Line 14: |
Line 14: |
| | page count = 5 | | | page count = 5 |
| | project = TAC:MD6083, TAC:MD6084 | | | project = TAC:MD6083, TAC:MD6084 |
| | stage = RAI | | | stage = Request |
| }} | | }} |
|
| |
|
Letter Sequence Request |
---|
|
|
MONTHYEARML0720603752007-07-17017 July 2007 Proposed Alternative to the American Society of Mechanical Engineers Code, Section XI Containment Inservice Inspection Program Project stage: Request ML0728904582007-10-16016 October 2007 Draft RAI Re. Extension of Cisi Interval Project stage: Draft RAI ML0733206112007-11-16016 November 2007 Containment Inservice Inspection Interval Extension Request for Additional Information Project stage: Request ML0804206812008-03-28028 March 2008 Approval of Alternative to Extend the Containment Inservice Inspection Interval by About 18 Months Project stage: Other 2007-11-16
[Table View] |
Similar Documents at Cook |
---|
Category:Letter
MONTHYEARAEP-NRC-2024-79, Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask2024-09-26026 September 2024 Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask AEP-NRC-2024-78, Reply to a Notice of Violation: EA-24-0472024-09-23023 September 2024 Reply to a Notice of Violation: EA-24-047 05000316/LER-2024-002, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-09-12012 September 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak IR 05000315/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000315/2024402 and 05000316/2024402, Independent Spent Fuel Storage Installation Security Inspection Report 07200072/2024401 AEP-NRC-2024-69, Core Operating Limits Report2024-09-0909 September 2024 Core Operating Limits Report IR 05000315/20243012024-09-0505 September 2024 NRC Initial License Examination Report 05000315/2024301 and 05000316/2024301 ML24225A0022024-09-0303 September 2024 Issuance of Amendment Nos. 363 and 344 Revising Technical Specifications Section 3.8.1, AC Sources-Operating, for a One-Time Extension of a Completion Time IR 05000315/20240112024-08-30030 August 2024 NRC Inspection Report 05000315/2024011 and 05000316/2024011 and Notice of Violation AEP-NRC-2024-51, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2024-08-28028 August 2024 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes AEP-NRC-2024-76, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-08-28028 August 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating 05000316/LER-2024-003, Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage2024-08-22022 August 2024 Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage IR 05000315/20240052024-08-21021 August 2024 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2024005 and 05000316/2024005) AEP-NRC-2024-61, Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request2024-08-15015 August 2024 Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request ML24221A2702024-08-0808 August 2024 Unit 2 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-62, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-08-0707 August 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask ML24256A1482024-08-0202 August 2024 2024 Post Examination Submittal Letter AEP-NRC-2024-47, Form OAR-1, Owners Activity Report2024-07-30030 July 2024 Form OAR-1, Owners Activity Report ML24183A0162024-07-25025 July 2024 Review of Reactor Vessel Material Surveillance Program Capsule W Technical Report ML24169A2142024-07-25025 July 2024 Issuance of Amendment No. 362 Regarding Change to Technical Specification 3.4.12, Low Temperature Overpressure Protection System IR 05000315/20240022024-07-24024 July 2024 Integrated Inspection Report 05000315/2024002 and 05000316/2024002 ML24197A1262024-07-15015 July 2024 Unit 2 - Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-52, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-07-15015 July 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak ML24191A0692024-07-0909 July 2024 Operator Licensing Examination Approval - Donald C. Cook Nuclear Power Plant, July 2024 AEP-NRC-2024-56, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-07-0808 July 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24176A1012024-06-21021 June 2024 57143-EN 57143 - Paragon Energy Solutions - Update 1 (Final) - 10CFR Part 21 Final Notification: P21-05242024-FN, Rev. 0 AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring ML24163A0132024-06-12012 June 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000315/2024012 and 05000316/2024012 AEP-NRC-2024-23, Core Operating Limits Report2024-05-23023 May 2024 Core Operating Limits Report ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection AEP-NRC-2024-30, Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip2024-05-20020 May 2024 Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip AEP-NRC-2024-40, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-05-16016 May 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-41, Annual Radiological Environmental Operating Report2024-05-15015 May 2024 Annual Radiological Environmental Operating Report IR 05000315/20240012024-05-14014 May 2024 Integrated Inspection Report 05000315/2024001 and 05000316/2024001 AEP-NRC-2024-07, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2024-05-14014 May 2024 Unit 2 - Transmittal of Report of Changes to the Emergency Plan IR 05000315/20244012024-05-14014 May 2024 – Security Baseline Inspection Report 05000315/2024401 and 05000316/2024401 AEP-NRC-2024-26, Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 492024-05-14014 May 2024 Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 49 AEP-NRC-2024-24, Form OAR-1, Owners Activity Report2024-05-0707 May 2024 Form OAR-1, Owners Activity Report ML24115A2152024-05-0707 May 2024 LTR: CNP Non-Acceptance with Opportunity TS 3-8-1 ML24256A1472024-05-0606 May 2024 DC Cook 2024 NRC Examination Submittal Letter: Submittal ML24116A0002024-05-0202 May 2024 – Regulatory Audit in Support of Review of the Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors AEP-NRC-2024-35, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-30030 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2024-28, 2023 Annual Radioactive Effluent Release Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report AEP-NRC-2024-31, Annual Report of Individual Monitoring2024-04-24024 April 2024 Annual Report of Individual Monitoring AEP-NRC-2024-02, Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-04-0303 April 2024 Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-29, (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-072024-04-0303 April 2024 (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-07 AEP-NRC-2024-19, Annual Report of Property Insurance2024-04-0101 April 2024 Annual Report of Property Insurance AEP-NRC-2024-04, License Amendment Request Regarding a Change to Unit 1 Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System2024-03-0606 March 2024 License Amendment Request Regarding a Change to Unit 1 Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System ML24073A2342024-03-0606 March 2024 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors IR 05000315/20230062024-02-28028 February 2024 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2023006 and 05000316/2023006) 2024-09-09
[Table view] |
Text
Indiana Michigan Power INDIANA Cook Nuclear Plant MICHIGAN One Cook Place Bridgman, MI 49106 AEP.com A unit of American Electric Power November 16, 2007 AEP:NRC:7055-06 10 CFR 50.55a Docket Nos.: 50-315 50-316 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop O-PI-17 Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Units 1 and 2 Containment Inservice Inspection Interval Extension Request for Additional Information
References:
- 1. Letter from J. N. Jensen, Indiana Michigan Power Company (I&M), to U. S. Nuclear Regulatory Commission (NRC) Document Control Desk,"Donald C. Cook Nuclear Plant Units 1 and 2, Proposed Alternative to the American Society of Mechanical Engineers Code,Section XI, Containment Inservice Inspection Program," AEP:NRC:7055-02, dated July 17, 2007 (ML072060375).
- 2. Electronic mail from P. S. Tam, NRC, to M. K. Scarpello, I&M, "D. C. Cook -Draft RAI re. Extension of CISI Interval (TAC MD6083, MD6084)," dated October 16, 2007 (ML072890458).
In Reference 1, Indiana Michigan Power Company (I&M), the licensee for Donald C. Cook Nuclear Plant (CNP) Units 1 and 2, requested Nuclear Regulatory Commission (NRC) approval of a proposed alternative to the American Society of Mechanical Engineers Code,Section XI, Containment Inservice Inspection (CISI) Program. Specifically, I&M requested an extension of CNP's current interval by approximately eighteen months to enable the CISI program to be coincident with CNP's Inservice Inspection Program.In Reference 2, the NRC requested additional information regarding I&M's request. The attachment to this letter provides I&M's response to the request for additional information.
A47m U. S. Nuclear Regulatory Commission AEP:NRC:7055-06 Page 2 This letter contains no new commitments.
Should you have any questions, please contact Ms. Susan D. Simpson, Regulatory Affairs Manager, at (269) 466-2428.Sincerely, Joseph N. Jensen Site Vice President RGV/rdw Attachment c: R. Aben -Department of Labor and Economic Growth J. L. Caldwell -NRC Region III K. D. Curry -AEP Ft. Wayne, w/o attachment J. T. King -MPSC, w/o attachment MDEQ -WHMD/RPMWS, w/o attachment NRC Resident Inspector P.S. Tam -NRC Washington DC Attachment to AEP:NRC:7055-06 Containment Inservice Inspection Interval Extension Request for Additional Information In Reference 1, Indiana Michigan Power Company (I&M), the licensee for Donald C. Cook Nuclear Plant (CNP) Units 1 and 2, requested Nuclear Regulatory Commission (NRC) approval of a proposed alternative to the American Society of Mechanical Engineers Code (ASME), Section. XI, Containment Inservice Inspection (CISI) Program. Specifically, I&M requested an extension of CNP's current interval by approximately eighteen months to enable the CISI program to be coincident with CNP's Inservice Inspection Program.In Reference 2, the NRC requested additional information regarding I&M's request. The following provides I&M's response to the request for additional information.
NRC Request 1 In Section 5.0 of the attachment to the 7/17/07 letter, I&M proposed that the first interval for the Containment In-service Inspection (CISI) be extended approximately 18 months from September 9, 2008 to March 1, 2010. The extension will permit I&M to achieve a common interval start date and a common In-service Inspection (ISI) code with the 1SI program. I&M also states that the code of record for the updated (2010) 1SI and CISI programs will be the latest edition incorporated by reference in 10 CFR 50.55a(b)(2) twelve months prior to March 1, 2010. These statements imply that March 1, 2010 applies to both Units 1 and 2.Please provide a table showing the current and proposed Units 1 and 2 ISI and CISI inspection interval dates and to clarify the statement relative to the code of record in the first paragraph of Section 5. 0, "Proposed Alternative and Basis for Use." I&M Response to Request 1 Table 1 provides the requested information.
NRC Request 2 The second paragraph of Section 5.0 of the attachment states that there are no augmented examination areas for either Unit 1 or Unit 2. This statement indicates that all surface areas (e.g., leak chase channels, sump liner) listed in IWE-1240 as likely areas requiring augmented examination and other areas such as space between ice baskets and the liner have been found acceptable and were not inspected in accordance with the augmented examination requirements of Table IWE 2500-1. Please provide further information relative to this statement, IWE-1240 and the Examination Category E C of Table IWE-2500-1 as applicable to the CNP Units 1 and 2.
Attachment to AEP:NRC:7055-06 Page 2 I&M Response to Request 2 There is no evidence of containment liner accessible areas experiencing accelerated degradation in either unit. Most of the liner plate behind the ice condensers is inaccessible.
The ice baskets and interior of the ice condenser are separated from the containment liner by a paneled wall with a gap between the wall and the liner. There are inspection ports in the ice condenser that are used to monitor conditions of the containment liner behind the ice condenser.
The liner in the area of the inspection ports shows no evidence of corrosion or accelerated degradation.
NRC Request 3 Please confirm and provide pertinent information that the examination and tests (required by the CISI program) performed during recent inspections have. satisfied the acceptance standards contained within Articles IWE-3000 and IWL-3000.I&M Response to Request 3 The recent examination results of the containment liner have satisfied the code acceptance criteria.
The overall condition of the containment liners of both containments is very good following the implementation of a coatings inspection and maintenance program that supplements the ASME Code,Section XI examinations.
The concrete examinations on both unit containments have been completed with the use of a crane and man-basket that provided a means to thoroughly examine the exterior concrete.
There. were no conditions that would adversely impact the structural integrity of either containment structure.
References:
- 1. Letter from J. N. Jensen, I&M, to NRC Document Control Desk,"Donald C. Cook Nuclear Plant Units 1 and 2, Proposed Alternative to the American Society of Mechanical Engineers Code,Section XI, Containment Inservice Inspection Program," ?AEP:NRC:7055-02, dated July 17, 2007 (ML072060375).
- 2. Electronic mail from P. S. Tam, NRC, to M. K. Scarpello, I&M, "D. C. Cook -Draft RAI re. Extension of CISI Interval (TAC MD6083, MD6084)," dated October 16, 2007 (ML072890458).
Attachment to AEP:NRC:7055-06 Page 3 Table 1 Current and Proposed ISI and CISI Intervals Next Inspection Interval Start Proposed Inspection Interval Extended Period Examinations Program Date Start Date (Current Requirement)
Start Date ISI Program examinations are not impacted by the ISI 3/1/2010 (Units I and 2) 3/1/2010 (Units I and 2) 1interval extension CISI 9/9/2008 (Units 1 and 2) 3/1/2010 (Units 1 and 2) ASME Section XI, 1992 Edition/Addenda IWE examinations that are performed during a typical inspection period Category E-A, Item Number El. 11: General visual examination of accessible surfaces Category E-D, Item Number E5.30: VT-3 visual examination of moisture barriers Category E-G, Item Number E8.10, Note 2: VT-1 visual examinations of bolting during maintenance disassemblies Note: IWL examinations were completed in 2007 and will remain on a five year schedule