ML20153C722: Difference between revisions
StriderTol (talk | contribs) StriderTol Bot insert |
StriderTol (talk | contribs) StriderTol Bot change |
||
| (One intermediate revision by the same user not shown) | |||
| Line 14: | Line 14: | ||
| document type = CORRESPONDENCE-LETTERS, OUTGOING CORRESPONDENCE | | document type = CORRESPONDENCE-LETTERS, OUTGOING CORRESPONDENCE | ||
| page count = 4 | | page count = 4 | ||
| project = TAC:M93887, TAC:M93888 | |||
| stage = Approval | |||
}} | }} | ||
=Text= | =Text= | ||
{{#Wiki_filter:____ ___._._ __..___ _ | {{#Wiki_filter:____ ___._._ __..___ _ | ||
l | l i | ||
L September 18, 1998 1 | |||
Mr. Oliver D. Kingsley, President Nudear Generation. Group Cemmonwealth Edison Ccmpany | Mr. Oliver D. Kingsley, President Nudear Generation. Group Cemmonwealth Edison Ccmpany E <ecutive Towers West til j | ||
t 400 Opus Place, Suite 500 Downers Grove,IL 60515 | |||
==SUBJECT:== | ==SUBJECT:== | ||
RESPONSE TO NRC BULLETIN 95 LASALLE COUNTY STATION, UNITS 1 AND 2 (TAC NOS. M93887 AND M93888) | RESPONSE TO NRC BULLETIN 95 LASALLE COUNTY STATION, UNITS 1 AND 2 (TAC NOS. M93887 AND M93888) | ||
Dear Mr. Kingsley- | Dear Mr. Kingsley-By letters dated November 14,1995, and January 10,1996, Commonwealth Edison Company (Comed, the licensee) submitted its response to NRC Bulletin 95-02," Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating in Suppression Pool Cooling Mode," for LaSalle County Station, Units 1 and 2. The staff's safety evaluation (SE) of the licensee's response is enclosed. | ||
l | l NRC Bulletin 95-02 requested that licensees review the operability of their emergency core cooling system (ECCS) and other pumps which draw suction from the suppression pool while l | ||
cooling system (ECCS) and other pumps which draw suction from the suppression pool while performing their safety function. The licensee's evaluation should be based on suppression pool cleanliness, suction strainer cleanliness, and the effectivenest of their foreign material exclusion (FME) practices, in addition, licensees were requested to implement appropriate procedural modifications and other actions (e.g., suppression pool cleaning) as necessary to minimize foreign material in the suppression pool, drywell, and containment. Licensees were also i | performing their safety function. The licensee's evaluation should be based on suppression pool cleanliness, suction strainer cleanliness, and the effectivenest of their foreign material exclusion (FME) practices, in addition, licensees were requested to implement appropriate procedural modifications and other actions (e.g., suppression pool cleaning) as necessary to minimize foreign material in the suppression pool, drywell, and containment. Licensees were also i | ||
l Sincerely, | requested to verify their operability evaluation through appropriate testing and inspection. In its I | ||
response letters of November 14,1995, and January 10,1996, the licensee agreed to comply with all of the requested actions. The staff has concluded that the licensee's response is acceptable. | |||
FOR | l Sincerely, I | ||
ORIG. SIGNED BY S. BAILEY FOR | |||
. Donna M. Skay, Project Manager I | |||
G | 9809240182 980918 | ||
.i Project Directorate ill-2 l | |||
PDR ADOCK 05000374 Division of Reactor Projects -lil/IV l | |||
G PDR Office of Nuclear Reactor Regulation DISTRIBUTION: | |||
J/ | |||
Docket Nos. 50-373, 50-374 Docket File PUBLIC PDill 2 r/f l | |||
EAdensam, EGA1 SRichards DSkay | |||
==Enclosure:== | ==Enclosure:== | ||
SE | SE CMoore OGC, 0-15818 ACRS, T2E26 RLanksbury, Rlli DHills, Rill RElliott cc w/ encl: See next page - | ||
JHickman l | |||
NAME | "7 NRC RLE CENTEB COPY l | ||
DOCUMENT NAME: G:\\CM\\LASALLE\\95 02.LAS To rtceive a copy of this document, indice' Oyhehen: *C* = Copy without enclosures *E* = Copy with enclosures *N* = No copy OFFICE PM:PDlli-2 LAS Jhl-2 Vs8CSB lC PM:PDill-2 lE D:PDlll-2 l (k, | |||
NAME DSKAY:sp (JV BMGOl%E RELLIOTT M'IP JHICKMANN'SRICHARDSW DATE 09/ H /98 " | |||
09/ % /98 09/1C /98 09/ /s/98F 09/ lb/98 OFFICIAL RECORD COPY p | |||
e | e usuq' p | ||
NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. ma m | t UNrfED STATES g | ||
j NUCLEAR REGULATORY COMMISSION o | |||
e WASHINGTON, D.C. ma m | |||
/ | |||
September 18, 1998 d | |||
Mr. Oliver D. Kingsley, President Nuclear Generation Group Commonwealth Edison Company Executive Towers West lli 1400 Opus Place, Suite 500 Downers Grove,IL 60515 | |||
==SUBJECT:== | ==SUBJECT:== | ||
RESPONSE TO NRC BULLETIN 95 LASALLE COUNTY STATION, UNITS 1 l | RESPONSE TO NRC BULLETIN 95 LASALLE COUNTY STATION, UNITS 1 l | ||
AND 2 (TAC NOS. M93887 AND M93888) 1 | |||
==Dear Mr. Kingsley:== | ==Dear Mr. Kingsley:== | ||
By letters dated November 14,1995, and January 10,1996, Commonwealth Edison Company (Comed, the licensee) submitted its response to NRC Bulletin 95-02, " Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating in Suppression Pool Cooling Mode," for LaSalle County Station, Units 1 and 2. The staff's safety evaluation (SE) of the I | |||
