ML120090229: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(3 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML120090229
| number = ML120090229
| issue date = 01/09/2012
| issue date = 01/09/2012
| title = Turkey Point Unit 3 - Notification of Inspection and Request for Information
| title = Notification of Inspection and Request for Information
| author name = Vias S J
| author name = Vias S
| author affiliation = NRC/RGN-III/DRS/EB3
| author affiliation = NRC/RGN-III/DRS/EB3
| addressee name = Nazar M
| addressee name = Nazar M
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 January 9, 2012  
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 January 9, 2012 Mr. Mano Nazar Executive Vice President and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420
 
Mr. Mano Nazar Executive Vice President and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420  


==SUBJECT:==
==SUBJECT:==
TURKEY POINT UNIT 3 - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION  
TURKEY POINT UNIT 3 - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION


==Dear Mr. Nazar:==
==Dear Mr. Nazar:==


From February 6-10, 2012, the NRC will perform the baseline in-service inspection (ISI) at the Turkey Point Unit 3 (NRC Inspection Procedure 71111.08 and Temporary Instruction 2515/172, "Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles"). Experience has shown that this inspection is resource intensive both for the NRC inspectors and your staff. In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. These documents have been divided into two groups. The first group (section A of the enclosure) identifies information to be provided prior to the inspection to ensure that the inspectors are adequately prepared. The second group (section B of the enclosure) identifies the information the inspectors will need upon arrival at the site. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.
From February 6-10, 2012, the NRC will perform the baseline in-service inspection (ISI) at the Turkey Point Unit 3 (NRC Inspection Procedure 71111.08 and Temporary Instruction 2515/172, Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles). Experience has shown that this inspection is resource intensive both for the NRC inspectors and your staff. In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. These documents have been divided into two groups. The first group (section A of the enclosure) identifies information to be provided prior to the inspection to ensure that the inspectors are adequately prepared.
We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Stavroula Mihalakea of your organization. Our inspection dates are subject to change based on your updated schedule of outage activities. If there are any questions about this inspection or the material requested, please contact the lead inspector Alexandra Rogers at (404) 997-4657 (alexandra.rogers@nrc.gov).
The second group (section B of the enclosure) identifies the information the inspectors will need upon arrival at the site. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document
We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Stavroula Mihalakea of your organization.
 
Our inspection dates are subject to change based on your updated schedule of outage activities. If there are any questions about this inspection or the material requested, please contact the lead inspector Alexandra Rogers at (404) 997-4657 (alexandra.rogers@nrc.gov).
2 FP&L  Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document
Sincerely,


      /RA/
2 FP&L Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Steven J. Vias, Chief       Engineering Branch 3 Division of Reactor Safety Docket No. 50-250 License No. DPR-31  
Sincerely,
                                          /RA/
Steven J. Vias, Chief Engineering Branch 3 Division of Reactor Safety Docket No. 50-250 License No. DPR-31


==Enclosure:==
==Enclosure:==
Pre-Inspection Document Request  
Pre-Inspection Document Request cc w/encl.: (See page 3)
 
cc w/encl.: (See page 3)  
 
_ML# 120090229________
X SUNSI REVIEW COMPLETE X  FORM 665 ATTACHED OFFICE RII:  DRS/EB3 RII:L  DRS/EB3 RII: DRP        SIGNATURE /RA/ /RA/ /RA/    NAME A. ROGERS S. VIAS D. RICH    DATE 1/6/2012 1/9/2012 1/9/2012    E-MAIL COPY    YES NO YES NO YES NO      YES NO      YES NO      YES NO      YES NO 3 FP&L Enclosure cc w/encl: Alison Brown Nuclear Licensing Florida Power & Light Company Electronic Mail Distribution
 
Larry Nicholson Director Licensing Florida Power & Light Company Electronic Mail Distribution
 
Michael Kiley Site Vice President Turkey Point Nuclear Plant Florida Power and Light Company Electronic Mail Distribution
 
Neil Batista Emergency Management Coordinator Department of Emergency Management and Homeland Security Electronic Mail Distribution
 
Robert J. Tomonto Licensing Manager Turkey Point Nuclear Plant Florida Power & Light Company Electronic Mail Distribution Eric McCartney Plant General Manager Turkey Point Nuclear Plant Florida Power and Light Company Electronic Mail Distribution Mitch S. Ross Vice President and General Counsel Nuclear Florida Power & Light Company Electronic Mail Distribution
 
William A. Passetti Chief Florida Bureau of Radiation Control Department of Health Electronic Mail Distribution
 
Senior Resident Inspector Turkey Point Nuclear Generating Station U.S. Nuclear Regulatory Commission 9762 SW 344th St. Florida City, FL  33035


