{{#Wiki_filter:Rafael Flores Senior Vice President& Chief Nuclear Officer rafael.flores@Luminant.com Luminant Luminant Power P 0 Box 1002 6322 North FM 56 Glen Rose, TX 76043 T 254 897 5550 C 817 559 0403 F 254 897 6652 CP-201201309 TXX-12161 10 CFR 50.80 10 CFR 50.75 October 24, 2012 U.S. Nuclear Regulatory Commission Attention: | {{#Wiki_filter:Rafael Flores Senior Vice President | ||
Document Control Desk Director, Office of Nuclear Reactor Regulation Washington, DC 20555 | & Chief Nuclear Officer rafael.flores@Luminant.com Luminant Luminant Power P 0 Box 1002 6322 North FM 56 Glen Rose, TX 76043 T 254 897 5550 C 817 559 0403 F 254 897 6652 CP-201201309 TXX-12161 10 CFR 50.80 10 CFR 50.75 October 24, 2012 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Director, Office of Nuclear Reactor Regulation Washington, DC 20555 | ||
==SUBJECT:== | ==SUBJECT:== | ||
| Line 25: | Line 25: | ||
==REFERENCE:== | ==REFERENCE:== | ||
: 1. Luminant Power Letter logged TXX-12149 from Rafael Flores to the NRC dated October 11, 2012, Application for Order Approving Indirect and Internal Transfer of Licenses (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)) | |||
1.Luminant Power Letter logged TXX-12149 from Rafael Flores to the NRC dated October 11, 2012, Application for Order Approving Indirect and Internal Transfer of Licenses (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)) | |||
==Dear Sir or Madam:== | ==Dear Sir or Madam:== | ||
Luminant Generation Company LLC ("Luminant Power"), acting on behalf of Energy Future Holdings Corp. ("EFH"), Energy Future Competitive Holdings Company ("EFCH"), Texas Competitive Electric Holdings Company LLC, and Luminant Holding Company LLC, hereby submits additional information in connection with the indirect transfer of licenses requested in Reference 1.As noted in Reference 1, Luminant Power will continue to provide financial assurance for decommissioning funding in accordance with 10 CFR 50.75(e)(1)(i) and (ii), using the external sinking fund method with access to non-bypassable charges to retail electric customers. | Luminant Generation Company LLC ("Luminant Power"), acting on behalf of Energy Future Holdings Corp. ("EFH"), Energy Future Competitive Holdings Company ("EFCH"), Texas Competitive Electric Holdings Company LLC, and Luminant Holding Company LLC, hereby submits additional information in connection with the indirect transfer of licenses requested in Reference 1. | ||
A report regarding the status of these funds was submitted to the NRC on March 28, 2011, as Luminant Power's biennial 50.75(f) report (Accession number ML110960274). | As noted in Reference 1, Luminant Power will continue to provide financial assurance for decommissioning funding in accordance with 10 CFR 50.75(e)(1)(i) and (ii), using the external sinking fund method with access to non-bypassable charges to retail electric customers. A report regarding the status of these funds was submitted to the NRC on March 28, 2011, as Luminant Power's biennial 50.75(f) report (Accession number ML110960274). An update to this status report is provided in an Attachment to this letter. | ||
An update to this status report is provided in an Attachment to this letter.A member of the STARS Alliance Callaway | A member of the STARS Alliance Callaway | ||
* Comanche Peak | * Comanche Peak | ||
* Diablo Canyon | * Diablo Canyon | ||
* Palo Verde -San Onofre -South Texas Project | * Palo Verde - San Onofre - South Texas Project | ||
* Wolf Creek Abb ( | * Wolf Creek Abb ( | ||
U. S. Nuclear Regulatory Commission TXX-12161 Page 2 of 2 10/24/2012 If the NRC requires additional information concerning this license transfer, please contact Fred Madden, Director Oversight and Regulatory Affairs, Luminant Power, tel: (254) 897-8601 and email: Fred.Madden@luminant.com. | |||
This letter contains no new licensing basis commitments regarding Comanche Peak Nuclear Power Plant Units 1 and 2.Sincerely, Luminant Generation Company LLC Rafael Flores By | U. S. Nuclear Regulatory Commission TXX-12161 Page 2 of 2 10/24/2012 If the NRC requires additional information concerning this license transfer, please contact Fred Madden, Director Oversight and Regulatory Affairs, Luminant Power, tel: (254) 897-8601 and email: | ||
Fred.Madden@luminant.com. | |||
This letter contains no new licensing basis commitments regarding Comanche Peak Nuclear Power Plant Units 1 and 2. | |||
Sincerely, Luminant Generation Company LLC Rafael Flores By redtW._Madden Director, Oversight and Regulatory Affairs Attachment NRC Decommissioning Funding Status Report for Financial Assurance at December 31, 2011 C - | |||
E. J. Leeds, Director, Office of Nuclear Reactor Regulation E. E. Collins, Region IV B. K. Singal, NRR Resident Inspectors, Comanche Peak | |||
Attachment to TXX-12161 Page 1 of 1 NRC Decommissioning Funding Status Report for Financial Assurance at December 31, 2011 Luminant Generation Company LLC Comanche Peak Nuclear Power Plant (CPNPP) | |||
