ML061430135: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(StriderTol Bot change)
 
(3 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML061430135
| number = ML061430135
| issue date = 10/04/2006
| issue date = 10/04/2006
| title = Millstone, Unit No. 3, Issuance of License Amendment 234 Deleting Section 2.F to Facility Operating License No. NPF-49
| title = Issuance of License Amendment 234 Deleting Section 2.F to Facility Operating License No. NPF-49
| author name = Nerses V
| author name = Nerses V
| author affiliation = NRC/NRR/ADRO/DORL/LPLI-2
| author affiliation = NRC/NRR/ADRO/DORL/LPLI-2
| addressee name = Christian D A
| addressee name = Christian D
| addressee affiliation = Dominion Nuclear Connecticut, Inc
| addressee affiliation = Dominion Nuclear Connecticut, Inc
| docket = 05000423
| docket = 05000423
Line 19: Line 19:


=Text=
=Text=
{{#Wiki_filter:October 4, 2006Mr. David A. ChristianSr. Vice President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.
{{#Wiki_filter:October 4, 2006 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.
Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711


==SUBJECT:==
==SUBJECT:==
MILLSTONE POWER STATION, UNIT NO. 3 - ISSUANCE OF AMENDMENTRE: DELETING SECTION 2.F TO FACILITY OPERATING LICENSE NO.
MILLSTONE POWER STATION, UNIT NO. 3 - ISSUANCE OF AMENDMENT RE: DELETING SECTION 2.F TO FACILITY OPERATING LICENSE NO.
NPF-49 (TAC NO. MD1056)
NPF-49 (TAC NO. MD1056)


==Dear Mr. Christian:==
==Dear Mr. Christian:==


The Commission has issued the enclosed Amendment No. 234 to Facility Operating LicenseNo. NPF-49 for the Millstone Power Station, Unit No. 3., in response to your application datedMarch 28, 2006. This amendment revises Facility Operating License No. NPF-49 by deletingSection 2.F, which specifies reporting of violations of the requirements of Section 2.C of the renewed operating license.A copy of our Safety Evaluation is also enclosed. Notice of Issuance will be included in theCommission's biweekly Federal Register notice. Sincerely,/RA/Victor Nerses, Senior Project ManagerPlant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No. 50-423  
The Commission has issued the enclosed Amendment No. 234 to Facility Operating License No. NPF-49 for the Millstone Power Station, Unit No. 3., in response to your application dated March 28, 2006. This amendment revises Facility Operating License No. NPF-49 by deleting Section 2.F, which specifies reporting of violations of the requirements of Section 2.C of the renewed operating license.
A copy of our Safety Evaluation is also enclosed. Notice of Issuance will be included in the Commissions biweekly Federal Register notice.
Sincerely,
                                              /RA/
Victor Nerses, Senior Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-423


==Enclosures:==
==Enclosures:==
: 1. Amendment No. 234 to License No. NPF-49  
: 1. Amendment No. 234 to License No. NPF-49
: 2. Safety Evaluationcc w/encls: See next page October 4, 2006Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.
: 2. Safety Evaluation cc w/encls: See next page
Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
 
October 4, 2006 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.
Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711


==SUBJECT:==
==SUBJECT:==
MILLSTONE POWER STATION, UNIT NO. 3 - ISSUANCE OF AMENDMENTRE: DELETING SECTION 2.F TO FACILITY OPERATING LICENSE NO.
MILLSTONE POWER STATION, UNIT NO. 3 - ISSUANCE OF AMENDMENT RE: DELETING SECTION 2.F TO FACILITY OPERATING LICENSE NO.
NPF-49 (TAC NO. MD1056)
NPF-49 (TAC NO. MD1056)


==Dear Mr. Christian:==
==Dear Mr. Christian:==


The Commission has issued the enclosed Amendment No. 234 to Facility Operating LicenseNo. NPF-49 for the Millstone Power Station, Unit No. 3., in response to your application datedMarch 28, 2006. This amendment revises Facility Operating License No. NPF-49 by deletingSection 2.F, which specifies reporting of violations of the requirements of Section 2.C of the renewed operating license.A copy of our Safety Evaluation is also enclosed. Notice of Issuance will be included in theCommission's biweekly Federal Register notice. Sincerely,/RA/Victor Nerses, Senior Project ManagerPlant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No. 50-423  
The Commission has issued the enclosed Amendment No. 234 to Facility Operating License No. NPF-49 for the Millstone Power Station, Unit No. 3., in response to your application dated March 28, 2006. This amendment revises Facility Operating License No. NPF-49 by deleting Section 2.F, which specifies reporting of violations of the requirements of Section 2.C of the renewed operating license.
A copy of our Safety Evaluation is also enclosed. Notice of Issuance will be included in the Commissions biweekly Federal Register notice.
Sincerely,
                                              /RA/
Victor Nerses, Senior Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-423


