2014 (ML 14094A048)_
Davis-Besse Nuclear Power Station, Unit 1 March 31, 2014 (ML 14090A143)
Donald C. Cook Nuclear Plant, Units 1 and 2 March 27, 2014 (ML 14092A327l Dresden Nuclear Power Station, Units 2 and 3 March 31, 2014 (ML 14091A012)
Duane Arnold Energy Center March 28, 2014 (ML 14092A331)
JoseQ_h M. Farley Nuclear Plant, Units 1 and 2 March 31, 2014 (ML 14092A020l Fermi, Unit 2 March 31, 2014 (ML 14090A326)
James A FitzPatrick Nuclear Power Plant March 31, 2014 (ML 14090A243)
Fort Calhoun Station, Unit 1 March 31, 2014 (ML 14097A087)
R.E. Ginna Nuclear Power Plant March 31, 2014_{_ML14099A196)
Grand Gulf Nuclear Station, Unit 1 March 31, 2014 (ML 14090A098)
Shearon Harris Nuclear Power Plant, Unit 1 March 27, 2014 (ML 14090A441)
Edwin I. Hatch Nuclear Plant, Units 1 and 2 March 31, 2014 (ML 14092A017)
Hope Creek Generatin_g_
Station March 28, 2014 (ML 14087A436)_
Indian Point Nuclear Generating Unit Nos. 2 March 31,2014 (ML14099A110 and and 3 ML 14099A111)
LaSalle County Station, Units 1 and 2 March 31, 2014 (ML 14091A013)
Limerick Generating Station, Units 1 and 2 March 31, 2014 (ML 14090A236)
William B. McGuire Nuclear Station, Units 1 March 20, 2014 (ML 14098A421) and 2 Millstone Power Station, Units 2 and 3 March 31, 2014 (ML 14092A417)
Monticello Nuclear Generating Plant March 31, 2014 (ML 14090A297) and April3, 2014 (ML 14093B361)
Nine Mile Point Nuclear Station, Units 1 and 2 March 31, 2014 (ML 14099A196)
Enclosure 3 Licensee Facility Date of letter(ADAMS Accession Nos.) North Anna Power Station, Units 1 and 2 March 31,2014 (ML 14092A416)
Oconee Nuclear Station, Units 1, 2, and 3 March 31, 2014 (ML 14092A024)
Oyster Creek Nuclear Generatino Station March 31, 2014 (ML 14090A241)
Palisades Nuclear Plant March 31, 2014 (ML 14090A069)
Peach Bottom Atomic Power Station Units 2 March 31, 2014 (ML 14090A247) and 3 Perry Nuclear Power Plant, Unit 1 March 31, 2014(ML 14090A143)
Pilgrim Nuclear Power Station, Unit No. 1 March 31, 2014 {ML 14092A023)
Point Beach Nuclear Plant, Units 1 and 2 March 31, 2014 (ML 14090A275)
Prairie Island Nuclear Generating Plant, Units March 27, 2014 (ML 14086A628) 1 and 2 Quad Cities Nuclear Power Station, Units 1 March 31, 2014 (ML 14090A526) and 2 River Bend Station March 26, 2014 (ML 14091A426)
H. B Robinson Steam Electric Plant, Unit No. March 31, 2014 (ML 14099A204) 2 St. Lucie Plant, Units 1 and 2 March 31, 2014 (ML 14099A 1 06) Salem Nuclear Generating Station, Units 1 March 31, 2014 (ML 14090A043) and 2 Seabrook, Unit 1 March 27, 2014 (ML 14092A413)
Sequoyah Nuclear Plant, Units 1 and 2 March 31, 2014-(ML 14098A478)
South Texas Project, Units 1 and 2 March 31, 2014 (ML 14099A235)
Surry Power Station, Unit Nos. 1 and 2 March 31, 2014 (ML 14092A414)
Susquehanna Steam Electric Station, Units 1 March 26, 2014 (ML 14086A163) and 2 Three Mile Island Nuclear Station, Unit 1 March 31, 2014 (ML 14090A271)
Turkey Point, Units 3 and 4 March 27, 2014(ML 14106A032)
Virgil C. Summer Nuclear Station, Unit 1 March 26, 2014 (ML 14092A250)
Vermont Yankee Nuclear Power Station March 12, 2014 (ML 14079A025)
Vogtle Electric Generating Plant, Units 1 and 2 March 31, 2014 (ML 14092A019)
Waterford Steam Electric Station, Unit 3 March 27, 2014(ML 14086A42i)
Watts Bar Nuclear Plant, Units 1 and 2 March 31, 2014 (ML 14098A478)
Wolf Creek Generating Station, Unit 1 March 31, 2014(ML 14097A026)
