| {{#Wiki_filter:[7590-01-P] NUCLEAR REGULATORY COMMISSION [Docket Nos. 52-025 and 52-026; NRC-2008-0252] Southern Nuclear Operating Company, Inc., Vogtle Electric Generating Plant, Units 3 and 4; AGENCY: Nuclear Regulatory Commission. ACTION: License amendment application; withdrawal by licensee. SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has granted a request by Southern Nuclear Operating Company to withdraw its application dated July 29, 2016, for a proposed amendment to Combined Licenses (COL), NPF-91 and NPF-92 for the Vogtle Electric Generating Plant (VEGP) Units 3 and 4, respectively. The COLs were issued to Southern Nuclear Operating Company, Inc., Georgia Power Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC, MEAG Power SPVJ, LLC, MEAG Power SPVP, LLC, and the City of Dalton, Georgia (the licensee); for construction and operation of the VEGP Units 3 and 4, located in Burke County, Georgia. The amendment would have added an Interim Amendment Request (IAR) Process to License Condition 2.D.(1) of VEGP Units 3 and 4 COLs for changes during construction when emergent conditions are present. DATES: March 20, 2018. | | {{#Wiki_filter:[7590-01-P] NUCLEAR REGULATORY COMMISSION [Docket Nos. 52-025 and 52-026; NRC-2008-0252] Southern Nuclear Operating Company, Inc., Vogtle Electric Generating Plant, Units 3 and 4; AGENCY: Nuclear Regulatory Commission. |
| 2 ADDRESSES: Please refer to Docket ID NRC-2008-0252 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods:
| | ACTION: License amendment application; withdrawal by licensee. |
| * Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2008-0252. Address questions about NRC dockets to Jennifer Borges; 301-287-9127; e-mail: Jennifer.Borges@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
| | SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has granted a request by Southern Nuclear Operating Company to withdraw its application dated July 29, 2016, for a proposed amendment to Combined Licenses (COL), NPF-91 and NPF-92 for the Vogtle Electric Generating Plant (VEGP) Units 3 and 4, respectively. The COLs were issued to Southern Nuclear Operating Company, Inc., Georgia Power Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC, MEAG Power SPVJ, LLC, MEAG Power SPVP, LLC, and the City of Dalton, Georgia (the licensee); for construction and operation of the VEGP Units 3 and 4, located in Burke County, Georgia. |
| * NRC's Agencywide Documents Access and Management System (ADAMS): You may obtain publicly-available documents online in the ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select "ADAMS Public Documents" and then select "Begin Web-based ADAMS Search." For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr.resource@nrc.gov. The ADAMS accession number for each document referenced (if it is available in ADAMS) is provided the first time that it is mentioned in this document. The request for the amendment was submitted by letter dated July 29, 2016, and supplemented by letter dated January 5, 2017. These letters are available in ADAMS under Accession Nos. ML16211A436 and ML17005A514.
| | The amendment would have added an Interim Amendment Request (IAR) Process to License Condition 2.D.(1) of VEGP Units 3 and 4 COLs for changes during construction when emergent conditions are present. |
| * NRC's PDR: You may examine and purchase copies of public documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. FOR FURTHER INFORMATION CONTACT: Chandu Patel, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-3025; e-mail: Chandu.Patel@nrc.gov.
| | DATES: March 20, 2018. |
| 3 SUPPLEMENTARY INFORMATION:
| |
| Southern Nuclear Operating Company is a holder of two COLs NPF-91 and NPF-92, issued to Southern Nuclear Operating Company, Inc., Georgia Power Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC, MEAG Power SPVJ, LLC, MEAG Power SPVP, LLC , and the City of Dalton, Georgia (the licensee), for construction and operation of the VEGP Units 3 and 4, located in Burke County, Georgia. The NRC has granted the licensee's request to withdraw the LAR to amend both COLs, dated July 29, 2016, as supplemented by letter dated January 5, 2017. The proposed amendment requested that the NRC staff approve an additional license amendment process called an IAR that would be added to License Condition 2.D.(1) in COLs NPF-91 and NPF-92. Based on the application and supplemental information the licensee provided, the licensee intended to use the proposed IAR process to obtain expedited approval of requested changes during construction in certain emergent conditions when the licensee finds that a construction activity is not in conformance with the licensing basis but there is little or no safety significance and the construction activity can't be adjusted. The proposed IAR process would have been used to allow construction to proceed until the non-conforming condition is resolved when there is insufficient time to conduct a detailed, technical, safety analysis to support a license amendment request or the preliminary amendment request process already approved by the Commission.