Attorney General Department of Legal Affairs The Capitol PL-01 Tallahassee, FL   32399-1050  
_ML# 120090229________        X SUNSI REVIEW COMPLETE  X FORM 665 ATTACHED OFFICE            RII: DRS/EB3 RII:L DRS/EB3 RII: DRP SIGNATURE                /RA/        /RA/          /RA/
NAME                A. ROGERS      S. VIAS      D. RICH DATE                  1/6/2012    1/9/2012      1/9/2012 E-MAIL COPY          YES    NO  YES      NO  YES      NO      YES  NO    YES  NO  YES  NO      YES  NO 3
FP&L cc w/encl:                          Mitch S. Ross Alison Brown                        Vice President and General Counsel Nuclear Licensing                    Nuclear Florida Power & Light Company        Florida Power & Light Company Electronic Mail Distribution        Electronic Mail Distribution Larry Nicholson                      William A. Passetti Director                            Chief Licensing                            Florida Bureau of Radiation Control Florida Power & Light Company        Department of Health Electronic Mail Distribution        Electronic Mail Distribution Michael Kiley                        Senior Resident Inspector Site Vice President                  Turkey Point Nuclear Generating Station Turkey Point Nuclear Plant          U.S. Nuclear Regulatory Commission Florida Power and Light Company      9762 SW 344th St.
Electronic Mail Distribution        Florida City, FL 33035 Neil Batista                        Attorney General Emergency Management Coordinator    Department of Legal Affairs Department of Emergency Management  The Capitol PL-01 and Homeland Security                Tallahassee, FL 32399-1050 Electronic Mail Distribution County Manager of Miami-Dade County Robert J. Tomonto                    111 NW 1st Street, 29th Floor Licensing Manager                    Miami, FL 33128 Turkey Point Nuclear Plant Florida Power & Light Company        Gene St. Pierre Electronic Mail Distribution        Vice President, Fleet Support Florida Power & Light Company Eric McCartney                      Electronic Mail Distribution Plant General Manager Turkey Point Nuclear Plant          George Gretsas Florida Power and Light Company      City Manager Electronic Mail Distribution        City of Homestead Electronic Mail Distribution Marjan Mashhadi Senior Attorney Florida Power & Light Company Electronic Mail Distribution Enclosure


County Manager of Miami-Dade County 111 NW 1st Street, 29th Floor Miami, FL  33128 Gene St. Pierre Vice President, Fleet Support Florida Power & Light Company Electronic Mail Distribution George Gretsas City Manager City of Homestead Electronic Mail DistributionMarjan Mashhadi Senior Attorney Florida Power & Light Company Electronic Mail Distribution
INSERVICE INSPECTION DOCUMENT REQUEST Inspection Dates:              February 6-10, 2012 Inspection Procedures:          IP 71111.08 Inservice Inspection (ISI) Activities TI 2515/172 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles Inspectors:                    Alexandra Rogers, Reactor Inspector (Lead Inspector - ISI)
A. Information Requested for the In-Office Preparation Week The following information should be sent to the Region II office in hard copy or electronic format (CD preferred), in care of Alexandra Rogers by January 27, 2012, to facilitate the selection of specific items that will be reviewed during the onsite inspection week. The inspector will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week (section B of this enclosure). We ask that the specific items selected from the lists be available and ready for review on the first day of inspection. *Please provide requested documentation electronically if possible. If requested documents are large and only hard copy formats are available, please inform the inspector, and provide subject documentation during the first day of the onsite inspection. If you have any questions regarding this information request, please call the inspector as soon as possible.
A.1    ISI / Welding Programs and Schedule Information a)      A detailed schedule (including preliminary dates) of:
i)      Nondestructive examinations (NDEs) planned for Class 1 & 2 systems and containment, performed as part of your ASME Section XI, Risk Informed (if applicable), and augmented ISI Programs during the upcoming outage.
Provide a status summary of the NDE inspection activities vs. the required inspection period percentages for this Interval by category per ASME Section XI, IWX-2400. (Do not provide separately if other documentation requested contains this information) ii)    Reactor pressure vessel head (RPVH) examinations planned for the upcoming outage.
iii)    Examinations planned for Alloy 82/182/600 components that are not included in the Section XI scope. (If applicable) iv)    Examinations planned as part of your Boric Acid Corrosion Control Program. (Mode 3 walkdowns, bolted connection walkdowns, etc.)
Enclosure


Enclosure INSERVICE INSPECTION DOCUMENT REQUEST
2 v)       Welding activities that are scheduled to be completed during the upcoming outage. (ASME Class 1, 2, or 3 structures, systems, or components (SSCs))
 
