| | issue date = 05/25/1995 | | | issue date = 05/25/1995 |
| | title = Application for Amends to Licenses DPR-58 & DPR-74.Amends Would Incorporate Cycle & Burnup Dependent Peaking Factor Penalty | | | title = Application for Amends to Licenses DPR-58 & DPR-74.Amends Would Incorporate Cycle & Burnup Dependent Peaking Factor Penalty |
| | author name = FITZPATRICK E | | | author name = Fitzpatrick E |
| | author affiliation = INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG | | | author affiliation = INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG |
| | addressee name = | | | addressee name = |
Line 14: |
Line 14: |
| | document type = OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING, TEXT-LICENSE APPLICATIONS & PERMITS | | | document type = OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING, TEXT-LICENSE APPLICATIONS & PERMITS |
| | page count = 11 | | | page count = 11 |
| | | project = |
| | | stage = Request |
| }} | | }} |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:~PRIGRITYl~CCELERATED RIDSPl<OCI'.SSIiG) | | {{#Wiki_filter:RIG RITY |
| REGULATORY INFORMATION DISTRIBUTION SYSTEM(RIDS)SACCESSION NBR:9505310313 DOC.DATE:95/05/25NOTARIZED: | | ~PCCELERATED RIDS l~ |
| YESDOCKETFACIL:50-315 DonaldC.CookNuclearPowerPlant,Unit1,IndianaM0500031550-316DonaldC.CookNuclearPowerPlant,Unit2,IndianaM05000316AUTH.NAME~AUTHORAFFILIATXON FITZPATRICK,E.
| | Pl<OCI'.SSIiG) |
| XndianaMichiganPowerCo.(formerly Indiana&MichiganElepRECIP.NAME RECIPIENT AFFILIATION DocumentControlBranch(Document ControlDesk)
| | REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS) |
| | S ACCESSION NBR: 9505310313 DOC. DATE: 95/05/25 NOTARIZED: YES DOCKET FACIL:50-315 Donald C. Cook Nuclear Power Plant, Unit 1, Indiana M 05000315 50-316 Donald C. Cook Nuclear Power Plant, Unit 2, Indiana M 05000316 AUTH. NAME ~ AUTHOR AFFILIATXON FITZPATRICK,E. Xndiana Michigan Power Co. (formerly Indiana & Michigan Ele p RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk) |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| Application foramendstolicensesDPR-58&DPR-74.Amends wouldincorporate cycle&burnupdependent peakingfactorpenalty.DISTRIBUTION CODE:AOOIDCOPIESRECEIVED:LTR jENCL2SIZE:&+/TITLE:ORSubmittal: | | Application for amends to licenses DPR-58 & DPR-74.Amends would incorporate cycle & burnup dependent peaking factor penalty. |
| GeneralDistribution NOTES:0RECIPIENT XDCODE/NAME PD3-1LA7HICKMAN,JXNTE'ENTE01*NRR/DSSA/SRXB OGC/HDS2EXTERNAL:
| | DISTRIBUTION CODE: AOOID TITLE: OR COPIES RECEIVED:LTR Submittal: General Distribution jENCL 2 SIZE: &+/ 0 NOTES: |
| NOACCOPIESLTTRENCL111111111110RECIPIENT IDCODE/NAME PD3-1PDNRR/DE/EMCB NRR/DSSA/SPLB NUDOCS-ABSTRACT NRCPDRCOPIESLTTRENCL1111111111D0UNNOTETOALL"RIDS"RECIPIENTS:
| | RECIPIENT COPIES RECIPIENT COPIES XD CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD3-1 LA 1 1 PD3-1 PD 1 1 7 HICKMAN,J 1 1 XNTE 'ENTE |
| PLEASEIHELPUSTOREDUCEiVKSTE!CONTACTTIIE DOCL'ifEY'I'CONTROL DESK,ROOMPI.37(EXT.564.0083)TOELIXIRl.PATEYOURNAifLITROifDIS'I'RIB U'I'IONLIS'I'SI'ORDOCI.'%lEN'I'SYOI'ON"I'ITl'.D!TOTALNUMBEROFCOPIESREQUIRED:
| | * 01 1 1 NRR/DE/EMCB 1 1 1 1 NRR/DSSA/SPLB 1 1 NRR/DSSA/SRXB 1 1 NUDOCS-ABSTRACT 1 1 OGC/HDS2 1 0 EXTERNAL: NOAC NRC PDR 1 1 D |
| LTTR12ENCL11 0
| | 0 U |
| IndianaMichiganPowerCompanyP.O.Box16631Columbus, OH43216May25,1995AEP;NRC:1071T DocketNos.:50-31550-316U.S.NuclearRegulatory Commission ATTN:DocumentControlDeskWashington, D.C,20555Gentlemen:
| | N NOTE TO ALL"RIDS" RECIPIENTS: |
| DonaldC.CookNuclearPlantUnits1and2TECHNICAL SPECIFICATION 3.2.6CHANGEFqPENALTY,FpsONALLOWABLE POWERLEVELTOBEBURNUPDEPENDENT ANDSPECIFYTHEVALUEINTHECOREOPERATION LIMITREPORTThisletteranditsattachments constitute anapplication foramendment ofthetechnical specifications (T/Ss)forDonaldC.CookNuclearPlantUnits1and2.Specifically, weproposetomodifytheT/Sstoincorporate acycleandburnupdependent peakingfactorpenalty(Fp).SincethevalueofFpwilltypically changeeachfuelcycle,weproposetospecifythevalueofFpintheCoreOperating LimitsReport(COLR).Yourstaff'ssafetyevaluation inNovember1993ofWCAP-10216-P, Rev.1,"Relaxation ofConstantAxialOffsetControl-F<Surveillance Technical Specification,"
| | PLEASE IHELP US TO REDUCE iVKSTE! CONTACTTIIE DOCL'ifEY'I'CONTROL DESK, ROOM PI.37 (EXT. 564.0083 ) TO ELIXIR l.PATE YOUR NAifLITROif DIS'I'RIB U'I'ION LIS'I'S I'OR DOCI.'%l EN'I'S YOI 'ON"I'ITl'.D! |
| foundtheproposedrevisiontotheFosurveillance acceptable.
| | TOTAL NUMBER OF COPIES REQUIRED: LTTR 12 ENCL 11 |
| Ourproposedchangessatisfytherequirements statedinthesafetyevaluation bypenalizing Fointheallowable powerlevelT/S(3.2.6).Attachment 1providesadetaileddescription oftheproposedchanges,justification forthechanges,andourdetermination ofnosignificant hazardsconsideration performed pursuantto10CFR50,92.Attachment 2containstheexistingT/Spagesmarkedtoreflecttheproposedchanges.Attachment 3containstheproposedrevisedT/Spages.Attachment 4containsanexampleofhowtheproposedchangewouldberepresented intheCOLR.