| |
|
| |
|
| 4 The NRC staff issued an initial Federal Register notice of opportunity to request a hearing on this LAR and a proposed No Significant Hazards Consideration determination on October 11, 2016 (81 FR 70184). Dated at Rockville, Maryland, this 13 day of March 2018. | | 2 ADDRESSES: |
| For the Nuclear Regulatory Commission. /RA/ Jennifer L. Dixon-Herrity, Chief, Licensing Branch 4, Division of New Reactor Licensing, Office of New Reactors.}} | | Please refer to Docket ID NRC-2008-0252 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods: |
| | * Federal Rulemaking Web site |
| | : Go to http://www.regulations.gov and search for Docket ID NRC-2008-0252. Address questions about NRC dockets to Jennifer Borges; 301-287-9127; e-mail: Jennifer.Borges@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document. |
| | * NRC's Agencywide Documents Access and Management System (ADAMS): You may obtain publicly-available documents online in the ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select " |
| | ADAMS Public Documents" and then select "Begin Web-based ADAMS Search." For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr.resource@nrc.gov. The ADAMS accession number for each document referenced (if it is available in ADAMS) is provided the first time that it is mentioned in this document. The request for the amendment was submitted by letter dated July 29, 2016, and supplemented by letter dated January 5, 2017. These letters are available in ADAMS under Accession Nos. ML16211A436 and ML17005A514. |
| | * NRC's PDR: You may examine and purchase copies of public documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. FOR FURTHER INFORMATION CONTACT: Chandu Patel, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-3025; e-mail: |
| | Chandu.Patel@nrc.gov |
| | . |
| | 3 SUPPLEMENTARY INFORMATION: |
| | |
| | Southern Nuclear Operating Company is a holder of two COLs NPF-91 and NPF-92, issued to Southern Nuclear Operating Company, Inc., Georgia Power Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC, MEAG Power SPVJ, LLC, MEAG Power SPVP, LLC , and the City of Dalton, Georgia (the licensee), for construction and operation of the VEGP Units 3 and 4, located in Burke County, Georgia. The NRC has granted the licensee's request to withdraw the LAR to amend both COLs, dated July 29, 2016, as supplemented by letter dated January 5, 2017. |
| | The proposed amendment requested that the NRC staff approve an additional license amendment process called an IAR that would be added to License Condition 2.D.(1) in COLs NPF-91 and NPF-92. Based on the application and supplemental information the licensee provided, the licensee intended to use the pr oposed IAR process to obtain expedited approval of requested changes during construction in certain emergent conditions when the licensee finds that a construction activity is not in conformance with the licensing basis but there is little or no safety significance and the construction activity can't be adjusted. The proposed IAR process would have been used to allow construction to proceed until the non-conforming condition is resolved when there is insufficient time to conduct a detailed, technical, safety analysis to support a license amendment request or the preliminary amendment request process already approved by the Commission. |
| | |
| | 4 The NRC staff issued an initial Federal Register notice of opportunity to request a hearing on this LAR and a proposed No Significant Hazards Consideration determination on October 11, 2016 (81 FR 70184). |
| | Dated at Rockville, Maryland, this 13 day of March 2018. |
| | |
| | For the Nuclear Regulatory Commission. |
| | /RA/ Jennifer L. Dixon-Herrity, Chief, Licensing Branch 4, Division of New Reactor Licensing, |
| | |
| | Office of New Reactors.}} |
|
---|
Category:Federal Register Notice