==Enclosures:==
==Enclosures:==
: 1. Amendment No. 234 to License No. NPF-49  
: 1. Amendment No. 234 to License No. NPF-49
: 2. Safety Evaluationcc w/encls: See next page DISTRIBUTION
: 2. Safety Evaluation cc w/encls: See next page DISTRIBUTION:
:RidsNrrLpl1-2RidsOgcRpRidsRgn1MailCenterPUBLICRidsNrrPMVNersesRidsAcrs AcnwMailCenter LPL1-2 R/FRidsNrrLACRaynorTKobetz RidsNrrDorlGHill (2)Package Accession Number: ML061930080Amendment Accession Number: ML061430135 Tech Specs. Accession Number: ML062790492OFFICELPL1-2/PMLPL1-2/LAITSB/BCOGC/NLOLPL1-2/BC (A)NAMEVNerses:rsaCRaynorTKobetzMZoblerBPooleDATE7/26/067/25/065/18/068/2/068/3/06OFFICIAL RECORD COPY DOMINION NUCLEAR CONNECTICUT, INC.DOCKET NO. 50-423MILLSTONE POWER STATION, UNIT NO. 3AMENDMENT TO FACILITY OPERATING LICENSEAmendment No. 234License No. NPF-491.The Nuclear Regulatory Commission (the Commission) has found that:A.The application for amendment filed by Dominion Nuclear Connecticut, Inc. (thelicensee) dated March 28, 2006, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in Title 10 of the Code of FederalRegulations (10 CFR), Chapter I;B.The facility will operate in conformity with the application, the provisions of theAct, and the rules and regulations of the Commission;C.There is reasonable assurance: (i) that the activities authorized by thisamendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with theCommission's regulations set forth in 10 CFR Chapter I;D.The issuance of this amendment will not be inimical to the common defense andsecurity or to the health and safety of the public; andE.The issuance of this amendment is in accordance with 10 CFR Part 51 of theCommission's regulations and all applicable requirements have been satisfied. 2.Accordingly, the license is amended by deleting paragraph 2.F of Facility OperatingLicense No. NPF-49 as indicated in the attachment to this license amendment.3.This license amendment is effective as of its date of issuance and shall be implementedwithin 60 days.FOR THE NUCLEAR REGULATORY COMMISSION/RA/Brooke D. Poole, Acting ChiefPlant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
RidsNrrLpl1-2          RidsOgcRp                      RidsRgn1MailCenter PUBLIC                RidsNrrPMVNerses              RidsAcrs AcnwMailCenter LPL1-2 R/F            RidsNrrLACRaynor              TKobetz RidsNrrDorl            GHill (2)
Package Accession Number: ML061930080 Amendment Accession Number: ML061430135 Tech Specs. Accession Number: ML062790492 OFFICE LPL1-2/PM              LPL1-2/LA      ITSB/BC        OGC/NLO      LPL1-2/BC (A)
NAME      VNerses:rsa        CRaynor        TKobetz        MZobler      BPoole DATE      7/26/06            7/25/06        5/18/06        8/2/06      8/3/06 OFFICIAL RECORD COPY
 
DOMINION NUCLEAR CONNECTICUT, INC.
DOCKET NO. 50-423 MILLSTONE POWER STATION, UNIT NO. 3 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 234 License No. NPF-49
: 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment filed by Dominion Nuclear Connecticut, Inc. (the licensee) dated March 28, 2006, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in Title 10 of the Code of Federal Regulations (10 CFR), Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations set forth in 10 CFR Chapter I; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
: 2. Accordingly, the license is amended by deleting paragraph 2.F of Facility Operating License No. NPF-49 as indicated in the attachment to this license amendment.
: 3. This license amendment is effective as of its date of issuance and shall be implemented within 60 days.
FOR THE NUCLEAR REGULATORY COMMISSION
                                          /RA/
Brooke D. Poole, Acting Chief Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation


==Attachment:==
==Attachment:==
Changes to the Renewed Operating                         LicenseDate of Issuance: October 4, 2006 ATTACHMENT TO LICENSE AMENDMENT NO. 234   FACILITY OPERATING LICENSE NO. NPF-49DOCKET NO. 50-423Replace the following page of Facility Operating License No. NPF-49 as indicated. The revisedpage is identified by amendment number and contains a marginal line indicating the area of change.Remove PageInsert Page SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATIONRELATED TO AMENDMENT NO.234 TO FACILITY OPERATINGLICENSE NO. NPF-49 DOMINION NUCLEAR CONNECTICUT, INC.MILLSTONE POWER STATION, UNIT NO. 3 DOCKET NO. 50-423  
Changes to the Renewed Operating License Date of Issuance: October 4, 2006
 
ATTACHMENT TO LICENSE AMENDMENT NO. 234 FACILITY OPERATING LICENSE NO. NPF-49 DOCKET NO. 50-423 Replace the following page of Facility Operating License No. NPF-49 as indicated. The revised page is identified by amendment number and contains a marginal line indicating the area of change.
Remove Page                                        Insert Page SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO.234 TO FACILITY OPERATING LICENSE NO. NPF-49 DOMINION NUCLEAR CONNECTICUT, INC.
MILLSTONE POWER STATION, UNIT NO. 3 DOCKET NO. 50-423
 
==1.0    INTRODUCTION==
 
By letter dated March 28, 2006, Dominion Nuclear Connecticut, Inc. (DNC or the licensee) requested a license amendment for Millstone Power Station, Unit No. 3 (MPS3). The licensee requested to delete Section 2.F of Facility Operating License No. NPF-49, which specifies reporting of violations of the requirements in Section 2.C. A notice announcing the availability of this proposed change using the consolidated line item improvement process (CLIIP) was published in the Federal Register on November 4, 2005 (70 FR 67202).
The Nuclear Regulatory Commission (NRC or the Commission) staffs proposed no significant hazards consideration determination of the licensees proposed amendment was published in the Federal Register on May 9, 2006 (71 FR 26997).
 
==2.0    REGULATORY EVALUATION==
 
A section or condition was included in the facility operating licenses issued to some nuclear power plants requiring the licensee to make reports to the NRC regarding violations of other sections of the operating license (typically Section 2.C). In the case of MPS3, Section 2.F of the Facility Operating License reads as follows:
Except as otherwise provided in the Technical Specifications or Environmental Protection Plan, [DNC] shall report any violations of the requirements contained in Section 2.C. of this renewed operating license in the following manner: initial notification shall be made within 24 hours to the NRC Operations Center via the Emergency Notification System with written followup within thirty days in accordance with the procedures described in [Title 10 of the Code of Federal Regulations (10 CFR)]
10 CFR Sections 50.73(b), (c) and (e).
In addition to the information provided to support licensing decisions, the NRC obtains information about plant operation, licensee programs, and other matters using a combination of inspections and reporting requirements. Routine or scheduled reports that are required to be submitted to the NRC are defined in the related regulations, specific license condition, technical specification, or an NRC-approved program document. The reporting of emergencies,
 
unplanned events or conditions, and other special cases may also be addressed within such documents by the inclusion of reporting thresholds and are also the focus of the reporting requirements in 10 CFR 50.72, Immediate notification requirements for operating nuclear power reactors, and 10 CFR 50.73, Licensee event report system. Changes to the reporting regulations in 10 CFR Sections 50.72 and 50.73 became effective in January 2001 (see Federal Register notice on October 25, 2000 (65 FR 63769) and included extending the allowable reporting times for licensee event reports (LERs) from 30 days to 60 days.


==1.0INTRODUCTION==
==3.0      TECHNICAL EVALUATION==
By letter dated March 28, 2006, Dominion Nuclear Connecticut, Inc. (DNC or the licensee)requested a license amendment for Millstone Power Station, Unit No. 3 (MPS3). The licenseerequested to delete Section 2.F of Facility Operating License No. NPF-49, which specifies reporting of violations of the requirements in Section 2.C. A notice announcing the availabilityof this proposed change using the consolidated line item improvement process (CLIIP) was published in the Federal Register on November 4, 2005 (70 FR 67202). The Nuclear Regulatory Commission (NRC or the Commission) staff's proposed no significanthazards consideration determination of the licensee's proposed amendment was published in