| | |
| fI U.S.NuclearRegulatory Commission Page2AEP:NRC:1071T Webelievethattheproposedchangeswillnotresultin(1)asignificant changeinthetypesofanyeffluentthatmaybereleasedoffsite,or(2)asignificant increaseinindividual orcumulative occupational radiation exposure.
| | 0 Indiana Michigan Power Company P.O. Box 16631 Columbus, OH 43216 May 25, 1995 AEP;NRC:1071T Docket Nos.: 50-315 50-316 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C, 20555 Gentlemen: |
| TheproposedchangeshavebeenreviewedbythePlantNuclearSafetyReviewCommittee andtheNuclearSafetyandDesignReviewCommittee.
| | Donald C. Cook Nuclear Plant Units 1 and 2 TECHNICAL SPECIFICATION 3.2.6 CHANGE Fq PENALTY, Fps ON ALLOWABLE POWER LEVEL TO BE BURNUP DEPENDENT AND SPECIFY THE VALUE IN THE CORE OPERATION LIMIT REPORT This letter and its attachments constitute an application for amendment of the technical specifications (T/Ss) for Donald C. Cook Nuclear Plant Units 1 and 2. Specifically, we propose to modify the T/Ss to incorporate a cycle and burnup dependent peaking factor penalty (Fp). Since the value of Fp will typically change each fuel cycle, we propose to specify the value of Fp in the Core Operating Limits Report (COLR). |
| Incompliance withtherequirements of10CFR50.91(b)(l),
| | Your staff's safety evaluation in November 1993 of WCAP-10216-P, Rev. 1, "Relaxation of Constant Axial Offset Control - F< |
| copiesofthisletteranditsattachments havebeentransmitted totheMichiganPublicServiceCommission andtotheMichiganDepartment ofPublicHealth.Sincerely, p~'.E.Fitzpatrick
| | Surveillance Technical Specification," found the proposed revision to the Fo surveillance acceptable. Our proposed changes satisfy the requirements stated in the safety evaluation by penalizing Fo in the allowable power level T/S (3.2.6). |
| ~VicePresident SWORNTOANDSUBSCRIBED BEFOREMETHIS~~4DAYOF1995NotaryPublicehAttachments CC:A.A.BlindG.CharnoffJ.B.MartinNFEMSectionChiefNRCResidentInspector | | Attachment 1 provides a detailed description of the proposed changes, justification for the changes, and our determination of no significant hazards consideration performed pursuant to 10 CFR 50,92. Attachment 2 contains the existing T/S pages marked to reflect the proposed changes. Attachment 3 contains the proposed revised T/S pages. Attachment 4 contains an example of how the proposed change would be represented in the COLR. |
| -BridgmanJ.R.Padgett | | |
| 'lI'Isaystry~~rlJ~1 ATTACHMENT 1TOAEP:NRC:1071T JUSTIFICATION AND10CFR50.92ANALYSISFORCHANGESTOTHEDONALDC.COOKNUCLEARPLANTUNITS1AND2TECHNICAL SPECIFICATIONS Attachment 1toAEP:NRC:1071T Page1DESCIPTIONOFCHANGESJ1.Units1and2,technical specification (T/S)3.2.6:WhereFzissetequalto1.02,modifytostatethatFpisaburnupdependent penaltyspecified intheCoreOperating LimitsReport(COLR).2.Units1and2,T/S6.9.1.9.2.c: | | f I |
| Updatereference toWCAP-10216-P, June1983,toWCAP-10216-P-A, Revision1A,February1994.3.Units1and2,COLR,Section2.8.3:Specifytheburnupdependent valuesofF>insteadofreferring tothevalueinT/S3.2.6(seeAttachment 4).REASONANDJUSTIFICATION FORCHANGESTheF<andallowable powerlevel(APL)T/Ssurveillances arerequiredevery31effective fullpowerdays(EFPDs).Totakeintoaccountthepossibility thatF<mayincreasebetweenfluxmaps,provisions areprovidedintheT/Sstoaccommodate suchoccurrences.
| | |
| TheT/SsrequirethatF<(Z)/K(Z) becomparedtothepreviousfluxmap,andifitisfoundtoincrease, thenadditional actionmustbetaken.Eithera2percentpenaltyisappliedtoF~,ornopenaltyisapplied,butFomeasurements mustbetakenevery7EFPDsuntiltwosuccessive fluxmapsindicatethatF<(Z)/K(Z) isnotincreasing.
| | U. S. Nuclear Regulatory Commission AEP:NRC:1071T Page 2 We believe that the proposed changes will not result in (1) a significant change in the types of any effluent that may be released offsite, or (2) a significant increase in individual or cumulative occupational radiation exposure. |
| Westinghouse ElectricCorporation (Westinghouse) hasdiscovered caseswherepredicted F<increases morethan2percent,causingthe2percentpenaltytobenon-conservative. | | The proposed changes have been reviewed by the Plant Nuclear Safety Review Committee and the Nuclear Safety and Design Review Committee. |
| Thesecasesaregenerally atbeginning ofcycle(BOC)burnupsandtheeffectstaperoffbeforereachingthepointofleastamountofF<margin.SincetheT/Ssonlyallowfora2percentpenaltytobeapplied,weeklyF<measurements havetobetakenduringtheBOCtoensurethatT/Ssurveillances aresatisfied.
| | In compliance with the requirements of 10 CFR 50.91(b)(l), copies of this letter and its attachments have been transmitted to the Michigan Public Service Commission and to the Michigan Department of Public Health. |
| Westinghouse revisedWCAP-10216-P-A, toaddresspredicted F<increases ofmorethan2percent,whichwasacceptedintheNRCsafetyevaluation datedNovember26,1993.TherevisiontotheWCAPspecifies twooptionsforincorporating changesintheT/Sstoaccommodate Fzofgreaterthan2percent.TheoptionsaretomakeFzburnupdependent andmoveitinCOLR,ortoaddapenaltytotheV(Z)function. | | Sincerely, p~'. |
| Wehavechosentoincorporate theoptionwhichspeci.fies useofaburnupdependent Fpthatwillbespecified intheCOLR.Theburnupdependent FpT/Schangespresented inWCAP-10216-P-A, Rev.1A,addressapplication ofthepenaltyintheFoT/S.CookNuclearPlantT/SsutilizeFpasitisappliedtoF<intheallowable powerlevel(APL)T/Ss.SincetheAPLcalculation isdependent onthevalueofF>,theprotection againstanincreasing F<isidentical tothatintherecommended T/Schangesspecified inWCAP-10216-P-A, Rev.1A.