By letters dated November 14,1995, and January 10,1996, Commonwealth Edison Company (Comed, the licensee) submitted its response to NRC Bulletin 95-02, " Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating in Suppression Pool Cooling | licensee's response is enclosed. | ||
~ | |||
NRC Bulletin 95-02 requested that licensees review the operability of their emergency core cooling system (ECCS) and other pumps which draw suction from the suppression pool while performing their safety function. The licensee's evaluation should be based on suppression pool cleanliness, suction strainer cleanliness, and the effectiveness of their foreign material exclusion (FME) practices. In addition, licensees were requested to implement appropriate procedural modifications and other actions (e.g., suppression pool cleaning) as necessary to minimize foreign materialin the suppression pool, drywell, and containment. Licensees were also | |||
NRC Bulletin 95-02 requested that licensees review the operability of their emergency core cooling system (ECCS) and other pumps which draw suction from the suppression pool while performing their safety function. The licensee's evaluation should be based on suppression pool cleanliness, suction strainer cleanliness, and the effectiveness of their foreign material exclusion (FME) practices. In addition, licensees were requested to implement appropriate procedural | . requested to verify their operability evaluation through appropriate testing and inspection. In its response letters of November 14,1995, and January 10,1996, the licensee agreed to comply with all of the requested actions. The staff has concluded that the licensee's response is acceptable. | ||
Sincerely, V onna M. Skay, P | |||
* nager D | |||
Sincerely, V onna | Project Directorate lil 2 Division of Reactor Projects - lil/IV Office of Nuclear Reactor Regulation Docket Nos. 50 373, 50-374 4 | ||
* nager Project Directorate lil 2 Division of Reactor Projects - lil/IV Office of Nuclear Reactor Regulation | |||
==Enclosure:== | ==Enclosure:== | ||
SE cc w/ encl: See next page | SE cc w/ encl: See next page | ||
_ . _ .. . _ q | _. _... _ q l | ||
l O. Kingsley LaSalle County Station Commonwealth Edison Company Units 1 and 2 cc: | |||
Phillip P. Steptoe, Esquire Michael 1. Miller, Esquire Sidley and Austin Sidley and Austin One First National Plaza One First National Plaza I | |||
l O. Kingsley | Chicago, Illinois 60603 Chicago, Illinois 60603 Assistant Attomey General Document Control Desk Licensing 100 W. Randolph St. Suite 12 Commonwealth Edison Company l | ||
Commonwealth Edison Company | Chicago, Illinois 60601 1400 Opus Place, Suite 400 U.S. NRC LaSalle Resident inspectors Omco l | ||
Phillip P. Steptoe, Esquire | 2605 N. 21st Road Commonwealth Edison Company 1 | ||
l Marseilles, Illinois 61341 9756 Site Vice President - LaSalle 2601 N. 21st Road Chairman Marseilles, Illinois 61341-9757 LaSalle County Board of Supervisors LaSalle County Courthouse Mr. David Helwig Ottawa, Illinois 61350 Senior Vice President Commonwealth Edison Company Attom6y General Executive Towers West lil 500 S. Second Street 1400 Opus Place, Suite 900 Springfiek', Illinois 62701 Downers Grove,IL 60515 Chairman Mr. Gene H. Stanley Illinois Commerce Commission PWR's Vice President 527 E. Capitol Avenue, Leland Building Commonwealth Edison Company Springfield, Illinois 62706 Executive Towers West ll1 | |||
Chicago, Illinois 60603 | ' 1400 Opus Place, Suite 900 lilinois Department of Nuclear Safety Downers Grove,IL 60515 Office of Nuclear Facility Safety 1035 Outer Park Drive Mr. Steve Perry Springfield, Illinois 62704 BWR's Vice President Commonwealth Edison Company Regional Administrator Executive Towers West lll U.C. NRC, Region lil 1400 Opus Place, Suite 900 601 Warrenville Road Downers Grove,IL 60515 | ||
Assistant Attomey General | < Lisle, Illinois 60532-4351 Mr. Dennis Farrar Commonwealth Edison Company Regulatory Services Manager LaSalle Station Manager Commonwealth Edison Company 2601 N. 21st Road Executive Towers West lil Marseilles, Illinois 61341 9757-1400 Opus Place, Suite 500 Downers Grove,IL 60515 Robert Cushing, Chief, Public Utilities Division | ||
'lilinois Attomey General's Office l | |||
l 100 W. Randolph Street | |||
Commonwealth Edison Company Regional Administrator | , Chicago, Illinois 60601 l | ||
. ~ | |||
l l | l l | ||
: 0. Kingsley | : 0. Kingsley LaSalle County Station Commonwealth Edison Company Units 1 and 2 Ms. Irene Johnson, Ucensing Director Nuclear Regulatory Services l | ||
Commonwealth Edison Company | Commonwealth Edison Company | ||
) | |||
l Executive Towers West til 1400 Opus Place, Suite 500 Downers Grove,IL 60515 Commonwealth Edison Company l | l Executive Towers West til 1400 Opus Place, Suite 500 Downers Grove,IL 60515 Commonwealth Edison Company l | ||
Mr. MichaelJ. Wallace | Reg. Assurance Supervisor-LaSalle l-2601 N. 21st Road l | ||
Marseilles, Illinois 61341-g757 Mr. MichaelJ. Wallace Senior Vice President Commonwealth Edison Company Executive Towers West til 1400 Opus Place, Suite 900 Downers Grove,IL 60515 i | |||
s a | s a | ||
$ Ktty p | |||
DOCKET NOS. 50-373 AND 50-374 | UNITED STATES g | ||
j NUCLEAR REGULATORY COMMISSION o, | |||