the Federal Register on May 9, 2006 (71 FR 26997).
Section 2.F of the MPS3 Facility Operating License requires the licensee to report any violations of the requirements of Section 2.C of the Facility Operating License and defines the method and allowable time periods for such reports. The reporting threshold (i.e., a violation) for the conditions included in Section 2.C of the Facility Operating License duplicate those defined in 10 CFR 50.72 and 10 CFR 50.73. However, the requirements in the Facility Operating License have different deadlines than those defined in the regulations following a rule change in 2001. This difference in reporting requirements has led to variations in reporting since many facility operating licenses do not contain the subject condition. For those licensees with a 30-day reporting requirement in the Facility Operating License, the condition has decreased the benefits of the rulemaking. For those cases where the current Facility Operating License requirement to report violations is also reportable in accordance with the regulations defined in 10 CFR 50.72 and 10 CFR 50.73, the NRC staff finds that the regulations adequately address this issue and the elimination of the duplicative requirement in the Facility Operating License is acceptable.
Some of the conditions addressed in Section 2.C of the Facility Operating License may address the maintenance of particular programs, administrative requirements, or other matters where a violation of the requirement would not result in a report to the NRC in accordance with 10 CFR 50.72 or 10 CFR 50.73. In most cases, there are requirements for reports to the NRC related to these conditions in other regulations, the specific license condition or technical specification, or an NRC-approved program document. In other cases, there are reports to other agencies or news releases that would prompt a report to the NRC (in accordance with 10 CFR 50.72(b)(2)(xi)). The NRC staff also assessed violations of administrative requirements that could be reportable under the current License Condition but that may not have a duplicative requirement in a regulation or other regulatory requirement. The NRC staff finds that the requirements to report such problems within 24 hours with written reports to follow using the LER process is not needed. The NRC staff is confident that the information related to such violations that is actually important to the NRCs regulatory functions would come to light in a time frame comparable to the 60-day LER requirements. The information would become available to the appropriate NRC staff through the inspection program, updates to program documents, resultant licensing actions, public announcements, or some other reliable mechanism.
The NRC staff finds that the elimination of Section 2.F in the MPS3 Facility Operating License will not result in a loss of information to the NRC that would adversely affect either its goal to protect public health and safety or its ability to carry out its various other regulatory responsibilities. Therefore, the elimination of Section 2.F of the Facility Operating License is acceptable.


==2.0REGULATORY EVALUATION==
==4.0    STATE CONSULTATION==
A section or condition was included in the facility operating licenses issued to somenuclear power plants requiring the licensee to make reports to the NRC regarding violations ofother sections of the operating license (typically Section 2.C). In the case of MPS3, Section 2.F of the Facility Operating License reads as follows:Except as otherwise provided in the Technical Specifications or EnvironmentalProtection Plan, [DNC] shall report any violations of the requirements contained inSection 2.C. of this renewed operating license in the following manner:  initial notification shall be made within 24 hours to the NRC Operations Center via the EmergencyNotification System with written followup within thirty days in accordance with the procedures described in [Title 10 of the Code of Federal Regulations (10 CFR)]10 CFR Sections 50.73(b), (c) and (e).In addition to the information provided to support licensing decisions, the NRC obtainsinformation about plant operation, licensee programs, and other matters using a combination of inspections and reporting requirements. Routine or scheduled reports that are required to be submitted to the NRC are defined in the related regulations, specific license condition, technicalspecification, or an NRC-approved program document. The reporting of emergencies,  unplanned events or conditions, and other special cases may also be addressed within suchdocuments by the inclusion of reporting thresholds and are also the focus of the reporting requirements in 10 CFR 50.72, "Immediate notification requirements for operating nuclearpower reactors," and 10 CFR 50.73, "Licensee event report system."  Changes to the reportingregulations in 10 CFR Sections 50.72 and 50.73 became effective in January 2001 (see Federal Register notice on October 25, 2000 (65 FR 63769) and included extending theallowable reporting times for licensee event reports (LERs) from 30 days to 60 days.


==3.0TECHNICAL EVALUATION==
In accordance with the Commissions regulations, the Connecticut State official was notified of the proposed issuance of the amendment. The State official had no comments.
Section 2.F of the MPS3 Facility Operating License requires the licensee to report anyviolations of the requirements of Section 2.C of the Facility Operating License and defines themethod and allowable time periods for such reports. The reporting threshold (i.e., a violation) for the conditions included in Section 2.C of the Facility Operating License duplicate thosedefined in 10 CFR 50.72 and 10 CFR 50.73. However, the requirements in the FacilityOperating License have different deadlines than those defined in the regulations following a rulechange in 2001. This difference in reporting requirements has led to variations in reporting since many facility operating licenses do not contain the subject condition. For those licenseeswith a 30-day reporting requirement in the Facility Operating License, the condition hasdecreased the benefits of the rulemaking. For those cases where the current Facility OperatingLicense requirement to report violations is also reportable in accordance with the regulations defined in 10 CFR 50.72 and 10 CFR 50.73, the NRC staff finds that the regulations adequatelyaddress this issue and the elimination of the duplicative requirement in the Facility OperatingLicense is acceptable.Some of the conditions addressed in Section 2.C of the Facility Operating License mayaddress the maintenance of particular programs, administrative requirements, or other matters where a violation of the requirement would not result in a report to the NRC in accordance with10 CFR 50.72 or 10 CFR 50.73. In most cases, there are requirements for reports to the NRC related to these conditions in other regulations, the specific license condition or technical specification, or an NRC-approved program document. In other cases, there are reports toother agencies or news releases that would prompt a report to the NRC (in accordance with10 CFR 50.72(b)(2)(xi)). The NRC staff also assessed violations of administrative requirementsthat could be reportable under the current License Condition but that may not have a duplicativerequirement in a regulation or other regulatory requirement. The NRC staff finds that therequirements to report such problems within 24 hours with written reports to follow using the LER process is not needed. The NRC staff is confident that the information related to suchviolations that is actually important to the NRC's regulatory functions would come to light in atime frame comparable to the 60-day LER requirements. The information would become available to the appropriate NRC staff through the inspection program, updates to programdocuments, resultant licensing actions, public announcements, or some other reliable mechanism.The NRC staff finds that the elimination of Section 2.F in the MPS3 Facility Operating Licensewill not result in a loss of information to the NRC that would adversely affect either its goal toprotect public health and safety or its ability to carry out its various other regulatoryresponsibilities. Therefore, the elimination of Section 2.F of the Facility Operating License isacceptable.


==4.0STATE CONSULTATION==
==5.0    ENVIRONMENTAL CONSIDERATION==
In accordance with the Commission's regulations, the Connecticut State official was notified ofthe proposed issuance of the amendment. The State official had no comments.


==5.0ENVIRONMENTAL CONSIDERATION==
The amendment changes recordkeeping, reporting, or administrative procedures or requirements. Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(10). Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.
The amendment changes recordkeeping, reporting, or administrative procedures orrequirements. Accordingly, the amendment meets the eligibility criteria for categorical exclusionset forth in 10 CFR 51.22(c)(10). Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.


==6.0CONCLUSION==
==6.0    CONCLUSION==
The Commission has concluded, based on the considerations discussed above, that (1) there isreasonable assurance that the health and safety of the public will not be endangered byoperation in the proposed manner, (2) such activities will be conducted in compliance with theCommission's regulations, and (3) the issuance of the amendment will not be inimical to thecommon defense and security or to the health and safety of the public. Principal Contributor:  E. Thomas Date: October 4, 2006 Millstone Power Station, Unit No. 3 cc:
Lillilan M. Cuoco, EsquireSenior Counsel Dominion Resources Services, Inc.
Building 475, 5 th FloorRope Ferry Road Waterford, CT  06385Edward L. Wilds, Jr., Ph.D.Director, Division of Radiation Department of Environmental Protection 79 Elm Street Hartford, CT  06106-5127Regional Administrator, Region IU.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA  19406First SelectmenTown of Waterford 15 Rope Ferry Road Waterford, CT  06385Mr. J. W. "Bill" S heehan Co-Chair NEAC 19 Laurel Crest Drive Waterford, CT 06385Mr. Evan W. WoollacottCo-Chair Nuclear Energy Advisory Council 128 Terry's Plain Road Simsbury, CT  06070Senior Resident InspectorMillstone Power Stationc/o U.S. Nuclear Regulatory Commission


P. O. Box 513 Niantic, CT  06357Ms. Nancy Burton147 Cross Highway Redding Ridge, CT  00870Mr. Joseph Roy, Director of Operations Massachusetts Municipal Wholesale Electric Company Moody Street
The Commission has concluded, based on the considerations discussed above, that (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commissions regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributor: E. Thomas Date: October 4, 2006


P.O. Box 426 Ludlow, MA 01056Mr. J. Alan PriceSite Vice President Dominion Nuclear Connecticut, Inc.
Millstone Power Station, Unit No. 3 cc:
Building 475, 5 th FloorRope Ferry Road Waterford, CT 06385Mr. Chris FunderburkDirector, Nuclear Licensing and Operations Support Dominion Resources Services, Inc.
Lillilan M. Cuoco, Esquire            Mr. Joseph Roy, Senior Counsel                        Director of Operations Dominion Resources Services, Inc.      Massachusetts Municipal Wholesale Building 475, 5th Floor                Electric Company Rope Ferry Road                        Moody Street Waterford, CT 06385                    P.O. Box 426 Ludlow, MA 01056 Edward L. Wilds, Jr., Ph.D.
5000 Dominion Boulevard Glen Allen, VA 23060-6711Mr. David W. DodsonLicensing Supervisor Dominion Nuclear Connecticut, Inc.
Director, Division of Radiation        Mr. J. Alan Price Department of Environmental Protection Site Vice President 79 Elm Street                          Dominion Nuclear Connecticut, Inc.
Building 475, 5 th FloorRope Ferry Road Waterford, CT 06385}}
Hartford, CT 06106-5127                Building 475, 5th Floor Rope Ferry Road Regional Administrator, Region I      Waterford, CT 06385 U.S. Nuclear Regulatory Commission 475 Allendale Road                    Mr. Chris Funderburk King of Prussia, PA 19406              Director, Nuclear Licensing and Operations Support First Selectmen                        Dominion Resources Services, Inc.
Town of Waterford                      5000 Dominion Boulevard 15 Rope Ferry Road                    Glen Allen, VA 23060-6711 Waterford, CT 06385 Mr. David W. Dodson Mr. J. W. "Bill" Sheehan              Licensing Supervisor Co-Chair NEAC                          Dominion Nuclear Connecticut, Inc.
19 Laurel Crest Drive                  Building 475, 5th Floor Waterford, CT 06385                    Rope Ferry Road Waterford, CT 06385 Mr. Evan W. Woollacott Co-Chair Nuclear Energy Advisory Council 128 Terry's Plain Road Simsbury, CT 06070 Senior Resident Inspector Millstone Power Station c/o U.S. Nuclear Regulatory Commission P. O. Box 513 Niantic, CT 06357 Ms. Nancy Burton 147 Cross Highway Redding Ridge, CT 00870}}

Latest revision as of 05:41, 14 March 2020

Issuance of License Amendment 234 Deleting Section 2.F to Facility Operating License No. NPF-49
ML061430135
Person / Time
Site: Millstone Dominion icon.png
Issue date: 10/04/2006
From: Nerses V
NRC/NRR/ADRO/DORL/LPLI-2
To: Christian D
Dominion Nuclear Connecticut
Nerses V, NRR//DLPM, 415-1484
Shared Package
ML061930080 List:
References
TAC MD1056
Download: ML061430135 (9)


Text

October 4, 2006 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NO. 3 - ISSUANCE OF AMENDMENT RE: DELETING SECTION 2.F TO FACILITY OPERATING LICENSE NO.

NPF-49 (TAC NO. MD1056)

Dear Mr. Christian:

The Commission has issued the enclosed Amendment No. 234 to Facility Operating License No. NPF-49 for the Millstone Power Station, Unit No. 3., in response to your application dated March 28, 2006. This amendment revises Facility Operating License No. NPF-49 by deleting Section 2.F, which specifies reporting of violations of the requirements of Section 2.C of the renewed operating license.

A copy of our Safety Evaluation is also enclosed. Notice of Issuance will be included in the Commissions biweekly Federal Register notice.

Sincerely,

/RA/

Victor Nerses, Senior Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-423

Enclosures:

1. Amendment No. 234 to License No. NPF-49
2. Safety Evaluation cc w/encls: See next page

October 4, 2006 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NO. 3 - ISSUANCE OF AMENDMENT RE: DELETING SECTION 2.F TO FACILITY OPERATING LICENSE NO.

NPF-49 (TAC NO. MD1056)

Dear Mr. Christian:

The Commission has issued the enclosed Amendment No. 234 to Facility Operating License No. NPF-49 for the Millstone Power Station, Unit No. 3., in response to your application dated March 28, 2006. This amendment revises Facility Operating License No. NPF-49 by deleting Section 2.F, which specifies reporting of violations of the requirements of Section 2.C of the renewed operating license.

A copy of our Safety Evaluation is also enclosed. Notice of Issuance will be included in the Commissions biweekly Federal Register notice.