| | E. Fitzpatrick |
| ~~a Page2Incorporating aburnupdependent F<penaltyintheCOLRwouldallowapplication ofthelargerpenalty,whennecessary, tomaintaina31EFPDsurveillance schedule. | | ~ |
| Therefore, theweeklyF<measurements wouldnotberequiredtosatisfytheT/Ssurveillance requirements. | | Vice President SWORN TO AND SUBSCRIBED BEFORE ME THIS ~~4 DAY OF 1995 Notary Public eh Attachments CC: A. A. Blind G. Charnoff J. B. Martin NFEM Section Chief NRC Resident Inspector - Bridgman J. R. Padgett |
| 10CFR50.92EVALUATION Per10CFR50.92,aproposedamendment.
| | |
| willnotinvolveasignificant hazardsconsideration iftheproposedamendment doesnot:(1)involveasignificant increaseintheprobability orconsequences of'"anaccidentpreviously evaluated, (2)createthepossibility ofanewordifferent kindofaccidentfromanyaccidentpreviously evaluated, or(3)involveasignificant reduction inamarginofsafety.Criterion 1Theproposedchangeswillnotinvolveasignificant increaseintheprobability ofanaccidentpreviously evaluated becausethechangeswillnotresultinachangetoanyoftheprocessvariables thatmightinitiateanaccident.
| | 'l says I try |
| Therearenophysicalchangestotheplantassociated withthisT/Schange.Theconsequences ofanaccidentpreviously evaluated willnotbeincreased becausethechangesincreasethepenaltyappliedtoF<whenitismeasuredtobeincreasing.
| | 'I l ~~r J~ |
| F<andallowable powerlevel(APL)T/Ssurveillance requirements arenotbeingchanged.Furthermore, allowingacycleandburnupdependent F<penaltytobelocatedintheCOLRwasacceptedbytheNRCin,asafetyevaluation onWCAP-10216-P, Rev.1.CRITERION 2Theproposedchangeswillnotcreatethepossibility ofanewordifferent kindofaccidentfromanyaccidentpreviously evaluated becausethechangeswillinvolvenophysicalchangestotheplantnoranychangesinplantoperations. | | 1 |
| Furthermore, theF<andAPLT/Ssurveillance requirements arenotbeingchanged,andthechangetotheF<penaltyisconservative. | | |
| CRITERION 3Theproposedamendment willnotinvolveasignificant reduction inamarginofsafety.Whentheincreased F<penaltyisapplied,itreducestheallowable powerlevel,thusincreasing themarginofsafety. | | ATTACHMENT 1 TO AEP:NRC:1071T JUSTIFICATION AND 10 CFR 50.92 ANALYSIS FOR CHANGES TO THE DONALD C. COOK NUCLEAR PLANT UNITS 1 AND 2 TECHNICAL SPECIFICATIONS to AEP:NRC:1071T Page 1 DESC IPTION OF CHANGES J |
| ATTACHMENT 2TOAEP:NRC:1071T EXISTINGTECHNICAL SPECIFICATION PAGESMARKEDTOREFLECTPROPOSEDCHANGES}} | | : 1. Units 1 and 2, technical specification (T/S) 3.2.6: |
| | Where Fz is set equal to 1.02, modify to state that Fp is a burnup dependent penalty specified in the Core Operating Limits Report (COLR). |
| | : 2. Units 1 and 2, T/S 6.9.1.9.2.c: |
| | Update reference to WCAP-10216-P, June 1983, to WCAP-10216-P-A, Revision 1A, February 1994. |
| | : 3. Units 1 and 2, COLR, Section 2.8.3: |
| | Specify the burnup dependent values of F> instead of referring to the value in T/S 3.2.6 (see Attachment 4). |
| | REASON AND JUSTIFICATION FOR CHANGES The F< and allowable power level (APL) T/S surveillances are required every 31 effective full power days (EFPDs). To take into account the possibility that F< may increase between flux maps, provisions are provided in the T/Ss to accommodate such occurrences. The T/Ss require that F<(Z)/K(Z) be compared to the previous flux map, and increase, then additional action must be taken. |
| | if it is found to Either a 2 percent penalty is applied to F~, or no penalty is applied, but Fo measurements must be taken every 7 EFPDs until two successive flux maps indicate that F<(Z)/K(Z) is not increasing. |
| | Westinghouse Electric Corporation (Westinghouse) has discovered cases where predicted F< increases more than 2 percent, causing the 2 percent penalty to be non-conservative. These cases are generally at beginning of cycle (BOC) burnups and the effects taper off before reaching the point of least amount of F< margin. Since the T/Ss only allow for a 2 percent penalty to be applied, weekly F< measurements have to be taken during the BOC to ensure that T/S surveillances are satisfied. |
| | Westinghouse revised WCAP-10216-P-A, to address predicted F< increases of more than 2 percent, which was accepted in the NRC safety evaluation dated November 26, 1993. The revision to the WCAP specifies two options for incorporating changes in the T/Ss to accommodate Fz of greater than 2 percent. The options are to make Fz burnup dependent and move it in COLR, or to add a penalty to the V(Z) function. We have chosen to incorporate the option which speci.fies use of a burnup dependent Fp that will be specified in the COLR. |
| | The burnup dependent Fp T/S changes presented in WCAP-10216-P-A, Rev. 1A, address application of the penalty in the Fo T/S. Cook Nuclear Plant T/Ss utilize Fp as it is applied to F< in the allowable power level (APL) T/Ss. |
| | Since the APL calculation is dependent on the value of F>, the protection against an increasing F< is identical to that in the recommended T/S changes specified in WCAP-10216-P-A, Rev. 1A. |
| | |
| | ~ ~ a Page 2 Incorporating a burnup dependent F< penalty in the COLR would allow application of the larger penalty, when necessary, to maintain a 31 EFPD surveillance schedule. Therefore, the weekly F< measurements would not be required to satisfy the T/S surveillance requirements. |
| | 10 CFR 50.92 EVALUATION Per 10 CFR 50.92, a proposed amendment. will not involve a significant hazards consideration if the proposed amendment does not: |
| | (1) involve a significant increase in the probability or consequences of |
| | '"an accident previously evaluated, (2) create the possibility of a new or different kind of accident from any accident previously evaluated, or (3) involve a significant reduction in a margin of safety. |
| | Criterion 1 The proposed changes will not involve a significant increase in the probability of an accident previously evaluated because the changes will not result in a change to any of the process variables that might initiate an accident. There are no physical changes to the plant associated with this T/S change. The consequences of an accident previously evaluated will not be increased because the changes increase the penalty applied to F< when it is measured to be increasing. F< and allowable power level (APL) T/S surveillance requirements are not being changed. Furthermore, allowing a cycle and burnup dependent F< penalty to be located in the COLR was accepted by the NRC in, a safety evaluation on WCAP-10216-P, Rev. 1. |
