Line 37: |
Line 37: |
| Joseph G. Giitter, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-456 and 50-457 cc: See next page | | Joseph G. Giitter, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-456 and 50-457 cc: See next page |
|
| |
|
| ML082520039 NRR-106 OFFICE DCI/CPNB DCI/CPNB LPL3-2/PM LPL3-2/LA LPL3-2/BC NAME JCollins TChan MDavid THarris RGibbs DATE 9/10/08 9/10/08 9/9/08 9/9/08 9/9/08 OFFICE DCI/D DRP/D RIII DORL/D NAME MEvans CPederson JGiitter DATE 9/10/08 9/11/08 9/16/08 | | ML082520039 NRR-106 OFFICE DCI/CPNB DCI/CPNB LPL3-2/PM LPL3-2/LA LPL3-2/BC NAME JCollins TChan MDavid THarris RGibbs DATE 9/10/08 9/10/08 9/9/08 9/9/08 9/9/08 OFFICE DCI/D DRP/D RIII DORL/D NAME MEvans CPederson JGiitter DATE 9/10/08 9/11/08 9/16/08 Braidwood Station, Units 1 and 2 cc: |
| | |
| Braidwood Station, Units 1 and 2 cc: | |
| Corporate Distribution Exelon Generation Company, LLC Via e-mail Braidwood Distribution Exelon Generation Company, LLC Via e-mail Mr. Dwain W. Alexander, Project Manager Westinghouse Electric Corporation Via e-mail Ms. Bridget Little Rorem Appleseed Coordinator Via e-mail Howard A. Learner Environmental Law and Policy Center of the Midwest Via e-mail Braidwood Resident Inspector U.S. Nuclear Regulatory Commission Via e-mail Illinois Emergency Management Agency Division of Nuclear Safety Via e-mail Will County Executive Via e-mail Attorney General Springfield, IL Via e-mail Chairman, Ogle County Board Via e-mail Ms. Lorraine Creek RR 1, Box 182 Manteno, IL 60950}} | | Corporate Distribution Exelon Generation Company, LLC Via e-mail Braidwood Distribution Exelon Generation Company, LLC Via e-mail Mr. Dwain W. Alexander, Project Manager Westinghouse Electric Corporation Via e-mail Ms. Bridget Little Rorem Appleseed Coordinator Via e-mail Howard A. Learner Environmental Law and Policy Center of the Midwest Via e-mail Braidwood Resident Inspector U.S. Nuclear Regulatory Commission Via e-mail Illinois Emergency Management Agency Division of Nuclear Safety Via e-mail Will County Executive Via e-mail Attorney General Springfield, IL Via e-mail Chairman, Ogle County Board Via e-mail Ms. Lorraine Creek RR 1, Box 182 Manteno, IL 60950}} |
Latest revision as of 21:22, 12 March 2020
Letter Sequence Other |
---|
|
|
MONTHYEARML0807403252008-03-14014 March 2008 Evaluation of New Information Related to Alloy 82/182 Pressurizer Butt Weld Inspections Confirmatory Action Letter NRR-07-008 Project stage: Other ML0819202872008-07-10010 July 2008 Closeout of Confirmatory Action Letter Requirements - Unit 2 Project stage: Other ML0825200392008-09-16016 September 2008 Closure of Confirmatory Action Letter NRR-07-008 Project stage: Other 2008-07-10
[Table View] |
|
---|
Category:Letter
MONTHYEARML24291A0012024-10-17017 October 2024 Submittal of Core Operating Limits Report, Cycle 25 RS-24-095, Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals2024-10-10010 October 2024 Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24263A1272024-09-23023 September 2024 – Request for Additional Information (EPID 2023-LLA-0136) - Non-Proprietary IR 05000456/20240112024-09-12012 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000456/2024011 and 05000457/2024011 ML24164A0032024-09-10010 September 2024 Issuance of Amendment Nos. 235 and 235 Revision of Technical Specifications for the Ultimate Heat Sink IR 05000456/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2024005 and 05000457/2024005) ML24227A0522024-08-29029 August 2024 Audit Plan for LAR to Remove ATWS Mtc Limit ML24225A1112024-08-13013 August 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000456/20240022024-08-0808 August 2024 Integrated Inspection Report 05000456/2024002 and 05000457/2024002 ML24172A1252024-07-26026 July 2024 Environmental Assessment and Finding of No Significant Impact Related to a Requested Increase in Ultimate Heat Sink Temperature (EPID L-2024-LLA-0075) - Transmittal Letter ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) 05000456/LER-2024-001, Submittal of LER 2024-001-00 for Braidwood Station, Unit 1, Trip on Low Steam Generator Level Due to Failure to Verify Isolation Valves Were Open2024-07-0303 July 2024 Submittal of LER 2024-001-00 for Braidwood Station, Unit 1, Trip on Low Steam Generator Level Due to Failure to Verify Isolation Valves Were Open ML24163A3922024-06-25025 June 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, & Opportunity for a Hearing (EPID L-2024-LLA-0075)- Letter RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24164A2132024-06-13013 June 2024 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Braidwood Nuclear Plant RS-24-057, License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink2024-06-0404 June 2024 License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink IR 05000456/20240102024-05-31031 May 2024 License Renewal Phase 1 Report 05000456/2024010 RS-24-044, License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed2024-05-28028 May 2024 