NRC Staff'S July 2014 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Nuclear Plant Unit 2 License Application
ML14182A656
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 07/01/2014
From: Catherine Kanatas
NRC/OGC
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-391-OL, ASLBP 09-893-01-OL-BD01, RAS 26145
Download: ML14182A656 (3)


Text

July 1, 2014 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

TENNESSEE VALLEY AUTHORITY ) Docket No. 50-391-OL

)

(Watts Bar Nuclear Plant, Unit 2) )

NRC STAFFS JULY 2014 BIMONTHLY REPORT REGARDING THE SCHEDULE FOR REVIEW OF THE WATTS BAR NUCLEAR PLANT UNIT 2 LICENSE APPLICATION The Staff of the Nuclear Regulatory Commission (Staff) hereby provides the information requested by the Atomic Safety and Licensing Board (Board) in its May 26, 2010 Scheduling Order (Order). In the Order, the Board instructed the Staff to submit a report on July 2, 2010, to be updated on the first Tuesday of every other month thereafter, updating its estimates of the dates on which the final Environmental Impact Statement (EIS) and the final Safety Evaluation Report (SER) will be issued, and in addition, promptly to inform the Board of any other developments that could potentially impact the schedule for this proceeding.1 In May of 2013, the NRC Staff published the final version of NUREG-0498, Supplement 2, Vol. 1, Final Environmental Impact Statement Related to the Operation of Watts Bar Nuclear Plant, Unit 2 (May 2013), and NUREG-0498, Supplement 2, Vol. 2 (May 2013).2 For its safety review, the Staff now estimates October of 20143 for the publication of its 1

No contentions are currently admitted in this proceeding, but a motion to admit a contention concerning the vacatur of the NRCs Waste Confidence Rule is being held in abeyance pending further order of the Commission. Order (Granting Motion to Withdraw Contention 7), at 2 (July 17, 2013)

(unpublished) (ADAMS Accession No. ML13198A195).

2 See Tennessee Valley Authority; Watts Bar Nuclear Plant, Unit 2, Final Environmental Statement; Issuance, 78 Fed. Reg. 35,989, 35,990 (June 14, 2013).

3 The previous estimate was July of 2014. NRC Staffs May 2014 Bi-monthly Report Regarding (continued. . .)

final supplement to NUREG-0847, Safety Evaluation Report Related to the Operation of Watts Bar Nuclear Plant, Units 1 and 2, (June 1982). However, the Staff anticipates that additional supplements to NUREG-0847 may be issued during the time period that Watts Bar Unit 2 construction remains uncompleted (i.e. through December of 2015).

Respectfully submitted,

/Signed (electronically) by/

Catherine E. Kanatas Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O15-D21 Washington, DC 20555 (301) 415-2321 Catherine.Kanatas@nrc.gov Date of signature: July 1, 2014.

(. . .continued) the Schedule for Review of the Watts Bar Nuclear Unit 2 License Application, at 1 (May 6, 2014) (ADAMS Accession No. ML14126A416).

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

TENNESSEE VALLEY AUTHORITY ) Docket No. 50-391-OL

)

(Watts Bar Nuclear Plant, Unit 2) )

CERTIFICATE OF SERVICE Pursuant to 10 C.F.R. § 2.305 (revised), I hereby certify that copies of the foregoing NRC STAFFS JULY 2014 BIMONTHLY REPORT REGARDING THE SCHEDULE FOR REVIEW OF THE WATTS BAR NUCLEAR PLANT UNIT 2 LICENSE APPLICATION dated July 1, 2014, has been served upon the Electronic Information Exchange, the NRCs E-Filing System, in the above captioned proceeding, this 1st day of July, 2014.

/Signed (electronically) by/

Catherine E. Kanatas Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O15-D21 Washington, DC 20555 (301) 415-2321 Catherine.Kanatas@nrc.gov Date of signature: July 1, 2014