ML13199A384: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(5 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML13199A384
| number = ML13199A384
| issue date = 07/18/2013
| issue date = 07/18/2013
| title = Fitzpatrick - Acceptance Review for Amendment Request to Revise Plant Shutdown Margin (TAC No. MF2325)
| title = Acceptance Review for Amendment Request to Revise Plant Shutdown Margin
| author name = Thadani M C
| author name = Thadani M
| author affiliation = NRC/NRR/DORL/LPLI-1
| author affiliation = NRC/NRR/DORL/LPLI-1
| addressee name = O'Farrill J
| addressee name = O'Farrill J
Line 9: Line 9:
| docket = 05000333
| docket = 05000333
| license number =  
| license number =  
| contact person = Thadani M C
| contact person = Thadani M
| case reference number = TAC MF2325
| case reference number = TAC MF2325
| document type = E-Mail
| document type = E-Mail
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:1Lee, Erika From:Thadani, Mohan Sent:Thursday, July 18, 2013 11:30 AM To:O'Farrill, Jorge
{{#Wiki_filter:Lee, Erika From:                               Thadani, Mohan Sent:                               Thursday, July 18, 2013 11:30 AM To:                                 O'Farrill, Jorge


==Subject:==
==Subject:==
Amendment Request to Revise the Plant shudown margin.-TAC No. MF2325
Amendment Request to Revise the Plant shudown margin.-TAC No. MF2325


==Dear Mr. O'Farrell:==
==Dear Mr. OFarrell:==


The NRC staff has reviewed the subject license amendment request for acceptance for a detailed technical review. Based in its review, the NRC staff concludes that the LAR is acceptable for detailed review. Our acceptance review is documented below.
The NRC staff has reviewed the subject license amendment request for acceptance for a detailed technical review. Based in its review, the NRC staff concludes that the LAR is acceptable for detailed review. Our acceptance review is documented below.
Best regards,  
Best regards, Mohan C Thadani Senior Project Manager FitzPatrick, Ginna, and Constellation Fleet Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476 Mohan.Thadani@nrc.gov Mr. Jeffrey Forbes, Executive Vice President, Nuclear Operations and CNO Entergy Nuclear Operations, Inc.
 
James A. FitzPatrick Nuclear Power Plant P.O. Box 31995 Jackson, MS 39286-1995
Mohan C Thadani Senior Project Manager FitzPatrick, Ginna, and Constellation Fleet Plant Licensing Branch I-1
 
Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476     Mohan.Thadani@nrc.gov
________________________________________________________________________________________
_____________________________________________________________ Mr. Jeffrey Forbes, Executive Vice President, Nuclear Operations and CNO Entergy Nuclear Operations, Inc.
James A. FitzPatrick Nuclear Power Plant P.O. Box 31995 Jackson, MS 39286-1995  


==SUBJECT:==
==SUBJECT:==
JAMES A. FITZPATRICK NUCLEAR POWER PLANT -
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - ACCEPTANCE REVIEW CONCERNING REQUEST FOR AMENDMENT TO REVISE THE DEFINITION OF SHUTDOWN MARGIN (TAC NO. MF2325)
ACCEPTANCE REVIEW CONCERNING REQUEST FOR AMENDMENT TO REVISE THE DEFINITION OF SHUTDOWN MARGIN (TAC NO. MF2325)  


==Dear Sir or Madam:==
==Dear Sir or Madam:==


By letter dated June 7, 2013 (ML13171A008),James A. FitzPatrick Nuclear Power Plant, LLC, (the Licensee), submitted a license amendment request (LAR) to revise the Technical Specification definition of shutdown margin (SDM) to require calculation of the SDM at a reactor moderator temperature of 68 degrees F or higher that represents the most reactive state throughout the Operating Cycle. This change is needed to address new boiling Water reactor fuel deigns which may be more reactive at shutdown temperatures above 68 degrees F.
By letter dated June 7, 2013 (ML13171A008),James A. FitzPatrick Nuclear Power Plant, LLC, (the Licensee),
The purpose of this email is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to a llow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.  
submitted a license amendment request (LAR) to revise the Technical Specification definition of shutdown margin (SDM) to require calculation of the SDM at a reactor moderator temperature of 68 degrees F or higher that represents the most reactive state throughout the Operating Cycle. This change is needed to address new boiling Water reactor fuel deigns which may be more reactive at shutdown temperatures above 68 degrees F.
 
The purpose of this email is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
2Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
1
 
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.


Mohan C Thadani Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476     Mohan.Thadani@nrc.gov}}
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.
Mohan C Thadani Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476 Mohan.Thadani@nrc.gov 2}}

Latest revision as of 03:13, 6 February 2020

Acceptance Review for Amendment Request to Revise Plant Shutdown Margin
ML13199A384
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 07/18/2013
From: Thadani M
Plant Licensing Branch 1
To: O'Farrill J
Entergy Nuclear Operations
Thadani M
References
TAC MF2325
Download: ML13199A384 (2)


Text

Lee, Erika From: Thadani, Mohan Sent: Thursday, July 18, 2013 11:30 AM To: O'Farrill, Jorge

Subject:

Amendment Request to Revise the Plant shudown margin.-TAC No. MF2325

Dear Mr. OFarrell:

The NRC staff has reviewed the subject license amendment request for acceptance for a detailed technical review. Based in its review, the NRC staff concludes that the LAR is acceptable for detailed review. Our acceptance review is documented below.

Best regards, Mohan C Thadani Senior Project Manager FitzPatrick, Ginna, and Constellation Fleet Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476 Mohan.Thadani@nrc.gov Mr. Jeffrey Forbes, Executive Vice President, Nuclear Operations and CNO Entergy Nuclear Operations, Inc.

James A. FitzPatrick Nuclear Power Plant P.O. Box 31995 Jackson, MS 39286-1995

SUBJECT:

JAMES A. FITZPATRICK NUCLEAR POWER PLANT - ACCEPTANCE REVIEW CONCERNING REQUEST FOR AMENDMENT TO REVISE THE DEFINITION OF SHUTDOWN MARGIN (TAC NO. MF2325)

Dear Sir or Madam:

By letter dated June 7, 2013 (ML13171A008),James A. FitzPatrick Nuclear Power Plant, LLC, (the Licensee),

submitted a license amendment request (LAR) to revise the Technical Specification definition of shutdown margin (SDM) to require calculation of the SDM at a reactor moderator temperature of 68 degrees F or higher that represents the most reactive state throughout the Operating Cycle. This change is needed to address new boiling Water reactor fuel deigns which may be more reactive at shutdown temperatures above 68 degrees F.

The purpose of this email is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

1

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.

Mohan C Thadani Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476 Mohan.Thadani@nrc.gov 2