ML070390040: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(2 intermediate revisions by the same user not shown)
Line 3: Line 3:
| issue date = 01/24/2007
| issue date = 01/24/2007
| title = APS Response to NRC Inspection Report 05000528/2006012; 05000529/2006012; 05000530/2006012
| title = APS Response to NRC Inspection Report 05000528/2006012; 05000529/2006012; 05000530/2006012
| author name = Levine J M
| author name = Levine J
| author affiliation = Arizona Public Service Co
| author affiliation = Arizona Public Service Co
| addressee name =  
| addressee name =  
Line 14: Line 14:
| page count = 11
| page count = 11
}}
}}
See also: [[followed by::IR 05000528/2006012]]


=Text=
=Text=
{{#Wiki_filter:LA subsidiary
{{#Wiki_filter:LA                               subsidiaryof Pinnacle West CapitalCorporation James M. Levine                                         Mail Station 7602 Palo Verde Nuclear         Executive Vice President     Tel (623) 393-5300       PO Box 52034 Generating Station         Generation                     Fax (623) 393-6077       Phoenix, Arizona 85072-2034 102-05636-JMLJSAB/TNW/CJS January 24, 2007 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
of Pinnacle West Capital Corporation
 
James M. Levine Mail Station 7602 Palo Verde Nuclear Executive  
==Dear Sir:==
Vice President  
 
Tel (623) 393-5300 PO Box 52034 Generating  
==Subject:==
Station Generation  
Palo Verde Nuclear Generating Station (PVNGS)
Fax (623) 393-6077 Phoenix, Arizona 85072-2034
Units 1, 2 and 3 Docket Nos. STN 50-528, 50-529, and 50-530 APS Response to NRC Inspection Report 05000528/2006012; 0500052912006012; 0500053012006012 In NRC Special Inspection Report 2006012, dated December 6, 2006, the NRC documented their examination of activities associated with the PVNGS Unit 3, Train A, emergency diesel generator (EDG) failures that occurred on July 25 and September 22, 2006. At a January 16, 2007 Regulatory Conference in Arlington, Texas, APS provided the NRC its perspective on the facts and analytical assumptions relevant to determining the safety significance of the findings, in accordance with the Inspection Manual Chapter 0609.
102-05636-JMLJSAB/TNW/CJS
The purpose of this letter is to provide the additional information requested by the NRC during the regulatory conference. The Enclosure to this letter contains 7 questions that were requested at the close of the conference and 4 additional questions that were part of the conference general discussion. There are no regulatory commitments in this letter.
January 24, 2007 U.S. Nuclear Regulatory  
If you have any questions, please contact Thomas N. Weber at (623) 393-5764.
Commission
Sincerely, JMLJSABITNW/CJS/gt
ATTN: Document Control Desk Washington, DC 20555 Dear Sir: Subject: Palo Verde Nuclear Generating  
 
Station (PVNGS)Units 1, 2 and 3 Docket Nos. STN 50-528, 50-529, and 50-530 APS Response to NRC Inspection  
U.S. Nuclear Regulatory Commission ATTN: Document Control Desk APS Response to NRC Inspection Report 05000528/2006012; 05000529/2006012; 05000530/2006012 Page 2
Report 05000528/2006012;
 
0500052912006012;  
==Enclosure:==
0500053012006012
Additional Information Requested at the January 16, 2007 NRC Regulatory Conference cc:   B. S. Malleft       NRC  Region IV Regional Administrator M. B. Fields         NRC  NRR Project Manager M. T. Markley       NRC  NRR Project Manager G. G. Warnick       NRC   Senior Resident Inspector for PVNGS
In NRC Special Inspection  
 
Report 2006012, dated December 6, 2006, the NRC documented  
ENCLOSURE Additional Information Requested at the January 16, 2007 NRC Regulatory Conference NRC Question 1 Is it acceptable to provide auxiliary feedwater to a steam generator after it has dried out?
their examination  
APS Response 1 Yes. The Unit 3 steam generators are designed with an allowance for feeding a hot dry steam generator with cold feedwater. APS asked ABB (the design authority for the PVNGS Steam Generators) about the maximum allowed flow rate for feedwater to a hot dry steam generator. The ABB response stated "the generators are designed to handle seven cycles of adding 40 degrees F feedwater at 1750 gpm." The information was requested to support development of the PVNGS Emergency Operating Procedures.
of activities  
This information is documented in ABB Inter-Office Correspondence V-MPS-91-163, dated, November 14, 1991.
associated  
NRC Question 2 What reliability/unavailability for the Gas Turbine Generators (GTGs) was assumed in the Probabilistic Risk Analysis (PRA)? Provide the data that was used to obtain these values. Please indicate how buried cable reliability is addressed in the PRA.
with the PVNGS Unit 3, Train A, emergency  
APS Response 2 GTG Reliability Gas Turbine Generator (GTG) fail to start and fail to run probabilities are Bayesian updated values based on the values in Advanced Light Water ReactorRequirements Document (ALWR), Volume II, Chapter 1, Appendix A - PRA Key Assumptions and Groundrules, Electric Power Research Institute, Revision 6, December 1993, pages A.A-67 and A.A-68. The number of GTG demands, accumulated run time, and failures were collected for the period of 1/1/1998 to 10/1/2004 and documented in study 13-NS-C076, Plant Specific Reliability Data for PRA Model, Revision 0, Appendix C: PRA Final Failures and Demands Report. The values were based on an actual count (they were not estimated). For the given time period and system boundary, there were 6 failures (3 on GTG 1 and 3 on GTG 2) in 267 demands and 0 failures in 283 hours. The final failure probabilities were 2.5E-2 per demand and 4.2E-5 per hour.
diesel generator (EDG) failures that occurred on July 25 and September  
1
22, 2006. At a January 16, 2007 Regulatory  
 
Conference  
GTG Unavailability GTG unavailability is based on an actual count of unavailable hours during the period 1/1/1999 through 12/31/2001 as documented in study 13-NS-C064, Plant Specific UnavailabilityData for PRA Model, Revision 0, Appendix A: Individual Parameter Unavailability Listings Gas Turbine Generator. There were 954.68 hours unavailable in the 26304 hour period for a probability of 1.81 E-2.
in Arlington, Texas, APS provided the NRC its perspective  
GTG UnderQround Cable Reliability The underground cables between the GTGs and the units are modeled separately from the GTGs. The cable is not direct buried but runs in an underground conduit. Two three phase cables are used to supply power to each unit. The failure probability is a Bayesian updated value based on the value in IEEE Standard 500-1984, IEEE Guide to the Collection and Presentationof Electrical,Electronic, Sensing Component and MechanicalEquipment ReliabilityData for Nuclear-PowerGeneratingStations, Institute of Electrical and Electronics Engineers, Inc., December 13, 1983, Reaffirmed 1991, page 770. This value is multiplied by the length of the cable (3475' for Unit 1, See note below) obtained from the Plant Data Management System EDB ElectricalDatabase, since the IEEE value is given per 1000' cable length. Based on a search of EPIX/NPRDS, Failure Data Trending, and CRDRs, there were zero cable failures since the GTGs were installed. In the search, 4 instances were identified (CRDRs 2559098, 2564721, 2580013, and 2843631) where the results of megger testing was less than the service criteria but greater than the emergency criteria. These tests had been evaluated by Maintenance Engineering and it was determined that since the as-found readings were greater than the emergency allowed value, the cables would have been able to perform their function. Appropriate corrective actions were taken in each case to restore the cables such that the service criteria were met.
on the facts and analytical  
Engineering Support provided a Maintenance Rule Hours in Mode Summary Report for the date range of 9/27/1993 (date of first GTG isochronous test) through 11/30/2006.
assumptions  
The exposure time was taken as the time spent in Modes 1 through 6 in each unit, for an exposure time of 334,836 hours for the 3 units. Since there are two cables per unit, the total exposure time is 669,672 hours. From a unit perspective, a load test powering that unit's cables from the GTGs is performed every 18 months per 40DP-9OP06, OperationsDepartmentRepetitive Task Program,Task GT002. The Bayesian updated failure rate for one cable was 1.46E-2 per hour, for a failure probability of a standby component of 9.59E-3. Since there are two cables, the final probability for the underground GTG cable was 1.91 E-2 (equivalent to an "OR" gate).
relevant to determining
Note: A single PRA model based on Unit 1 is used at PVNGS. Plant differences are accounted for when performing specific applications. Since a continuously energized failure rate is being applied to a cable energized only a very short period of its exposed life, the value is very conservative and bounds all three units.
the safety significance  
2
of the findings, in accordance  
 