b)     A copy of ASME Section XI Code Relief Requests and associated NRC Safety Evaluations applicable to the examinations identified above.
Inspection Dates:  February 6-10, 2012 Inspection Procedures: IP 71111.08 "Inservice Inspection (ISI) Activities" TI 2515/172 "Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles" Inspectors:  Alexandra Rogers, Reactor Inspector (Lead Inspector - ISI)
c)     A list of NDE reports (ultrasonic, radiography, magnetic particle, and dye penetrant) which have identified surface or volumetric indications that were analytically evaluated and accepted for continued service on Code Class 1, 2, &
A. Information Requested for the In-Office Preparation Week The following information should be sent to the Region II office in hard copy or electronic format (CD preferred), in care of Alexandra Rogers by January 27, 2012, to facilitate the selection of specific items that will be reviewed during the onsite inspection week. The inspector will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week (section B of this enclosure). We ask that the specific items selected from the lists be available and ready for review on the first day of inspection.  *Please provide requested documentation electronically if possible. If requested documents are large and only hard copy formats are available, please inform the inspector, and provide subject documentation during the first day of the onsite inspection. If you have any questions regarding this information request, please call the inspector as soon as possible.
3 systems since the beginning of the last refueling outage. This should include the previous Section XI pressure test(s) conducted during start up and any evaluations associated with the results of the pressure tests.
A.1 ISI / Welding Programs and Schedule Information a) A detailed schedule (including preliminary dates) of:
d)     A list with a brief description (e.g. system, material, pipe size, weld number, and NDE performed) of the welds in Code Class 1, 2, and 3 systems which have been fabricated due to component repair/replacement activities since the beginning of the last refueling outage, or are planned to be fabricated this refueling outage. Also, please indicate which of those welds are risk significant.
i)  Nondestructive examinations (NDEs) planned for Class 1 & 2 systems and containment, performed as part of your ASME Section XI, Risk Informed (if applicable), and augmented ISI Programs during the upcoming outage. Provide a status summary of the NDE inspection activities vs. the required inspection period percentages for this Interval by category per ASME Section XI, IWX-2400.  (Do not provide separately if other documentation requested contains this information) ii)  Reactor pressure vessel head (RPVH) examinations planned for the upcoming outage.
e)     If reactor vessel shell weld examinations required by the ASME Code are scheduled to occur during the upcoming outage, provide a detailed description of the welds to be examined, and the extent of the planned examination. Please also provide reference numbers for applicable procedures that will be used to conduct these examinations.
iii)  Examinations planned for Alloy 82/182/600 components that are not included in the Section XI scope.  (If applicable) iv) Examinations planned as part of your Boric Acid Corrosion Control Program.  (Mode 3 walkdowns, bolted connection walkdowns, etc.)
f)     Copy of any 10 CFR Part 21 reports applicable to your SSCs within the scope of Section XI of the ASME Code that have been identified since the beginning of the last refueling outage.
 
g)     A list of any temporary non-code repairs in service (e.g. pinhole leaks).
2  Enclosure v)         Welding activities that are scheduled to be completed during the upcoming outage. (ASME Class 1, 2, or 3 structures, systems, or components (SSCs))
h)     Please provide copies of the most recent self assessments for the ISI, Welding, and Alloy 600 Programs.
b) A copy of ASME Section XI Code Relief Requests and associated NRC Safety Evaluations applicable to the examinations identified above.
c) A list of NDE reports (ultrasonic, radiography, magnetic particle, and dye penetrant) which have identified surface or volumetric indications that were analytically evaluated and accepted for continued service on Code Class 1, 2, & 3 systems since the beginning of the last refueling outage. This should include the previous Section XI pressure test(s) conducted during start up and any evaluations associated with the results of the pressure tests.
d) A list with a brief description (e.g. system, material, pipe size, weld number, and NDE performed) of the welds in Code Class 1, 2, and 3 systems which have been fabricated due to component repair/replacement activities since the beginning of the last refueling outage, or are planned to be fabricated this refueling outage. Also, please indicate which of those welds are risk significant.
e) If reactor vessel shell weld examinations required by the ASME Code are scheduled to occur during the upcoming outage, provide a detailed description of the welds to be examined, and the extent of the planned examination. Please also provide reference numbers for applicable procedures that will be used to conduct these examinations.
f) Copy of any 10 CFR Part 21 reports applicable to your SSCs within the scope of Section XI of the ASME Code that have been identified since the beginning of the last refueling outage.
g) A list of any temporary non-code repairs in service (e.g. pinhole leaks).
h) Please provide copies of the most recent self assessments for the ISI, Welding, and Alloy 600 Programs.
A.2 Reactor Pressure Vessel Head (RPVH): If this inspection will not be performed, this outage provide when the last inspection was performed and what type of inspection was performed.
A.2 Reactor Pressure Vessel Head (RPVH): If this inspection will not be performed, this outage provide when the last inspection was performed and what type of inspection was performed.
a) Provide the detailed scope of the planned NDE of the reactor vessel head which identifies the types of NDE methods to be used on each specific part of the vessel head to meet the augmented inspection requirements of 10CFR50.55a(g)(6)(ii)(D). Also, include examination scope expansion criteria and planned expansion sample sizes if relevant indications are identified. (If applicable) b) A list of the standards and/or requirements that will be used to evaluate indications identified during NDE of the reactor vessel head (e.g. the specific industry or procedural standards that will be used to evaluate potential leakage and/or flaw indications).  
a)     Provide the detailed scope of the planned NDE of the reactor vessel head which identifies the types of NDE methods to be used on each specific part of the vessel head to meet the augmented inspection requirements of 10CFR50.55a(g)(6)(ii)(D). Also, include examination scope expansion criteria and planned expansion sample sizes if relevant indications are identified. (If applicable) b)     A list of the standards and/or requirements that will be used to evaluate indications identified during NDE of the reactor vessel head (e.g. the specific industry or procedural standards that will be used to evaluate potential leakage and/or flaw indications).
 
Enclosure
Enclosure c) Also, include in the list the NDE reports with identified surface or volumetric indications in the RPVH penetration nozzles, which have been analytically evaluated and accepted for continued service. The list of NDE reports should include a brief description of the SSC where the recordable indication was identified.
 