MONTHYEARML24102A2662024-09-11011 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - FRN ML24102A2642024-09-0909 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - Letter ML24102A2652024-09-0909 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - Exemption ML24114A3102024-05-0303 May 2024 Monthly (28-Day) Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 14, 2024 ML24096A1322024-04-0505 April 2024 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for Hearing and Order (EPID L-2024-LLA-0043) - Letter ML24096A1332024-04-0505 April 2024 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for Hearing and Order (EPID L-2024-LLA-0043) - FRN ML23275A2402024-03-22022 March 2024 SNC Fleet - Issuance of Environmental Assessment and Finding of No Significant Impact Regarding Exemption from the Requirements of 10 CFR Part 73, Section 73.2, Definitions (EPID Nos. L-2023-LLE-0018 & L-2023-LLE-0021) - Letter ML23275A2382024-03-22022 March 2024 SNC Fleet, Issuance of Environmental Assessment and Finding of No Significant Impact Regarding Exemption from the Requirements of 10 CFR Part 73, Section 73.2, Definitions (EPID Nos. L-2023-LLE-0018 & L-2023-LLE-0021) - FRN ML24044A0732024-02-28028 February 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - January 2024 ML23096A1982023-08-0202 August 2023 Exemption from the Requirements of 10 CFR 50, Appendix K, ECCS (Emergency Core Cooling Systems) Evaluation Models (EPID L-2022-LLE-0021) - FRN ML23094A0992023-08-0202 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 68, Criticality Accident Requirements (EPID L-2022-LLE-0022)- FRN ML23093A1052023-08-0202 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors (EPID L-2022-LLE-0020) - FRN ML22348A1022023-07-28028 July 2023 103g - FRN ML23123A3572023-05-16016 May 2023 Individual Federal Register Notice of Consideration Regarding License Amendment Request Timing of Technical Specification Effectiveness Prior to Initial Criticality (LAR-23-005) ML23044A0962023-02-24024 February 2023 Federal Register Final Notice of Issuance - Vogtle Unit 3 Amendment No. 190 Technical Specification Exceptions for In-containment Refueling Water Storage Tank Operability Prior to Initial Criticality ML23018A2282023-01-30030 January 2023 FRN Notice of Issuance of Vogtle Electric Generating Plant, Unit 3, Emergency License Amendment Request: Technical Specification Limiting Conditions for Operation 3.4.11, 3.4.12, and 3.4.13 Operability Requirements for Auto Depressurization ML22286A0382022-11-23023 November 2022 Federal Register Notice of Issuance for Amendment and Exemption Electrical Inspections, Tests, Analyses, and Acceptance Criteria Optimization (LAR 22-003) ML22251A3552022-09-21021 September 2022 FRN - Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing, VEGP 4 ML22210A1932022-08-0909 August 2022 Federal Register Notice - Vogtle Multiple ITAAC FRN Q1 and Q2 2022 ML20290A2832022-08-0303 August 2022 Federal Register Notice Regarding Affirmative 10 CFR 52.103(g) Finding and Commencement of Operations ML21320A0442021-11-23023 November 2021 FRN Exemption from the Requirements of 73.55(a)(4) and 73.56(a)(3) (EPID L-2021-LLE-0049)_Rev.1 ML21279A1922021-11-23023 November 2021 Draft Federal Register Notice Regarding Exemption from Operator Written Examination and Operating Test for Unit 4 Licenses ML21179A1762021-08-0505 August 2021 FRN for Issuance of Exemption - Farley and Vogtle FSAR Update Exemption - Rev 1 ML21179A1852021-08-0404 August 2021 Exemption - Farley and Vogtle - FSAR Update Exemption - Rev 1 ML21071A0512021-08-0303 August 2021 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors (FRN) ML21070A3172021-04-0202 April 2021 Environmental Assessment and Finding of No Significant Impact; Issuance ML21070A3102021-04-0202 April 2021 Environmental Assessment and Finding of No Significant Impact Related to Exemption from the Requirements of 10 CFR Part 50, Section 50.46, Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power ML20147A6632020-09-17017 September 2020 Proposed Alternative Requirements for ASME Code Preservice Inspection Acceptance of Volumetric and Surface Examinations ML20126G2972020-07-21021 July 2020 Federal Register Notice for Vogtle Electric Generating Plant Unit 4 