{{#Wiki_filter:Michael K. Scarpello Director Nuclear Regulatory Affairs Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106
{{#Wiki_filter:Michael K. Scarpello Director Nuclear Regulatory Affairs Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106


==SUBJECT:==
==SUBJECT:==
Line 21: Line 21:


==Dear Michael K. Scarpello:==
==Dear Michael K. Scarpello:==
The U.S. Nuclear Regulatory Commission (NRC) staff received your letter titled Donald C.
The U.S. Nuclear Regulatory Commission (NRC) staff received your letter titled Donald C.
Cook Nuclear Plant Units 1 and 2, Triennial Evaluated Force-on-Force Cycle Schedule Change Request (Agencywide Documents Access and Management System accession number ML24032A137) and has conducted a review of the information contained within. Your letter stated that Indiana Michigan Power Company (l&M), the licensee for Donald C. Cook Nuclear Plant (CNP) Units 1 and 2, is formally requesting a schedule change to the NRC-evaluated force-on-force (FOF) cycle year because (1) the current CNP NRC-evaluated FOF Cycle Schedule occurs in the same years that the site has both spring and fall refueling outages and (2) from a CNP staffing perspective, is challenging for the Security Department during a dual outage year concurrently with having an NRC-evaluated FOF in that same year.
Cook Nuclear Plant Units 1 and 2, Triennial Evaluated Force-on-Force Cycle Schedule Change Request (Agencywide Documents Access and Management System accession number ML24032A137) and has conducted a review of the information contained within. Your letter stated that Indiana Michigan Power Company (l&M), the licensee for Donald C. Cook Nuclear Plant (CNP) Units 1 and 2, is formally requesting a schedule change to the NRC-evaluated force-on-force (FOF) cycle year because (1) the current CNP NRC-evaluated FOF Cycle Schedule occurs in the same years that the site has both spring and fall refueling outages and (2) from a CNP staffing perspective, is challenging for the Security Department during a dual outage year concurrently with having an NRC-evaluated FOF in that same year.
Line 28: Line 27:
Sincerely, Jefferson Clark, Chief Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response Docket Nos.: 05000315 and 05000316 February 6, 2024 Signed by Clark, Jefferson on 02/06/24
Sincerely, Jefferson Clark, Chief Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response Docket Nos.: 05000315 and 05000316 February 6, 2024 Signed by Clark, Jefferson on 02/06/24


Ltr ML24037A052 OFFICE           NSIR/DSO/SPEB     NSIR/DSO/SPEB     NSIR/DSO         NSIR/DSO/SPEB
Ltr ML24037A052 OFFICE NSIR/DSO/SPEB NSIR/DSO/SPEB NSIR/DSO NSIR/DSO/SPEB
                  /ETB             /ETA                               /ETA NAME             JBerry         JB JClark         JC TInverso       TIJClark         JC DATE             Feb 6, 2024       Feb 6, 2024       Feb 6, 2024       Feb 6, 2024}}
/ETB /ETA /ETA NAME JBerry JB JClark JC TInverso TIJClark JC DATE Feb 6, 2024 Feb 6, 2024 Feb 6, 2024 Feb 6, 2024}}

Latest revision as of 15:26, 5 October 2024

NRC Response to DC Cook Triennial Evaluated Force-on-Force Cycle Schedule Change Request
ML24037A052
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 02/07/2024
From: Clark J
Security Performance Evaluation Branch
To: Scarpello M
Indiana Michigan Power Co
References
Download: ML24037A052 (1)


Text

Michael K. Scarpello Director Nuclear Regulatory Affairs Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106

SUBJECT:

THE U.S. NUCLEAR REGULATORY COMMISSION RESPONSE TO INDIANA MICHIGAN POWER COMPANY, DONALD C. COOK TRIENNIAL U.S. NUCLEAR REGULATORY COMMISSION-EVALUATED FORCE-ON-FORCE INSPECTION YEAR CHANGE WITHIN THE CYCLE

Dear Michael K. Scarpello:

The U.S. Nuclear Regulatory Commission (NRC) staff received your letter titled Donald C.

Cook Nuclear Plant Units 1 and 2, Triennial Evaluated Force-on-Force Cycle Schedule Change Request (Agencywide Documents Access and Management System accession number ML24032A137) and has conducted a review of the information contained within. Your letter stated that Indiana Michigan Power Company (l&M), the licensee for Donald C. Cook Nuclear Plant (CNP) Units 1 and 2, is formally requesting a schedule change to the NRC-evaluated force-on-force (FOF) cycle year because (1) the current CNP NRC-evaluated FOF Cycle Schedule occurs in the same years that the site has both spring and fall refueling outages and (2) from a CNP staffing perspective, is challenging for the Security Department during a dual outage year concurrently with having an NRC-evaluated FOF in that same year.

The staff finds reasonable I&Ms request to shift the NRC-evaluated FOF inspection from the third year of the NRC-evaluated FOF inspection cycle to the second year, and therefore approves the new schedule accordingly. CNPs currently scheduled NRC-evaluated FOF inspection in July/August 2025 will be subsequently rescheduled to the end of calendar year 2024. Inspections following the 2024 NRC-evaluated FOF inspection, CNP will resume a triennial schedule.

Please feel free to contact me at (301) 287-3666 with any questions you have regarding this letter.

Sincerely, Jefferson Clark, Chief Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response Docket Nos.: 05000315 and 05000316 February 6, 2024 Signed by Clark, Jefferson on 02/06/24

Ltr ML24037A052 OFFICE NSIR/DSO/SPEB NSIR/DSO/SPEB NSIR/DSO NSIR/DSO/SPEB

/ETB /ETA /ETA NAME JBerry JB JClark JC TInverso TIJClark JC DATE Feb 6, 2024 Feb 6, 2024 Feb 6, 2024 Feb 6, 2024