f WASHINGTON, D.C. 2000Hl001 g,.....p SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO NRC But i PTIN 95-02 COMMONWEALTH EDISON COMPANY LASALLE COUNTY STATION. UNITS 1 AND 2 DOCKET NOS. 50-373 AND 50-374 | |||
==1.0 INTRODUCTION== | ==1.0 INTRODUCTION== | ||
NRC Bulletin 95-02, " Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating in Suppression Pool Cooling Mode," was issued on October 17,1995, it requested all holders of boiling-water reactor (BWR) operating licenses or construction permits for nuclear power reactors to take five actions to ensure that unacceptable buildup of debris that could clog strainers does not occur during normal operation. By letteis dated November 14, 1995, and January 10,1996, Commonwealth Edison Company (Comed, the licensee) submitted its response to NRC Bulletin 95-02 for LaSalle County Station, Units 1 and 2. In its response, the licensee stated its intent to comply with the requested actions !n the bulletin. | NRC Bulletin 95-02, " Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating in Suppression Pool Cooling Mode," was issued on October 17,1995, it requested all holders of boiling-water reactor (BWR) operating licenses or construction permits for nuclear power reactors to take five actions to ensure that unacceptable buildup of debris that could clog strainers does not occur during normal operation. By letteis dated November 14, 1995, and January 10,1996, Commonwealth Edison Company (Comed, the licensee) submitted its response to NRC Bulletin 95-02 for LaSalle County Station, Units 1 and 2. In its response, the licensee stated its intent to comply with the requested actions !n the bulletin. | ||
2.0 DISCUSSION | 2.0 DISCUSSION The following describes the requested actions in NRC Bulletin 95 02 and the licensee's response to each requested action. | ||
The following describes the requested actions in NRC Bulletin 95 02 and the licensee's response to each requested action. | |||
Action i Verify the operability of all pumps which draw suction from the suppression pool when performing their safety functions (e.g., ECCS (emergency core cooling system), containment spray, etc.), | Action i Verify the operability of all pumps which draw suction from the suppression pool when performing their safety functions (e.g., ECCS (emergency core cooling system), containment spray, etc.), | ||
based on an evaluation of suppression pool and suction strainer cleanliness conditions. This | based on an evaluation of suppression pool and suction strainer cleanliness conditions. This evaluation should be based on the pool and strainer conditions during the last inspection or cleaning and an assessment of the potential for the introduction of debris or other materials that could clog the strainers since the pool was last cleaned. | ||
evaluation should be based on the pool and strainer conditions during the last inspection or cleaning and an assessment of the potential for the introduction of debris or other materials that could clog the strainers since the pool was last cleaned. | |||
===Response=== | ===Response=== | ||
The Unit 1 suppression pool strainers were inspected during that unit's refueling outage in April 1994, and the Unit 2 suppression pool strainers were inspected during that unit's refueling outage in March 1995. During that inspection, all identified foreign material was removed and the suppression pool cleanup system was used to improve the turbidity and lonic quality of the suppression pool water. On Unit 1, a SCRAM, with a safety relief valve lift, occurred in August 1995, followed by Residual Heat Removal (RHR) A and B operation for suppression pool cooling. | The Unit 1 suppression pool strainers were inspected during that unit's refueling outage in April 1994, and the Unit 2 suppression pool strainers were inspected during that unit's refueling outage in March 1995. During that inspection, all identified foreign material was removed and the suppression pool cleanup system was used to improve the turbidity and lonic quality of the suppression pool water. On Unit 1, a SCRAM, with a safety relief valve lift, occurred in August 1995, followed by Residual Heat Removal (RHR) A and B operation for suppression pool cooling. | ||
No flow degradation was identified in the pump discharge pressure from those runs. For both units, quarterty in service testing ECCS pump surveillance data was reviewed and no ENCLOSURE 9009240194 980918 PDR | No flow degradation was identified in the pump discharge pressure from those runs. For both units, quarterty in service testing ECCS pump surveillance data was reviewed and no ENCLOSURE 9009240194 980918 PDR ADOCK 05000373 G | ||
PDR | |||
7.. _ | 7.. _ | ||
~ _. _ _. _ _ _ -. | |||
2-degradation of pump suction pressure was identified. Finally, a foreign material exclusion (FME) program, developed in response to NRC Bulletin 93-02 and 93-02, Supplement 1, has been in place since February 1994. Based on the above, the licensee concluded that all pumps which draw suction from the suppression pool while performing their safety function are operable. | |||
Action 2 Confirm the operability evaluation in requested action 1 above through appropriate test (s) and strainer inspection (s) within 120 days of the date of this bulletin. | Action 2 Confirm the operability evaluation in requested action 1 above through appropriate test (s) and strainer inspection (s) within 120 days of the date of this bulletin. | ||