A.3 Boric Acid Corrosion Control Program (BACCP) a)  Copy of the procedures that govern the scope, equipment, and implementation of the inspections required to identify boric acid leakage and the procedures for boric acid leakage/corrosion evaluation.
b) Please provide a list of leaks (including code class of the components) that have been identified since the last refueling outage and associated corrective action documentation. If during the last cycle, the Unit was shutdown, please provide documentation of containment walk-down inspections performed as part of the BACCP. c) Please provide a copy of the most recent self-assessment performed for the BACCP. A.4 Steam Generator (SG) Inspections


a) Please include a copy of the Operational Assessment from last outage, and a copy of the following documents as they become available:
3 c)    Also, include in the list the NDE reports with identified surface or volumetric indications in the RPVH penetration nozzles, which have been analytically evaluated and accepted for continued service. The list of NDE reports should include a brief description of the SSC where the recordable indication was identified.
i) Degradation Assessment ii) Condition Monitoring Assessment A.5 Additional information related to all ISI activities a) A list with a brief description of ISI, BACCP, and SG ISI related issues (e.g., condition reports) entered into your corrective action program since the beginning of the last refueling outage (for Units 3 and 4). For example, a list based upon data base searches using key words related to piping or SG tube degradation such as: ISI, ASME Code, Section XI, NDE, cracks, wear, thinning, leakage, rust, corrosion, boric acid, or errors in piping/SG tube examinations.
A.3 Boric Acid Corrosion Control Program (BACCP) a)    Copy of the procedures that govern the scope, equipment, and implementation of the inspections required to identify boric acid leakage and the procedures for boric acid leakage/corrosion evaluation.
b) Please provide names and phone numbers for the following program leads:
b)    Please provide a list of leaks (including code class of the components) that have been identified since the last refueling outage and associated corrective action documentation. If during the last cycle, the Unit was shutdown, please provide documentation of containment walk-down inspections performed as part of the BACCP.
i) ISI contacts (Examination, planning) ii) Containment Exams   iii) PVH Exams iv) Snubbers and Supports v) Repair and Replacement Program Manager vi) Licensing Contact vii) Site Welding Engineer viii) Boric Acid Corrosion Control Program ix) SG Inspection Activities (site lead and vendor contact) Enclosure B. Information to be provided on-site to the inspector at the entrance meeting (February 6, 2012):
c)    Please provide a copy of the most recent self-assessment performed for the BACCP.
B.1 ISI / Welding Programs and Schedule Information a) Updated schedules for ISI/NDE activities, including SG ISI, planned welding activities, and schedule showing contingency repair plans, if available.
A.4 Steam Generator (SG) Inspections a)     Please include a copy of the Operational Assessment from last outage, and a copy of the following documents as they become available:
b) For ASME Class 1, 2, and 3 welds selected by the inspector from the lists provided from section A of this enclosure, please provide copies of the following documentation for each subject weld:
i)       Degradation Assessment ii)     Condition Monitoring Assessment A.5 Additional information related to all ISI activities a)     A list with a brief description of ISI, BACCP, and SG ISI related issues (e.g.,
i) Weld data sheet (traveler) ii) Weld configuration and system location iii) Applicable Code Edition and Addenda for weldment iv) Applicable Code Edition and Addenda for welding procedures v) Applicable weld procedures (WPS) used to fabricate the welds vi) Copies of procedure qualification records (PQRs) supporting the WPS from B.1.b.v vii) Copies of mechanical test reports identified in the PQRs above viii) Copies of the nonconformance reports for the selected welds (If Applicable) ix) Radiographs of the selected welds and access to equipment to allow viewing radiographs (If RT was performed) x) Copies of the pre-service examination records for the selected welds. xi) Copies of welder performance qualifications records applicable to WPS, including documentation that welder maintained proficiency in the applicable welding processes specified in the WPS (At least six months prior to date subject work) xii) Copies of NDE personnel qualifications (VT, PT, UT, RT) As applicable c) For the ISI related corrective action issues selected by the inspector from section A of this enclosure, provide a copy of the corrective actions and supporting documentation.
condition reports) entered into your corrective action program since the beginning of the last refueling outage (for Units 3 and 4). For example, a list based upon data base searches using key words related to piping or SG tube degradation such as: ISI, ASME Code, Section XI, NDE, cracks, wear, thinning, leakage, rust, corrosion, boric acid, or errors in piping/SG tube examinations.
d) For the NDE reports with relevant indications on Code Class 1, 2, & 3 systems selected by the inspector from section A above, provide a copy of the examination records, examiner qualification records, and associated corrective action documents.
b)     Please provide names and phone numbers for the following program leads:
e) A copy of (or ready access to) most current revision of the ISI Program Manual and Plan for the current Interval.
i)       ISI contacts (Examination, planning) ii)     Containment Exams iii)     PVH Exams iv)     Snubbers and Supports v)       Repair and Replacement Program Manager vi)     Licensing Contact vii)     Site Welding Engineer viii)   Boric Acid Corrosion Control Program ix)     SG Inspection Activities (site lead and vendor contact)
f) For the NDEs selected by the inspector from section A of this enclosure, provide copy of the NDE procedures used to perform the examinations (including calibration and flaw characterization/sizing procedures). For ultrasonic examination procedures qualified in accordance with ASME Code, Section XI,    Appendix VIII, provide documentation supporting the procedure qualification 
Enclosure