LIST OF APPLICABLE POWER REACTOR LICENSEES AND HOLDERS OF CONSTRUCTION PERMITS IN ACTIVE OR DEFERRED STATUS Arkansas Nuclear One Entergy Operations, Inc. Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6 Vice President, Operations Arkansas Nuclear One Entergy Operations, Inc. 1448 S.R. 333 Russellville, AR 72802 Beaver Valley Power Station First Energy Nuclear Operating Co. Docket Nos. 50-334 and 50-412 License Nos. DPR-66 and NPF-73 Mr. Eric A. Larson Site Vice President Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Bellefonte Nuclear Plant Tennessee Valley Authority Docket Nos. 50-438 and 50-439 Construction Permit Nos. CPPR No. 122 and CPPR No. 123 Mr. Michael D. Skaggs Senior Vice President, Nuclear Construction Tennessee Valley Authority Lookout Place 6A 1101 Market Street Chattanooga, TN 37402-2801 Braidwood Station Exelon Generation Co., LLC Docket Nos. STN 50-456 and STN 50-457 License Nos. NPF-72 and NPF-77 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Browns Ferry Nuclear Plant Tennessee Valley Authority Docket Nos. 50-259, 50-260 and 50-296 License Nos. DPR-33, DPR-52 and DPR-68 Mr. Joseph W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street, LP 3D-C Chattanooga, TN 37402-2801 Brunswick Steam Electric Plant Duke Energy Progress, Inc. Docket Nos. 50-325 and 50-324 License Nos. DPR-71 and DPR-62 George T. Hammrick, Vice President Brunswick Steam Electric Plant P.O. Box 10429 Southport, NC 28461 Byron Station Exelon Generation Co., LLC Docket Nos. STN 50-454 and STN 50-455 License Nos. NPF-37 and NPF-66 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Enclosure 4
Callaway Plant Union Electric Company Docket No. 50-483 License No. NPF-30 Mr. Fadi Diya Senior Vice President and Chief Nuclear Officer Ameren Missouri Callaway Plant P.O. Box 620 Fulton, MO 65251 Calvert Cliffs Nuclear Power Plant Calvert Cliffs Nuclear Power Plant, LLC Docket Nos. 50-317 and 50-318 License Nos. DPR-53 and DPR-69 Mr. George H. Gellrich, Vice President Calvert Cliffs Nuclear Power Plant, LLC. Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702 Catawba Nuclear Station Duke Energy Carolinas, LLC Docket Nos. 50-413 and 50-414 License Nos. NPF-35 and NPF-52 Mr. Kelvin Henderson Site Vice President Duke Energy Carolinas, LLC Catawba Nuclear Station 4800 Concord Road York, SC 297 45 Clinton Power Station Exelon Generation Co., LLC Docket No. 50-461 License No. NPF-62 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Comanche Peak Nuclear Power Plant Luminant Generation Co., LLC Docket Nos. 50-445 and 50-446 License Nos. NPF-87 and NPF-89 Mr. Rafael Flores Senior Vice President and Chief Nuclear Officer Attention:
Regulatory Affairs Luminant Generation Company, LLC P.O. Box 1002 Glen Rose, TX 76043 Cooper Nuclear Station Nebraska Public Power District Docket No. 50-298 License No. DPR-46 Mr. Oscar A Limpias Vice President Nuclear and Chief Nuclear Officer Nebraska Public Power District 72676 648A Avenue P.O. Box 98 Brownville, NE 68321 Davis-Besse Nuclear Power Station First Energy Nuclear Operating Co. Docket No. 50-346 License No. NPF-3 Mr. Raymond A Lieb Site Vice President FirstEnergy Nuclear Operating Company c/o Davis-Besse NPS 5501 N. State Route 2 Oak Harbor, OH 43449-9760 Donald C. Cook Nuclear Plant Indiana Michigan Power Company Docket Nos. 50-315 and 50-316 License Nos. DPR-58 and DPR-74 Mr. Lawrence J. Weber Senior Vice President and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, Ml 49106 Dresden Nuclear Power Station Exelon Generation Company Docket Nos. 50-237 and 50-249 License Nos. DPR-19 and DPR-25 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Duane Arnold Energy Center NextEra Energy Duane Arnold, LLC Docket No. 50-331 License No. DPR-49 Mr. Rich Anderson Site Vice President NextEra Energy Duane Arnold Energy Center 3277 DAEC Road Palo, lA 52324-9785 Edwin I. Hatch Nuclear Plant Southern Nuclear Operating Co. Docket Nos. 50-321 and 50-366 License Nos. DPR-57 and NPF-5 Mr. C.R. Pierce Regulatory Affairs Director Southern Nuclear Operating Company, Inc. P.O. Box 1295/BIN B038 Birmingham, AL 35201-1295 Fermi DTE Electric Company Docket No. 50-341 License No. NPF-43 Mr. Joseph