===Response=== | ===Response=== | ||
Multiple ECCS (RHR and Low Pressure Core Spray) pump tests were performed to confirm ECCS suction strainer operability on January 4,1996, for Unit 1 and on January 5,1996, for Unit 2. No decrease in pump suction pressure was identified over the course of the 8 hour tests. | |||
Action 3 Schedule a suppression pool (torus) cleaning. The schedule for cleaning the suppression pool should be consistent with the operability evaluation in requested action 1 above. in addition, a program for periodic cleaning of the suppression pool should be established, including procedures for the cleaning of the pool, criteria for determining the appropriate cleaning frequency, and criteria for evaluating the adequacy of the pool cleanliness. | Action 3 Schedule a suppression pool (torus) cleaning. The schedule for cleaning the suppression pool should be consistent with the operability evaluation in requested action 1 above. in addition, a program for periodic cleaning of the suppression pool should be established, including procedures for the cleaning of the pool, criteria for determining the appropriate cleaning frequency, and criteria for evaluating the adequacy of the pool cleanliness. | ||
===Response=== | ===Response=== | ||
i | i In the {{letter dated|date=November 14, 1995|text=November 14,1995, letter}}, the licensee committed to clean, inspect, and desludge the suppression pools for each unit during its next scheduled refueling outage. in addition, cleanliness of the suppressio pool will be maintained by the following program. A multiple ECCS pump run will be repeated starting at every second future refueling outage of each unit. | ||
Two strainers will be inspected at every second outage, altemating between using remote cameras (or equivalent) or a direct diver inspection. | Two strainers will be inspected at every second outage, altemating between using remote cameras (or equivalent) or a direct diver inspection. | ||
Action 4 Review FME pnacedures and their implementation to determine whether adequate control of materials in the drywell, suppression pool, and systems that interface with the suppression pool | Action 4 Review FME pnacedures and their implementation to determine whether adequate control of materials in the drywell, suppression pool, and systems that interface with the suppression pool exists. This review should determine if comprehensive FME controls have been established to prevent materials that could potentially impact ECCS operation from being introduced into the suppression pool, and that workers are sufficiently aware of their responsibilities regarding FME. | ||
Any identified weaknesses should be corrected in addition, the effectiveness of the FME controls since the last time the suppression pool was cleaned and the ECCS strainers inspected, and the impact that any weaknesses noted may have on the operability of the ECCS, should be assessed. | Any identified weaknesses should be corrected in addition, the effectiveness of the FME controls since the last time the suppression pool was cleaned and the ECCS strainers inspected, and the impact that any weaknesses noted may have on the operability of the ECCS, should be assessed. | ||
4 4 | 4 4 | ||
) | |||
v- | |||
3- | |||
controls include drywell closecut procedural steps, FME logs, and expande6 availability of FME | |||
===Response=== | |||
Action 5 j | The licensee stated that, although existing FME procedures are adequate, it is continuously working to enhance the FME program. A standardized maintenance procedure will be implemented which includes actions to preclude FME events. The suppression pool and drywell i | ||
are permanently designated as zones requiring the highest level of FME controls. Additional controls include drywell closecut procedural steps, FME logs, and expande6 availability of FME 4 | |||
devices to preclude introduction of foreign material into the suppression pool. | |||
Action 5 j | |||
Consider additional measures such as suppression pool water sampling and trending of pump suction pressure to detect clogging of ECCS suction strainers. | |||
Resoonse Beyond the actions described above, ECCS pump suction pressure will be trended and an inspection program for the suppression pool downcomers will be implemented. | Resoonse Beyond the actions described above, ECCS pump suction pressure will be trended and an inspection program for the suppression pool downcomers will be implemented. | ||
I | I 3.0 EVALUATION The purpose of the requested actions in the bulletin is to ensure that ECCS and other pumps drawing suction from the suppression pool do not experience unacceptable buildup of debris that could c69 strainers during normal operation which would prevent them from performing their safety function. Action 1 requested licensees to evaluate the operability of their pumps based on the cleanliness of the suppression pool and strainers. Action 2 then requested a verification of i | ||