License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed RS-24-043, Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications2024-05-24024 May 2024 Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24136A0132024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report ML24136A2452024-05-15015 May 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000457/2024004 ML24128A1212024-05-0707 May 2024 Response to Braidwood and Dresden FOF Dates Change Request (2025) ML24122A6522024-05-0101 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests IR 05000456/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000456/2024301; 05000457/2024301 RS-24-026, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR)2024-04-25025 April 2024 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML24116A0052024-04-25025 April 2024 Transmittal of Braidwood Station, Unit 1, Core Operating Limits Report, Braidwood Unit 1 Cycle 25 IR 05000456/20240012024-04-24024 April 2024 Integrated Inspection Report 05000456/2024001 and 05000457/2024001 ML24113A1272024-04-22022 April 2024 Audit Plan in Support of Review of LAR Revision of TS 3.7.15, 3.7.16, and 4.3.1 (EPID: L-2023-LLA-0136) (Non-Proprietary) IR 05000457/20240902024-04-19019 April 2024 Final Significance Determination for 2b Auxiliary Feedwater Pump Diesel Engine Fuel Oil Dilution Issue - NRC Inspection Report 05000457/2024090 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-24-034, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-04-10010 April 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors ML24094A2692024-04-0303 April 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Report, WCAP-17451-P, Revision 2, Reactor Internals Guide Tube Wear Westinghouse Domestic Fleet Operational Projections RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24057A0372024-03-26026 March 2024 Proposed Alternative from Certain Requirements Contained in the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI RS-24-024, Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2024-03-22022 March 2024 Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML24067A3252024-03-0707 March 2024 U.S. Department of Energy, Office of Legacy Management, 2023 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites ML24066A0122024-03-0606 March 2024 Operator Licensing Examination Approval Braidwood Station, Units 1 and 2, March 2024 IR 05000456/20244012024-03-0505 March 2024 Cyber Security Inspection Report 05000456/2024401 and 05000457/2024401 (Public) IR 05000456/20230062024-02-28028 February 2024 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2023006 and 05000457/2023006) ML24057A3022024-02-26026 February 2024 Regulatory Conference Supplemental Information ML24047A2382024-02-20020 February 2024 Regulatory Conference to Discuss Risk Associated with 2b Auxiliary Feedwater Pump Diesel Engine Fuel Oil Leak RS-24-013, Response to Request for Additional Information Regarding Proposed Alternative to Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators2024-02-13013 February 2024 Response to Request for Additional Information Regarding Proposed Alternative to Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators IR 05000456/20230042024-02-0202 February 2024 Integrated Inspection Report 05000456/2023004 and 05000457/2023004 2024-09-23
[Table view] Category:Confirmatory Action Letter (CAL)
MONTHYEARML0825200392008-09-16016 September 2008 Closure of Confirmatory Action Letter NRR-07-008 ML0819202872008-07-10010 July 2008 Closeout of Confirmatory Action Letter Requirements - Unit 2 ML0807403252008-03-14014 March 2008 Evaluation of New Information Related to Alloy 82/182 Pressurizer Butt Weld Inspections Confirmatory Action Letter NRR-07-008 ML0733901792007-12-17017 December 2007 Completion of Actions for Confirmatory Action Letter NRR-07-008 ML0731803832007-11-14014 November 2007 Closeout of Confirmatory Action Letter Requirements ML0724302922007-09-0707 September 2007 Evaluation of Finite Element Analysis in Support of Alloy 82/182 Pressurizer Butt Weld Inspections in 2008 as Provided by Completion of Analysis Required by CAL NRR-07-008 ML0707402942007-03-22022 March 2007 Confirmatory Action Letter - Braidwood, Units 1 and 2 2008-09-16
[Table view] |
Text
September 16, 2008 Mr. Bryan Hanson Site Vice President Exelon Generation Company, LLC Braidwood Station 35100 South Route 53, Suite 84 Braceville, IL 60407-9619
SUBJECT:
BRAIDWOOD STATION, UNITS 1 AND 2 - CLOSURE OF CONFIRMATORY ACTION LETTER (CAL) NRR-07-008 (TAC NO. MD7295)
Dear Mr. Hanson:
On March 22, 2007, the U.S. Nuclear Regulatory Commission (NRC) issued Confirmatory Action Letter (CAL) No. NRR-07-008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML070740294) regarding dissimilar metal welds in the pressurizer at Braidwood Station (Braidwood), Units 1 and 2. This letter acknowledges receipt of your letter dated July 10, 2008 (ADAMS Accession No. ML081920287), informing the NRC staff of actions taken in response to this CAL.