with the Inspection  
NRC Question 3 Describe how the PRA handles the recovery of the Auxiliary Feedwater (AF) Train "N" pump once the GTG is on line. What dependency exists between getting GTG alignment and AF "N" alignment?
Manual Chapter 0609.The purpose of this letter is to provide the additional  
APS Response 3 In a Station Blackout, restoration of a motor-driven AFW pump after alignment of the GTGs is required if auxiliary feedwater from the turbine driven pump is lost to the SGs and power is not available. This scenario involves failure of both the Maintenance of Vital Auxiliaries and RCS Heat Removal safety functions. As such, Operations would be directed to the Functional Recovery procedure 40EP-9EO09 for this condition. The Control Room Supervisor retains the option to proceed with the Blackout procedure with the understanding that the mitigating strategy (restoration of power) will resolve both failed safety functions. The procedure actions are similar, and both direct Operations to initially restore power to PBA-S03 from a GTG, after determination that offsite power and EDGs can not be restored within 1 hour.
information  
Procedure 40EP-9EO09, FunctionalRecovery, Section 8.0, Maintenance of Vital Auxiliaries, Success path MVAC 3: GTGs, provides the instructions to start and load the GTGs onto a Class 1E 4.16kV AC Bus. Step 8.7 directs performance of Appendix 80 "When NAN-S07 is energized, align GTG to PBA-S03 (BO)". Alternately available to Operations is step 8.7.1 which directs performance of Appendix 81 "When NAN-S07 is energized, Align GTGs to PBB-S04 (BO)". The equivalent steps to align a GTG to a Class 1E 4.16kV AC bus are provided in the Blackout procedure 40EP-9EO08, in steps 13 and 13.1.
requested  
Standard Appendix 80 [81] (40EP-9EO10) step 7 [9] completes the actions necessary to energize the Class 1E 4.16kV AC bus PBA-S03 [PBB-S04]. At this time power is available to start an AFW pump and initiate AFW flow to a SG. Step 9, of Appendix 80, directs an Operator [Licensed Control Room Operator] to check that AFA is being used to maintain at least one SG at 45%-60% NR level, else if the AFA pump is not available, then align and start AFN-P01 to restore SG level. Step 11, of Appendix 81, directs the Operator to start AFB-P01 to restore SG level.
by the NRC during the regulatory  
The Control Room Supervisor (CRS) has the responsibility to manage the operator resources during the event. The description below reflects what would typically be the assignments made for power recovery and AFW recovery. Specific assignments may vary, but there are always two licensed control room operators available to perform the two main functions of power recovery and AFW recovery without dependency between the tasks. The tasks are also separated in time, with power recovery required prior to AFW recovery for this scenario. The same is true of the 4 Auxiliary Operators. The specific operator assigned to a task may vary, but sufficient resources exist to perform all the tasks without any dependency.
conference.  
3
The Enclosure  
 
to this letter contains 7 questions  
Actions necessary to start and align the AFN-P01 pump or AFB-P01 pump are typically performed by the Controls Operator from the Control Room. To initiate flow from the AFN-P01 pump, the Controls Operator must open the two (2) suction MOVs, open a Downcomer Bypass MOV (one per SG), open the Downcomer Isolation valves (2 per SG), and start the pump. To initiate flow from the AFB-P01 pump, the Controls Operator must only start the pump, given the discharge isolation and regulation valves are open due to the AFAS actuation. The time to take these actions is less than 5 minutes.
that were requested  
The Licensed Operators are extensively trained on these actions during various simulator events. The detailed actions are not prescriptively described in the Emergency Operating Procedures, but are simple and easily accomplished by any control room operator as a result of their training. Failure of the Controls Operator to initiate AFW flow to at least one SG would be immediately recovered by the Control Room Supervisor and/or the STA. The Controls Operator typically has no other dependent responsibilities for power restoration. Initiation of AFW for restoration of the RCS Heat Removal safety function is the Control Operator's primary focus, thus ample time is available for proper diagnosis and recovery. The PRA does not model a specific HRA for failure to establish AFW flow after power is restored to a Class 1E 4.16kV AC bus because the failure probability for the AFW restoration action is so low it is negligible compared to the action to restore power.
at the close of the conference  
Recovery of the 4.16KV AC bus from a GTG is typically performed bythe Reactor Operator [Licensed Control Room Operator] with assistance from an assigned Auxiliary Operator (AO), typically the Area 4 AO and the Water Reclamation Facility Operator.
and 4 additional  
The assigned AO would have no responsibilities for assisting with the recovery of the assumed failed AFA-P01 pump, which is typically assigned to a different AO (Area 1).
questions  
There are no required actions of the Controls Operator to support the power recovery actions, nor any actions of the Reactor Operator to support the AFW recovery actions, other than the standard actions to maintain cognizance of critical system parameters.
that were part of the conference  
No Auxiliary Operators are required for recovery of AFW after power has been restored to a 4.16kV AC bus. Actions to restore power and initiate AFW are considered to have zero dependency.
general discussion.  
NRC Question 4 Which EOP covers overriding automatic control (AFAS) and taking manual control of AF "A"? How soon does this happen based on simulator experience? This relates to the battery analysis assumption that the AF isolation valves do not continuously cycle, as assumed in the design calculation.
There are no regulatory  
APS Response 4 Procedure 40EP-9EO01, StandardPost Trip Actions, has the Secondary Operator override AFAS valves to ensure feed flow is not excessive. Operators are trained to take manual control of the feed rate to preclude a SIAS, which would likely follow an AFAS, due to overcooling. The operator will typically initiate this action by starting AFA-4
commitments  
 
in this letter.If you have any questions, please contact Thomas N. Weber at (623) 393-5764.Sincerely, JMLJSABITNW/CJS/gt  
P01 from control room panel B06, and establish feed by opening the block valves and throttling the regulation valves. This would normally occur (assuming a Station Blackout) prior to an AFAS actuation. The isolation valves are left open and are not cycled and the only valve manipulations are adjustments to feed rate using the regulation valves.
U.S. Nuclear Regulatory  
In the event of an AFAS automatic actuation, the operator will take control of feed rate, and not allow the regulation valves to control level. The specific feed rate is not scripted, but the safety function is met when level in at least one steam generator is increasing towards its normal band as required by Procedure 40EP-9EO01. Experience in the simulator is that operators~will take manual control of AF in no longer than 10 minutes during a station blackout (SBO) event.
Commission
Once level is recovered, the operator feeds at a rate sufficient to makeup for level lost due to steaming out the Atmospheric Dump Valves (ADVs).
ATTN: Document Control Desk APS Response to NRC Inspection  
NRC Question 5 In the lower recovery path of the "Event Timelines for Station Blackout @ t=0" slide of the presentation, APS provided times of 58 and 95 minutes for 'steam generator (SG) dryout' and 'latest SG makeup can be initiated'. How does the PRA use these two values? What importance is given to each value?
Report 05000528/2006012;  
APS Response 5 The 58 minute time is used in Loss of Offsite Power accident sequences as the basis for the time to start and align the gas turbine generators. The 95 minute time is not used for Loss of Offsite Power accident sequences. The 95 minute time is used as the time available for providing feed to the steam generators using the condensate pumps for sequences that do not include a Loss of Offsite Power. Thus the 95 minute time has no importance in the K-1 relay significance determination.
05000529/2006012;
NRC Question 6 Provide the analysis that was done to extend the battery life from the 2 hour design requirement to 3 hours for the PRA.
05000530/2006012
APS Response 6 NUS-5058, Analysis of Station Blackout Accidents at PVNGS-1, Yovan Lukic, NUS Corporation, November 1987, Section 4.1, "Description of Top Events within the SBO event tree", subsection "Failure to Restore Power within 3 Hours", is the basis document for the 3 hour battery life in the PVNGS PRA model. This source states:
Page 2 Enclosure:
5
Additional  
 
Information  
Based on a review of 125 VDC bus loads typical to an SBO event and the 18 month and 60 months test of the DC batteries (Refs. 6 and 7), it is assessed that DC batteries will last for at least 3 hours into an SBO event. The 60 month test established that 1200 amp-hours can be provided by each DC battery (PKA and PKB) before the 105 VDC battery under-voltage condition is reached. Given a conservative estimate of the battery loads during SBO, each battery would have to provide on the order of 1000 amp-hours during the first 3 hours into an SBO event. This 20% excess in battery capacity is sufficient to cover the power requirements when the battery is operated at near 80% capacity (end-of-life).
Requested  
It should be noted that batteries with larger capacity (2415 amp-hours) were installed since this change was implemented in the PRA model.
at the January 16, 2007 NRC Regulatory  
NRC Question 7 Provide updated analysis for seven hour battery capacity.
Conference
APS Response 7 The updated analysis for seven hour battery capacity was provided to the NRC on January 19, 2007. This updated analysis reflects additional capacity loss for the 'A' battery, which was recognized following the January 16, 2007 Regulatory Conference.
cc: B. S. Malleft M. B. Fields M. T. Markley G. G. Warnick NRC Region IV Regional Administrator
This additional battery capacity loss resulted in the total capacity loss being greater than 10 percent, which placed the 'A' battery in Technical Specification 3.8.4.8, requiring a 12 month surveillance test, like the 'C' battery. This surveillance test will be performed along with the 'C' battery test in the upcoming Unit 3 mid-cycle outage. The updated analysis demonstrates that the assumptions for the risk significance evaluation remain valid, with margin.
NRC NRR Project Manager NRC NRR Project Manager NRC Senior Resident Inspector  
NRC Question 8 Did operator failure probabilities for restoration of the Emergency Diesel Generator (EDG) include the potential that operations would fail to shut down the EDG as required if it started but the field did not flash, because of the lack of jacket cooling water?
for PVNGS  
APS Response 8 Yes. APS considered the operator failing to stop the EDG after the field did not flash.
ENCLOSURE Additional  
The step was not identified as critical because the failure contribution (-2E-4) was not a significant contribution to the total value of the HRA value for recovery of the EDG. HRA quantification 4DG-RECVR-KI-1-HR has a value of 5.8E-2 and 4DG-RECVR-K1-7-HR has a value of 3.2E-3 (reference 13-NS-C081, App D).
Information  
6
Requested  
 
at the January 16, 2007 NRC Regulatory  
NRC Question 9 Who is relied upon to actually recover the EDG (maintenance, operations or engineering personnel)? How is that accounted for in your results?
Conference
APS Response 9 The associated HRA credited the recovery of K-1 relay contactor by Electrical Maintenance personnel with technical support from Electrical Maintenance Engineering personnel.
NRC Question 1 Is it acceptable  
Operations would immediately know of the EDG output failure after the engine start by control room indication/alarms as well as by Emergency Response Facility Data Acquisition Display System (ERFDADS) flat line output. Operations would not attempt to correct this condition since no specific proceduralized instructions are readily available to them. Electrical Maintenance personnel and Electrical Maintenance Engineering would be immediately called (Maintenance onsite 24/7). Maintenance and Engineering would have the primary responsibility for recovery of the affected EDG after a loss of generator output. If not onsite, Electrical Maintenance Engineering personnel would be contacted immediately for technical assistance by phone or pager. Although the faulted EDG may not be running at the time when Maintenance and/or Engineering become involved, Maintenance and Engineering personnel would be informed that the EDG started and ran without power output. Prior plant experience is that it takes 2-3 hours to replace the K-1 contactor. That repair action, however, is not required because recovery can be easily accomplished by manual bypass (opening) of the K-1 relay contactor.
to provide auxiliary  
Following the involvement of Electrical Maintenance personnel and their Engineering support, the time required for EDG 3A loss of output diagnosis is estimated at 5 to 10 minutes. It is based on operating experience at PVNGS (including a recent failure in Unit 3) and engineering knowledge that when there is no voltage buildup at all by the generator immediately after an engine start, the most likely cause would be a failure of the field shorting (K-1) contactor.
feedwater  
No immediate indications of a K-1 problem would exist at the EDG with it in a shutdown condition, however, the plant ERFDADS computer (powered by uninterruptible power supply E-NQN-D01) monitors and records the voltage and frequency buildup for each EDG start. Those records are preserved for several hours. A data flat line showing no attempt at all to build up generator output voltage would be a strong indicator of a K-1 contactor problem. In contrast, if the generator rotor is spinning, the K-1 has dropped out properly and field flashing fails to occur, then generator output voltage would still build up slowly due to its residual magnetism.
to a steam generator  
With the engine in a shutdown condition, Engineering may advise Maintenance to functionally test the K-1 and field flash (FF) contactors using the Manual Field Flash 7
after it has dried out?APS Response 1 Yes. The Unit 3 steam generators  
 
are designed with an allowance  
(MFFPB) push button on the generator control panel as long as 135 VDC control power was still available. One wire inside the cabinet would have to be lifted and the 135 VDC FF breaker would have to be opened prior to the manual field flash test. This functional test was recently used (7/26/2006 3A loss of output event) to verify that a newly installed spare K-1 was working properly.
for feeding a hot dry steam generator  
The task of establishing EDG 3A output is considered a recovery action consistent with RG 1.200, Table A-1. The following justifications are provided:
with cold feedwater.  
* The failed K-1 relay would very likely be bypassed rather than repaired. Bypass is particularly easy to perform. The fault is recoverable by a simple manual action of releasing the K-1 contactor reset latch after an engine start. After the 2nd EDG 3A no output failure (9/22/06), no equipment was required to be replaced.
APS asked ABB (the design authority  
    "   Ease of diagnosis is supported by recent similar incidents and adequate personnel training, which includes K-1 relays.
for the PVNGS Steam Generators)  
    "   Responsible plant personnel are easily accessible by pager or telephone.
about the maximum allowed flow rate for feedwater  
    "   Ample time is available for diagnosis and action to bypass the failed relay contactor.
to a hot dry steam generator.  
    "   No special tools are required for diagnosis or relay bypass manual action, and there are no issues with accessibility.
The ABB response stated "the generators  
* Plant personnel responsible for diagnosis and bypass would not be subjected to the potentially high stress level facing the control room personnel.
are designed to handle seven cycles of adding 40 degrees F feedwater  
    "   Flat line data for EDG voltage and frequency on ERFDADS computer would quickly lead to the determination that K-1 relay has malfunctioned.
at 1750 gpm." The information  
NRC Question 10 Why did we not use the Unit 3 battery design calculation? How does that affect the applicability of the results to the Unit 3 battery?
was requested  
APS Response 10 The Unit 2 calculation was used because it had been updated to reflect a number of implemented design changes, which the existing Unit 3 calculation had not yet incorporated. The designs of the DC systems are quite similar in all three units, and one model was originally used to represent any of the units. Due to a desire to improve accuracy and the availability of more powerful modeling tools, Palo Verde converted the Class 1E DC system calculation to unitized models in the mid-1 990's.
to support development  
A comparison between the Unit 2 calculation results to an updated Unit 3 computerized model, which reflects the current configuration (though not yet finalized), was performed. The load profiles are comparable with only minor variations due to nameplate voltage ratings of motor operated valves and variations due to differences in cable lengths. Two of the auxiliary feed water valves on Unit 3 were found to have lower voltages than the same valves in Unit 2, however, the valves have adequate 8
of the PVNGS Emergency  
 
Operating  
margin to accommodate these voltage differences. In light of the considerable margins between the battery capacities and the load demands of a 7-hour station blackout event (27 and 60 percent for the 'A' and 'C' batteries respectively), the differences between the designs of Unit 2 and 3 are insignificant to the conclusions of the evaluation of the K-1 relay issue.
Procedures.
NRC Question 11 Do the spikes in battery 'E' graph in presentation slide "Empirical Data 'E' Battery" correlate with battery recharging?
This information  
APS Response 11 Yes. The first spike shown on the graph (November 7, 2004) is a result of the recharge of the battery under PMWO 2647054 and the second recharge was performed under PMWO 2794319, on May 5, 2006.
is documented  
9}}
in ABB Inter-Office  
Correspondence  
V-MPS-91-163, dated, November 14, 1991.NRC Question 2 What reliability/unavailability  
for the Gas Turbine Generators (GTGs) was assumed in the Probabilistic  
Risk Analysis (PRA)? Provide the data that was used to obtain these values. Please indicate how buried cable reliability  
is addressed  
in the PRA.APS Response 2 GTG Reliability
Gas Turbine Generator (GTG) fail to start and fail to run probabilities  
are Bayesian updated values based on the values in Advanced Light Water Reactor Requirements
Document (ALWR), Volume II, Chapter 1, Appendix A -PRA Key Assumptions  
and Groundrules, Electric Power Research Institute, Revision 6, December 1993, pages A.A-67 and A.A-68. The number of GTG demands, accumulated  
run time, and failures were collected  
for the period of 1/1/1998 to 10/1/2004  
and documented  
in study 13-NS-C076, Plant Specific Reliability  
Data for PRA Model, Revision 0, Appendix C: PRA Final Failures and Demands Report. The values were based on an actual count (they were not estimated).  
For the given time period and system boundary, there were 6 failures (3 on GTG 1 and 3 on GTG 2) in 267 demands and 0 failures in 283 hours. The final failure probabilities  
were 2.5E-2 per demand and 4.2E-5 per hour.1  
GTG Unavailability
GTG unavailability  
is based on an actual count of unavailable  
hours during the period 1/1/1999 through 12/31/2001  
as documented  
in study 13-NS-C064, Plant Specific Unavailability
Data for PRA Model, Revision 0, Appendix A: Individual  
Parameter Unavailability  
Listings Gas Turbine Generator.  
There were 954.68 hours unavailable  
in the 26304 hour period for a probability  
of 1.81 E-2.GTG UnderQround  
Cable Reliability
The underground  
cables between the GTGs and the units are modeled separately  
from the GTGs. The cable is not direct buried but runs in an underground  
conduit. Two three phase cables are used to supply power to each unit. The failure probability  
is a Bayesian updated value based on the value in IEEE Standard 500-1984, IEEE Guide to the Collection  
and Presentation
of Electrical, Electronic, Sensing Component  
and Mechanical
Equipment
Reliability
Data for Nuclear-Power
Generating
Stations, Institute of Electrical  
and Electronics  
Engineers, Inc., December 13, 1983, Reaffirmed  
1991, page 770. This value is multiplied  
by the length of the cable (3475' for Unit 1, See note below) obtained from the Plant Data Management  
System EDB Electrical
Database, since the IEEE value is given per 1000' cable length. Based on a search of EPIX/NPRDS, Failure Data Trending, and CRDRs, there were zero cable failures since the GTGs were installed.  
In the search, 4 instances  
were identified (CRDRs 2559098, 2564721, 2580013, and 2843631) where the results of megger testing was less than the service criteria but greater than the emergency  
criteria.  
These tests had been evaluated by Maintenance  
Engineering  
and it was determined  
that since the as-found readings were greater than the emergency  
allowed value, the cables would have been able to perform their function.  
Appropriate  
corrective  
actions were taken in each case to restore the cables such that the service criteria were met.Engineering  
Support provided a Maintenance  
Rule Hours in Mode Summary Report for the date range of 9/27/1993 (date of first GTG isochronous  
test) through 11/30/2006.
The exposure time was taken as the time spent in Modes 1 through 6 in each unit, for an exposure time of 334,836 hours for the 3 units. Since there are two cables per unit, the total exposure time is 669,672 hours. From a unit perspective, a load test powering that unit's cables from the GTGs is performed  
every 18 months per 40DP-9OP06, Operations
Department
Repetitive
Task Program, Task GT002. The Bayesian updated failure rate for one cable was 1.46E-2 per hour, for a failure probability  
of a standby component  
of 9.59E-3. Since there are two cables, the final probability  
for the underground  
GTG cable was 1.91 E-2 (equivalent  
to an "OR" gate).Note: A single PRA model based on Unit 1 is used at PVNGS. Plant differences  
are accounted  
for when performing  
specific applications.  
Since a continuously  
energized failure rate is being applied to a cable energized  
only a very short period of its exposed life, the value is very conservative  
and bounds all three units.2  
NRC Question 3 Describe how the PRA handles the recovery of the Auxiliary  
Feedwater (AF) Train "N" pump once the GTG is on line. What dependency  
exists between getting GTG alignment  
and AF "N" alignment?
APS Response 3 In a Station Blackout, restoration  
of a motor-driven  
AFW pump after alignment  
of the GTGs is required if auxiliary  
feedwater  
from the turbine driven pump is lost to the SGs and power is not available.  
This scenario involves failure of both the Maintenance  
of Vital Auxiliaries  
and RCS Heat Removal safety functions.  
As such, Operations  
would be directed to the Functional  
Recovery procedure  
40EP-9EO09  
for this condition.  
The Control Room Supervisor  
retains the option to proceed with the Blackout procedure  
with the understanding  
that the mitigating  
strategy (restoration  
of power) will resolve both failed safety functions.  
The procedure  
actions are similar, and both direct Operations  
to initially  
restore power to PBA-S03 from a GTG, after determination  
that offsite power and EDGs can not be restored within 1 hour.Procedure  
40EP-9EO09, Functional
Recovery, Section 8.0, Maintenance  
of Vital Auxiliaries, Success path MVAC 3: GTGs, provides the instructions  
to start and load the GTGs onto a Class 1E 4.16kV AC Bus. Step 8.7 directs performance  
of Appendix 80"When NAN-S07 is energized, align GTG to PBA-S03 (BO)". Alternately  
available  
to Operations  
is step 8.7.1 which directs performance  
of Appendix 81 "When NAN-S07 is energized, Align GTGs to PBB-S04 (BO)". The equivalent  
steps to align a GTG to a Class 1 E 4.16kV AC bus are provided in the Blackout procedure  
40EP-9EO08, in steps 13 and 13.1.Standard Appendix 80 [81] (40EP-9EO10)  
step 7 [9] completes  
the actions necessary  
to energize the Class 1 E 4.16kV AC bus PBA-S03 [PBB-S04].  
At this time power is available  
to start an AFW pump and initiate AFW flow to a SG. Step 9, of Appendix 80, directs an Operator [Licensed  
Control Room Operator]  
to check that AFA is being used to maintain at least one SG at 45%-60% NR level, else if the AFA pump is not available, then align and start AFN-P01 to restore SG level. Step 11, of Appendix 81, directs the Operator to start AFB-P01 to restore SG level.The Control Room Supervisor (CRS) has the responsibility  
to manage the operator resources  
during the event. The description  
below reflects what would typically  
be the assignments  
made for power recovery and AFW recovery.  
Specific assignments  
may vary, but there are always two licensed control room operators  
available  
to perform the two main functions  
of power recovery and AFW recovery without dependency  
between the tasks. The tasks are also separated  
in time, with power recovery required prior to AFW recovery for this scenario.  
The same is true of the 4 Auxiliary  
Operators.  
The specific operator assigned to a task may vary, but sufficient  
resources  
exist to perform all the tasks without any dependency.
3  
Actions necessary  
to start and align the AFN-P01 pump or AFB-P01 pump are typically performed  
by the Controls Operator from the Control Room. To initiate flow from the AFN-P01 pump, the Controls Operator must open the two (2) suction MOVs, open a Downcomer  
Bypass MOV (one per SG), open the Downcomer  
Isolation  
valves (2 per SG), and start the pump. To initiate flow from the AFB-P01 pump, the Controls Operator must only start the pump, given the discharge  
isolation  
and regulation  
valves are open due to the AFAS actuation.  
The time to take these actions is less than 5 minutes.The Licensed Operators  
are extensively  
trained on these actions during various simulator  
events. The detailed actions are not prescriptively  
described  
in the Emergency Operating  
Procedures, but are simple and easily accomplished  
by any control room operator as a result of their training.  
Failure of the Controls Operator to initiate AFW flow to at least one SG would be immediately  
recovered  
by the Control Room Supervisor
and/or the STA. The Controls Operator typically  
has no other dependent  
responsibilities
for power restoration.  
Initiation  
of AFW for restoration  
of the RCS Heat Removal safety function is the Control Operator's  
primary focus, thus ample time is available  
for proper diagnosis  
and recovery.  
The PRA does not model a specific HRA for failure to establish AFW flow after power is restored to a Class 1 E 4.16kV AC bus because the failure probability  
for the AFW restoration  
action is so low it is negligible  
compared to the action to restore power.Recovery of the 4.16KV AC bus from a GTG is typically  
performed  
bythe Reactor Operator [Licensed  
Control Room Operator]  
with assistance  
from an assigned Auxiliary Operator (AO), typically  
the Area 4 AO and the Water Reclamation  
Facility Operator.The assigned AO would have no responsibilities  
for assisting  
with the recovery of the assumed failed AFA-P01 pump, which is typically  
assigned to a different  
AO (Area 1).There are no required actions of the Controls Operator to support the power recovery actions, nor any actions of the Reactor Operator to support the AFW recovery actions, other than the standard actions to maintain cognizance  
of critical system parameters.
No Auxiliary  
Operators  
are required for recovery of AFW after power has been restored to a 4.16kV AC bus. Actions to restore power and initiate AFW are considered  
to have zero dependency.
NRC Question 4 Which EOP covers overriding  
automatic  
control (AFAS) and taking manual control of AF"A"? How soon does this happen based on simulator  
experience?  
This relates to the battery analysis assumption  
that the AF isolation  
valves do not continuously  
cycle, as assumed in the design calculation.
APS Response 4 Procedure  
40EP-9EO01, Standard Post Trip Actions, has the Secondary  
Operator override AFAS valves to ensure feed flow is not excessive.  
Operators  
are trained to take manual control of the feed rate to preclude a SIAS, which would likely follow an AFAS, due to overcooling.  
The operator will typically  
initiate this action by starting AFA-4  
P01 from control room panel B06, and establish  
feed by opening the block valves and throttling  
the regulation  
valves. This would normally occur (assuming  
a Station Blackout)  
prior to an AFAS actuation.  
The isolation  
valves are left open and are not cycled and the only valve manipulations  
are adjustments  
to feed rate using the regulation  
valves.In the event of an AFAS automatic  
actuation, the operator will take control of feed rate, and not allow the regulation  
valves to control level. The specific feed rate is not scripted, but the safety function is met when level in at least one steam generator  
is increasing  
towards its normal band as required by Procedure  
40EP-9EO01.  
Experience
in the simulator  
is that operators~will  
take manual control of AF in no longer than 10 minutes during a station blackout (SBO) event.Once level is recovered, the operator feeds at a rate sufficient  
to makeup for level lost due to steaming out the Atmospheric  
Dump Valves (ADVs).NRC Question 5 In the lower recovery path of the "Event Timelines  
for Station Blackout @ t=0" slide of the presentation, APS provided times of 58 and 95 minutes for 'steam generator (SG)dryout' and 'latest SG makeup can be initiated'.  
How does the PRA use these two values? What importance  
is given to each value?APS Response 5 The 58 minute time is used in Loss of Offsite Power accident sequences  
as the basis for the time to start and align the gas turbine generators.  
The 95 minute time is not used for Loss of Offsite Power accident sequences.  
The 95 minute time is used as the time available  
for providing  
feed to the steam generators  
using the condensate  
pumps for sequences  
that do not include a Loss of Offsite Power. Thus the 95 minute time has no importance  
in the K-1 relay significance  
determination.
NRC Question 6 Provide the analysis that was done to extend the battery life from the 2 hour design requirement  
to 3 hours for the PRA.APS Response 6 NUS-5058, Analysis of Station Blackout Accidents  
at PVNGS-1, Yovan Lukic, NUS Corporation, November 1987, Section 4.1, "Description  
of Top Events within the SBO event tree", subsection "Failure to Restore Power within 3 Hours", is the basis document for the 3 hour battery life in the PVNGS PRA model. This source states: 5  
Based on a review of 125 VDC bus loads typical to an SBO event and the 18 month and 60 months test of the DC batteries (Refs. 6 and 7), it is assessed that DC batteries  
will last for at least 3 hours into an SBO event. The 60 month test established  
that 1200 amp-hours  
can be provided by each DC battery (PKA and PKB) before the 105 VDC battery under-voltage  
condition is reached. Given a conservative  
estimate of the battery loads during SBO, each battery would have to provide on the order of 1000 amp-hours  
during the first 3 hours into an SBO event. This 20% excess in battery capacity is sufficient  
to cover the power requirements  
when the battery is operated at near 80% capacity (end-of-life).
It should be noted that batteries  
with larger capacity (2415 amp-hours)  
were installed since this change was implemented  
in the PRA model.NRC Question 7 Provide updated analysis for seven hour battery capacity.APS Response 7 The updated analysis for seven hour battery capacity was provided to the NRC on January 19, 2007. This updated analysis reflects additional  
capacity loss for the 'A'battery, which was recognized  
following  
the January 16, 2007 Regulatory  
Conference.
This additional  
battery capacity loss resulted in the total capacity loss being greater than 10 percent, which placed the 'A' battery in Technical  
Specification  
3.8.4.8, requiring  
a 12 month surveillance  
test, like the 'C' battery. This surveillance  
test will be performed along with the 'C' battery test in the upcoming Unit 3 mid-cycle  
outage. The updated analysis demonstrates  
that the assumptions  
for the risk significance  
evaluation  
remain valid, with margin.NRC Question 8 Did operator failure probabilities  
for restoration  
of the Emergency  
Diesel Generator (EDG) include the potential  
that operations  
would fail to shut down the EDG as required if it started but the field did not flash, because of the lack of jacket cooling water?APS Response 8 Yes. APS considered  
the operator failing to stop the EDG after the field did not flash.The step was not identified  
as critical because the failure contribution  
(-2E-4) was not a significant  
contribution  
to the total value of the HRA value for recovery of the EDG. HRA quantification  
4DG-RECVR-KI-1-HR  
has a value of 5.8E-2 and 4DG-RECVR-K1-7-HR
has a value of 3.2E-3 (reference  
13-NS-C081, App D).6  
NRC Question 9 Who is relied upon to actually recover the EDG (maintenance, operations  
or engineering  
personnel)?  
How is that accounted  
for in your results?APS Response 9 The associated  
HRA credited the recovery of K-1 relay contactor  
by Electrical
Maintenance  
personnel  
with technical  
support from Electrical  
Maintenance  
Engineering
personnel.
Operations  
would immediately  
know of the EDG output failure after the engine start by control room indication/alarms  
as well as by Emergency  
Response Facility Data Acquisition  
Display System (ERFDADS)  
flat line output. Operations  
would not attempt to correct this condition  
since no specific proceduralized  
instructions  
are readily available  
to them. Electrical  
Maintenance  
personnel  
and Electrical  
Maintenance
Engineering  
would be immediately  
called (Maintenance  
onsite 24/7). Maintenance  
and Engineering  
would have the primary responsibility  
for recovery of the affected EDG after a loss of generator  
output. If not onsite, Electrical  
Maintenance  
Engineering  
personnel would be contacted  
immediately  
for technical  
assistance  
by phone or pager. Although the faulted EDG may not be running at the time when Maintenance  
and/or Engineering
become involved, Maintenance  
and Engineering  
personnel  
would be informed that the EDG started and ran without power output. Prior plant experience  
is that it takes 2-3 hours to replace the K-1 contactor.  
That repair action, however, is not required because recovery can be easily accomplished  
by manual bypass (opening)  
of the K-1 relay contactor.
Following  
the involvement  
of Electrical  
Maintenance  
personnel  
and their Engineering
support, the time required for EDG 3A loss of output diagnosis  
is estimated  
at 5 to 10 minutes. It is based on operating  
experience  
at PVNGS (including  
a recent failure in Unit 3) and engineering  
knowledge  
that when there is no voltage buildup at all by the generator  
immediately  
after an engine start, the most likely cause would be a failure of the field shorting (K-1) contactor.
No immediate  
indications  
of a K-1 problem would exist at the EDG with it in a shutdown condition, however, the plant ERFDADS computer (powered by uninterruptible  
power supply E-NQN-D01)  
monitors and records the voltage and frequency  
buildup for each EDG start. Those records are preserved  
for several hours. A data flat line showing no attempt at all to build up generator  
output voltage would be a strong indicator  
of a K-1 contactor  
problem. In contrast, if the generator  
rotor is spinning, the K-1 has dropped out properly and field flashing fails to occur, then generator  
output voltage would still build up slowly due to its residual magnetism.
With the engine in a shutdown condition, Engineering  
may advise Maintenance  
to functionally  
test the K-1 and field flash (FF) contactors  
using the Manual Field Flash 7  
(MFFPB) push button on the generator  
control panel as long as 135 VDC control power was still available.  
One wire inside the cabinet would have to be lifted and the 135 VDC FF breaker would have to be opened prior to the manual field flash test. This functional
test was recently used (7/26/2006  
3A loss of output event) to verify that a newly installed  
spare K-1 was working properly.The task of establishing  
EDG 3A output is considered  
a recovery action consistent  
with RG 1.200, Table A-1. The following  
justifications  
are provided:* The failed K-1 relay would very likely be bypassed rather than repaired.  
Bypass is particularly  
easy to perform. The fault is recoverable  
by a simple manual action of releasing  
the K-1 contactor  
reset latch after an engine start. After the 2nd EDG 3A no output failure (9/22/06), no equipment  
was required to be replaced." Ease of diagnosis  
is supported  
by recent similar incidents  
and adequate personnel  
training, which includes K-1 relays." Responsible  
plant personnel  
are easily accessible  
by pager or telephone." Ample time is available  
for diagnosis  
and action to bypass the failed relay contactor." No special tools are required for diagnosis  
or relay bypass manual action, and there are no issues with accessibility.
* Plant personnel  
responsible  
for diagnosis  
and bypass would not be subjected  
to the potentially  
high stress level facing the control room personnel." Flat line data for EDG voltage and frequency  
on ERFDADS computer would quickly lead to the determination  
that K-1 relay has malfunctioned.
NRC Question 10 Why did we not use the Unit 3 battery design calculation?  
How does that affect the applicability  
of the results to the Unit 3 battery?APS Response 10 The Unit 2 calculation  
was used because it had been updated to reflect a number of implemented  
design changes, which the existing Unit 3 calculation  
had not yet incorporated.  
The designs of the DC systems are quite similar in all three units, and one model was originally  
used to represent  
any of the units. Due to a desire to improve accuracy and the availability  
of more powerful modeling tools, Palo Verde converted  
the Class 1E DC system calculation  
to unitized models in the mid-1 990's.A comparison  
between the Unit 2 calculation  
results to an updated Unit 3 computerized
model, which reflects the current configuration (though not yet finalized), was performed.  
The load profiles are comparable  
with only minor variations  
due to nameplate  
voltage ratings of motor operated valves and variations  
due to differences  
in cable lengths. Two of the auxiliary  
feed water valves on Unit 3 were found to have lower voltages than the same valves in Unit 2, however, the valves have adequate 8  
margin to accommodate  
these voltage differences.  
In light of the considerable  
margins between the battery capacities  
and the load demands of a 7-hour station blackout event (27 and 60 percent for the 'A' and 'C' batteries  
respectively), the differences  
between the designs of Unit 2 and 3 are insignificant  
to the conclusions  
of the evaluation  
of the K-1 relay issue.NRC Question 11 Do the spikes in battery 'E' graph in presentation  
slide "Empirical  
Data 'E' Battery" correlate  
with battery recharging?
APS Response 11 Yes. The first spike shown on the graph (November  
7, 2004) is a result of the recharge of the battery under PMWO 2647054 and the second recharge was performed  
under PMWO 2794319, on May 5, 2006.9
}}

Latest revision as of 09:39, 23 November 2019

APS Response to NRC Inspection Report 05000528/2006012; 05000529/2006012; 05000530/2006012
ML070390040
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 01/24/2007
From: James M. Levine
Arizona Public Service Co
To:
Document Control Desk, NRC Region 4
References
102-05636/JML/SAB/TNW/CJS, IR-06-012
Download: ML070390040 (11)


Text

LA subsidiaryof Pinnacle West CapitalCorporation James M. Levine Mail Station 7602 Palo Verde Nuclear Executive Vice President Tel (623) 393-5300 PO Box 52034 Generating Station Generation Fax (623) 393-6077 Phoenix, Arizona 85072-2034 102-05636-JMLJSAB/TNW/CJS January 24, 2007 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

Dear Sir:

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Units 1, 2 and 3 Docket Nos. STN 50-528, 50-529, and 50-530 APS Response to NRC Inspection Report 05000528/2006012; 0500052912006012; 0500053012006012 In NRC Special Inspection Report 2006012, dated December 6, 2006, the NRC documented their examination of activities associated with the PVNGS Unit 3, Train A, emergency diesel generator (EDG) failures that occurred on July 25 and September 22, 2006. At a January 16, 2007 Regulatory Conference in Arlington, Texas, APS provided the NRC its perspective on the facts and analytical assumptions relevant to determining the safety significance of the findings, in accordance with the Inspection Manual Chapter 0609.

The purpose of this letter is to provide the additional information requested by the NRC during the regulatory conference. The Enclosure to this letter contains 7 questions that were requested at the close of the conference and 4 additional questions that were part of the conference general discussion. There are no regulatory commitments in this letter.

If you have any questions, please contact Thomas N. Weber at (623) 393-5764.

Sincerely, JMLJSABITNW/CJS/gt

U.S. Nuclear Regulatory Commission ATTN: Document Control Desk APS Response to NRC Inspection Report 05000528/2006012; 05000529/2006012; 05000530/2006012 Page 2

Enclosure:

Additional Information Requested at the January 16, 2007 NRC Regulatory Conference cc: B. S. Malleft NRC Region IV Regional Administrator M. B. Fields NRC NRR Project Manager M. T. Markley NRC NRR Project Manager G. G. Warnick NRC Senior Resident Inspector for PVNGS

ENCLOSURE Additional Information Requested at the January 16, 2007 NRC Regulatory Conference NRC Question 1 Is it acceptable to provide auxiliary feedwater to a steam generator after it has dried out?

APS Response 1 Yes. The Unit 3 steam generators are designed with an allowance for feeding a hot dry steam generator with cold feedwater. APS asked ABB (the design authority for the PVNGS Steam Generators) about the maximum allowed flow rate for feedwater to a hot dry steam generator. The ABB response stated "the generators are designed to handle seven cycles of adding 40 degrees F feedwater at 1750 gpm." The information was requested to support development of the PVNGS Emergency Operating Procedures.

This information is documented in ABB Inter-Office Correspondence V-MPS-91-163, dated, November 14, 1991.

NRC Question 2 What reliability/unavailability for the Gas Turbine Generators (GTGs) was assumed in the Probabilistic Risk Analysis (PRA)? Provide the data that was used to obtain these values. Please indicate how buried cable reliability is addressed in the PRA.

APS Response 2 GTG Reliability Gas Turbine Generator (GTG) fail to start and fail to run probabilities are Bayesian updated values based on the values in Advanced Light Water ReactorRequirements Document (ALWR), Volume II, Chapter 1, Appendix A - PRA Key Assumptions and Groundrules, Electric Power Research Institute, Revision 6, December 1993, pages A.A-67 and A.A-68. The number of GTG demands, accumulated run time, and failures were collected for the period of 1/1/1998 to 10/1/2004 and documented in study 13-NS-C076, Plant Specific Reliability Data for PRA Model, Revision 0, Appendix C: PRA Final Failures and Demands Report. The values were based on an actual count (they were not estimated). For the given time period and system boundary, there were 6 failures (3 on GTG 1 and 3 on GTG 2) in 267 demands and 0 failures in 283 hours0.00328 days <br />0.0786 hours <br />4.679233e-4 weeks <br />1.076815e-4 months <br />. The final failure probabilities were 2.5E-2 per demand and 4.2E-5 per hour.

1

GTG Unavailability GTG unavailability is based on an actual count of unavailable hours during the period 1/1/1999 through 12/31/2001 as documented in study 13-NS-C064, Plant Specific UnavailabilityData for PRA Model, Revision 0, Appendix A: Individual Parameter Unavailability Listings Gas Turbine Generator. There were 954.68 hours7.87037e-4 days <br />0.0189 hours <br />1.124339e-4 weeks <br />2.5874e-5 months <br /> unavailable in the 26304 hour period for a probability of 1.81 E-2.