the 'icensee's assessment through a pump test and strainerinspection. These two actions serve to ensure that the pumps are currently operable and not experiencing unacceptable debris buildup. Actions 3,4'and 5 serve to ensure that appropriate measures, such as cleariing of suppression pools and strengthening of FME practices, are taken in the long term to prevent debns accumulation in the pool. | |||
j. | |||
As committed to in the licensee's response to action 3, the suppression pools were cleaned and desludged during the 1996 refueling outages. During the Unit 1 cleaning, a number of small Items were found and removed under the silt layer as well as a quantity of silt. No concems were identified. During the Unit 2 cleaning, however, a significant quantity of foreign material was 4 | |||
removed from under the sitt layer which appeared to have been in the pool since initial construction. These findings are documented in Licensee Event Report 96-09. Although this material raised questions with regard to past operability, the foreign material and the silt were 1 | |||
removed as part of this cleaning. | |||
a The staff has concluded that the licensee's assessment of the ability of all pumps drawing suction from the suppression pool to perform their safety function has a reasonable basis for concluding that all of the pumps evaluated are operable. The licensee conducted an inspection to confirm that the ECCS were not affected by an unacceptable buildup of debris that could clog the pump strainers. Initial strainer cleanliness was considered good. The staff has concluded i | |||
The staff has concluded that the licensee's assessment of the ability of all pumps drawing suction from the suppression pool to perform their safety function has a reasonable basis for | that the licensee's response meets the intent of requested actions 1 and 2 and is acceptable. | ||
d n | |||
--- ~ | |||
d | m,- | ||
,c w-- | |||
~ --- -.- | |||
4 The staff has also concluded that the licensee's evaluation of its FME program and suppression pool cleaning program meet the intent of requested actions 3 and 4, and are acceptable. | 4 The staff has also concluded that the licensee's evaluation of its FME program and suppression pool cleaning program meet the intent of requested actions 3 and 4, and are acceptable. | ||
Although the Unit 2 sump had a significant quantity of foreign material at the time of the licensee response, the subsequent cleaning removed the material. The discovery of this material did not call into question the licensee's current FME program because the majority of material was deterrrined to have been deposited prior to implementation of the licensee's enhanced FME controls. | Although the Unit 2 sump had a significant quantity of foreign material at the time of the licensee response, the subsequent cleaning removed the material. The discovery of this material did not call into question the licensee's current FME program because the majority of material was deterrrined to have been deposited prior to implementation of the licensee's enhanced FME controls. | ||
The licensee's programs fMending pump suction pressure data, sampling torus water / sediment, and periodically inspecting the strainers and torus provide additional opportunity for early identificatioa of potential strainer fouling. The staff has concluded that these additior.al actions meet the intent of requested action 5 and are acceptable. The staff has also concluded that the schedule for implementation of the actions proposed by the licensee is appropriate given the actions already taken. | |||
4.0 CQNr.LUSION Based on the staff's evaluation of the licensee's submittals, the staff finds the licensea's response to NRC Bulletin 95-02 acceptable. | 4.0 CQNr.LUSION Based on the staff's evaluation of the licensee's submittals, the staff finds the licensea's response to NRC Bulletin 95-02 acceptable. | ||
Principal Contributors: John B. Hickman R. Elliot (By precedent) | Principal Contributors: John B. Hickman R. Elliot (By precedent) | ||
Date: September 18, 1998 l | Date: September 18, 1998 l | ||
l | l | ||
... -}} | |||
Latest revision as of 03:01, 11 December 2024
| ML20153C722 | |
| Person / Time | |
|---|---|
| Site: | LaSalle |
| Issue date: | 09/18/1998 |
| From: | Skay D NRC (Affiliation Not Assigned) |
| To: | Kingsley O COMMONWEALTH EDISON CO. |
| Shared Package | |
| ML20153C725 | List: |
| References | |
| IEB-95-002, IEB-95-2, TAC-M93887, TAC-M93888, NUDOCS 9809240182 | |
| Download: ML20153C722 (4) | |
Text
____ ___._._ __..___ _
l i
L September 18, 1998 1
Mr. Oliver D. Kingsley, President Nudear Generation. Group Cemmonwealth Edison Ccmpany E <ecutive Towers West til j
t 400 Opus Place, Suite 500 Downers Grove,IL 60515
SUBJECT:
RESPONSE TO NRC BULLETIN 95 LASALLE COUNTY STATION, UNITS 1 AND 2 (TAC NOS. M93887 AND M93888)
Dear Mr. Kingsley-By letters dated November 14,1995, and January 10,1996, Commonwealth Edison Company (Comed, the licensee) submitted its response to NRC Bulletin 95-02," Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating in Suppression Pool Cooling Mode," for LaSalle County Station, Units 1 and 2. The staff's safety evaluation (SE) of the licensee's response is enclosed.