5  Enclosure  (e.g., the EPRI performance demonstration qualification summary sheets). Also, include documentation of the specific equipment to be used (e.g., ultrasonic unit, cables, and transducers including serial numbers) and NDE personnel qualification records.
4 B. Information to be provided on-site to the inspector at the entrance meeting (February 6, 2012):
B.2 Reactor Pressure Vessel Head (RPVH) a) Provide the NDE personnel qualification records for the examiners who will perform examinations of the RPVH.
B.1 ISI / Welding Programs and Schedule Information a)     Updated schedules for ISI/NDE activities, including SG ISI, planned welding activities, and schedule showing contingency repair plans, if available.
b) Provide drawings showing the following: (If a visual examination is planned for  the upcoming refueling outage) i) RPVH and CRDM nozzle configurations  ii) RPVH insulation configuration The drawings listed above should include fabrication drawings for the nozzle attachment welds as applicable.
b)     For ASME Class 1, 2, and 3 welds selected by the inspector from the lists provided from section A of this enclosure, please provide copies of the following documentation for each subject weld:
c) Copy of NDE reports from the last RPVH examination.
i)      Weld data sheet (traveler) ii)     Weld configuration and system location iii)     Applicable Code Edition and Addenda for weldment iv)     Applicable Code Edition and Addenda for welding procedures v)      Applicable weld procedures (WPS) used to fabricate the welds vi)      Copies of procedure qualification records (PQRs) supporting the WPS from B.1.b.v vii)     Copies of mechanical test reports identified in the PQRs above viii)   Copies of the nonconformance reports for the selected welds (If Applicable) ix)      Radiographs of the selected welds and access to equipment to allow viewing radiographs (If RT was performed) x)      Copies of the pre-service examination records for the selected welds.
d) Copy of evaluation or calculation demonstrating that the scope of the visual examination of the upper head will meet the 95% minimum coverage required by ASME Code Case N-729-1 (If a visual examination is planned for the upcoming refueling outage).
xi)     Copies of welder performance qualifications records applicable to WPS, including documentation that welder maintained proficiency in the applicable welding processes specified in the WPS (At least six months prior to date subject work) xii)    Copies of NDE personnel qualifications (VT, PT, UT, RT) As applicable c)    For the ISI related corrective action issues selected by the inspector from section A of this enclosure, provide a copy of the corrective actions and supporting documentation.
e) Provide a copy of the procedures that will be used to identify the source of any boric acid deposits identified on the RPVH. If no explicit procedures exist which govern this activity, provide a description of the process to be followed including personnel responsibilities and expectations.
d)     For the NDE reports with relevant indications on Code Class 1, 2, & 3 systems selected by the inspector from section A above, provide a copy of the examination records, examiner qualification records, and associated corrective action documents.
f) Provide a copy of the updated calculation of effective degradation years (EDY)  and re-inspection years (RIY) for the RPVH crack initiation and propagation susceptibility parameters.
e)     A copy of (or ready access to) most current revision of the ISI Program Manual and Plan for the current Interval.
g) Provide copy of the vendor qualification report(s) that demonstrates the detection  capability of the NDE equipment used for the RPVH examinations. Also, identify  any changes in equipment configurations used for the RPVH examinations which differ from that used in the vendor qualification or demonstration report(s).
f)    For the NDEs selected by the inspector from section A of this enclosure, provide copy of the NDE procedures used to perform the examinations (including calibration and flaw characterization/sizing procedures). For ultrasonic examination procedures qualified in accordance with ASME Code, Section XI, Appendix VIII, provide documentation supporting the procedure qualification Enclosure
B.3 Boric Acid Corrosion Control Program (BACCP) a) Please provide boric acid walk down inspection results, an updated list of boric acid leaks identified so far this outage, associated corrective action documentation, and overall status of planned boric acid inspections.
b) Please provide any engineering evaluations completed for boric acid leaks identified since the end of the last refueling outage. Please include a status of corrective actions to repair and/or clean these boric acid leaks. Please specify which known leaks, if any, have remained in service, or will remain in service as active leaks.
6  Enclosure c) In accordance with NRC inspection procedure 71111.08, the inspector would like to conduct an independent boric acid walk down of the Reactor Building early in the inspection week. Please have knowledgeable BACCP staff available to accompany the inspector during the walk down.


B.4 Codes and Standards a) Ready access to: (i.e. copies provided to the inspector to use for the duration of the inspection at the on-site inspection location, or room number and location where available) i) Applicable editions of the ASME Code (Sections V, IX and XI) for the in-service inspection program and the repair/replacement program.
5 (e.g., the EPRI performance demonstration qualification summary sheets). Also, include documentation of the specific equipment to be used (e.g., ultrasonic unit, cables, and transducers including serial numbers) and NDE personnel qualification records.
Inspector Contact Information
B.2 Reactor Pressure Vessel Head (RPVH) a)     Provide the NDE personnel qualification records for the examiners who will perform examinations of the RPVH.
:  Alexandra Rogers. Reactor Inspector    404-997-4657                Alexandra.Rogers@nrc.gov 
b)    Provide drawings showing the following: (If a visual examination is planned for the upcoming refueling outage) i)      RPVH and CRDM nozzle configurations ii)      RPVH insulation configuration The drawings listed above should include fabrication drawings for the nozzle attachment welds as applicable.
c)    Copy of NDE reports from the last RPVH examination.
d)    Copy of evaluation or calculation demonstrating that the scope of the visual examination of the upper head will meet the 95% minimum coverage required by ASME Code Case N-729-1 (If a visual examination is planned for the upcoming refueling outage).
e)    Provide a copy of the procedures that will be used to identify the source of any boric acid deposits identified on the RPVH. If no explicit procedures exist which govern this activity, provide a description of the process to be followed including personnel responsibilities and expectations.
f)    Provide a copy of the updated calculation of effective degradation years (EDY) and re-inspection years (RIY) for the RPVH crack initiation and propagation susceptibility parameters.
g)     Provide copy of the vendor qualification report(s) that demonstrates the detection capability of the NDE equipment used for the RPVH examinations. Also, identify any changes in equipment configurations used for the RPVH examinations which differ from that used in the vendor qualification or demonstration report(s).
B.3 Boric Acid Corrosion Control Program (BACCP) a)    Please provide boric acid walk down inspection results, an updated list of boric acid leaks identified so far this outage, associated corrective action documentation, and overall status of planned boric acid inspections.
b)     Please provide any engineering evaluations completed for boric acid leaks identified since the end of the last refueling outage. Please include a status of corrective actions to repair and/or clean these boric acid leaks. Please specify which known leaks, if any, have remained in service, or will remain in service as active leaks.
Enclosure


