Correction to Three Mile Island Nuclear Station, Unit 1 and Unit 2 Combined 2015 Annual Radioactive Effluent Release Report On 4/29/16, Three Mile Island Nuclear Station (TMINS) submitted the subject Combined 2015 Annual Radioactive Effluent Release Report (ARERR). This report included a revision to the site Process Control Program (PCP) for Radioactive Wastes (RW-AA-100) which was marked Exelon Confidential/Proprietary. Although the PCP was submitted as company confidential, Exelon has re-evaluated this marking and does not consider this procedure to be company confidential. The PCP should not have included the Exelon Confidential/Proprietary label and therefore, there is no need for the NRC to process this as a proprietary document. This oversight has been entered in our Corrective Action Program. Respectfully, Plant Manager, Three Mile Island Unit 1 Exelon Generation Co., LLC cc: NRC Senior Resident Inspector -TMl-1 NRC Project Manager, NRR-TMl-1 (Justin.poole@nrc.gov) NRC Regional Administrator-Region I Exelon Generation TMl-16-058 May 25, 2016 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Three Mile Island Nuclear Station, Unit 1 and Unit 2 Renewed Facility Operating License No. DPR-50 and Possession Only License No. DPR-73 NRC Docket Nos. 50-289 and 50-320 10 CFR 50.4 | |||
Correction to Three Mile Island Nuclear Station, Unit 1 and Unit 2 Combined 2015 Annual Radioactive Effluent Release Report On 4/29/16, Three Mile Island Nuclear Station (TMINS) submitted the subject Combined 2015 Annual Radioactive Effluent Release Report (ARERR). | |||
This report included a revision to the site Process Control Program (PCP) for Radioactive Wastes (RW-AA-100) which was marked Exelon Confidential/Proprietary. | |||
Although the PCP was submitted as company confidential, Exelon has re-evaluated this marking and does not consider this procedure to be company confidential. | |||
The PCP should not have included the Exelon Confidential/Proprietary label and therefore, there is no need for the NRC to process this as a proprietary document. | |||
This oversight has been entered in our Corrective Action Program. | |||
Respectfully, Plant Manager, Three Mile Island Unit 1 Exelon Generation Co., LLC cc: NRC Senior Resident Inspector | |||
-TMl-1 NRC Project Manager, NRR-TMl-1 (Justin.poole@nrc.gov) | |||
NRC Regional Administrator-Region I Exelon Generation TMl-16-058 May 25, 2016 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Three Mile Island Nuclear Station, Unit 1 and Unit 2 Renewed Facility Operating License No. DPR-50 and Possession Only License No. DPR-73 NRC Docket Nos. 50-289 and 50-320 10 CFR 50.4 | |||
==Subject:== | ==Subject:== | ||
Correction to Three Mile Island Nuclear Station, Unit 1 and Unit 2 Combined 2015 Annual Radioactive Effluent Release Report On 4/29/16, Three Mile Island Nuclear Station (TMINS) submitted the subject Combined 2015 Annual Radioactive Effluent Release Report (ARERR). This report included a revision to the site Process Control Program (PCP) for Radioactive Wastes (RW-AA-100) which was marked Exelon Confidential/Proprietary. Although the PCP was submitted as company confidential, Exelon has re-evaluated this marking and does not consider this procedure to be company confidential. The PCP should not have included the Exelon Confidential/Proprietary label and therefore, there is no need for the NRC to process this as a proprietary document. This oversight has been entered in our Corrective Action Program. Respectfully, Plant Manager, Three Mile Island Unit 1 Exelon Generation Co., LLC cc: NRC Senior Resident Inspector -TMl-1 NRC Project Manager, NRR-TMl-1 (Justin.poole@nrc.gov) NRC Regional Administrator-Region I}} | |||
Correction to Three Mile Island Nuclear Station, Unit 1 and Unit 2 Combined 2015 Annual Radioactive Effluent Release Report On 4/29/16, Three Mile Island Nuclear Station (TMINS) submitted the subject Combined 2015 Annual Radioactive Effluent Release Report (ARERR). | |||
This report included a revision to the site Process Control Program (PCP) for Radioactive Wastes (RW-AA-100) which was marked Exelon Confidential/Proprietary. | |||
Although the PCP was submitted as company confidential, Exelon has re-evaluated this marking and does not consider this procedure to be company confidential. | |||
The PCP should not have included the Exelon Confidential/Proprietary label and therefore, there is no need for the NRC to process this as a proprietary document. | |||
This oversight has been entered in our Corrective Action Program. | |||
Respectfully, Plant Manager, Three Mile Island Unit 1 Exelon Generation Co., LLC cc: NRC Senior Resident Inspector | |||
-TMl-1 NRC Project Manager, NRR-TMl-1 (Justin.poole@nrc.gov) | |||
NRC Regional Administrator-Region I}} |
Revision as of 07:57, 30 June 2018
ML16153A243 | |
Person / Time | |
---|---|
Site: | Three Mile Island |
Issue date: | 05/25/2016 |
From: | Haaf T P Exelon Generation Co |
To: | Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation |
References | |
TMl-16-058 | |
Download: ML16153A243 (1) | |
Text
Exelon Generation TMl-16-058 May 25, 2016 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Three Mile Island Nuclear Station, Unit 1 and Unit 2 Renewed Facility Operating License No. DPR-50 and Possession Only License No. DPR-73 NRC Docket Nos. 50-289 and 50-320 10 CFR 50.4
Subject:
Correction to Three Mile Island Nuclear Station, Unit 1 and Unit 2 Combined 2015 Annual Radioactive Effluent Release Report On 4/29/16, Three Mile Island Nuclear Station (TMINS) submitted the subject Combined 2015 Annual Radioactive Effluent Release Report (ARERR).
This report included a revision to the site Process Control Program (PCP) for Radioactive Wastes (RW-AA-100) which was marked Exelon Confidential/Proprietary.
Although the PCP was submitted as company confidential, Exelon has re-evaluated this marking and does not consider this procedure to be company confidential.
The PCP should not have included the Exelon Confidential/Proprietary label and therefore, there is no need for the NRC to process this as a proprietary document.
This oversight has been entered in our Corrective Action Program.
Respectfully, Plant Manager, Three Mile Island Unit 1 Exelon Generation Co., LLC cc: NRC Senior Resident Inspector
-TMl-1 NRC Project Manager, NRR-TMl-1 (Justin.poole@nrc.gov)
NRC Regional Administrator-Region I Exelon Generation TMl-16-058 May 25, 2016 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Three Mile Island Nuclear Station, Unit 1 and Unit 2 Renewed Facility Operating License No. DPR-50 and Possession Only License No. DPR-73 NRC Docket Nos. 50-289 and 50-320 10 CFR 50.4
Subject:
Correction to Three Mile Island Nuclear Station, Unit 1 and Unit 2 Combined 2015 Annual Radioactive Effluent Release Report On 4/29/16, Three Mile Island Nuclear Station (TMINS) submitted the subject Combined 2015 Annual Radioactive Effluent Release Report (ARERR).
This report included a revision to the site Process Control Program (PCP) for Radioactive Wastes (RW-AA-100) which was marked Exelon Confidential/Proprietary.
Although the PCP was submitted as company confidential, Exelon has re-evaluated this marking and does not consider this procedure to be company confidential.
The PCP should not have included the Exelon Confidential/Proprietary label and therefore, there is no need for the NRC to process this as a proprietary document.
This oversight has been entered in our Corrective Action Program.
Respectfully, Plant Manager, Three Mile Island Unit 1 Exelon Generation Co., LLC cc: NRC Senior Resident Inspector