Issuance of Exemption from 10 CFR Part 50, Appendix E ML20035C4082020-02-18018 February 2020 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 02/25/2020 ML19183A0242019-07-15015 July 2019 Federal Register Notice (FRN) for NRC Staff'S Determination of Completion of Multiple ITAAC for Vogtle Electric Generating Plant, Units 3 and 4 ML19171A0072019-06-26026 June 2019 Final Individual Federal Register Notice (Notice of Issuance) for LAR 18-030 ML19168A0842019-06-26026 June 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 07/02/2019 ML19137A3252019-06-12012 June 2019 Final Individual FRN for LAR 18-028 ML19108A2442019-06-0707 June 2019 Federal Register Notice, Issuance of Exemption for Vogtle Electric Generating Plant Units 3 and 4, for 10 CFR Part 26 Visitor Access Requirements ML19126A0582019-05-31031 May 2019 Federal Register Notice - Vogtle Electric Generating Plant Units 3 and 4 Request for Exemption from Operator Written Examination and Operating Test ML19140A4562019-05-28028 May 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 06/04/2019 ML19073A0092019-04-24024 April 2019 (LAR-18-024) Final Individual Federal Register Notice (Notice of Issuance) ML19060A2752019-04-24024 April 2019 Individual Final Federal Register Notice for LAR 18-031, Clarification of ASME Code Section III Compliance and Alternative Requirements ML19091A2832019-04-0808 April 2019 2019-Q1 Vogtle - Multiple ITAAC FRN ML19085A2172019-03-29029 March 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 04/09/2019 ML19046A4062019-03-12012 March 2019 Individual Final FRN for LAR 18-025 ML19064A3992019-03-0606 March 2019 Individual FRN for LAR 18-019 (Correction) ML19056A5352019-02-28028 February 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 03/12/2019 NRC-2019-0065, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 03/12/20192019-02-28028 February 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 03/12/2019 ML18318A3362019-02-26026 February 2019 (LAR 17-043) Federal Register Individual Notice of Issuance ML19032A6302019-02-22022 February 2019 Individual Federal Register Notice (LAR 18-019) ML19052A2352019-02-22022 February 2019 Individual FRN (LAR 18-016) ML19042A3062019-02-15015 February 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 2/26/2019 ML19010A2802019-01-25025 January 2019 Individual Issuance FRN Amendment Nos. 149 and 148 (LAR 18-022) 2024-09-09
[Table view] Category:License-Combined License (COL) (New/Renewal/Amendments) DKT 52
MONTHYEARML23243B0542023-12-19019 December 2023 VEGP Unit 4 Amendment No. 193 - Enclosure 2 ML23243A9682023-12-19019 December 2023 VEGP Unit 3 Amendment No. 197 - Enclosure 1 ML23310A2922023-12-0707 December 2023 Issuance of Amendment for Exception to Regulatory Guide 1.163, LAR 23 007 ML23339A1812023-12-0707 December 2023 Correction Letter Regarding License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 ML23289A1632023-11-28028 November 2023 Letter and Amendment 195 and 192 LAR-23-006R1 TS 3.1.9 More Restrictive Action ML23159A0972023-07-31031 July 2023 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 23-001) ML23072A2722023-05-0101 May 2023 Enclosure 1 - LAR 22-005 Amendment No. 191 Vogtle Unit 3 ML23072A2732023-05-0101 May 2023 Enclosure 2 - LAR 22-005 Amendment No. 188 Vogtle, Unit 4 ML23072A2762023-05-0101 May 2023 Attachment to Enclosure 2 - VEGP U4 Amendment 188 LAR-22-005 ML23037A0892023-02-0808 February 2023 Amendment - Vogtle Unit 3 Amendment No. 190, Tech Spec Exceptions for In-Containment Refueling Water Storage Tank Operability Prior to Initial Criticality (Exigent Circumstances) ML20290A2822022-08-0303 August 2022 Finding That Acceptance Criteria in the Combined License Are Met (10 CFR 103g - Finding) ML21237A2342021-10-15015 October 2021 Amendment Unit 3 - Vogtle Electric Generating Plant LAR 21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2352021-10-15015 October 2021 Attachment Unit 3 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2372021-10-15015 October 2021 Attachment Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2362021-10-15015 