GTG UnderQround Cable Reliability The underground cables between the GTGs and the units are modeled separately from the GTGs. The cable is not direct buried but runs in an underground conduit. Two three phase cables are used to supply power to each unit. The failure probability is a Bayesian updated value based on the value in IEEE Standard 500-1984, IEEE Guide to the Collection and Presentationof Electrical,Electronic, Sensing Component and MechanicalEquipment ReliabilityData for Nuclear-PowerGeneratingStations, Institute of Electrical and Electronics Engineers, Inc., December 13, 1983, Reaffirmed 1991, page 770. This value is multiplied by the length of the cable (3475' for Unit 1, See note below) obtained from the Plant Data Management System EDB ElectricalDatabase, since the IEEE value is given per 1000' cable length. Based on a search of EPIX/NPRDS, Failure Data Trending, and CRDRs, there were zero cable failures since the GTGs were installed. In the search, 4 instances were identified (CRDRs 2559098, 2564721, 2580013, and 2843631) where the results of megger testing was less than the service criteria but greater than the emergency criteria. These tests had been evaluated by Maintenance Engineering and it was determined that since the as-found readings were greater than the emergency allowed value, the cables would have been able to perform their function. Appropriate corrective actions were taken in each case to restore the cables such that the service criteria were met.

Engineering Support provided a Maintenance Rule Hours in Mode Summary Report for the date range of 9/27/1993 (date of first GTG isochronous test) through 11/30/2006.

The exposure time was taken as the time spent in Modes 1 through 6 in each unit, for an exposure time of 334,836 hours0.00968 days <br />0.232 hours <br />0.00138 weeks <br />3.18098e-4 months <br /> for the 3 units. Since there are two cables per unit, the total exposure time is 669,672 hours0.00778 days <br />0.187 hours <br />0.00111 weeks <br />2.55696e-4 months <br />. From a unit perspective, a load test powering that unit's cables from the GTGs is performed every 18 months per 40DP-9OP06, OperationsDepartmentRepetitive Task Program,Task GT002. The Bayesian updated failure rate for one cable was 1.46E-2 per hour, for a failure probability of a standby component of 9.59E-3. Since there are two cables, the final probability for the underground GTG cable was 1.91 E-2 (equivalent to an "OR" gate).

Note: A single PRA model based on Unit 1 is used at PVNGS. Plant differences are accounted for when performing specific applications. Since a continuously energized failure rate is being applied to a cable energized only a very short period of its exposed life, the value is very conservative and bounds all three units.

2

NRC Question 3 Describe how the PRA handles the recovery of the Auxiliary Feedwater (AF) Train "N" pump once the GTG is on line. What dependency exists between getting GTG alignment and AF "N" alignment?

APS Response 3 In a Station Blackout, restoration of a motor-driven AFW pump after alignment of the GTGs is required if auxiliary feedwater from the turbine driven pump is lost to the SGs and power is not available. This scenario involves failure of both the Maintenance of Vital Auxiliaries and RCS Heat Removal safety functions. As such, Operations would be directed to the Functional Recovery procedure 40EP-9EO09 for this condition. The Control Room Supervisor retains the option to proceed with the Blackout procedure with the understanding that the mitigating strategy (restoration of power) will resolve both failed safety functions. The procedure actions are similar, and both direct Operations to initially restore power to PBA-S03 from a GTG, after determination that offsite power and EDGs can not be restored within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

Procedure 40EP-9EO09, FunctionalRecovery, Section 8.0, Maintenance of Vital Auxiliaries, Success path MVAC 3: GTGs, provides the instructions to start and load the GTGs onto a Class 1E 4.16kV AC Bus. Step 8.7 directs performance of Appendix 80 "When NAN-S07 is energized, align GTG to PBA-S03 (BO)". Alternately available to Operations is step 8.7.1 which directs performance of Appendix 81 "When NAN-S07 is energized, Align GTGs to PBB-S04 (BO)". The equivalent steps to align a GTG to a Class 1E 4.16kV AC bus are provided in the Blackout procedure 40EP-9EO08, in steps 13 and 13.1.

Standard Appendix 80 [81] (40EP-9EO10) step 7 [9] completes the actions necessary to energize the Class 1E 4.16kV AC bus PBA-S03 [PBB-S04]. At this time power is available to start an AFW pump and initiate AFW flow to a SG. Step 9, of Appendix 80, directs an Operator [Licensed Control Room Operator] to check that AFA is being used to maintain at least one SG at 45%-60% NR level, else if the AFA pump is not available, then align and start AFN-P01 to restore SG level. Step 11, of Appendix 81, directs the Operator to start AFB-P01 to restore SG level.

The Control Room Supervisor (CRS) has the responsibility to manage the operator resources during the event. The description below reflects what would typically be the assignments made for power recovery and AFW recovery. Specific assignments may vary, but there are always two licensed control room operators available to perform the two main functions of power recovery and AFW recovery without dependency between the tasks. The tasks are also separated in time, with power recovery required prior to AFW recovery for this scenario. The same is true of the 4 Auxiliary Operators. The specific operator assigned to a task may vary, but sufficient resources exist to perform all the tasks without any dependency.

3

Actions necessary to start and align the AFN-P01 pump or AFB-P01 pump are typically performed by the Controls Operator from the Control Room. To initiate flow from the AFN-P01 pump, the Controls Operator must open the two (2) suction MOVs, open a Downcomer Bypass MOV (one per SG), open the Downcomer Isolation valves (2 per SG), and start the pump. To initiate flow from the AFB-P01 pump, the Controls Operator must only start the pump, given the discharge isolation and regulation valves are open due to the AFAS actuation. The time to take these actions is less than 5 minutes.

The Licensed Operators are extensively trained on these actions during various simulator events. The detailed actions are not prescriptively described in the Emergency Operating Procedures, but are simple and easily accomplished by any control room operator as a result of their training. Failure of the Controls Operator to initiate AFW flow to at least one SG would be immediately recovered by the Control Room Supervisor and/or the STA. The Controls Operator typically has no other dependent responsibilities for power restoration. Initiation of AFW for restoration of the RCS Heat Removal safety function is the Control Operator's primary focus, thus ample time is available for proper diagnosis and recovery. The PRA does not model a specific HRA for failure to establish AFW flow after power is restored to a Class 1E 4.16kV AC bus because the failure probability for the AFW restoration action is so low it is negligible compared to the action to restore power.

Recovery of the 4.16KV AC bus from a GTG is typically performed bythe Reactor Operator [Licensed Control Room Operator] with assistance from an assigned Auxiliary Operator (AO), typically the Area 4 AO and the Water Reclamation Facility Operator.

The assigned AO would have no responsibilities for assisting with the recovery of the assumed failed AFA-P01 pump, which is typically assigned to a different AO (Area 1).

There are no required actions of the Controls Operator to support the power recovery actions, nor any actions of the Reactor Operator to support the AFW recovery actions, other than the standard actions to maintain cognizance of critical system parameters.

No Auxiliary Operators are required for recovery of AFW after power has been restored to a 4.16kV AC bus. Actions to restore power and initiate AFW are considered to have zero dependency.

NRC Question 4 Which EOP covers overriding automatic control (AFAS) and taking manual control of AF "A"? How soon does this happen based on simulator experience? This relates to the battery analysis assumption that the AF isolation valves do not continuously cycle, as assumed in the design calculation.

APS Response 4 Procedure 40EP-9EO01, StandardPost Trip Actions, has the Secondary Operator override AFAS valves to ensure feed flow is not excessive. Operators are trained to take manual control of the feed rate to preclude a SIAS, which would likely follow an AFAS, due to overcooling. The operator will typically initiate this action by starting AFA-4

P01 from control room panel B06, and establish feed by opening the block valves and throttling the regulation valves. This would normally occur (assuming a Station Blackout) prior to an AFAS actuation. The isolation valves are left open and are not cycled and the only valve manipulations are adjustments to feed rate using the regulation valves.

In the event of an AFAS automatic actuation, the operator will take control of feed rate, and not allow the regulation valves to control level. The specific feed rate is not scripted, but the safety function is met when level in at least one steam generator is increasing towards its normal band as required by Procedure 40EP-9EO01. Experience in the simulator is that operators~will take manual control of AF in no longer than 10 minutes during a station blackout (SBO) event.

Once level is recovered, the operator feeds at a rate sufficient to makeup for level lost due to steaming out the Atmospheric Dump Valves (ADVs).

