ML20023B359: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot change)
(StriderTol Bot change)
 
Line 2: Line 2:
| number = ML20023B359
| number = ML20023B359
| issue date = 01/23/2020
| issue date = 01/23/2020
| title = NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Relief Requests in Support of the Fourth Inservice Inspection Interval (EPID: L-2020-LLR-0002, L-2020-LLR-0003, L-2020-LLR-0004, L-2020-LLR-0005)
| title = NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Relief Requests in Support of the Fourth Inservice Inspection Interval
| author name = Wall S
| author name = Wall S
| author affiliation = NRC/NRR/DORL/LPL3
| author affiliation = NRC/NRR/DORL/LPL3

Latest revision as of 09:33, 15 March 2020

NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Relief Requests in Support of the Fourth Inservice Inspection Interval
ML20023B359
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 01/23/2020
From: Scott Wall
NRC/NRR/DORL/LPL3
To: Lashley P
FirstEnergy Nuclear Operating Co
Wall S
References
L-2020-LLR-0002, L-2020-LLR-0003, L-2020-LLR-0004, L-2020-LLR-0005
Download: ML20023B359 (3)


Text

From: Wall, Scott Sent: Thursday, January 23, 2020 11:32 AM To: Lashley, Phil H.

Cc: Morgan, Jeffrey D.

Subject:

Perry Nuclear Power Plant - Acceptance of Relief Requests In Support of the Fourth Inservice Inspection Interval (EPID: L-2020-LLR-0002, L-2020-LLR-0003, L-2020-LLR-0004, L-2020-LLR-0005)

Dear Mr. Lashley:

By letter dated January 6, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20006D984), FirstEnergy Nuclear Operating Company (FENOC, the licensee) submitted four (4) relief requests (RRs) for Perry Nuclear Power Plant (Perry).

The proposed RRs are in support of the fourth 10-year inservice inspection interval.

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of these relief requests. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. Pursuant to Sections 50.55a(z)(1) and 50.55a(z)(2) of Title 10 of the Code of Federal Regulations (10 CFR),

the applicant shall demonstrate that the proposed alternatives would provide an acceptable level of quality and safety, or that compliance with the specified requirements of Section 50.55a would result in hardship or unusual difficulty without a compensating increase in the level of quality or safety.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed exemption in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated the following for each RR:

1. PT-001, Rev. 3
  • Hours to Complete: 60 hours2.5 days <br />0.357 weeks <br />0.0822 months <br />
  • Target Completion Date: January 2021
2. IR-054, Rev. 2
  • Hours to Complete: 60 hours2.5 days <br />0.357 weeks <br />0.0822 months <br />
  • Target Completion Date: January 2021
3. IR-056, Rev. 3
  • Hours to Complete: 60 hours2.5 days <br />0.357 weeks <br />0.0822 months <br />
  • Target Completion Date: January 2021
4. IR-060, Rev. 0
  • Hours to Complete: 60 hours2.5 days <br />0.357 weeks <br />0.0822 months <br />
  • Target Completion Date: January 2021 If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, and unanticipated addition of scope to the review. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me at (301) 415-2855 or e-mail at Scott.Wall@nrc.gov.

Scott P. Wall, LSS BB, BSP Senior Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation 301.415.2855 Scott.Wall@nrc.gov

Hearing Identifier: NRR_DRMA Email Number: 412 Mail Envelope Properties (BYAPR09MB2549239EA083EE9B686A671D920F0)

Subject:

Perry Nuclear Power Plant - Acceptance of Relief Requests In Support of the Fourth Inservice Inspection Interval (EPID: L-2020-LLR-0002, L-2020-LLR-0003, L-2020-LLR-0004, L-2020-LLR-0005)

Sent Date: 1/23/2020 11:31:53 AM Received Date: 1/23/2020 11:31:56 AM From: Wall, Scott Created By: Scott.Wall@nrc.gov Recipients:

"Morgan, Jeffrey D." <jdmorgan@firstenergycorp.com>

Tracking Status: None "Lashley, Phil H." <phlashley@firstenergycorp.com>

Tracking Status: None Post Office: BYAPR09MB2549.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3960 1/23/2020 11:31:56 AM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: