|
|
Line 2: |
Line 2: |
| | number = ML102100503 | | | number = ML102100503 |
| | issue date = 07/29/2010 | | | issue date = 07/29/2010 |
| | title = Monticello - Letter of 7/16/10 Withdrawal from NFPA 805 Transition Acceptable for Review (TAC ME4250) | | | title = Monticello - Letter of 7/16/10 Withdrawal from NFPA 805 Transition Acceptable for Review |
| | author name = Tam P S | | | author name = Tam P S |
| | author affiliation = NRC/NRR/DORL/LPLIII-1 | | | author affiliation = NRC/NRR/DORL/LPLIII-1 |
Revision as of 08:36, 9 February 2019
|
---|
Category:E-Mail
MONTHYEARML24254A3932024-08-26026 August 2024 SLRA - 2nd Round Request for Additional Information ML24218A2282024-08-0505 August 2024 Request for Confirmation of Information for Relief Request RR-017, Inservice Inspection Impracticality During the Fifth Ten-Year Interval ML24131A0802024-05-10010 May 2024 Final RAI for LAR to Revise TS 3.8.6, Battery Parameters, SR 3.8.6.6 ML24036A2462024-04-24024 April 2024 NRC to Fws, NRC Issuance of Draft Environmental Impact Statement for Monticello Subsequent License Renewal, Opportunity for Public Comment, and Endangered Species Act Determinations ML24092A2152024-03-27027 March 2024 Email: Requests for Information to Support Deis ML24068A0612024-03-0707 March 2024 Extension of Audit for License Amendment Request to Revise TS 3.8.6, Battery Parameters, SR 3.8.6.6 ML24064A1802024-03-0404 March 2024 Acceptance of Relief Request RR-017, Inservice Inspection (ISI) Impracticality During the Fifth Ten-Year Interval ML24036A0932024-02-0202 February 2024 Acceptance of License Amendment Request to Revise TS 5.6.5 and Update PTLR Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data ML24022A0212024-01-20020 January 2024 NRR E-mail Capture - Monticello - Request for Additional Information ISI RR-002 Alternative to Use IWB-2500(f) ML23353A0742023-12-19019 December 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Proposed Alternative VR-09, Modifications to OMN-17 ML23348A3462023-12-14014 December 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of License Amendment Request to Revise TS 3.8.6, Battery Parameters, SR 3.8.6.6 ML23268A0292023-09-20020 September 2023 SLRA - Requests for Confirmation of Information - Set 2 - Email from Marieliz Johnson to Shawn Hafen ML23249A2092023-09-0606 September 2023 NRR E-mail Capture - Action: Opportunity to Review and Comment on a New NRC Information Collection, 10 CFR Part 50.55a, Codes and Standards (3150-XXXX) ML23248A3462023-09-0505 September 2023 NRR E-mail Capture - Request for Additional Information for Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant - Decommissioning Funding Status Reports ML23237A4822023-08-25025 August 2023 SLRA - Request for Additional Information - Set 3 - Email from Marieliz Johnson to Shawn Hafen ML23228A1212023-08-16016 August 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Alternative Request VR-11 for MO-2397 ML23227A2182023-08-15015 August 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Alternative Request RR-002 to Use IWB-2500(f) ML23219A1072023-08-0707 August 2023 SLRA - Requests for Additional Information - Set 2 - Email from Marieliz Johnson to Shawn Hafen ML23200A3502023-07-19019 July 2023 SLRA - Requests for Additional Information - Set 1 - Email from Marieliz Johnson to Christopher Domingos ML23172A1122023-06-21021 June 2023 SLRA - Requests for Confirmation of Information - Set 1 - Email from Marieliz Johnson to Christopher Domingos ML23054A3322023-02-23023 February 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Relief Request to Use Later Edition of ASME BPV Code, Section XI, for ISI Program Code of Record ML23053A1362023-02-13013 February 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Relief Request to Use Later Edition of ASME BPV Code, Section XI, for Cisi Program ML23017A2222023-01-13013 January 2023 Verbal Authorization of Proposed Alternative PR-08 Regarding Inservice Testing Requirements of Certain High Pressure Coolant Injection System Components (EPID L-2022-LLR-0088) (Email) ML23004A1982023-01-0404 January 2023 NRR E-mail Capture - Draft Request for Additional Information Monticello Nuclear Generating Plant Request Pr 08, HPCI Pump Quarterly Testing ML23012A2102022-07-26026 July 2022 Letter Submitting Monticello Outline Package ML22181A1962022-06-24024 June 2022 NRR E-mail Capture - Draft RAI Monticello Alternative VR-08 ML22175A1602022-06-24024 June 2022 NRR E-mail Capture - RAI Monticello Fuel Oil Storage Tank Inspection ML22131A2652022-05-11011 May 2022 NRR E-mail Capture - Request for Additional Information Xcel Energy Amendment Request to Create a Common Eplan and EOF for Monticello and Prairie Island ML22123A2822022-05-0303 May 2022 NRR E-mail Capture - Request for Additional Information Monticello Alternative VR-10, EFCV Testing Frequency ML22101A0712022-04-11011 April 2022 NRR E-mail Capture - Monticello - Acceptance of Requested Licensing Action License Amendment Request to Revise TS 3.6.1.8 Residual Heat Removal (RHR) Drywell Spray Header and Nozzle Surveillance Frequency ML22089A1302022-03-30030 March 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Alternative Related Excess Flow Check Valve Testing Frequency ML22082A1812022-03-23023 March 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of VR-08 Alternative to Adopt ASME OM Code Case OMN-28 ML22075A2612022-03-16016 March 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of VR-07 Alternative Related to MOV Testing Per ASME OM Code Case OMN-26 ML22067A2032022-03-0808 March 2022 Audit Plan to Support Review of an Amendment to Transition to Atrium 11 Fuel (Redacted) ML22011A0642022-01-11011 January 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Licensing Action License Amendment Request to Support Diesel Generator Fuel Oil Storage Tank Inspection ML22005A3612022-01-0505 January 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Pump Vibration Testing Per ASME OM Code Case OMN-22 ML21347A0082021-12-10010 December 2021 NRR E-mail Capture - Monticello and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested License Amendment Standard Emergency Plan and Consolidated Emergency Operations Facility ML21330A0382021-11-18018 November 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related RHR and RHRSW Pump Testing ML21286A7882021-10-0606 October 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Residual Heat Removal Heat Exchanger Flow Control Valve Stroke Timing ML21256A1882021-09-13013 September 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Vibration Testing Range for the Sblc Pumps ML21256A1892021-09-13013 September 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Testing the Control Rod Drive Scram Discharge Header Check Valves ML21256A1862021-09-13013 September 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to HPCI and RCIC Pump Testing ML21253A2002021-09-10010 September 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Pressure Isolation Valve Testing ML21252A0132021-08-31031 August 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Licensing Action License Amendment Request to Adopt Advanced Framatome Methodologies ML21130A3022021-05-0707 May 2021 Initial and Final Written 10 CFR 21 Notification for GE Hitachi Numac Prnm System ML21110A7042021-04-20020 April 2021 Response: Monticello Nuclear Plant Outage - Covid Risk to On-Site Employees ML21084A2522021-03-24024 March 2021 NRR E-mail Capture - Revised Review Schedule for Monticello TSTF-505 (EPID L-20200LLA-0062) ML21068A2772021-03-0909 March 2021 NRR E-mail Capture - Monticello TSTF-505, Request for Additional Information ML20343A1292020-12-0808 December 2020 NRR E-mail Capture - Request for Additional Information ML20342A1782020-12-0707 December 2020 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-564 Safety Limit MCPR 2024-08-05
[Table view] |
Text
Accession No. ML102100503
From: Tam, Peter Sent: Thursday, July 29, 2010 2:48 PM To: 'Hazelhoff, Amy'; 'Loeffler, Richard A.'; 'Salamon, Gabor' Cc: Frumkin, Daniel
Subject:
Monticello - Letter of 7/16/10 re. withdrawl from NFPA 805 transition acceptable for review (TAC ME4250) Attachments: ML1020004330.pdf Amy: By letter dated July 16, 2010 (Accession No. ML102000433), NSPM proposed to withdraw from a previous commitment to transition to the guidance of NFPA 805 (regarding fire protection). The NRC staff has found the subject submittal acceptable for review per NRR Office Instruction LIC-109. I understand that NSPM plans to supplement the July 16, 2010, letter as a result of a verbal request from me; we will treat that supplement as a response to an RAI and look forward to receiving it in the near future.
Peter S. Tam , Senior Project Manager (for Kewaunee and Monticello) Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Tel. 301-415-1451 E-mail Properties Mail Envelope Properties (0A64B42AAA8FD4418CE1EB5240A6FED11B56AAA279)
Subject:
Monticello - Letter of 7/16/10 re. withdrawl from NFPA 805 transition acceptable for review (TAC ME4250)
Sent Date: 7/29/2010 2:47:41 PM Received Date: 7/29/2010 2:47:00 PM From: Tam, Peter
Created By: Peter.Tam@nrc.gov
Recipients:
Amy.Hazelhoff@xenuclear.com ('Hazelhoff, Amy')
Tracking Status: None Richard.Loeffler@xenuclear.com ('Loeffler, Richard A.')
Tracking Status: None Gabor.Salamon@xenuclear.com ('Salamon, Gabor') Tracking Status: None Daniel.Frumkin@nrc.gov (Frumkin, Daniel) Tracking Status: None
Post Office:
HQCLSTR02.nrc.gov
Files Size Date & Time
MESSAGE 112925 7/29/2010 ML1020004330.pdf 107093
Options Expiration Date:
Priority: olImportanceNormal ReplyRequested: False Return Notification: False
Sensitivity: olNormal Recipients received: