MONTHYEARJAFP-20-0083, Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule2020-12-11011 December 2020 Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing Project stage: Request ML21014A5112021-01-12012 January 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-545 Revision 3 Project stage: Acceptance Review JAFP-21-0041, Supplement to Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing2021-05-17017 May 2021 Supplement to Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing Project stage: Supplement ML21181A0572021-11-0404 November 2021 Issuance of Amendment No. 344 Adoption of TSTF-545 Project stage: Approval 2021-01-12
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24298A1382024-10-24024 October 2024 Final RAI for FitzPatrick JAFP-24-0047 (L-2024-LLA-0134) ML24250A1062024-09-0606 September 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24156A1072024-06-0404 June 2024 NRR E-mail Capture - (External_Sender) Supplement for FitzPatrick TS 3.4.2-2 ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24122B5072024-05-0101 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-591, Revision 0 ML24060A0512024-02-28028 February 2024 NRR E-mail Capture - FitzPatrick - Final Arcb RAI Regarding Amendment to Update the Fuel Handling Accident Analysis ML24033A0542024-02-0101 February 2024 NRR E-mail Capture - FitzPatrick - Final HFE RAI Regarding Amendment to Update the Fuel Handling Accident Analysis ML24024A1372024-01-24024 January 2024 NRR E-mail Capture - Final Snsb RAI Regarding FitzPatrick Amendment to Modify Safety Relief Valves Setpoint Lower Tolerance ML24017A1112024-01-17017 January 2024 NRR E-mail Capture - Acceptance of Requested Licensing Action Amendment Request to Adopt TSTF-529, Clarifyuse and Applicaion Rules, Revision 4 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC – Fleet Request – License Amendment Request to Adopt TSTF-580, Revision 1 ML23261C3982023-09-0808 September 2023 Acceptance Review of Amendment to Update the Fuel Handling Accident Analysis ML23244A2662023-09-0101 September 2023 Acceptance of Requested Licensing Action Amendment Request to Modify Surveillance Requirement 3.4.3.1, Safety Relief Valves Setpoint Lower Tolerance ML23237B3972023-08-24024 August 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Alternative Request to Use Updated BWRVIP Guidelines ML23194A1822023-08-0303 August 2023 Acceptance Review for LAR Re SRM 3.3.1.2 ML23163A2292023-06-12012 June 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-580, Revision 1 ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI NRC-2100-2022, EN 55999 Valcor Coil Shell Assemblies Final Notification (004)2022-09-12012 September 2022 EN 55999 Valcor Coil Shell Assemblies Final Notification (004) NRC 2110-2022, EN 55999 - Valcor Engineering Corporation (009)2022-07-18018 July 2022 EN 55999 - Valcor Engineering Corporation (009) ML22124A2672022-05-0404 May 2022 Request for Additional Information for James A. FitzPatrick Nuclear Power Plant TSTF-505 ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML22063A4742021-11-29029 November 2021 Acceptance of Requested Licensing Action License Amendment Request to Eliminate Selected Response Time Testing ML21301A0672021-10-28028 October 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-541 ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21252A0482021-09-0707 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21246A2112021-09-0303 September 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-505 ML21246A2072021-09-0303 September 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 ML21215A3502021-08-0303 August 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-554 ML21187A0522021-07-0606 July 2021 Fitz RAI Regarding FitzPatrick Amendment Request to Modify SR 3.5.1.6 ML21246A2142021-06-23023 June 2021 Acceptance of Requested Licensing Action Regarding License Amendment Request to Adopt TSTF-264 ML21154A0142021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0132021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0112021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21144A1072021-05-17017 May 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-582 ML21117A0442021-04-26026 April 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21084A2532021-03-24024 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Transfer Application ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21033A8552021-02-0202 February 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request to Expand the Use ASME Codes Cases N-878 and N-880 ML21014A5112021-01-12012 January 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-545 Revision 3 ML20352A2752020-12-17017 December 2020 Request for Additional Information Regarding FitzPatrick Primary Containment Isolation Valve Amendment Request ML20350B5582020-12-14014 December 2020 NRR E-mail Capture - Exelon Generation Company, LLC -Alternative Request for Documentation of Replacement of Pressure Retaining Bolting ML20294A0372020-10-19019 October 2020 Request for Additional Information Primary Containment Isolation Valve License Amendment Request ML20266G3032020-09-22022 September 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Request to Use Paragraph IWA-5120 of the 2017 Edition of the ASME B&PV Code, Section XI ML20217L3882020-08-0404 August 2020 Acceptance of Requested Licensing Action License Amendment Request to Modify Primary Containment Isolation Valve TS (EPID L-2020-LLA-0145) (E-Mail) ML20204A9692020-07-22022 July 2020 Acceptance of Requested Licensing Action License Amendment Request to Adopt-TSTF-478 Revision 2 ML20122A2302020-05-0101 May 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of Fleet License Amendment Request to Adopt TSTF-566 ML20066L3682020-03-0505 March 2020 Request for Additional Information: License Amendment Request for Change to the Technical Specifications to Revise the Allowable Value for Reactor Water Cleanup (RWCU) System Primary Containment 2024-09-06
[Table view] |
Text
From: Poole, Justin To: Villar, Enrique:(Exelon Nuclear)
Cc: Danna, James
Subject:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - ACCEPTANCE OF REQUESTED LICENSING ACTION RE:
LICENSE AMENDMENT REQUEST TO ADOPT TSTF-545 REVISION 3 (EPID L-2020-LLA-0268)
Date: Tuesday, January 12, 2021 9:58:00 AM
SUBJECT:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: LICENSE AMENDMENT REQUEST TO ADOPT TSTF-545 REVISION 3 (EPID L-2020-LLA-0268)
By letter dated December 11, 2020 (ADAMS Accession No. ML20346A025), Exelon Generation Company, LLC submitted a license amendment request for James A.
FitzPatrick Nuclear Power Plant. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an application for an amendment to a license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 140 hours0.00162 days <br />0.0389 hours <br />2.314815e-4 weeks <br />5.327e-5 months <br /> to complete. The NRC staff expects to complete this review by January 2022. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the
NRC in advance or in parallel with industry program initiatives or pilot applications.
If you have any questions, please contact me.
Justin C. Poole Project Manager NRR/DORL/LPL I U.S. Nuclear Regulatory Commission (301)415-2048