05000255/FIN-2010005-01: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
Line 12: Line 12:
| identified by = NRC
| identified by = NRC
| Inspection procedure = IP 71111.08
| Inspection procedure = IP 71111.08
| Inspector = M Holmberg, B Jose, J Cassidy, M Mitchell, J Ellegood, T Taylor, J Corujo,-Sandin G, Hanse
| Inspector = M Holmberg, B Jose, J Cassidy, M Mitchell, J Ellegood, T Taylor, J Corujo-Sandin, G Hansen
| CCA = H.7
| CCA = H.7
| INPO aspect = WP.3
| INPO aspect = WP.3
| description = A finding of very low safety significance and associated NCV of 10 CFR 50.55a(g)4 was identified by the inspectors for the licensees failure to establish a weld reference system for 11 welds in the cross-tie line between the chemical and volume control system and the containment spray system. Consequently, these welds had not been entered into the inservice inspection weld database used to schedule followup surface or volumetric examinations. To correct this issue, the licensee implemented changes to the applicable Inservice Inspection isometric drawings and entered these welds into the Inservice Inspection database. The violation was entered into the licensees corrective action program as CR PLP-2010-05229. The finding was determined to be more than minor because the finding, if left uncorrected, would become a more significant safety concern. Absent NRC identification, the licensee would not have examined a sample of these welds, which could have allowed service induced cracks to go undetected. Undetected cracks would place the cross-tie pipe segment at increased risk for through-wall leakage and/or failure, which affected the Mitigating System Cornerstone attribute of Equipment Performance (reliability). The licensee promptly corrected this issue and scheduled weld examinations to ensure cracks would be detected. The inspectors answered Yes to the Significance Determination Process Phase I screening question; Is the finding a design or qualification deficiency confirmed not to result in loss of operability or functionality? Therefore, the finding screened as having very low safety significance. This finding had a cross-cutting aspect in the area of Human Performance, Resources because the licensee did not provide complete, accurate, and up-to-date procedures, or work packages for the correct labeling of components. Specifically, the licensee staff failed to establish a weld reference system because up-to-date procedures were not developed to ensure identification and labeling of new welds installed in safety-related systems. (H.2(c)) (Section 1R08.1).
| description = A finding of very low safety significance and associated NCV of 10 CFR 50.55a(g)4 was identified by the inspectors for the licensees failure to establish a weld reference system for 11 welds in the cross-tie line between the chemical and volume control system and the containment spray system. Consequently, these welds had not been entered into the inservice inspection weld database used to schedule followup surface or volumetric examinations. To correct this issue, the licensee implemented changes to the applicable Inservice Inspection isometric drawings and entered these welds into the Inservice Inspection database. The violation was entered into the licensees corrective action program as CR PLP-2010-05229. The finding was determined to be more than minor because the finding, if left uncorrected, would become a more significant safety concern. Absent NRC identification, the licensee would not have examined a sample of these welds, which could have allowed service induced cracks to go undetected. Undetected cracks would place the cross-tie pipe segment at increased risk for through-wall leakage and/or failure, which affected the Mitigating System Cornerstone attribute of Equipment Performance (reliability). The licensee promptly corrected this issue and scheduled weld examinations to ensure cracks would be detected. The inspectors answered Yes to the Significance Determination Process Phase I screening question; Is the finding a design or qualification deficiency confirmed not to result in loss of operability or functionality? Therefore, the finding screened as having very low safety significance. This finding had a cross-cutting aspect in the area of Human Performance, Resources because the licensee did not provide complete, accurate, and up-to-date procedures, or work packages for the correct labeling of components. Specifically, the licensee staff failed to establish a weld reference system because up-to-date procedures were not developed to ensure identification and labeling of new welds installed in safety-related systems. (H.2(c)) (Section 1R08.1).
}}
}}

Latest revision as of 19:40, 20 February 2018

01
Site: Palisades Entergy icon.png
Report IR 05000255/2010005 Section 1R08
Date counted Dec 31, 2010 (2010Q4)
Type: NCV: Green
cornerstone Mitigating Systems
Identified by: NRC identified
Inspection Procedure: IP 71111.08
Inspectors (proximate) M Holmberg
B Jose
J Cassidy
M Mitchell
J Ellegood
T Taylor
J Corujo-Sandin
G Hansen
CCA H.7, Documentation
INPO aspect WP.3
'