l NRC Bulletin 95-02 requested that licensees review the operability of their emergency core cooling system (ECCS) and other pumps which draw suction from the suppression pool while l
performing their safety function. The licensee's evaluation should be based on suppression pool cleanliness, suction strainer cleanliness, and the effectivenest of their foreign material exclusion (FME) practices, in addition, licensees were requested to implement appropriate procedural modifications and other actions (e.g., suppression pool cleaning) as necessary to minimize foreign material in the suppression pool, drywell, and containment. Licensees were also i
requested to verify their operability evaluation through appropriate testing and inspection. In its I
response letters of November 14,1995, and January 10,1996, the licensee agreed to comply with all of the requested actions. The staff has concluded that the licensee's response is acceptable.
l Sincerely, I
ORIG. SIGNED BY S. BAILEY FOR
. Donna M. Skay, Project Manager I
9809240182 980918
.i Project Directorate ill-2 l
PDR ADOCK 05000374 Division of Reactor Projects -lil/IV l
G PDR Office of Nuclear Reactor Regulation DISTRIBUTION:
J/
Docket Nos. 50-373, 50-374 Docket File PUBLIC PDill 2 r/f l
EAdensam, EGA1 SRichards DSkay
Enclosure:
SE CMoore OGC, 0-15818 ACRS, T2E26 RLanksbury, Rlli DHills, Rill RElliott cc w/ encl: See next page -
JHickman l
"7 NRC RLE CENTEB COPY l
DOCUMENT NAME: G:\\CM\\LASALLE\\95 02.LAS To rtceive a copy of this document, indice' Oyhehen: *C* = Copy without enclosures *E* = Copy with enclosures *N* = No copy OFFICE PM:PDlli-2 LAS Jhl-2 Vs8CSB lC PM:PDill-2 lE D:PDlll-2 l (k,
NAME DSKAY:sp (JV BMGOl%E RELLIOTT M'IP JHICKMANN'SRICHARDSW DATE 09/ H /98 "
09/ % /98 09/1C /98 09/ /s/98F 09/ lb/98 OFFICIAL RECORD COPY p
e usuq' p
t UNrfED STATES g
j NUCLEAR REGULATORY COMMISSION o
e WASHINGTON, D.C. ma m
/
September 18, 1998 d
Mr. Oliver D. Kingsley, President Nuclear Generation Group Commonwealth Edison Company Executive Towers West lli 1400 Opus Place, Suite 500 Downers Grove,IL 60515
SUBJECT:
RESPONSE TO NRC BULLETIN 95 LASALLE COUNTY STATION, UNITS 1 l
AND 2 (TAC NOS. M93887 AND M93888) 1
Dear Mr. Kingsley:
By letters dated November 14,1995, and January 10,1996, Commonwealth Edison Company (Comed, the licensee) submitted its response to NRC Bulletin 95-02, " Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating in Suppression Pool Cooling Mode," for LaSalle County Station, Units 1 and 2. The staff's safety evaluation (SE) of the I
licensee's response is enclosed.
~
NRC Bulletin 95-02 requested that licensees review the operability of their emergency core cooling system (ECCS) and other pumps which draw suction from the suppression pool while performing their safety function. The licensee's evaluation should be based on suppression pool cleanliness, suction strainer cleanliness, and the effectiveness of their foreign material exclusion (FME) practices. In addition, licensees were requested to implement appropriate procedural modifications and other actions (e.g., suppression pool cleaning) as necessary to minimize foreign materialin the suppression pool, drywell, and containment. Licensees were also
. requested to verify their operability evaluation through appropriate testing and inspection. In its response letters of November 14,1995, and January 10,1996, the licensee agreed to comply with all of the requested actions. The staff has concluded that the licensee's response is acceptable.