| | CRITERION 2 The proposed changes will not create the possibility of a new or different kind of accident from any accident previously evaluated because the changes will involve no physical changes to the plant nor any changes in plant operations. Furthermore, the F< and APL T/S surveillance requirements are not being changed, and the change to the F< penalty is conservative. |
| | CRITERION 3 The proposed amendment will not involve a significant reduction in a margin of safety. When the increased F< penalty is applied, it reduces the allowable power level, thus increasing the margin of safety. |
| | |
| | ATTACHMENT 2 TO AEP:NRC:1071T EXISTING TECHNICAL SPECIFICATION PAGES MARKED TO REFLECT PROPOSED CHANGES}} |
Similar Documents at Cook |
---|
Category:OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING
MONTHYEARML17335A5551999-10-12012 October 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising TS Surveillance Requirement 4.6.2.2.d for Spray Additive Sys to Relocate Details Associated with Acceptance Criteria & Test Parameters to Associated TS Bases ML17335A5591999-10-11011 October 1999 Supplement to Application for Amends to Licenses DPR-58 & DPR-74,replacing Correct TS Pages Inadvertently Included in 990923 Submittal.Attached Pages Also Include Appropriate Administrative Changes ML17335A5411999-10-0101 October 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising Containment Recirculation Sump Water Inventory.Calculation & non-proprietary WCAP-15302 Rept Also Encl ML17326A1571999-09-23023 September 1999 Application for Amends to Licenses DPR-58 & DPR-74,involving Movement of Loads in Excess of Design Basis Seismic Capability of Auxiliary Bldg Load Handling Equipment & Structures ML17326A1421999-09-17017 September 1999 Application for Amends to Licenses DPR-58 & DPR-74,to Allow Credit of Rod Cluster Control Assemblies for Cold Leg Large Break LOCA Subcriticality.Ts Pages & non-proprietary Versions of WCAP-15246 Encl.Proprietary Version Withheld ML17326A1161999-09-10010 September 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising TS Surveillance Requirement 4.4.7,TS Tables 4.4-3,3.4-1 & TS Surveillance Requirement 4.11.2.2 Re RCS & Gas Storage Tank Sampling ML17326A0921999-08-17017 August 1999 Application for Amend to License DPR-58,to Change TS 3/4.4.5 & Bases for TS 3/4.4.5,3/4.4.6.2 & 3/4.4.8 to Remove voltage-based Repair Criteria,F* Repair Criteria & Sleeving Methodologies from Unit 1 TS & Clarify Bases Sections ML17325B6041999-05-21021 May 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising Limitations of Positive Reactivity Additions in Several TS Action Statements ML17325B5511999-04-19019 April 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 3/4.8.1.2, Electrical Power Systems & Associated Bases to Provide one-time Extension of 18-month Surveillance Interval for Specific SRs ML17335A3661998-12-0303 December 1998 Application for Amends to Licenses DPR-58 & DPR-74,adding TS for Distributed Ignition Sys ML17335A3631998-12-0303 December 1998 Application for Amend to License DPR-58,revising TS 3/4.7.7, Sealed Source Contamination & Associated Bases to Address Testing Requirements for Fission Detectors ML17335A3591998-12-0303 December 1998 Application for Amends to Licenses DPR-58 & DPR-74,making Administrative Changes to Remove Obsolete Info,To Provide Consistency Between Units 1 & 2,to Provide Consistency with Std Tech Specs,To Provide Clarification & to Correct Typos ML17335A3561998-12-0303 December 1998 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 4.6.5.1, Ice Condenser,Ice Bed & Associated Bases to Reflect Max Ice Condenser Flow Channel Blockage Assumed in Accident Analyses ML17335A2631998-10-0808 October 1998 Application for Amends to Licenses DPR-58 & DPR-74,revising TS Containment Sys Bases 3/4.6.1.4 Re Internal Pressure & 3/4.6.1.5 Re Air Temp ML17335A2761998-10-0808 October 1998 Application for Amends to Licenses DPR-58 & DPR-74,placing Tighter Restrictions on Amount of Time RWST Water Level Instrumentation Can Be Out of Svc Before Compensatory Actions Are Required ML17335A2671998-10-0808 October 1998 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 3.4.1.3, RCS - Shutdown & Associated Bases to Provide Separate Requirements for Modes 4 & 5 with Loops Filled & Mode 5 with Loops Not Filled ML17335A2311998-09-14014 September 1998 Application for Amends to Licenses DPR-58 & DPR-74,changing Runout Limits for Safety Injection Pump to 675 Gpm Unless Pump Is Specifically Tested to Higher Flow Rate Not Exceeding 700 Gpm ML17335A1901998-08-28028 August 1998 Application for Amend to License DPR-58,requesting Extension of SG Surveillance,Which TSs Require to Be Performed on or Before 990408,until End of Current Refuel Cycle Currently Scheduled for Mar 2000.W/assessment of SG Degradation & TSs ML17334A7471998-06-10010 June 1998 Application for Amends to Licenses DPR-54 & DPR-78,changing Implementation Date to Reduce Boric Acid Concentration in Boric Acid Storage Sys.Attachment 1 to Ltr Contains Description of Proposed Change & Justification for Change ML17334B7011998-03-0303 March 1998 Application for Amends to TS for Licenses DPR-58 & DPR-74, Removing Word Immediately from Unit 1 Hydrogen Recombiner Surveillance Requirement 4.6.4.2.b.4 & Revising Plants TS 3/4.6.4 Bases ML17334B6561997-10-0808 October 1997 Application for Amends to Licenses DPR-58 & DPR-78,changing TSs 3/4.6.5 & 3/4.5.5 to Increase Both Minimum Required Ice Mass Per Ice Basket & Total Minimum Required Ice Mass. Proprietary Summary of Sump Inventory Calculations,Encl ML17333B0431997-09-19019 September 1997 Application for Amends to Licenses DPR-58 & DPR-74,deleting Requirement for Automatic Valve Closure Feature on RHR Sys Suction from RCS ML17333A9831997-08-11011 August 1997 Application for