05000255/FIN-2010005-05
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Failure to Perform Daily Crane Checks |
Description | The inspectors identified a NCV of TS 5.4 for the licensees failure to implement procedures specified by Regulatory Guide 1.33. Specifically, the licensee failed to perform a check of the main hook in preparations for the head lift. The procedure used to perform checks lacked details regarding the polar crane for features to be tested on a daily basis. The individual who performed the initial daily check was not familiar with the features to be checked. After the inspectors brought this condition to the attention of the licensee, the licensee delayed the head lift and performed the daily check on the main hook. The licensee has entered this condition into their corrective action program. The inspectors concluded that the finding was more than minor, because it revealed programmatic weaknesses that could lead to more significant safety concerns if left uncorrected. Daily crane checks provide assurance that the probability of a heavy load drop is extremely small as discussed in Generic Letter 85-11, the Operating Requirements Manual, and NUREG-0612. The issue impacts the Initiating Event Cornerstone in that load drops could result in a failure of the primary coolant system boundary. Since no load drop occurred and no significant issues were identified with the polar crane, the inspectors concluded the finding was of very low safety significance in accordance with Appendix M. Since the failure to perform the daily check on the main hook resulted, in part, from ineffective coordination between personnel performing load moves, the inspectors concluded that there is an associated cross-cutting aspect in human performance, work control, appropriate coordination of work activities. (H.3(b)) (Section 1R22) |
Site: | Palisades |
---|---|
Report | IR 05000255/2010005 Section 1R22 |
Date counted | Dec 31, 2010 (2010Q4) |
Type: | NCV: Green |
cornerstone | Initiating Events |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.22 |
Inspectors (proximate) | M Holmberg B Jose J Cassidy M Mitchell J Ellegood T Taylor J Corujo-Sandin G Hansen |
CCA | H.5, Work Management |
INPO aspect | WP.1 |
' | |
Finding - Palisades - IR 05000255/2010005 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Palisades) @ 2010Q4