Sincerely, V onna M. Skay, P
- nager D
Project Directorate lil 2 Division of Reactor Projects - lil/IV Office of Nuclear Reactor Regulation Docket Nos. 50 373, 50-374 4
Enclosure:
SE cc w/ encl: See next page
_. _... _ q l
l O. Kingsley LaSalle County Station Commonwealth Edison Company Units 1 and 2 cc:
Phillip P. Steptoe, Esquire Michael 1. Miller, Esquire Sidley and Austin Sidley and Austin One First National Plaza One First National Plaza I
Chicago, Illinois 60603 Chicago, Illinois 60603 Assistant Attomey General Document Control Desk Licensing 100 W. Randolph St. Suite 12 Commonwealth Edison Company l
Chicago, Illinois 60601 1400 Opus Place, Suite 400 U.S. NRC LaSalle Resident inspectors Omco l
2605 N. 21st Road Commonwealth Edison Company 1
l Marseilles, Illinois 61341 9756 Site Vice President - LaSalle 2601 N. 21st Road Chairman Marseilles, Illinois 61341-9757 LaSalle County Board of Supervisors LaSalle County Courthouse Mr. David Helwig Ottawa, Illinois 61350 Senior Vice President Commonwealth Edison Company Attom6y General Executive Towers West lil 500 S. Second Street 1400 Opus Place, Suite 900 Springfiek', Illinois 62701 Downers Grove,IL 60515 Chairman Mr. Gene H. Stanley Illinois Commerce Commission PWR's Vice President 527 E. Capitol Avenue, Leland Building Commonwealth Edison Company Springfield, Illinois 62706 Executive Towers West ll1
' 1400 Opus Place, Suite 900 lilinois Department of Nuclear Safety Downers Grove,IL 60515 Office of Nuclear Facility Safety 1035 Outer Park Drive Mr. Steve Perry Springfield, Illinois 62704 BWR's Vice President Commonwealth Edison Company Regional Administrator Executive Towers West lll U.C. NRC, Region lil 1400 Opus Place, Suite 900 601 Warrenville Road Downers Grove,IL 60515
< Lisle, Illinois 60532-4351 Mr. Dennis Farrar Commonwealth Edison Company Regulatory Services Manager LaSalle Station Manager Commonwealth Edison Company 2601 N. 21st Road Executive Towers West lil Marseilles, Illinois 61341 9757-1400 Opus Place, Suite 500 Downers Grove,IL 60515 Robert Cushing, Chief, Public Utilities Division
'lilinois Attomey General's Office l
l 100 W. Randolph Street
, Chicago, Illinois 60601 l
. ~
l l
- 0. Kingsley LaSalle County Station Commonwealth Edison Company Units 1 and 2 Ms. Irene Johnson, Ucensing Director Nuclear Regulatory Services l
Commonwealth Edison Company
)
l Executive Towers West til 1400 Opus Place, Suite 500 Downers Grove,IL 60515 Commonwealth Edison Company l
Reg. Assurance Supervisor-LaSalle l-2601 N. 21st Road l
Marseilles, Illinois 61341-g757 Mr. MichaelJ. Wallace Senior Vice President Commonwealth Edison Company Executive Towers West til 1400 Opus Place, Suite 900 Downers Grove,IL 60515 i
s a
$ Ktty p
UNITED STATES g
j NUCLEAR REGULATORY COMMISSION o,
f WASHINGTON, D.C. 2000Hl001 g,.....p SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO NRC But i PTIN 95-02 COMMONWEALTH EDISON COMPANY LASALLE COUNTY STATION. UNITS 1 AND 2 DOCKET NOS. 50-373 AND 50-374
1.0 INTRODUCTION
NRC Bulletin 95-02, " Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating in Suppression Pool Cooling Mode," was issued on October 17,1995, it requested all holders of boiling-water reactor (BWR) operating licenses or construction permits for nuclear power reactors to take five actions to ensure that unacceptable buildup of debris that could clog strainers does not occur during normal operation. By letteis dated November 14, 1995, and January 10,1996, Commonwealth Edison Company (Comed, the licensee) submitted its response to NRC Bulletin 95-02 for LaSalle County Station, Units 1 and 2. In its response, the licensee stated its intent to comply with the requested actions !n the bulletin.
2.0 DISCUSSION The following describes the requested actions in NRC Bulletin 95 02 and the licensee's response to each requested action.
Action i Verify the operability of all pumps which draw suction from the suppression pool when performing their safety functions (e.g., ECCS (emergency core cooling system), containment spray, etc.),
based on an evaluation of suppression pool and suction strainer cleanliness conditions. This evaluation should be based on the pool and strainer conditions during the last inspection or cleaning and an assessment of the potential for the introduction of debris or other materials that could clog the strainers since the pool was last cleaned.
Response
The Unit 1 suppression pool strainers were inspected during that unit's refueling outage in April 1994, and the Unit 2 suppression pool strainers were inspected during that unit's refueling outage in March 1995. During that inspection, all identified foreign material was removed and the suppression pool cleanup system was used to improve the turbidity and lonic quality of the suppression pool water. On Unit 1, a SCRAM, with a safety relief valve lift, occurred in August 1995, followed by Residual Heat Removal (RHR) A and B operation for suppression pool cooling.
No flow degradation was identified in the pump discharge pressure from those runs. For both units, quarterty in service testing ECCS pump surveillance data was reviewed and no ENCLOSURE 9009240194 980918 PDR ADOCK 05000373 G
7.. _
~ _. _ _. _ _ _ -.
2-degradation of pump suction pressure was identified. Finally, a foreign material exclusion (FME) program, developed in response to NRC Bulletin 93-02 and 93-02, Supplement 1, has been in place since February 1994. Based on the above, the licensee concluded that all pumps which draw suction from the suppression pool while performing their safety function are operable.
Action 2 Confirm the operability evaluation in requested action 1 above through appropriate test (s) and strainer inspection (s) within 120 days of the date of this bulletin.
