Line 12: | Line 12: | ||
| identified by = Licensee | | identified by = Licensee | ||
| Inspection procedure = | | Inspection procedure = | ||
| Inspector = C Henderson, D Allen, J Josey, J Laughlin, J O, | | Inspector = C Henderson, D Allen, J Josey, J Laughlin, J O'Donnell, L Ricketson, P Elkmann | ||
| CCA = N/A for ROP | | CCA = N/A for ROP | ||
| INPO aspect = | | INPO aspect = | ||
| description = Title 10 CFR 50.54(q)(2), requires that a power reactor licensee follow an emergency plan that meets the requirements of 10 CFR 50.47(b) and Appendix E to Part 50. Title 10 CFR 50.47(b)(1), requires that a licensee have staff to augment its initial emergency response. Section 5.3.1 of the Cooper Nuclear Station Emergency Plan, Revision 63, requires Joint Information Center management to be supported by the Joint Information Center Facility Manager. Contrary to the above, between approximately May 1 and July 10, 2012, the Cooper Nuclear Station did not follow an emergency plan that met the requirements of 10 CFR 50.47(b) and Appendix E to Part 50. Specifically, it did not follow emergency plan Section 5.3.1 of the Cooper Nuclear Station Emergency Plan because there were no qualified staff assigned to the position of Joint Information Center Facility Manager. This finding was more than minor because it affected the emergency response organization readiness cornerstone attribute (duty roster). The finding was evaluated by the Emergency Preparedness Significance Determination Process and determined to be of very low safety significance (Green) because it was a failure to comply with NRC requirements, and was not a loss of planning standard function. The planning standard function was not lost because the Joint Information Center would have been able to perform its emergency function without a Joint Information Center Facility Manager, although in a degraded manner. This finding was entered into the licensees corrective action program as Condition Report CR-CNS-2012-04492. | | description = Title 10 CFR 50.54(q)(2), requires that a power reactor licensee follow an emergency plan that meets the requirements of 10 CFR 50.47(b) and Appendix E to Part 50. Title 10 CFR 50.47(b)(1), requires that a licensee have staff to augment its initial emergency response. Section 5.3.1 of the Cooper Nuclear Station Emergency Plan, Revision 63, requires Joint Information Center management to be supported by the Joint Information Center Facility Manager. Contrary to the above, between approximately May 1 and July 10, 2012, the Cooper Nuclear Station did not follow an emergency plan that met the requirements of 10 CFR 50.47(b) and Appendix E to Part 50. Specifically, it did not follow emergency plan Section 5.3.1 of the Cooper Nuclear Station Emergency Plan because there were no qualified staff assigned to the position of Joint Information Center Facility Manager. This finding was more than minor because it affected the emergency response organization readiness cornerstone attribute (duty roster). The finding was evaluated by the Emergency Preparedness Significance Determination Process and determined to be of very low safety significance (Green) because it was a failure to comply with NRC requirements, and was not a loss of planning standard function. The planning standard function was not lost because the Joint Information Center would have been able to perform its emergency function without a Joint Information Center Facility Manager, although in a degraded manner. This finding was entered into the licensees corrective action program as Condition Report CR-CNS-2012-04492. | ||
}} | }} |
Revision as of 00:20, 22 February 2018
Site: | Cooper |
---|---|
Report | IR 05000298/2013004 Section 4OA7 |
Date counted | Sep 30, 2013 (2013Q3) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | Licensee-identified |
Inspection Procedure: | |
Inspectors (proximate) | C Henderson D Allen J Josey J Laughlin J O'Donnell L Ricketson P Elkmann |
Violation of: | 10 CFR 50.47(b)(1) 10 CFR 50.47 10 CFR 50.54(q) 10 CFR 50.54 |
INPO aspect | |
' | |