October 2021 Amendment Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21217A0242021-09-17017 September 2021 Amendment No. 187 - Vogtle Electric Generating Plant Unit 3 ML21217A0252021-09-17017 September 2021 Amendment No. 185 - Vogtle Electric Generating Plant Unit 4 ML21217A0272021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment No. 185 ML21217A0262021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment No. 187 ML20314A0132020-12-0707 December 2020 License Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 20-005) ML20314A0142020-12-0707 December 2020 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment 184 (LAR-20-005) ML20314A0102020-12-0707 December 2020 License Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 20-005) ML20314A0112020-12-0707 December 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 186 (LAR-20-005) ML20247J4612020-10-14014 October 2020 Amendment 183 - Vogtle Electric Generating Plant Unit 4 (LAR 20-004) ML20247J4592020-10-14014 October 2020 Amendment 185 - Vogtle Electric Generating Plant Unit 3 (LAR 20-004) ML20237F4922020-09-24024 September 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 184 (LAR-20-003) ML20237F4942020-09-24024 September 2020 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment 182 (LAR-20-003) ML20237F4932020-09-24024 September 2020 Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 20-003) ML20237F4912020-09-24024 September 2020 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 20-003) ML20196L6772020-08-11011 August 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 183 for LAR-20-002 ML20196L6782020-08-11011 August 2020 Amendment 181 - Vogtle Electric Generating Plant Unit 4 for LAR 20-002 ML20196L6792020-08-11011 August 2020 Attachment - Vogtle Electric Generating Plant Unit 4 for Amendment 181 for LAR-20-002 ML20132A0762020-08-0404 August 2020 Attachment - Vogtle Electric Generating Plant Unit 3 (LAR 20-001) ML20059N7792020-05-12012 May 2020 Amendment 181 - LAR-19-010: Auxiliary Building Room Heatup ML20059N7822020-05-12012 May 2020 Amendment 180 - LAR-19-010: Auxiliary Building Room Heatup ML20106F1632020-05-12012 May 2020 Attachment to Amendment 180 - LAR-19-010: Auxiliary Building Room Heatup ML20106F1622020-05-12012 May 2020 Attachment to Amendment 181 - LAR-19-010: Auxiliary Building Room Heatup ML20120A0072020-04-30030 April 2020 Attachment for Amendment 178 Cyber Security Plan Changes (LAR-19-020) ML20106F1592020-04-30030 April 2020 Attachment for Amendment 179 Cyber Security Plan Changes (LAR-19-020) ML20057E1172020-04-30030 April 2020 Amendment 178 - Issuance of Amendments for Cyber Security Plan Changes (LAR-19-020) ML20057E1062020-04-30030 April 2020 Amendment 179 - Issuance of Amendments for Cyber Security Plan Changes (LAR-19-020) ML20064E6682020-03-23023 March 2020 Enclosure 4: Supplemental Attachment to License Amendment No. 148 for COL No. NPF-91 ML20064E6802020-03-23023 March 2020 Enclosure 5: Supplemental Attachment to License Amendment No. 147 for COL No. NPF-92 ML20064E5722020-03-23023 March 2020 Supplemental Attachment to License Amendment No. 36 for COL No. NPF-92 ML20064E6122020-03-23023 March 2020 Enclosure 2: Supplemental Attachment to License Amendment No. 125 for COL No. NPF-91 ML20064E6282020-03-23023 March 2020 Enclosure 3: Supplemental Attachment to License Amendment No. 124 for COL No. NPF-92 ML20013G6882020-02-0303 February 2020 Amendment - Vogtle Electric Generating Plant Unit 4 ML19350C7002020-01-28028 January 2020 Attachment - Vogtle Electric Generating Plant Unit 3 (LAR 19-015).d ML19350C7142020-01-28028 January 2020 Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 19-015) ML19350C6862020-01-28028 January 2020 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 19-015) 2023-07-31
[Table view] |
Text
[7590-01-P] NUCLEAR REGULATORY COMMISSION [Docket Nos.52-025 and 52-026; NRC-2008-0252] Southern Nuclear Operating Company, Inc., Vogtle Electric Generating Plant, Units 3 and 4; AGENCY: Nuclear Regulatory Commission.