Sincerely,

/RA/

Victor Nerses, Senior Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-423

Enclosures:

1. Amendment No. 234 to License No. NPF-49
2. Safety Evaluation cc w/encls: See next page DISTRIBUTION:

RidsNrrLpl1-2 RidsOgcRp RidsRgn1MailCenter PUBLIC RidsNrrPMVNerses RidsAcrs AcnwMailCenter LPL1-2 R/F RidsNrrLACRaynor TKobetz RidsNrrDorl GHill (2)

Package Accession Number: ML061930080 Amendment Accession Number: ML061430135 Tech Specs. Accession Number: ML062790492 OFFICE LPL1-2/PM LPL1-2/LA ITSB/BC OGC/NLO LPL1-2/BC (A)

NAME VNerses:rsa CRaynor TKobetz MZobler BPoole DATE 7/26/06 7/25/06 5/18/06 8/2/06 8/3/06 OFFICIAL RECORD COPY

DOMINION NUCLEAR CONNECTICUT, INC.

DOCKET NO. 50-423 MILLSTONE POWER STATION, UNIT NO. 3 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 234 License No. NPF-49

1. The Nuclear Regulatory Commission (the Commission) has found that:

A. The application for amendment filed by Dominion Nuclear Connecticut, Inc. (the licensee) dated March 28, 2006, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in Title 10 of the Code of Federal Regulations (10 CFR), Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations set forth in 10 CFR Chapter I; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.

2. Accordingly, the license is amended by deleting paragraph 2.F of Facility Operating License No. NPF-49 as indicated in the attachment to this license amendment.
3. This license amendment is effective as of its date of issuance and shall be implemented within 60 days.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Brooke D. Poole, Acting Chief Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Attachment:

Changes to the Renewed Operating License Date of Issuance: October 4, 2006

ATTACHMENT TO LICENSE AMENDMENT NO. 234 FACILITY OPERATING LICENSE NO. NPF-49 DOCKET NO. 50-423 Replace the following page of Facility Operating License No. NPF-49 as indicated. The revised page is identified by amendment number and contains a marginal line indicating the area of change.

Remove Page Insert Page SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO.234 TO FACILITY OPERATING LICENSE NO. NPF-49 DOMINION NUCLEAR CONNECTICUT, INC.

MILLSTONE POWER STATION, UNIT NO. 3 DOCKET NO. 50-423

1.0 INTRODUCTION

By letter dated March 28, 2006, Dominion Nuclear Connecticut, Inc. (DNC or the licensee) requested a license amendment for Millstone Power Station, Unit No. 3 (MPS3). The licensee requested to delete Section 2.F of Facility Operating License No. NPF-49, which specifies reporting of violations of the requirements in Section 2.C. A notice announcing the availability of this proposed change using the consolidated line item improvement process (CLIIP) was published in the Federal Register on November 4, 2005 (70 FR 67202).

The Nuclear Regulatory Commission (NRC or the Commission) staffs proposed no significant hazards consideration determination of the licensees proposed amendment was published in the Federal Register on May 9, 2006 (71 FR 26997).

2.0 REGULATORY EVALUATION

A section or condition was included in the facility operating licenses issued to some nuclear power plants requiring the licensee to make reports to the NRC regarding violations of other sections of the operating license (typically Section 2.C). In the case of MPS3, Section 2.F of the Facility Operating License reads as follows:

Except as otherwise provided in the Technical Specifications or Environmental Protection Plan, [DNC] shall report any violations of the requirements contained in Section 2.C. of this renewed operating license in the following manner: initial notification shall be made within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to the NRC Operations Center via the Emergency Notification System with written followup within thirty days in accordance with the procedures described in [Title 10 of the Code of Federal Regulations (10 CFR)]

10 CFR Sections 50.73(b), (c) and (e).

In addition to the information provided to support licensing decisions, the NRC obtains information about plant operation, licensee programs, and other matters using a combination of inspections and reporting requirements. Routine or scheduled reports that are required to be submitted to the NRC are defined in the related regulations, specific license condition, technical specification, or an NRC-approved program document. The reporting of emergencies,

unplanned events or conditions, and other special cases may also be addressed within such documents by the inclusion of reporting thresholds and are also the focus of the reporting requirements in 10 CFR 50.72, Immediate notification requirements for operating nuclear power reactors, and 10 CFR 50.73, Licensee event report system. Changes to the reporting regulations in 10 CFR Sections 50.72 and 50.73 became effective in January 2001 (see Federal Register notice on October 25, 2000 (65 FR 63769) and included extending the allowable reporting times for licensee event reports (LERs) from 30 days to 60 days.