H. Plena Senior Vice President and Chief Nuclear Officer DTE Electric Company Fermi 2-210 NOC 6400 North Dixie Highway Newport, Ml 48166 Fort Calhoun Station Omaha Public Power District Docket No. 50-285 License No. DPR-40 Mr. Louis Cortopassi Site Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station Mail Stop FC-2-4 961 0 Power Lane Blair, NE 68008 Grand Gulf Nuclear Station Entergy Operations, Inc. Docket No. 50-416 License No. NPF-29 Vice President, Operations Entergy Operations, Inc. Grand Gulf Nuclear Station P.O. Box 756 Port Gibson, MS 39150 H. B. Robinson Steam Electric Plant Duke Energy Progress, Inc. Docket No. 50-261 License No. DPR-23 Mr. William R. Gideon, Vice President H.B. Robinson Steam Electric Plant 3581 West Entrance Road Hartsville, SC 29550 Hope Creek Generating Station PSEG Nuclear, LLC Docket No. 50-354 License No. NPF-57 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC -N09 P.O. Box 236 Hancocks Bridge, NJ 08038 Indian Point Energy Nuclear Generating Entergy Nuclear Operations, Inc. Docket Nos. 50-247 and 50-286 License Nos. DPR-26 and DPR-64 Vice President, Operations Entergy Nuclear Operations, Inc. Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 James A. FitzPatrick Nuclear Power Plant Entergy Nuclear Operations, Inc. Docket No. 50-333 License No. DPR-59 Mr. Chris Adner, Licensing Manager Entergy Nuclear Operations, Inc. James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093 Joseph M. Farley Nuclear Plant Southern Nuclear Operating Co. Docket Nos. 50-348 and 50-364 License Nos. NPF-2 and NPF-8 Mr. C.R. Pierce Regulatory Affairs Director Southern Nuclear Operating Co., Inc. P.O. Box 1295/Bin 038 Birmingham, AL 35201-1295 LaSalle County Station Exelon Generation Company Docket Nos. 50-373 and 50-37 4 License Nos. NPF-11 and NPF-18 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Limerick Generating Station Exelon Generation Co., LLC Docket Nos. 50-352 and 50-353 License Nos. NPF-39 and NPF-85 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Millstone Nuclear Power Station Dominion Nuclear Connecticut, Inc. Docket Nos. 50-336 and 50-423 License Nos. DPR-65 and NPF-49 Mr. David A. Heacock President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc. lnnsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Monticello Nuclear Generating Plant Northern States Power Company -Minnesota Docket No. 50-263 License No. DPR-22 Mrs. Karen D. Feli Site Vice President Northern States Power Company -Minnesota Monticello Nuclear Generating Plant 2807 West County Road 75 Monticello, MN 55362-9637 Nine Mile Point Nuclear Station Nine Mile Point Nuclear Station, LLC Docket No. 50-220 License No. DPR-63 Mr. Christopher Costanzo Vice President Nine Mile Point Nine Mile Point Nuclear Station, LLC P. 0. Box 63 Lycoming, New York 13093 North Anna Power Station Virginia Electric & Power Co. Docket Nos. 50-338 and 50-339 License Nos. NPF-4 and NPF-7 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric & Power Co. lnnsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Oconee Nuclear Station Duke Energy Carolinas, LLC Docket Nos. 50-269, 50-270 and 50-287 License Nos. DPR-38, DPR-47 and DPR-55 Mr. Scott Batson Vice President, Oconee Nuclear Station Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC 29672 Oyster Creek Nuclear Generating Station Exelon Generation Co., LLC Docket No. 50-219 License No. DPR-16 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Palisades Nuclear Plant Entergy Nuclear Operations, Inc. Docket No. 50-255 License No. DPR-20 Vice President, Operations Entergy Nuclear Operations, Inc. Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, Ml 49043 Peach Bottom Atomic Power Station Exelon Generation Co, LLC Docket Nos. 50-277 and 50-278 License Nos. DPR-44 and DPR-56 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Perry Nuclear Power Plant FirstEnergy Nuclear Operating Co. Docket No. 50-440 License No. NPF-58 Mr. Ernest J. Harkness Site Vice President