ACTION: License amendment application; withdrawal by licensee.
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has granted a request by Southern Nuclear Operating Company to withdraw its application dated July 29, 2016, for a proposed amendment to Combined Licenses (COL), NPF-91 and NPF-92 for the Vogtle Electric Generating Plant (VEGP) Units 3 and 4, respectively. The COLs were issued to Southern Nuclear Operating Company, Inc., Georgia Power Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC, MEAG Power SPVJ, LLC, MEAG Power SPVP, LLC, and the City of Dalton, Georgia (the licensee); for construction and operation of the VEGP Units 3 and 4, located in Burke County, Georgia.
The amendment would have added an Interim Amendment Request (IAR) Process to License Condition 2.D.(1) of VEGP Units 3 and 4 COLs for changes during construction when emergent conditions are present.
DATES: March 20, 2018.
2 ADDRESSES:
Please refer to Docket ID NRC-2008-0252 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods:
- Federal Rulemaking Web site
- Go to http://www.regulations.gov and search for Docket ID NRC-2008-0252. Address questions about NRC dockets to Jennifer Borges; 301-287-9127; e-mail: Jennifer.Borges@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
ADAMS Public Documents" and then select "Begin Web-based ADAMS Search." For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr.resource@nrc.gov. The ADAMS accession number for each document referenced (if it is available in ADAMS) is provided the first time that it is mentioned in this document. The request for the amendment was submitted by letter dated July 29, 2016, and supplemented by letter dated January 5, 2017. These letters are available in ADAMS under Accession Nos. ML16211A436 and ML17005A514.
- NRC's PDR: You may examine and purchase copies of public documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. FOR FURTHER INFORMATION CONTACT: Chandu Patel, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-3025; e-mail:
Chandu.Patel@nrc.gov
.
3 SUPPLEMENTARY INFORMATION:
Southern Nuclear Operating Company is a holder of two COLs NPF-91 and NPF-92, issued to Southern Nuclear Operating Company, Inc., Georgia Power Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC, MEAG Power SPVJ, LLC, MEAG Power SPVP, LLC , and the City of Dalton, Georgia (the licensee), for construction and operation of the VEGP Units 3 and 4, located in Burke County, Georgia. The NRC has granted the licensee's request to withdraw the LAR to amend both COLs, dated July 29, 2016, as supplemented by letter dated January 5, 2017.
The proposed amendment requested that the NRC staff approve an additional license amendment process called an IAR that would be added to License Condition 2.D.(1) in COLs NPF-91 and NPF-92. Based on the application and supplemental information the licensee provided, the licensee intended to use the pr oposed IAR process to obtain expedited approval of requested changes during construction in certain emergent conditions when the licensee finds that a construction activity is not in conformance with the licensing basis but there is little or no safety significance and the construction activity can't be adjusted. The proposed IAR process would have been used to allow construction to proceed until the non-conforming condition is resolved when there is insufficient time to conduct a detailed, technical, safety analysis to support a license amendment request or the preliminary amendment request process already approved by the Commission.
4 The NRC staff issued an initial Federal Register notice of opportunity to request a hearing on this LAR and a proposed No Significant Hazards Consideration determination on October 11, 2016 (81 FR 70184).
Dated at Rockville, Maryland, this 13 day of March 2018.
For the Nuclear Regulatory Commission.
/RA/ Jennifer L. Dixon-Herrity, Chief, Licensing Branch 4, Division of New Reactor Licensing,
Office of New Reactors.