3.0 TECHNICAL EVALUATION

Section 2.F of the MPS3 Facility Operating License requires the licensee to report any violations of the requirements of Section 2.C of the Facility Operating License and defines the method and allowable time periods for such reports. The reporting threshold (i.e., a violation) for the conditions included in Section 2.C of the Facility Operating License duplicate those defined in 10 CFR 50.72 and 10 CFR 50.73. However, the requirements in the Facility Operating License have different deadlines than those defined in the regulations following a rule change in 2001. This difference in reporting requirements has led to variations in reporting since many facility operating licenses do not contain the subject condition. For those licensees with a 30-day reporting requirement in the Facility Operating License, the condition has decreased the benefits of the rulemaking. For those cases where the current Facility Operating License requirement to report violations is also reportable in accordance with the regulations defined in 10 CFR 50.72 and 10 CFR 50.73, the NRC staff finds that the regulations adequately address this issue and the elimination of the duplicative requirement in the Facility Operating License is acceptable.

Some of the conditions addressed in Section 2.C of the Facility Operating License may address the maintenance of particular programs, administrative requirements, or other matters where a violation of the requirement would not result in a report to the NRC in accordance with 10 CFR 50.72 or 10 CFR 50.73. In most cases, there are requirements for reports to the NRC related to these conditions in other regulations, the specific license condition or technical specification, or an NRC-approved program document. In other cases, there are reports to other agencies or news releases that would prompt a report to the NRC (in accordance with 10 CFR 50.72(b)(2)(xi)). The NRC staff also assessed violations of administrative requirements that could be reportable under the current License Condition but that may not have a duplicative requirement in a regulation or other regulatory requirement. The NRC staff finds that the requirements to report such problems within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> with written reports to follow using the LER process is not needed. The NRC staff is confident that the information related to such violations that is actually important to the NRCs regulatory functions would come to light in a time frame comparable to the 60-day LER requirements. The information would become available to the appropriate NRC staff through the inspection program, updates to program documents, resultant licensing actions, public announcements, or some other reliable mechanism.

The NRC staff finds that the elimination of Section 2.F in the MPS3 Facility Operating License will not result in a loss of information to the NRC that would adversely affect either its goal to protect public health and safety or its ability to carry out its various other regulatory responsibilities. Therefore, the elimination of Section 2.F of the Facility Operating License is acceptable.

4.0 STATE CONSULTATION

In accordance with the Commissions regulations, the Connecticut State official was notified of the proposed issuance of the amendment. The State official had no comments.

5.0 ENVIRONMENTAL CONSIDERATION

The amendment changes recordkeeping, reporting, or administrative procedures or requirements. Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(10). Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.

6.0 CONCLUSION

The Commission has concluded, based on the considerations discussed above, that (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commissions regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.

Principal Contributor: E. Thomas Date: October 4, 2006

Millstone Power Station, Unit No. 3 cc:

Lillilan M. Cuoco, Esquire Mr. Joseph Roy, Senior Counsel Director of Operations Dominion Resources Services, Inc. Massachusetts Municipal Wholesale Building 475, 5th Floor Electric Company Rope Ferry Road Moody Street Waterford, CT 06385 P.O. Box 426 Ludlow, MA 01056 Edward L. Wilds, Jr., Ph.D.

Director, Division of Radiation Mr. J. Alan Price Department of Environmental Protection Site Vice President 79 Elm Street Dominion Nuclear Connecticut, Inc.

Hartford, CT 06106-5127 Building 475, 5th Floor Rope Ferry Road Regional Administrator, Region I Waterford, CT 06385 U.S. Nuclear Regulatory Commission 475 Allendale Road Mr. Chris Funderburk King of Prussia, PA 19406 Director, Nuclear Licensing and Operations Support First Selectmen Dominion Resources Services, Inc.

Town of Waterford 5000 Dominion Boulevard 15 Rope Ferry Road Glen Allen, VA 23060-6711 Waterford, CT 06385 Mr. David W. Dodson Mr. J. W. "Bill" Sheehan Licensing Supervisor Co-Chair NEAC Dominion Nuclear Connecticut, Inc.

19 Laurel Crest Drive Building 475, 5th Floor Waterford, CT 06385 Rope Ferry Road Waterford, CT 06385 Mr. Evan W. Woollacott Co-Chair Nuclear Energy Advisory Council 128 Terry's Plain Road Simsbury, CT 06070 Senior Resident Inspector Millstone Power Station c/o U.S. Nuclear Regulatory Commission P. O. Box 513 Niantic, CT 06357 Ms. Nancy Burton 147 Cross Highway Redding Ridge, CT 00870