Information is submitted to provide Financial Assurance Unit # 1 Unit # 2 | |||
: 1. The minimum amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75 (b) and (c). | |||
At December 31, 2011 Using NRC 10 CFR 50.75(c) formulas Site-specific study | |||
$ 474.3 million | |||
$ 593.0 million | |||
$ 474.3 million | |||
$ 693.8 million | |||
: 2. The amount accumulated at the end of the calendar year preceding the date of the report for items included in 10 CFR 50.75 (b) and (c). | |||
Investment categories per Regulatory Guide 1.159 2.6.2. | |||
Cash U.S. Equities U.S. Fixed Income Market Value at December 31, 2011 | |||
: 3. A schedule of the annual amounts remaining to be collected for items in 10 CFR 50.75 (b) and (c). | |||
Years 2012 through 2029 (18 years) | |||
Year 2030 Year 2031 Year 2032 Year 2033 Totals | |||
: 4. The assumptions used regarding escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates of other factors used in funding projections. | |||
Estimated Escalation rate for decommissioning costs Estimated Earnings rates on decommissioning funds 2012 through 2028 2029 through 2059 2060 and thereafter Rates of other factors used in funding projections | Estimated Escalation rate for decommissioning costs Estimated Earnings rates on decommissioning funds 2012 through 2028 2029 through 2059 2060 and thereafter Rates of other factors used in funding projections | ||
: 5. Any power sale contracts upon which licensee is relying to certifying financial assurance. | : 5. Any power sale contracts upon which licensee is relying to certifying financial assurance. | ||
: 6. Modifications to licensee's method of providing financial assurance since previous report.7. Material changes to trust agreement. | : 6. Modifications to licensee's method of providing financial assurance since previous report. | ||
0%58%42%100%$ 267.8 million Unit # 1 7.5 million 1.2 million$ 135.4 million 0%58%42%100%$ 306.6 million Unit # 2 7.3 million 7.3 million 7.3 million 7.3 million 1.2 million$ 153.8 million Unit # 1 2.5248%4.83%3.99%3.07%None None None None Unit # 2 2.5043%4.83%3.99%3.07%None None None None Notes: 1. Labor (South) and Energy are based on BLS (L,=2.277, E,=2.580). | : 7. Material changes to trust agreement. | ||
Burial inflation factors are based on NUREG 1307, "Report on Waste Burial Charges," Revision 14 (B,=12.280) | 0% | ||
: 2. All forecast data are based on the decommissioning cost study filed with the Public Utility Commission on June 17, 2010 and is subject to approval by the Commission.}} | 58% | ||
42% | |||
100% | |||
$ 267.8 million Unit # 1 7.5 million 1.2 million | |||
$ 135.4 million 0% | |||
58% | |||
42% | |||
100% | |||
$ 306.6 million Unit # 2 7.3 million 7.3 million 7.3 million 7.3 million 1.2 million | |||
$ 153.8 million Unit # 1 2.5248% | |||
4.83% | |||
3.99% | |||
3.07% | |||
None None None None Unit # 2 2.5043% | |||
4.83% | |||
3.99% | |||
3.07% | |||
None None None None Notes: | |||
: 1. | |||
Labor (South) and Energy are based on BLS (L,=2.277, E,=2.580). Burial inflation factors are based on NUREG 1307, "Report on Waste Burial Charges," Revision 14 (B,=12.280) | |||
: 2. | |||
All forecast data are based on the decommissioning cost study filed with the Public Utility Commission on June 17, 2010 and is subject to approval by the Commission.}} | |||
Latest revision as of 21:15, 11 January 2025
| ML12312A071 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 10/24/2012 |
| From: | Madden F, Flores R Luminant Generation Co, Luminant Power |
| To: | Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation |
| References | |
| CP-201201309, TAC ME9767, TAC ME9768, TXX-12161 | |
| Download: ML12312A071 (3) | |
Text
Rafael Flores Senior Vice President
& Chief Nuclear Officer rafael.flores@Luminant.com Luminant Luminant Power P 0 Box 1002 6322 North FM 56 Glen Rose, TX 76043 T 254 897 5550 C 817 559 0403 F 254 897 6652 CP-201201309 TXX-12161 10 CFR 50.80 10 CFR 50.75 October 24, 2012 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Director, Office of Nuclear Reactor Regulation Washington, DC 20555
SUBJECT:
Comanche Peak Nuclear Power Plant (CPNPP) and Independent Spent Fuel Storage Installation (ISFSI), Docket Nos. 50-445, 50-446, 72-74 Additional Information Regarding Application for Order Approving Indirect and Internal Transfer of Licenses (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89)) (TAC NOS. ME9767 and ME9768)
REFERENCE:
- 1. Luminant Power Letter logged TXX-12149 from Rafael Flores to the NRC dated October 11, 2012, Application for Order Approving Indirect and Internal Transfer of Licenses (CPNPP Unit 1 Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89))
Dear Sir or Madam:
Luminant Generation Company LLC ("Luminant Power"), acting on behalf of Energy Future Holdings Corp. ("EFH"), Energy Future Competitive Holdings Company ("EFCH"), Texas Competitive Electric Holdings Company LLC, and Luminant Holding Company LLC, hereby submits additional information in connection with the indirect transfer of licenses requested in Reference 1.