Amends to Licenses DPR-58 & DPR-74,allowing Filling of ECCS Accumulators W/O Declaring ECCS Equipment Inoperable ML17335A2101997-08-0101 August 1997 Application for Amends to Licenses DPR-58 & DPR-74,deleting Wording When Secondary Steam Supply Pressure Is Greater than 310 Psig from TS ML17333A8281997-03-26026 March 1997 Application for Amends to Licenses DPR-58 & DPR-74, Modifying TS 4.7.5.1.e.2 Which Describes Control Room Ventilation Sys Autostart Functions ML17333A8311997-03-26026 March 1997 Application for Amends to Licenses DPR-58 & DPR-74,changing Grammatical Correction to Wording of Unit 2 TS 3.4.8,Action a for Modes 1,2 & 3 & Returning Frequency Requirement to TS 4.7.1.2.c & 4.7.1.2.d That Was Inadvertently Deleted ML17333A7121996-12-20020 December 1996 Application for Amends to Licenses DPR-58 & DPR-74, Requesting Rev of Reactor Coolant Pump Flywheel Insp Frequency ML17334B5941996-07-11011 July 1996 Application for Amends to Licenses DPR-58 & DPR-74,revising TS to Support Operation of Unit 2 at Increased Core Rated Thermal Power of 3,588 Mwt.Rev 1 to WCAP-14489, ...Unit 2 3,600 Mwt Uprating Program Licensing Rept Encl ML17334B5901996-06-19019 June 1996 Application for Amend to License DPR-58,addressing Applicable Requirements of NRC GL 95-05, Voltage-Based Repair Criteria for Repair of Westinghouse SG Tubes Affected by Outside Diameter Stress Corrosion Cracking. ML17334B5891996-06-11011 June 1996 Application for Amends to Licenses DPR-58 & DPR-74,removing TSs Certain Requirements for Administrative Controls,Related to QA Requirements,Per Administrative Ltr 96-05 ML17333A4201996-04-0808 April 1996 Application for Amends to Licenses DPR-58 & DPR-74,moving TS 4.0.4 Exemption Statement for MSSVs Into Section 4.7.1.1 ML17333A3551996-03-12012 March 1996 Application for Amend to License DPR-74,removing TSs Re Shutdown & Control Rod Position Indication While in Modes 3, 4 & 5 ML17334B5751996-02-29029 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,revising TS to Reduce Boric Acid Concentration in Boric Acid Storage Sys from Approx 12 Percent to Approx 4 Percent by Weight. Technical Rept Presenting Justificaion for Changes Encl ML17334B5741996-02-26026 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS 5.6.2 to Increase Current Limit on Nominal Fuel Assembly Enrichment for New,Westinghouse - Fabricated Fuel Stored in New Fuel Storage Racks ML17333A3201996-02-22022 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,proposing to Remove Requirement That Operations Superintendent Must Hold or Have Held Sol at Plant or Similar Reactor ML17333A3151996-02-22022 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,modifying Table 4.8-1,DG Test Schedule by Ref Rg 1.9,Rev 3 Rather than Rg 1.108,Rev 1 Criteria for Determination of Valid DG Test ML17333A2641996-01-12012 January 1996 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS Section 4.4.11 to Eliminate SR Demonstrating Operability of Emergency Power Supply for Pressurizer PORVs & Block Valves ML17333A2391995-12-19019 December 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS 3/4.6.1.2,3/4.6.1.3,3/4.6.1.6 & 3/4.6.1.6 to Require Types A,B & C Tests (Overall Integrated & Local Containment Leakage Rate) to Be Performed Per 10CFR50,App J Option B ML17332B0111995-11-10010 November 1995 Application for Amends to Licenses DPR-58 & DPR-74,revising Ts,By Modifying Surveillance Testing of EDG During Refueling & Normal Operations ML17332A9971995-10-20020 October 1995 Application for Amends to Licenses DPR-58 & DPR-74,proposing to Add Exemption to TS 4.0.4 in Surveillance Requirements for MSIV ML17332A9111995-08-0606 August 1995 Application for Amends to Licenses DPR-58 & DPR-74,informing That Licensee Has 45 Days from Date of Issuance to Implement Amend Unless Otherwise Specified ML17334B5561995-08-0404 August 1995 Application for Exigent Amend to License DPR-58,modifying TS 4.4.5.4 & 4.4.5.5 for Repair of Hybrid Expansion Joint Sleeved SG Tubes.Proprietary W Rept WCAP-14446, Repair...Of Hybrid Expansion Joint...Tubes Encl.W Rept Withheld ML17332A8271995-06-30030 June 1995 Application for Amends to Licenses DPR-58 & DPR-74,changing TS Section 5.3.1 to Allow Fuel Reconstitution,Per GL 90-02, Suppl 1 ML17334B5501995-06-20020 June 1995 License Amend Request to Licenses DPR-58 & DPR-74,to Remove Requirements for Fire Protection Systems from Licenses & Guidance in GL 86-10,GL 88-12 & GL 93-07 ML17332A7991995-06-15015 June 1995 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 4.8.1.1.2.e.7 to Reduce Duration of Surveillance Testing for EDGs During Refueling Operations from 24 H to 8 H ML17334B5481995-05-26026 May 1995 Application for Amends to Licenses DPR-58 & DPR-74.Amends Would Support Operation of Unit 1 at SG Tube Plugging Levels Up to 30%,make One Unit 1 TS More Nearly Like Corresponding Unit 2 TS & Maintain Consistency of Unit 2 Criteria ML17334B5461995-05-26026 May 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying Tech Specs 3/4.3.1 (Reactor Trip Sys Instrumentation) & 3/4.3.2 (ESFAS Instrumentation) & Bases to Relocate Tables of Response Time Limits to Ufsar,Per GL 93-08 ML17332A7661995-05-25025 May 1995 Application for Amends to Licenses DPR-58 & DPR-74.Amends Would Incorporate Cycle & Burnup Dependent Peaking Factor Penalty ML17332A7741995-05-25025 May 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS 5.3.1 to Allow Fuel Reconstitution,Per GL 90-02,Suppl 1 ML17332A7771995-05-25025 May 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS Table 4.3-2 to Change Main Steam Line Isolation Valve Manual Actuation Sys Surveillance Frequency from Monthly to Quarterly 1999-09-23