Mailing Address
6 c)    In accordance with NRC inspection procedure 71111.08, the inspector would like to conduct an independent boric acid walk down of the Reactor Building early in the inspection week. Please have knowledgeable BACCP staff available to accompany the inspector during the walk down.
: U.S. Nuclear Regulatory Commission Region II Attn: Alexandra Rogers 245 Peachtree Center Ave NE Suite 1200 Atlanta, GA 30303}}
B.4    Codes and Standards a)    Ready access to: (i.e. copies provided to the inspector to use for the duration of the inspection at the on-site inspection location, or room number and location where available) i)    Applicable editions of the ASME Code (Sections V, IX and XI) for the in-service inspection program and the repair/replacement program.
Inspector Contact Information:
Alexandra Rogers.
Reactor Inspector 404-997-4657 Alexandra.Rogers@nrc.gov Mailing Address:
U.S. Nuclear Regulatory Commission Region II Attn: Alexandra Rogers 245 Peachtree Center Ave NE Suite 1200 Atlanta, GA 30303 Enclosure}}

Latest revision as of 20:06, 6 February 2020

Notification of Inspection and Request for Information
ML120090229
Person / Time
Site: Turkey Point NextEra Energy icon.png
Issue date: 01/09/2012
From: Vias S
Engineering Branch 3
To: Nazar M
Florida Power & Light Co
References
Download: ML120090229 (10)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 January 9, 2012 Mr. Mano Nazar Executive Vice President and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

SUBJECT:

TURKEY POINT UNIT 3 - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION

Dear Mr. Nazar:

From February 6-10, 2012, the NRC will perform the baseline in-service inspection (ISI) at the Turkey Point Unit 3 (NRC Inspection Procedure 71111.08 and Temporary Instruction 2515/172, Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles). Experience has shown that this inspection is resource intensive both for the NRC inspectors and your staff. In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. These documents have been divided into two groups. The first group (section A of the enclosure) identifies information to be provided prior to the inspection to ensure that the inspectors are adequately prepared.

The second group (section B of the enclosure) identifies the information the inspectors will need upon arrival at the site. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.

We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Stavroula Mihalakea of your organization.

Our inspection dates are subject to change based on your updated schedule of outage activities. If there are any questions about this inspection or the material requested, please contact the lead inspector Alexandra Rogers at (404) 997-4657 (alexandra.rogers@nrc.gov).

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document

2 FP&L Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Steven J. Vias, Chief Engineering Branch 3 Division of Reactor Safety Docket No. 50-250 License No. DPR-31

Enclosure:

Pre-Inspection Document Request cc w/encl.: (See page 3)

_ML# 120090229________ X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII: DRS/EB3 RII:L DRS/EB3 RII: DRP SIGNATURE /RA/ /RA/ /RA/

NAME A. ROGERS S. VIAS D. RICH DATE 1/6/2012 1/9/2012 1/9/2012 E-MAIL COPY YES NO YES NO YES NO YES NO YES NO YES NO YES NO 3

FP&L cc w/encl: Mitch S. Ross Alison Brown Vice President and General Counsel Nuclear Licensing Nuclear Florida Power & Light Company Florida Power & Light Company Electronic Mail Distribution Electronic Mail Distribution Larry Nicholson William A. Passetti Director Chief Licensing Florida Bureau of Radiation Control Florida Power & Light Company Department of Health Electronic Mail Distribution Electronic Mail Distribution Michael Kiley Senior Resident Inspector Site Vice President Turkey Point Nuclear Generating Station Turkey Point Nuclear Plant U.S. Nuclear Regulatory Commission Florida Power and Light Company 9762 SW 344th St.