As noted in Reference 1, Luminant Power will continue to provide financial assurance for decommissioning funding in accordance with 10 CFR 50.75(e)(1)(i) and (ii), using the external sinking fund method with access to non-bypassable charges to retail electric customers. A report regarding the status of these funds was submitted to the NRC on March 28, 2011, as Luminant Power's biennial 50.75(f) report (Accession number ML110960274). An update to this status report is provided in an Attachment to this letter.
A member of the STARS Alliance Callaway
- Comanche Peak
- Diablo Canyon
- Palo Verde - San Onofre - South Texas Project
- Wolf Creek Abb (
U. S. Nuclear Regulatory Commission TXX-12161 Page 2 of 2 10/24/2012 If the NRC requires additional information concerning this license transfer, please contact Fred Madden, Director Oversight and Regulatory Affairs, Luminant Power, tel: (254) 897-8601 and email:
Fred.Madden@luminant.com.
This letter contains no new licensing basis commitments regarding Comanche Peak Nuclear Power Plant Units 1 and 2.
Sincerely, Luminant Generation Company LLC Rafael Flores By redtW._Madden Director, Oversight and Regulatory Affairs Attachment NRC Decommissioning Funding Status Report for Financial Assurance at December 31, 2011 C -
E. J. Leeds, Director, Office of Nuclear Reactor Regulation E. E. Collins, Region IV B. K. Singal, NRR Resident Inspectors, Comanche Peak
Attachment to TXX-12161 Page 1 of 1 NRC Decommissioning Funding Status Report for Financial Assurance at December 31, 2011 Luminant Generation Company LLC Comanche Peak Nuclear Power Plant (CPNPP)
Information is submitted to provide Financial Assurance Unit # 1 Unit # 2
- 1. The minimum amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75 (b) and (c).
At December 31, 2011 Using NRC 10 CFR 50.75(c) formulas Site-specific study
$ 474.3 million
$ 593.0 million
$ 474.3 million
$ 693.8 million
- 2. The amount accumulated at the end of the calendar year preceding the date of the report for items included in 10 CFR 50.75 (b) and (c).
Investment categories per Regulatory Guide 1.159 2.6.2.
Cash U.S. Equities U.S. Fixed Income Market Value at December 31, 2011
- 3. A schedule of the annual amounts remaining to be collected for items in 10 CFR 50.75 (b) and (c).
Years 2012 through 2029 (18 years)
Year 2030 Year 2031 Year 2032 Year 2033 Totals
- 4. The assumptions used regarding escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates of other factors used in funding projections.
Estimated Escalation rate for decommissioning costs Estimated Earnings rates on decommissioning funds 2012 through 2028 2029 through 2059 2060 and thereafter Rates of other factors used in funding projections
- 5. Any power sale contracts upon which licensee is relying to certifying financial assurance.
- 6. Modifications to licensee's method of providing financial assurance since previous report.
- 7. Material changes to trust agreement.
0%
58%
42%
100%
$ 267.8 million Unit # 1 7.5 million 1.2 million
$ 135.4 million 0%
58%
42%
100%
$ 306.6 million Unit # 2 7.3 million 7.3 million 7.3 million 7.3 million 1.2 million
$ 153.8 million Unit # 1 2.5248%
4.83%
3.99%
3.07%
None None None None Unit # 2 2.5043%
4.83%
3.99%
3.07%
None None None None Notes:
- 1.
Labor (South) and Energy are based on BLS (L,=2.277, E,=2.580). Burial inflation factors are based on NUREG 1307, "Report on Waste Burial Charges," Revision 14 (B,=12.280)
- 2.
All forecast data are based on the decommissioning cost study filed with the Public Utility Commission on June 17, 2010 and is subject to approval by the Commission.