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML17335A5551999-10-12012 October 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising TS Surveillance Requirement 4.6.2.2.d for Spray Additive Sys to Relocate Details Associated with Acceptance Criteria & Test Parameters to Associated TS Bases ML17335A5591999-10-11011 October 1999 Supplement to Application for Amends to Licenses DPR-58 & DPR-74,replacing Correct TS Pages Inadvertently Included in 990923 Submittal.Attached Pages Also Include Appropriate Administrative Changes ML17335A5411999-10-0101 October 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising Containment Recirculation Sump Water Inventory.Calculation & non-proprietary WCAP-15302 Rept Also Encl ML17326A1571999-09-23023 September 1999 Application for Amends to Licenses DPR-58 & DPR-74,involving Movement of Loads in Excess of Design Basis Seismic Capability of Auxiliary Bldg Load Handling Equipment & Structures ML17326A1421999-09-17017 September 1999 Application for Amends to Licenses DPR-58 & DPR-74,to Allow Credit of Rod Cluster Control Assemblies for Cold Leg Large Break LOCA Subcriticality.Ts Pages & non-proprietary Versions of WCAP-15246 Encl.Proprietary Version Withheld ML17326A1161999-09-10010 September 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising TS Surveillance Requirement 4.4.7,TS Tables 4.4-3,3.4-1 & TS Surveillance Requirement 4.11.2.2 Re RCS & Gas Storage Tank Sampling ML17326A0921999-08-17017 August 1999 Application for Amend to License DPR-58,to Change TS 3/4.4.5 & Bases for TS 3/4.4.5,3/4.4.6.2 & 3/4.4.8 to Remove voltage-based Repair Criteria,F* Repair Criteria & Sleeving Methodologies from Unit 1 TS & Clarify Bases Sections ML17325B6041999-05-21021 May 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising Limitations of Positive Reactivity Additions in Several TS Action Statements ML17325B5511999-04-19019 April 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 3/4.8.1.2, Electrical Power Systems & Associated Bases to Provide one-time Extension of 18-month Surveillance Interval for Specific SRs ML17335A3661998-12-0303 December 1998 Application for Amends to Licenses DPR-58 & DPR-74,adding TS for Distributed Ignition Sys ML17335A3631998-12-0303 December 1998 Application for Amend to License DPR-58,revising TS 3/4.7.7, Sealed Source Contamination & Associated Bases to Address Testing Requirements for Fission Detectors ML17335A3591998-12-0303 December 1998 Application for Amends to Licenses DPR-58 & DPR-74,making Administrative Changes to Remove Obsolete Info,To Provide Consistency Between Units 1 & 2,to Provide Consistency with Std Tech Specs,To Provide Clarification & to Correct Typos ML17335A3561998-12-0303 December 1998 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 4.6.5.1, Ice Condenser,Ice Bed & Associated Bases to Reflect Max Ice Condenser Flow Channel Blockage Assumed in Accident Analyses ML17335A2631998-10-0808 October 1998 Application for Amends to Licenses DPR-58 & DPR-74,revising TS Containment Sys Bases 3/4.6.1.4 Re Internal Pressure & 3/4.6.1.5 Re Air Temp ML17335A2761998-10-0808 October 1998 Application for Amends to Licenses DPR-58 & DPR-74,placing Tighter Restrictions on Amount of Time RWST Water Level Instrumentation Can Be Out of Svc Before Compensatory Actions Are Required ML17335A2671998-10-0808 October 1998 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 3.4.1.3, RCS - Shutdown & Associated Bases to Provide Separate Requirements for Modes 4 & 5 with Loops Filled & Mode 5 with Loops Not Filled ML17335A2311998-09-14014 September 1998 Application for Amends to Licenses DPR-58 & DPR-74,changing Runout Limits for Safety Injection Pump to 675 Gpm Unless Pump Is Specifically Tested to Higher Flow Rate Not Exceeding 700 Gpm ML17335A1901998-08-28028 August 1998 Application for Amend to License DPR-58,requesting Extension of SG Surveillance,Which TSs Require to Be Performed on or Before 990408,until End of Current Refuel Cycle Currently Scheduled for Mar 2000.W/assessment of SG Degradation & TSs ML17334A7471998-06-10010 June 1998 Application for Amends to Licenses DPR-54 & DPR-78,changing Implementation Date to Reduce Boric Acid Concentration in Boric Acid Storage Sys.Attachment 1 to Ltr Contains Description of Proposed Change & Justification for Change ML17334B7011998-03-0303 March 1998 Application for Amends to TS for Licenses DPR-58 & DPR-74, Removing Word Immediately from Unit 1 Hydrogen Recombiner Surveillance Requirement 4.6.4.2.b.4 & Revising Plants TS 3/4.6.4 Bases ML17334B6561997-10-0808 October 1997 Application for Amends to Licenses DPR-58 & DPR-78,changing TSs 3/4.6.5 & 3/4.5.5 to Increase Both Minimum Required Ice Mass Per Ice Basket & Total Minimum Required Ice Mass. Proprietary Summary of Sump Inventory Calculations,Encl ML17333B0431997-09-19019 September 1997 Application for Amends to Licenses DPR-58 & DPR-74,deleting Requirement for Automatic Valve Closure Feature on RHR Sys Suction from RCS ML17333A9831997-08-11011 August 1997 Application for Amends to Licenses DPR-58 & DPR-74,allowing Filling of ECCS Accumulators W/O Declaring ECCS Equipment Inoperable ML17335A2101997-08-0101 August 1997 Application for Amends to Licenses DPR-58 & DPR-74,deleting Wording When Secondary Steam Supply Pressure Is Greater than 310 Psig from TS ML17333A8281997-03-26026 March 1997 Application for Amends to Licenses DPR-58 & DPR-74, Modifying TS 4.7.5.1.e.2 Which Describes Control Room Ventilation Sys Autostart Functions ML17333A8311997-03-26026 March 1997 Application for Amends to Licenses DPR-58 & DPR-74,changing Grammatical Correction to Wording of Unit 2 TS 3.4.8,Action a for Modes 1,2 & 3 & Returning Frequency Requirement to TS 4.7.1.2.c & 4.7.1.2.d That Was Inadvertently Deleted ML17333A7121996-12-20020 December 1996 Application for Amends to Licenses DPR-58 & DPR-74, Requesting Rev of Reactor Coolant Pump Flywheel Insp Frequency ML17334B5941996-07-11011 July 1996 Application for Amends to Licenses DPR-58 & DPR-74,revising TS to Support Operation of Unit 2 at Increased Core Rated Thermal Power of 3,588 Mwt.Rev 1 to WCAP-14489, ...Unit 2 3,600 Mwt Uprating Program Licensing Rept Encl ML17334B5901996-06-19019 June 1996 Application for Amend to License DPR-58,addressing Applicable Requirements of NRC GL 95-05, Voltage-Based Repair Criteria for Repair of Westinghouse SG Tubes Affected by Outside Diameter Stress Corrosion Cracking. ML17334B5891996-06-11011 June 1996 Application for Amends to Licenses DPR-58 & DPR-74,removing TSs Certain Requirements for Administrative Controls,Related to QA Requirements,Per Administrative Ltr 96-05 ML17333A4201996-04-0808 