Electronic Mail Distribution Florida City, FL 33035 Neil Batista Attorney General Emergency Management Coordinator Department of Legal Affairs Department of Emergency Management The Capitol PL-01 and Homeland Security Tallahassee, FL 32399-1050 Electronic Mail Distribution County Manager of Miami-Dade County Robert J. Tomonto 111 NW 1st Street, 29th Floor Licensing Manager Miami, FL 33128 Turkey Point Nuclear Plant Florida Power & Light Company Gene St. Pierre Electronic Mail Distribution Vice President, Fleet Support Florida Power & Light Company Eric McCartney Electronic Mail Distribution Plant General Manager Turkey Point Nuclear Plant George Gretsas Florida Power and Light Company City Manager Electronic Mail Distribution City of Homestead Electronic Mail Distribution Marjan Mashhadi Senior Attorney Florida Power & Light Company Electronic Mail Distribution Enclosure

INSERVICE INSPECTION DOCUMENT REQUEST Inspection Dates: February 6-10, 2012 Inspection Procedures: IP 71111.08 Inservice Inspection (ISI) Activities TI 2515/172 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles Inspectors: Alexandra Rogers, Reactor Inspector (Lead Inspector - ISI)

A. Information Requested for the In-Office Preparation Week The following information should be sent to the Region II office in hard copy or electronic format (CD preferred), in care of Alexandra Rogers by January 27, 2012, to facilitate the selection of specific items that will be reviewed during the onsite inspection week. The inspector will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week (section B of this enclosure). We ask that the specific items selected from the lists be available and ready for review on the first day of inspection. *Please provide requested documentation electronically if possible. If requested documents are large and only hard copy formats are available, please inform the inspector, and provide subject documentation during the first day of the onsite inspection. If you have any questions regarding this information request, please call the inspector as soon as possible.

A.1 ISI / Welding Programs and Schedule Information a) A detailed schedule (including preliminary dates) of:

i) Nondestructive examinations (NDEs) planned for Class 1 & 2 systems and containment, performed as part of your ASME Section XI, Risk Informed (if applicable), and augmented ISI Programs during the upcoming outage.

Provide a status summary of the NDE inspection activities vs. the required inspection period percentages for this Interval by category per ASME Section XI, IWX-2400. (Do not provide separately if other documentation requested contains this information) ii) Reactor pressure vessel head (RPVH) examinations planned for the upcoming outage.

iii) Examinations planned for Alloy 82/182/600 components that are not included in the Section XI scope. (If applicable) iv) Examinations planned as part of your Boric Acid Corrosion Control Program. (Mode 3 walkdowns, bolted connection walkdowns, etc.)

Enclosure

2 v) Welding activities that are scheduled to be completed during the upcoming outage. (ASME Class 1, 2, or 3 structures, systems, or components (SSCs))

b) A copy of ASME Section XI Code Relief Requests and associated NRC Safety Evaluations applicable to the examinations identified above.

c) A list of NDE reports (ultrasonic, radiography, magnetic particle, and dye penetrant) which have identified surface or volumetric indications that were analytically evaluated and accepted for continued service on Code Class 1, 2, &

3 systems since the beginning of the last refueling outage. This should include the previousSection XI pressure test(s) conducted during start up and any evaluations associated with the results of the pressure tests.

d) A list with a brief description (e.g. system, material, pipe size, weld number, and NDE performed) of the welds in Code Class 1, 2, and 3 systems which have been fabricated due to component repair/replacement activities since the beginning of the last refueling outage, or are planned to be fabricated this refueling outage. Also, please indicate which of those welds are risk significant.

e) If reactor vessel shell weld examinations required by the ASME Code are scheduled to occur during the upcoming outage, provide a detailed description of the welds to be examined, and the extent of the planned examination. Please also provide reference numbers for applicable procedures that will be used to conduct these examinations.

f) Copy of any 10 CFR Part 21 reports applicable to your SSCs within the scope of Section XI of the ASME Code that have been identified since the beginning of the last refueling outage.

g) A list of any temporary non-code repairs in service (e.g. pinhole leaks).

h) Please provide copies of the most recent self assessments for the ISI, Welding, and Alloy 600 Programs.

A.2 Reactor Pressure Vessel Head (RPVH): If this inspection will not be performed, this outage provide when the last inspection was performed and what type of inspection was performed.

a) Provide the detailed scope of the planned NDE of the reactor vessel head which identifies the types of NDE methods to be used on each specific part of the vessel head to meet the augmented inspection requirements of 10CFR50.55a(g)(6)(ii)(D). Also, include examination scope expansion criteria and planned expansion sample sizes if relevant indications are identified. (If applicable) b) A list of the standards and/or requirements that will be used to evaluate indications identified during NDE of the reactor vessel head (e.g. the specific industry or procedural standards that will be used to evaluate potential leakage and/or flaw indications).

Enclosure

3 c) Also, include in the list the NDE reports with identified surface or volumetric indications in the RPVH penetration nozzles, which have been analytically evaluated and accepted for continued service. The list of NDE reports should include a brief description of the SSC where the recordable indication was identified.

A.3 Boric Acid Corrosion Control Program (BACCP) a) Copy of the procedures that govern the scope, equipment, and implementation of the inspections required to identify boric acid leakage and the procedures for boric acid leakage/corrosion evaluation.

b) Please provide a list of leaks (including code class of the components) that have been identified since the last refueling outage and associated corrective action documentation. If during the last cycle, the Unit was shutdown, please provide documentation of containment walk-down inspections performed as part of the BACCP.

c) Please provide a copy of the most recent self-assessment performed for the BACCP.