Response
Multiple ECCS (RHR and Low Pressure Core Spray) pump tests were performed to confirm ECCS suction strainer operability on January 4,1996, for Unit 1 and on January 5,1996, for Unit 2. No decrease in pump suction pressure was identified over the course of the 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> tests.
Action 3 Schedule a suppression pool (torus) cleaning. The schedule for cleaning the suppression pool should be consistent with the operability evaluation in requested action 1 above. in addition, a program for periodic cleaning of the suppression pool should be established, including procedures for the cleaning of the pool, criteria for determining the appropriate cleaning frequency, and criteria for evaluating the adequacy of the pool cleanliness.
Response
i In the November 14,1995, letter, the licensee committed to clean, inspect, and desludge the suppression pools for each unit during its next scheduled refueling outage. in addition, cleanliness of the suppressio pool will be maintained by the following program. A multiple ECCS pump run will be repeated starting at every second future refueling outage of each unit.
Two strainers will be inspected at every second outage, altemating between using remote cameras (or equivalent) or a direct diver inspection.
Action 4 Review FME pnacedures and their implementation to determine whether adequate control of materials in the drywell, suppression pool, and systems that interface with the suppression pool exists. This review should determine if comprehensive FME controls have been established to prevent materials that could potentially impact ECCS operation from being introduced into the suppression pool, and that workers are sufficiently aware of their responsibilities regarding FME.
Any identified weaknesses should be corrected in addition, the effectiveness of the FME controls since the last time the suppression pool was cleaned and the ECCS strainers inspected, and the impact that any weaknesses noted may have on the operability of the ECCS, should be assessed.
4 4
)
v-
3-
Response
The licensee stated that, although existing FME procedures are adequate, it is continuously working to enhance the FME program. A standardized maintenance procedure will be implemented which includes actions to preclude FME events. The suppression pool and drywell i
are permanently designated as zones requiring the highest level of FME controls. Additional controls include drywell closecut procedural steps, FME logs, and expande6 availability of FME 4
devices to preclude introduction of foreign material into the suppression pool.
Action 5 j
Consider additional measures such as suppression pool water sampling and trending of pump suction pressure to detect clogging of ECCS suction strainers.
Resoonse Beyond the actions described above, ECCS pump suction pressure will be trended and an inspection program for the suppression pool downcomers will be implemented.
I 3.0 EVALUATION The purpose of the requested actions in the bulletin is to ensure that ECCS and other pumps drawing suction from the suppression pool do not experience unacceptable buildup of debris that could c69 strainers during normal operation which would prevent them from performing their safety function. Action 1 requested licensees to evaluate the operability of their pumps based on the cleanliness of the suppression pool and strainers. Action 2 then requested a verification of i
the 'icensee's assessment through a pump test and strainerinspection. These two actions serve to ensure that the pumps are currently operable and not experiencing unacceptable debris buildup. Actions 3,4'and 5 serve to ensure that appropriate measures, such as cleariing of suppression pools and strengthening of FME practices, are taken in the long term to prevent debns accumulation in the pool.
j.
As committed to in the licensee's response to action 3, the suppression pools were cleaned and desludged during the 1996 refueling outages. During the Unit 1 cleaning, a number of small Items were found and removed under the silt layer as well as a quantity of silt. No concems were identified. During the Unit 2 cleaning, however, a significant quantity of foreign material was 4
removed from under the sitt layer which appeared to have been in the pool since initial construction. These findings are documented in Licensee Event Report 96-09. Although this material raised questions with regard to past operability, the foreign material and the silt were 1
removed as part of this cleaning.
a The staff has concluded that the licensee's assessment of the ability of all pumps drawing suction from the suppression pool to perform their safety function has a reasonable basis for concluding that all of the pumps evaluated are operable. The licensee conducted an inspection to confirm that the ECCS were not affected by an unacceptable buildup of debris that could clog the pump strainers. Initial strainer cleanliness was considered good. The staff has concluded i
that the licensee's response meets the intent of requested actions 1 and 2 and is acceptable.
d n
--- ~
m,-
,c w--
~ --- -.-
4 The staff has also concluded that the licensee's evaluation of its FME program and suppression pool cleaning program meet the intent of requested actions 3 and 4, and are acceptable.
Although the Unit 2 sump had a significant quantity of foreign material at the time of the licensee response, the subsequent cleaning removed the material. The discovery of this material did not call into question the licensee's current FME program because the majority of material was deterrrined to have been deposited prior to implementation of the licensee's enhanced FME controls.
The licensee's programs fMending pump suction pressure data, sampling torus water / sediment, and periodically inspecting the strainers and torus provide additional opportunity for early identificatioa of potential strainer fouling. The staff has concluded that these additior.al actions meet the intent of requested action 5 and are acceptable. The staff has also concluded that the schedule for implementation of the actions proposed by the licensee is appropriate given the actions already taken.
4.0 CQNr.LUSION Based on the staff's evaluation of the licensee's submittals, the staff finds the licensea's response to NRC Bulletin 95-02 acceptable.
Principal Contributors: John B. Hickman R. Elliot (By precedent)
Date: September 18, 1998 l
l
... -