April 1996 Application for Amends to Licenses DPR-58 & DPR-74,moving TS 4.0.4 Exemption Statement for MSSVs Into Section 4.7.1.1 ML17333A3551996-03-12012 March 1996 Application for Amend to License DPR-74,removing TSs Re Shutdown & Control Rod Position Indication While in Modes 3, 4 & 5 ML17334B5751996-02-29029 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,revising TS to Reduce Boric Acid Concentration in Boric Acid Storage Sys from Approx 12 Percent to Approx 4 Percent by Weight. Technical Rept Presenting Justificaion for Changes Encl ML17334B5741996-02-26026 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS 5.6.2 to Increase Current Limit on Nominal Fuel Assembly Enrichment for New,Westinghouse - Fabricated Fuel Stored in New Fuel Storage Racks ML17333A3201996-02-22022 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,proposing to Remove Requirement That Operations Superintendent Must Hold or Have Held Sol at Plant or Similar Reactor ML17333A3151996-02-22022 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,modifying Table 4.8-1,DG Test Schedule by Ref Rg 1.9,Rev 3 Rather than Rg 1.108,Rev 1 Criteria for Determination of Valid DG Test ML17333A2641996-01-12012 January 1996 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS Section 4.4.11 to Eliminate SR Demonstrating Operability of Emergency Power Supply for Pressurizer PORVs & Block Valves ML17333A2391995-12-19019 December 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS 3/4.6.1.2,3/4.6.1.3,3/4.6.1.6 & 3/4.6.1.6 to Require Types A,B & C Tests (Overall Integrated & Local Containment Leakage Rate) to Be Performed Per 10CFR50,App J Option B ML17332B0111995-11-10010 November 1995 Application for Amends to Licenses DPR-58 & DPR-74,revising Ts,By Modifying Surveillance Testing of EDG During Refueling & Normal Operations ML17332A9971995-10-20020 October 1995 Application for Amends to Licenses DPR-58 & DPR-74,proposing to Add Exemption to TS 4.0.4 in Surveillance Requirements for MSIV ML17332A9111995-08-0606 August 1995 Application for Amends to Licenses DPR-58 & DPR-74,informing That Licensee Has 45 Days from Date of Issuance to Implement Amend Unless Otherwise Specified ML17334B5561995-08-0404 August 1995 Application for Exigent Amend to License DPR-58,modifying TS 4.4.5.4 & 4.4.5.5 for Repair of Hybrid Expansion Joint Sleeved SG Tubes.Proprietary W Rept WCAP-14446, Repair...Of Hybrid Expansion Joint...Tubes Encl.W Rept Withheld ML17332A8271995-06-30030 June 1995 Application for Amends to Licenses DPR-58 & DPR-74,changing TS Section 5.3.1 to Allow Fuel Reconstitution,Per GL 90-02, Suppl 1 ML17334B5501995-06-20020 June 1995 License Amend Request to Licenses DPR-58 & DPR-74,to Remove Requirements for Fire Protection Systems from Licenses & Guidance in GL 86-10,GL 88-12 & GL 93-07 ML17332A7991995-06-15015 June 1995 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 4.8.1.1.2.e.7 to Reduce Duration of Surveillance Testing for EDGs During Refueling Operations from 24 H to 8 H ML17334B5481995-05-26026 May 1995 Application for Amends to Licenses DPR-58 & DPR-74.Amends Would Support Operation of Unit 1 at SG Tube Plugging Levels Up to 30%,make One Unit 1 TS More Nearly Like Corresponding Unit 2 TS & Maintain Consistency of Unit 2 Criteria ML17334B5461995-05-26026 May 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying Tech Specs 3/4.3.1 (Reactor Trip Sys Instrumentation) & 3/4.3.2 (ESFAS Instrumentation) & Bases to Relocate Tables of Response Time Limits to Ufsar,Per GL 93-08 ML17332A7661995-05-25025 May 1995 Application for Amends to Licenses DPR-58 & DPR-74.Amends Would Incorporate Cycle & Burnup Dependent Peaking Factor Penalty ML17332A7741995-05-25025 May 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS 5.3.1 to Allow Fuel Reconstitution,Per GL 90-02,Suppl 1 ML17332A7771995-05-25025 May 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS Table 4.3-2 to Change Main Steam Line Isolation Valve Manual Actuation Sys Surveillance Frequency from Monthly to Quarterly 1999-09-23
[Table view] |
Text
RIG RITY
~PCCELERATED RIDS l~
Pl<OCI'.SSIiG)
REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
S ACCESSION NBR: 9505310313 DOC. DATE: 95/05/25 NOTARIZED: YES DOCKET FACIL:50-315 Donald C. Cook Nuclear Power Plant, Unit 1, Indiana M 05000315 50-316 Donald C. Cook Nuclear Power Plant, Unit 2, Indiana M 05000316 AUTH. NAME ~ AUTHOR AFFILIATXON FITZPATRICK,E. Xndiana Michigan Power Co. (formerly Indiana & Michigan Ele p RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)
SUBJECT:
Application for amends to licenses DPR-58 & DPR-74.Amends would incorporate cycle & burnup dependent peaking factor penalty.
DISTRIBUTION CODE: AOOID TITLE: OR COPIES RECEIVED:LTR Submittal: General Distribution jENCL 2 SIZE: &+/ 0 NOTES:
RECIPIENT COPIES RECIPIENT COPIES XD CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD3-1 LA 1 1 PD3-1 PD 1 1 7 HICKMAN,J 1 1 XNTE 'ENTE
- 01 1 1 NRR/DE/EMCB 1 1 1 1 NRR/DSSA/SPLB 1 1 NRR/DSSA/SRXB 1 1 NUDOCS-ABSTRACT 1 1 OGC/HDS2 1 0 EXTERNAL: NOAC NRC PDR 1 1 D
0 U
N NOTE TO ALL"RIDS" RECIPIENTS:
PLEASE IHELP US TO REDUCE iVKSTE! CONTACTTIIE DOCL'ifEY'I'CONTROL DESK, ROOM PI.37 (EXT. 564.0083 ) TO ELIXIR l.PATE YOUR NAifLITROif DIS'I'RIB U'I'ION LIS'I'S I'OR DOCI.'%l EN'I'S YOI 'ON"I'ITl'.D!
TOTAL NUMBER OF COPIES REQUIRED: LTTR 12 ENCL 11
0 Indiana Michigan Power Company P.O. Box 16631 Columbus, OH 43216 May 25, 1995 AEP;NRC:1071T Docket Nos.: 50-315 50-316 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C, 20555 Gentlemen:
Donald C. Cook Nuclear Plant Units 1 and 2 TECHNICAL SPECIFICATION 3.2.6 CHANGE Fq PENALTY, Fps ON ALLOWABLE POWER LEVEL TO BE BURNUP DEPENDENT AND SPECIFY THE VALUE IN THE CORE OPERATION LIMIT REPORT This letter and its attachments constitute an application for amendment of the technical specifications (T/Ss) for Donald C. Cook Nuclear Plant Units 1 and 2. Specifically, we propose to modify the T/Ss to incorporate a cycle and burnup dependent peaking factor penalty (Fp). Since the value of Fp will typically change each fuel cycle, we propose to specify the value of Fp in the Core Operating Limits Report (COLR).