-Nuclear -Perry FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant PO Box 97, A290 Perry, OH 44081 Pilgrim Nuclear Power Station Unit No. 1 Entergy Nuclear Operations, Inc. Docket No. 50-293 License No. DPR-35 Mr. John Dent, Jr. Vice President and Site Vice President Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Point Beach Nuclear Plant NextEra Energy Point Beach, LLC Docket Nos. 50-266 and 50-301 License Nos. DPR-24 and DPR-27 Mr. Eric McCartney Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516 Prairie Island Nuclear Generating Plant Northern States Power Co. -Minnesota Docket Nos. 50-282 and 50-306 License Nos. DPR-42 and DPR-60 Mr. Kevin K. Davison Site Vice President Northern States Power Minnesota Prairie Island Nuclear Generating Plant 1717 Wakonade Drive East Welch, MN 55089-9642 Quad Cities Nuclear Power Station Exelon Generation Company Docket Nos. 50-254 and 50-265 License Nos. DPR-29 and DPR-30 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 R.E. Ginna Nuclear Power Plant R. E. Ginna Power Plant, LLC Docket No. 50-244 License No. DPR-18 Mr. Joseph E. Pacher Vice President R. E. Ginna Nuclear Power Plant R. E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519 River Bend Station Entergy Operations, Inc. Docket No. 50-458 License No. NPF-47 Vice President, Operations Entergy Operations, Inc. River Bend Station 5485 U.S. Highway 61 N St. Francisville, LA 70775 Salem Nuclear Generating Station PSEG Nuclear, LLC. Docket Nos. 50-272 & 50-311 License Nos. DPR-70 and DPR-75 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC -N09 P.O. Box 236 Hancocks Bridge, NJ 08038 Seabrook Nuclear Plant NextEra Energy Seabrook, LLC Docket No 50-443 License No. NFP-86 Mr. Kevin Walsh Vice President, Seabrook Nuclear Plant c/o Mr. Michael O'Keefe NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874 Sequoyah Nuclear Plant Tennessee Valley Authority Docket Nos. 50-327 and 50-328 License Nos. DPR-77 and DPR-79 Mr. Joseph W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street LP 3D-C Chattanooga, TN 37 402 Shearon Harris Nuclear Power Plant Duke Energy Progress, Inc. Docket No. 50-400 License No. NPF-63 Mr. Ernest J. Kapopoulos, Jr. Vice President Shearon Harris Nuclear Power Plant 5413 Shearon Harris Rd New Hill, NC 27562-0165 South Texas Project STP Nuclear Operating Company Docket Nos. 50-498 and 50-499 License Nos. NPF-76 and NPF-80 Mr. Dennis L. Koehl President and CEO/CNO STP Nuclear Operating Company South Texas Project Electric Generating Station P.O. Box 289 Wadsworth, TX 77483 St. Lucie Plant Florida Power and Light Company Docket Nos. 50-335 and 50-389 License Nos. DPR-67 and NPF-16 Mr. Mano Nazar Executive Vice President and Chief Nuclear Officer NextEra Energy P. 0. Box 14000 700 Universe Boulevard Juno Beach, FL 33408-0420 Surry Power Station Virginia Electric & Power Company Docket Nos. 50-280 and 50-281 License Nos. DPR-32 and DPR-37 Mr. David A Heacock President and Chief Nuclear Officer, Dominion Nuclear Virginia Electric & Power Company 5000 Dominion Blvd. Glen Allen, VA 23060 Susquehanna Steam Electric Station PPL Susquehanna, LLC Docket Nos. 50-387 and 50-388 License Nos. NPF-14 and NPF-22 Mr. Timothy S. Rausch Senior Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Boulevard NUCSB3 Berwick, PA 18603-0467 Three Mile Island Nuclear Station Exelon Generation Company, LLC. Docket No. 50-289 License No. Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Turkey Point Nuclear Generating Station Florida Power & Light Company Docket Nos. 50-250 & 50-251 License Nos. DPR-031 and DPR-41 Mr. Mano Nazar Executive Vicep President and Chief Nuclear Officer NextEra Energy P. 0. Box 14000 Juno Beach, FL 33408-0420 Vermont Yankee Nuclear Power Station Entergy Nuclear Operations Docket No. 50-271 License No. DPR-28 Vice President, Operations Entergy Nuclear Operations, Inc. Vermont Yankee Nuclear Power Station P.O. Box 250 Governor Hunt Road Vernon, VT 05354 Virgil C. Summer Nuclear Station South Carolina Electric & Gas Company Docket No. 50-395 License No. NPF-12 Mr. Thomas D. Gatlin, Vice President Nuclear Operations South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Post Office Box 88, Mail Code 800 Jenkinsville, SC 29065 Vogtle Electric Generating Plant Southern Nuclear Operating Company, Inc. Docket Nos. 50-424 & 50-425 License Nos. NPF-68 and NPF-81 Mr. C. R. Pierce Regulatory Affairs Director Southern Nuclear Operating Co., Inc. P. 0. Box 1295 I Bin 038 Birmingham, AL 35201-1295 Waterford Steam Electric Station Entergy Operations, Inc. Docket No. 50-382 License No. NPF-38 Vice President, Operations Entergy Operations, Inc. Waterford Steam Electric Station, Unit 3 17265 River Road Killona, LA 70057-0751 Watts Bar Nuclear Plant Tennessee Valley Authority Docket Nos. 50-390 & 50-391 License Nos. NPF-90 Mr. Joseph W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street, LP 3D-C Chattanooga, TN 37 402-2801 William B. McGuire Nuclear Station Duke Energy Carolinas, LLC Docket Nos. 50-369 and 50-370 License Nos. NPF-9 and NPF-17 Steven D. Capps Duke Energy Carolinas, LLC McGuire Nuclear Station 12700 Hagers Ferry Road Huntersville, NC 28078-8985 Wolf Creek Generating Station Wolf Creek Nuclear Operating Corporation Docket No. 50-482 License No. NPF-42 Mr. Adam C. Heflin President, Chief Executive Officer, and Chief Nuclear Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 with stakeholders in the near future as part of the development of any revised guidance documents.
Given the generic nature of the limited-scope evaluations, it is expected that these evaluations will be completed for plants within the next two years. This letter transmits the NRC staff's results of the seismic hazard submittals for the purposes of screening and prioritizing the plants. It does not convey the staff's final determination regarding the adequacy of any plant's calculated hazard. As such, the NRC staff will continue its review of the submitted seismic hazard re-evaluations, and may request additional plant-specific information to support this review. The staff has placed a high priority on this review for the early identification of issues that might adversely affect each licensee's seismic risk evaluations.
Initial interactions with licensees will occur as soon as practicable.
The NRC staff plans to issue a staff assessment on the re-evaluated seismic hazard once each review is completed in approximately 12 to 18 months. If you have any questions on this matter, please contact your NRC licensing Project Manager. Sincerely, /RA by Jennifer Uhle for/ Eric J. Leeds, Director Office of Nuclear Reactor Regulation
Enclosures:
- 1. Glossary of Evaluations
- 2. Screening and Prioritization Results 3. List of Licensee March 2014 Re-evaluated Seismic Hazard Submittals
- 4. List of Addressees Distribution:
See next page ADAMS Accession No.: ML 14111A147
- Via E-mail OFFICE NRR/JLD/PMB/PM NRR/JLD/LA NRR/JLD/PMB/BC NRO/DSENRGS2/BC NAME NDiFrancesco SLent MMitchell DJackson DATE 04/22/2014 04/22/2014 04/30/2014 05/05/2014 OFFICE NRO/DSEND OGC NRR/DORL/D NRR/D NAME SFianders EWilliamson MEvans ELeeds (JUhle for) DATE 05/06/2014 05/02/2014 05/06/2014 05/9/2014 OFFICIAL RECORD COPY NRR/JLD/D OS keen 05/06/2014 Letter to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status from Eric J. Leeds dated May 9, 2014.