A.4 Steam Generator (SG) Inspections a) Please include a copy of the Operational Assessment from last outage, and a copy of the following documents as they become available:

i) Degradation Assessment ii) Condition Monitoring Assessment A.5 Additional information related to all ISI activities a) A list with a brief description of ISI, BACCP, and SG ISI related issues (e.g.,

condition reports) entered into your corrective action program since the beginning of the last refueling outage (for Units 3 and 4). For example, a list based upon data base searches using key words related to piping or SG tube degradation such as: ISI, ASME Code,Section XI, NDE, cracks, wear, thinning, leakage, rust, corrosion, boric acid, or errors in piping/SG tube examinations.

b) Please provide names and phone numbers for the following program leads:

i) ISI contacts (Examination, planning) ii) Containment Exams iii) PVH Exams iv) Snubbers and Supports v) Repair and Replacement Program Manager vi) Licensing Contact vii) Site Welding Engineer viii) Boric Acid Corrosion Control Program ix) SG Inspection Activities (site lead and vendor contact)

Enclosure

4 B. Information to be provided on-site to the inspector at the entrance meeting (February 6, 2012):

B.1 ISI / Welding Programs and Schedule Information a) Updated schedules for ISI/NDE activities, including SG ISI, planned welding activities, and schedule showing contingency repair plans, if available.

b) For ASME Class 1, 2, and 3 welds selected by the inspector from the lists provided from section A of this enclosure, please provide copies of the following documentation for each subject weld:

i) Weld data sheet (traveler) ii) Weld configuration and system location iii) Applicable Code Edition and Addenda for weldment iv) Applicable Code Edition and Addenda for welding procedures v) Applicable weld procedures (WPS) used to fabricate the welds vi) Copies of procedure qualification records (PQRs) supporting the WPS from B.1.b.v vii) Copies of mechanical test reports identified in the PQRs above viii) Copies of the nonconformance reports for the selected welds (If Applicable) ix) Radiographs of the selected welds and access to equipment to allow viewing radiographs (If RT was performed) x) Copies of the pre-service examination records for the selected welds.

xi) Copies of welder performance qualifications records applicable to WPS, including documentation that welder maintained proficiency in the applicable welding processes specified in the WPS (At least six months prior to date subject work) xii) Copies of NDE personnel qualifications (VT, PT, UT, RT) As applicable c) For the ISI related corrective action issues selected by the inspector from section A of this enclosure, provide a copy of the corrective actions and supporting documentation.

d) For the NDE reports with relevant indications on Code Class 1, 2, & 3 systems selected by the inspector from section A above, provide a copy of the examination records, examiner qualification records, and associated corrective action documents.

e) A copy of (or ready access to) most current revision of the ISI Program Manual and Plan for the current Interval.

f) For the NDEs selected by the inspector from section A of this enclosure, provide copy of the NDE procedures used to perform the examinations (including calibration and flaw characterization/sizing procedures). For ultrasonic examination procedures qualified in accordance with ASME Code,Section XI, Appendix VIII, provide documentation supporting the procedure qualification Enclosure

5 (e.g., the EPRI performance demonstration qualification summary sheets). Also, include documentation of the specific equipment to be used (e.g., ultrasonic unit, cables, and transducers including serial numbers) and NDE personnel qualification records.

B.2 Reactor Pressure Vessel Head (RPVH) a) Provide the NDE personnel qualification records for the examiners who will perform examinations of the RPVH.

b) Provide drawings showing the following: (If a visual examination is planned for the upcoming refueling outage) i) RPVH and CRDM nozzle configurations ii) RPVH insulation configuration The drawings listed above should include fabrication drawings for the nozzle attachment welds as applicable.

c) Copy of NDE reports from the last RPVH examination.

d) Copy of evaluation or calculation demonstrating that the scope of the visual examination of the upper head will meet the 95% minimum coverage required by ASME Code Case N-729-1 (If a visual examination is planned for the upcoming refueling outage).

e) Provide a copy of the procedures that will be used to identify the source of any boric acid deposits identified on the RPVH. If no explicit procedures exist which govern this activity, provide a description of the process to be followed including personnel responsibilities and expectations.

f) Provide a copy of the updated calculation of effective degradation years (EDY) and re-inspection years (RIY) for the RPVH crack initiation and propagation susceptibility parameters.

g) Provide copy of the vendor qualification report(s) that demonstrates the detection capability of the NDE equipment used for the RPVH examinations. Also, identify any changes in equipment configurations used for the RPVH examinations which differ from that used in the vendor qualification or demonstration report(s).

B.3 Boric Acid Corrosion Control Program (BACCP) a) Please provide boric acid walk down inspection results, an updated list of boric acid leaks identified so far this outage, associated corrective action documentation, and overall status of planned boric acid inspections.

b) Please provide any engineering evaluations completed for boric acid leaks identified since the end of the last refueling outage. Please include a status of corrective actions to repair and/or clean these boric acid leaks. Please specify which known leaks, if any, have remained in service, or will remain in service as active leaks.

Enclosure

6 c) In accordance with NRC inspection procedure 71111.08, the inspector would like to conduct an independent boric acid walk down of the Reactor Building early in the inspection week. Please have knowledgeable BACCP staff available to accompany the inspector during the walk down.

B.4 Codes and Standards a) Ready access to: (i.e. copies provided to the inspector to use for the duration of the inspection at the on-site inspection location, or room number and location where available) i) Applicable editions of the ASME Code (Sections V, IX and XI) for the in-service inspection program and the repair/replacement program.

Inspector Contact Information:

Alexandra Rogers.

Reactor Inspector 404-997-4657 Alexandra.Rogers@nrc.gov Mailing Address:

U.S. Nuclear Regulatory Commission Region II Attn: Alexandra Rogers 245 Peachtree Center Ave NE Suite 1200 Atlanta, GA 30303 Enclosure