Your staff's safety evaluation in November 1993 of WCAP-10216-P, Rev. 1, "Relaxation of Constant Axial Offset Control - F<
Surveillance Technical Specification," found the proposed revision to the Fo surveillance acceptable. Our proposed changes satisfy the requirements stated in the safety evaluation by penalizing Fo in the allowable power level T/S (3.2.6).
Attachment 1 provides a detailed description of the proposed changes, justification for the changes, and our determination of no significant hazards consideration performed pursuant to 10 CFR 50,92. Attachment 2 contains the existing T/S pages marked to reflect the proposed changes. Attachment 3 contains the proposed revised T/S pages. Attachment 4 contains an example of how the proposed change would be represented in the COLR.
f I
U. S. Nuclear Regulatory Commission AEP:NRC:1071T Page 2 We believe that the proposed changes will not result in (1) a significant change in the types of any effluent that may be released offsite, or (2) a significant increase in individual or cumulative occupational radiation exposure.
The proposed changes have been reviewed by the Plant Nuclear Safety Review Committee and the Nuclear Safety and Design Review Committee.
In compliance with the requirements of 10 CFR 50.91(b)(l), copies of this letter and its attachments have been transmitted to the Michigan Public Service Commission and to the Michigan Department of Public Health.
Sincerely, p~'.
E. Fitzpatrick
~
Vice President SWORN TO AND SUBSCRIBED BEFORE ME THIS ~~4 DAY OF 1995 Notary Public eh Attachments CC: A. A. Blind G. Charnoff J. B. Martin NFEM Section Chief NRC Resident Inspector - Bridgman J. R. Padgett
'l says I try
'I l ~~r J~
1
ATTACHMENT 1 TO AEP:NRC:1071T JUSTIFICATION AND 10 CFR 50.92 ANALYSIS FOR CHANGES TO THE DONALD C. COOK NUCLEAR PLANT UNITS 1 AND 2 TECHNICAL SPECIFICATIONS to AEP:NRC:1071T Page 1 DESC IPTION OF CHANGES J
- 1. Units 1 and 2, technical specification (T/S) 3.2.6:
Where Fz is set equal to 1.02, modify to state that Fp is a burnup dependent penalty specified in the Core Operating Limits Report (COLR).
- 2. Units 1 and 2, T/S 6.9.1.9.2.c:
Update reference to WCAP-10216-P, June 1983, to WCAP-10216-P-A, Revision 1A, February 1994.
- 3. Units 1 and 2, COLR, Section 2.8.3:
Specify the burnup dependent values of F> instead of referring to the value in T/S 3.2.6 (see Attachment 4).
REASON AND JUSTIFICATION FOR CHANGES The F< and allowable power level (APL) T/S surveillances are required every 31 effective full power days (EFPDs). To take into account the possibility that F< may increase between flux maps, provisions are provided in the T/Ss to accommodate such occurrences. The T/Ss require that F<(Z)/K(Z) be compared to the previous flux map, and increase, then additional action must be taken.
if it is found to Either a 2 percent penalty is applied to F~, or no penalty is applied, but Fo measurements must be taken every 7 EFPDs until two successive flux maps indicate that F<(Z)/K(Z) is not increasing.
Westinghouse Electric Corporation (Westinghouse) has discovered cases where predicted F< increases more than 2 percent, causing the 2 percent penalty to be non-conservative. These cases are generally at beginning of cycle (BOC) burnups and the effects taper off before reaching the point of least amount of F< margin. Since the T/Ss only allow for a 2 percent penalty to be applied, weekly F< measurements have to be taken during the BOC to ensure that T/S surveillances are satisfied.
Westinghouse revised WCAP-10216-P-A, to address predicted F< increases of more than 2 percent, which was accepted in the NRC safety evaluation dated November 26, 1993. The revision to the WCAP specifies two options for incorporating changes in the T/Ss to accommodate Fz of greater than 2 percent. The options are to make Fz burnup dependent and move it in COLR, or to add a penalty to the V(Z) function. We have chosen to incorporate the option which speci.fies use of a burnup dependent Fp that will be specified in the COLR.
The burnup dependent Fp T/S changes presented in WCAP-10216-P-A, Rev. 1A, address application of the penalty in the Fo T/S. Cook Nuclear Plant T/Ss utilize Fp as it is applied to F< in the allowable power level (APL) T/Ss.
Since the APL calculation is dependent on the value of F>, the protection against an increasing F< is identical to that in the recommended T/S changes specified in WCAP-10216-P-A, Rev. 1A.
~ ~ a Page 2 Incorporating a burnup dependent F< penalty in the COLR would allow application of the larger penalty, when necessary, to maintain a 31 EFPD surveillance schedule. Therefore, the weekly F< measurements would not be required to satisfy the T/S surveillance requirements.
10 CFR 50.92 EVALUATION Per 10 CFR 50.92, a proposed amendment. will not involve a significant hazards consideration if the proposed amendment does not:
(1) involve a significant increase in the probability or consequences of
'"an accident previously evaluated, (2) create the possibility of a new or different kind of accident from any accident previously evaluated, or (3) involve a significant reduction in a margin of safety.
Criterion 1 The proposed changes will not involve a significant increase in the probability of an accident previously evaluated because the changes will not result in a change to any of the process variables that might initiate an accident. There are no physical changes to the plant associated with this T/S change. The consequences of an accident previously evaluated will not be increased because the changes increase the penalty applied to F< when it is measured to be increasing. F< and allowable power level (APL) T/S surveillance requirements are not being changed. Furthermore, allowing a cycle and burnup dependent F< penalty to be located in the COLR was accepted by the NRC in, a safety evaluation on WCAP-10216-P, Rev. 1.
CRITERION 2 The proposed changes will not create the possibility of a new or different kind of accident from any accident previously evaluated because the changes will involve no physical changes to the plant nor any changes in plant operations. Furthermore, the F< and APL T/S surveillance requirements are not being changed, and the change to the F< penalty is conservative.
CRITERION 3 The proposed amendment will not involve a significant reduction in a margin of safety. When the increased F< penalty is applied, it reduces the allowable power level, thus increasing the margin of safety.
ATTACHMENT 2 TO AEP:NRC:1071T EXISTING TECHNICAL SPECIFICATION PAGES MARKED TO REFLECT PROPOSED CHANGES