SUBJECT:
SCREENING AND PRIORITIZATION RESULTS OF REQUEST FOR INFORMATION PURSUANT TO TITLE 10 OF THE CODE OF FEDERAL REGULATIONS 50.54(f) REGARDING SEISMIC HAZARD RE-EVALUATIONS FOR RECOMMENDATION 2.1 OF THE NEAR-TERM TASK FORCE REVIEW OF INSIGHTS FROM THE FUKUSHIMA DAI-ICHI ACCIDENT DISTRIBUTION:
PUBLIC LPL 1-1 R/F LPL 1-2 R/F LPL2-1 R/F LPL2-2 R/F LPL3-1 R/F LPL3-2 R/F LPL4-1 R/F LPL4-2 R/F RidsNroOd RidsNrrDorl RidsNrrDorllpl1-1 RidsNrrDorllpl1-2 RidsNrrDorllpl2-1 RidsNrrDorllpl2-2
RidsNrrDorllpl3-1 RidsNrrDorllpl3-2 RidsNrrDorllpl4-1 RidsNrrDorllpl4-2 RidsNrrOd RidsNsirOd RidsOeMaiiCenter RidsOgcMaiiCenter LRegner, NRR MKhanna, NRR RPascarelli, NRR BBeasley, NRR JQuichocho, NRR TTate, NRR RCarlson, NRR MMarkley, NRR DBroaddus, NRR NDiFrancesco, NRR MJardaneh, NRO RidsNrrLAABaxter RidsNrrLAJBurkhardt RidsN rrLABCiayton RidsNrrLASFigueroa RidsNrrLAKGoldstein RidsNrrLASRohrer RidsNrrlaSLent RidsNrrLAMHenderson RidsNrrPMANO RidsNrrPMBeaverValley RidsNrrPMBellefonte RidsN rrPM Braidwood RidsNrrPMBrownsFerry RidsNrrPMBrunswick RidsNrrPMByron RidsNrrPMCallaway RidsNrrPMCalvertCiiffs RidsNrrPMCatawba RidsNrrPMCiinton RidsNrrPMComanchePeak RidsNrrPMCooper RidsNrrPMDCCook RidsNrrPM DavisBesse RidsNrrPMDresden RidsNrrPMDuaneArnold RidsNrrPMFarley RidsNrrPMFermi2 RidsNrrPMFitzPatrick RidsNrrPMFortCalhoun RidsNrrPMGrandGulf RidsNrrPMHatch RidsN rrPM HopeCreek RidsNrrPMindianPoint RidsNrrPMLaSalle RidsNrrPMLimerick RidsNrrPMMcGuire RidsNrrPMMillstone RidsNrrPMMonticello RidsNrrPMNineMile RidsNrrPMNorthAnna RidsN rrPMOconee RidsNrrPMOysterCreek RidsNrrPMPalisades RidsN rrPM Peach Bottom RidsNrrPMPerry RidsNrrPMPilgrim RidsNrrPMPointBeach RidsNrrPMPrairielsland RidsNrrPMQuadCities RidsNrrPMREGinna RidsNrrPMRiverBend RidsNrrPMRobinson RidsNrrPMSalem RidsNrrPMSeabrook RidsNrrPMSequoyah RidsNrrPMShearonHarris RidsN rrPM South Texas RidsNrrPMStLucie RidsNrrPMSummer RidsNrrPMSurry RidsNrrPMSusquehanna
RidsNrrPMThreeMilelsland RidsNrrPMTurkeyPoint RidsNrrPMVermontYankee RidsNrrPMVogtle RidsNrrPMWaterford RidsNrrPMWattsBar1 RidsN rrPMWattsBar2 RidsNrrPMWolfCreek RidsOgcRp Resource RidsRgn 1 MaiiCenter Resource RidsRgn2MaiiCenter
Resource RidsRgn3MaiiCenter Resource RidsRgn4MaiiCenter Resource RidsEdoMaiiCenter Resource