In your letter, you stated that actions and commitments related to CAL NRR-07-008 have been completed for Braidwood, Unit 2, and confirmed actions previously reported by letter dated May 19, 2008 (ADAMS Accession No. ML081400792), regarding the application of structural weld overlays to the pressurizer spray, relief, safety and surge nozzle safe ends for Braidwood, Unit 2, including satisfactory non-destructive examination results. Based on your letters, the NRC staff has found that all the commitments listed in the CAL and supporting commitment letter (ADAMS Accession No. ML070520499) have been met for Braidwood, Unit 2. As such, it is no longer necessary to implement enhanced inspection and leakage monitoring requirements for the reactor coolant system at Braidwood, Unit 2. Technical Assignment Control (TAC)
No. MD7295 has been closed.
Further, by letter dated December 17, 2007 (ADAMS Accession No. ML073390179), the NRC staff acknowledged the completion of the applicable confirmatory action items for Braidwood, Unit 1. Therefore, no further response is required regarding the CAL. We consider the CAL closed for both Braidwood units.
Thank you for informing us of the actions documented in your letter. These actions may be examined during a future NRC inspection of your facility.
Current NRC guidance regarding CALs is contained in the NRC Enforcement Policy and the NRC Enforcement Manual, which are available at the NRC web site at http://www.nrc.gov/about-nrc/regulatory/enforcement.html (click on Enforcement Policy or Enforcement Guidance) or by contacting the Government Printing Office (GPO) toll-free at 1-888-293-6498. The GPO is open from 7:00 a.m. to 9:00 p.m. EST, Monday through Friday (except Federal holidays).
B. Hanson In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRC's "Rules of Practice," a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room or from the NRC=s document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm.html.
Sincerely,
/RA/
Joseph G. Giitter, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-456 and 50-457 cc: See next page
ML082520039 NRR-106 OFFICE DCI/CPNB DCI/CPNB LPL3-2/PM LPL3-2/LA LPL3-2/BC NAME JCollins TChan MDavid THarris RGibbs DATE 9/10/08 9/10/08 9/9/08 9/9/08 9/9/08 OFFICE DCI/D DRP/D RIII DORL/D NAME MEvans CPederson JGiitter DATE 9/10/08 9/11/08 9/16/08 Braidwood Station, Units 1 and 2 cc:
Corporate Distribution Exelon Generation Company, LLC Via e-mail Braidwood Distribution Exelon Generation Company, LLC Via e-mail Mr. Dwain W. Alexander, Project Manager Westinghouse Electric Corporation Via e-mail Ms. Bridget Little Rorem Appleseed Coordinator Via e-mail Howard A. Learner Environmental Law and Policy Center of the Midwest Via e-mail Braidwood Resident Inspector U.S. Nuclear Regulatory Commission Via e-mail Illinois Emergency Management Agency Division of Nuclear Safety Via e-mail Will County Executive Via e-mail Attorney General Springfield, IL Via e-mail Chairman, Ogle County Board Via e-mail Ms. Lorraine Creek RR 1, Box 182 Manteno, IL 60950