NRC Question 5 In the lower recovery path of the "Event Timelines for Station Blackout @ t=0" slide of the presentation, APS provided times of 58 and 95 minutes for 'steam generator (SG) dryout' and 'latest SG makeup can be initiated'. How does the PRA use these two values? What importance is given to each value?

APS Response 5 The 58 minute time is used in Loss of Offsite Power accident sequences as the basis for the time to start and align the gas turbine generators. The 95 minute time is not used for Loss of Offsite Power accident sequences. The 95 minute time is used as the time available for providing feed to the steam generators using the condensate pumps for sequences that do not include a Loss of Offsite Power. Thus the 95 minute time has no importance in the K-1 relay significance determination.

NRC Question 6 Provide the analysis that was done to extend the battery life from the 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> design requirement to 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> for the PRA.

APS Response 6 NUS-5058, Analysis of Station Blackout Accidents at PVNGS-1, Yovan Lukic, NUS Corporation, November 1987, Section 4.1, "Description of Top Events within the SBO event tree", subsection "Failure to Restore Power within 3 Hours", is the basis document for the 3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> battery life in the PVNGS PRA model. This source states:

5

Based on a review of 125 VDC bus loads typical to an SBO event and the 18 month and 60 months test of the DC batteries (Refs. 6 and 7), it is assessed that DC batteries will last for at least 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> into an SBO event. The 60 month test established that 1200 amp-hours can be provided by each DC battery (PKA and PKB) before the 105 VDC battery under-voltage condition is reached. Given a conservative estimate of the battery loads during SBO, each battery would have to provide on the order of 1000 amp-hours during the first 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> into an SBO event. This 20% excess in battery capacity is sufficient to cover the power requirements when the battery is operated at near 80% capacity (end-of-life).

It should be noted that batteries with larger capacity (2415 amp-hours) were installed since this change was implemented in the PRA model.

NRC Question 7 Provide updated analysis for seven hour battery capacity.

APS Response 7 The updated analysis for seven hour battery capacity was provided to the NRC on January 19, 2007. This updated analysis reflects additional capacity loss for the 'A' battery, which was recognized following the January 16, 2007 Regulatory Conference.

This additional battery capacity loss resulted in the total capacity loss being greater than 10 percent, which placed the 'A' battery in Technical Specification 3.8.4.8, requiring a 12 month surveillance test, like the 'C' battery. This surveillance test will be performed along with the 'C' battery test in the upcoming Unit 3 mid-cycle outage. The updated analysis demonstrates that the assumptions for the risk significance evaluation remain valid, with margin.

NRC Question 8 Did operator failure probabilities for restoration of the Emergency Diesel Generator (EDG) include the potential that operations would fail to shut down the EDG as required if it started but the field did not flash, because of the lack of jacket cooling water?

APS Response 8 Yes. APS considered the operator failing to stop the EDG after the field did not flash.

The step was not identified as critical because the failure contribution (-2E-4) was not a significant contribution to the total value of the HRA value for recovery of the EDG. HRA quantification 4DG-RECVR-KI-1-HR has a value of 5.8E-2 and 4DG-RECVR-K1-7-HR has a value of 3.2E-3 (reference 13-NS-C081, App D).

6

NRC Question 9 Who is relied upon to actually recover the EDG (maintenance, operations or engineering personnel)? How is that accounted for in your results?

APS Response 9 The associated HRA credited the recovery of K-1 relay contactor by Electrical Maintenance personnel with technical support from Electrical Maintenance Engineering personnel.

Operations would immediately know of the EDG output failure after the engine start by control room indication/alarms as well as by Emergency Response Facility Data Acquisition Display System (ERFDADS) flat line output. Operations would not attempt to correct this condition since no specific proceduralized instructions are readily available to them. Electrical Maintenance personnel and Electrical Maintenance Engineering would be immediately called (Maintenance onsite 24/7). Maintenance and Engineering would have the primary responsibility for recovery of the affected EDG after a loss of generator output. If not onsite, Electrical Maintenance Engineering personnel would be contacted immediately for technical assistance by phone or pager. Although the faulted EDG may not be running at the time when Maintenance and/or Engineering become involved, Maintenance and Engineering personnel would be informed that the EDG started and ran without power output. Prior plant experience is that it takes 2-3 hours to replace the K-1 contactor. That repair action, however, is not required because recovery can be easily accomplished by manual bypass (opening) of the K-1 relay contactor.

Following the involvement of Electrical Maintenance personnel and their Engineering support, the time required for EDG 3A loss of output diagnosis is estimated at 5 to 10 minutes. It is based on operating experience at PVNGS (including a recent failure in Unit 3) and engineering knowledge that when there is no voltage buildup at all by the generator immediately after an engine start, the most likely cause would be a failure of the field shorting (K-1) contactor.

No immediate indications of a K-1 problem would exist at the EDG with it in a shutdown condition, however, the plant ERFDADS computer (powered by uninterruptible power supply E-NQN-D01) monitors and records the voltage and frequency buildup for each EDG start. Those records are preserved for several hours. A data flat line showing no attempt at all to build up generator output voltage would be a strong indicator of a K-1 contactor problem. In contrast, if the generator rotor is spinning, the K-1 has dropped out properly and field flashing fails to occur, then generator output voltage would still build up slowly due to its residual magnetism.

With the engine in a shutdown condition, Engineering may advise Maintenance to functionally test the K-1 and field flash (FF) contactors using the Manual Field Flash 7

(MFFPB) push button on the generator control panel as long as 135 VDC control power was still available. One wire inside the cabinet would have to be lifted and the 135 VDC FF breaker would have to be opened prior to the manual field flash test. This functional test was recently used (7/26/2006 3A loss of output event) to verify that a newly installed spare K-1 was working properly.

The task of establishing EDG 3A output is considered a recovery action consistent with RG 1.200, Table A-1. The following justifications are provided:

  • The failed K-1 relay would very likely be bypassed rather than repaired. Bypass is particularly easy to perform. The fault is recoverable by a simple manual action of releasing the K-1 contactor reset latch after an engine start. After the 2nd EDG 3A no output failure (9/22/06), no equipment was required to be replaced.

" Ease of diagnosis is supported by recent similar incidents and adequate personnel training, which includes K-1 relays.

" Responsible plant personnel are easily accessible by pager or telephone.

" Ample time is available for diagnosis and action to bypass the failed relay contactor.

" No special tools are required for diagnosis or relay bypass manual action, and there are no issues with accessibility.

  • Plant personnel responsible for diagnosis and bypass would not be subjected to the potentially high stress level facing the control room personnel.

" Flat line data for EDG voltage and frequency on ERFDADS computer would quickly lead to the determination that K-1 relay has malfunctioned.

NRC Question 10 Why did we not use the Unit 3 battery design calculation? How does that affect the applicability of the results to the Unit 3 battery?

APS Response 10 The Unit 2 calculation was used because it had been updated to reflect a number of implemented design changes, which the existing Unit 3 calculation had not yet incorporated. The designs of the DC systems are quite similar in all three units, and one model was originally used to represent any of the units. Due to a desire to improve accuracy and the availability of more powerful modeling tools, Palo Verde converted the Class 1E DC system calculation to unitized models in the mid-1 990's.

A comparison between the Unit 2 calculation results to an updated Unit 3 computerized model, which reflects the current configuration (though not yet finalized), was performed. The load profiles are comparable with only minor variations due to nameplate voltage ratings of motor operated valves and variations due to differences in cable lengths. Two of the auxiliary feed water valves on Unit 3 were found to have lower voltages than the same valves in Unit 2, however, the valves have adequate 8

margin to accommodate these voltage differences. In light of the considerable margins between the battery capacities and the load demands of a 7-hour station blackout event (27 and 60 percent for the 'A' and 'C' batteries respectively), the differences between the designs of Unit 2 and 3 are insignificant to the conclusions of the evaluation of the K-1 relay issue.

NRC Question 11 Do the spikes in battery 'E' graph in presentation slide "Empirical Data 'E' Battery" correlate with battery recharging?

APS Response 11 Yes. The first spike shown on the graph (November 7, 2004) is a result of the recharge of the battery under PMWO 2647054 and the second recharge was performed under PMWO 2794319, on May 5, 2006.

9