{{#Wiki_filter:., . e Public Service Electric and Gas Company P.O. Box E Hancocks Bridge, New Jersey 08038 Salem Generating Station U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555  
{{#Wiki_filter:., .                             e
  *ops~G Public Service Electric and Gas Company P.O. Box E Hancocks Bridge, New Jersey 08038 Salem Generating Station June 12, 1990 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC               20555


==Dear Sir:==
==Dear Sir:==
MONTHLY OPERATING REPORT SALEM NO. 1 DOCKET NO. 50-272 June 12, 1990 In compliance with Section 6.9.1.6, Reporting Requirements for the Salem Technical Specifications, the original copy of the monthly operating reports for the month of May 1990 are being sent to you. Average Daily Unit Power Level Operating Data Report Unit Shutdowns and Power Reductions Safety Related Maintenance RH:pc Major Plant Modifications Operating Summary Refueling Information Sincerely yours, L. K. Miller General Manager -Salem Operations cc: Mr. Thomas T. Martin Regional Administrator USNRC Region I 631 Park Avenue King of Prussia, PA 19046 Enclosures 8-1-7.R4 The Energy People 9006190091-900531 PDR ADOCK 05000272 R PDC pf.I '// 95-2189 (11 M) 12-84
 
.. Month MAY, 1990 Day Average Daily Power (MWe-NET) 1 0 2 0 3 0 4 0 5 0 6 0 7 0 8 0 9 0 10 0 11 0 12 0 13 0 14 0 15 0 16 0 P. 8.1-7 Rl AVERAGE DAILY UNIT POWER LEVEL Level Docket No. Unit Name Date Completed by Telephone 50-272 Salem # 1 06-10-90 Art Orticelle 609-339-2122 Day Average Daily Power Level (MWe-NET) 17 0 18 0 19 0 20 0 21 0 22 0 23 0 24 0 25 0 26 0 27 0 28 0 29 0 30 0 31 0
MONTHLY OPERATING REPORT SALEM NO. 1 DOCKET NO. 50-272 In compliance with Section 6.9.1.6, Reporting Requirements for the Salem Technical Specifications, the original copy of the monthly operating reports for the month of May 1990 are being sent to you.
.. OPERATING DATA REPORT Docket No: 50-272 Date: 06-10-90 Completed by: Art Orticelle Telephone:
Average Daily Unit Power Level Operating Data Report Unit Shutdowns and Power Reductions Safety Related Maintenance Major Plant Modifications Operating Summary Refueling Information Sincerely yours, L. K. Miller General Manager -
609-339-2122 Operating Status 1. Unit Name Salem No. 1 Notes 2. Reporting Period May 1990 3. Licensed Thermal Power (MWt) 3411 4. Nameplate Rating (Gross MWe) 1170 5. Design Electrical Rating (Net MWe) 1115 6. Maximum Dependable Capacity(Gross MWe) 1149 7. Maximum Dependable Capacity (Net MWe) 1106 8. If Changes Occur in Capacity Ratings (items 3 through 7) since Last Report, Give Reason N/A
Salem Operations RH:pc cc:     Mr. Thomas T. Martin Regional Administrator USNRC Region I 631 Park Avenue King of Prussia, PA               19046 Enclosures 8-1-7.R4 The Energy People 9006190091- 900531 PDR R
: 9. Power Level to Which Restricted, if any (Net MWe)
ADOCK 05000272 PDC                               pf.I
: 10. Reasons for Restrictions, if any This Month Year to Date Cumulative
                                                                                        ' / / 95-2189 (11 M) 12-84
: 11. Hours in Reporting Period 744 3623 113256 12. No. of Hrs. Reactor was Critical 0 2162.7 73071.2 13. Reactor Reserve Shutdown Hrs. 0 0 0 14. Hours Generator On-Line 0 2102.8 70798.6 15. Unit Reserve Shutdown Hours 0 0 0 16. Gross Thermal Energy Generated (MWH) 0 6892562.4 221993488.4
 
: 17. Gross Elec. Energy Generated (MWH) 0 2290760 73752120 18. Net Elec. Energy Generated (MWH) -10044 2193174 70204884 19. Unit Service Factor 0 58.0 62.5 20. Unit Availability Factor 0 58.0 62.5 21. Unit Capacity Factor -{using MDC Net) 0 54.7 56.0 22. Unit Capacity Factor {using DER Net) 0 54.3 55.6 23. Unit Forced Outage Rate 100 41. 9 22.3 24. Shutdowns scheduled over next 6 months (type, date and duration of each) Unit #1 Ninth Refueling scheduled on October 6, 1990 and lasting 45 davs. 25. If shutdown at end of Report Period, Estimated Date of Startup: Estimated start-up date of June 7, 1990. 8-l-7.R2 NO. DATE 0035 5-01-90 i i i 1 F: Forced S: Scheduled UNIT SHUTOOWN AND POWER REDUCTIONS lXJCKEI'NO.:
AVERAGE DAILY UNIT POWER LEVEL Docket No. 50-272 Unit Name      Salem # 1 Date          06-10-90 Completed by  Art Orticelle Telephone      609-339-2122 Month    MAY, 1990 Day Average Daily Power Level           Day Average Daily Power Level (MWe-NET)                                (MWe-NET) 1          0                                17           0 2          0                                18           0 3          0                               19           0 4          0                               20           0 5          0                                21           0 6          0                                22           0 7          0                               23           0 8          0                               24           0 9          0                               25           0 10          0                               26           0 11          0                               27           0 12          0                               28           0 13          0                                29           0 14          0                                30           0 15          0                               31           0 16          0 P. 8.1-7 Rl
___ _
 
r-uNTH
OPERATING DATA REPORT Docket No:     50-272 Date:           06-10-90 Completed by:   Art Orticelle             Telephone:     609-339-2122 Operating Status
___ _ UNIT NAME: Salem #1 '1YPE 1 F I 2 Reason: DURATION (BOORS) REASON 2 744 A l A-F.quiprent Failure (Explain)
: 1. Unit Name                         Salem No. 1     Notes
B-Maintenance or Test C-Refueling D-Regulatory Restriction MEI'HOD OF SHUTI'ING OOWN REACTOR 3 I E-Dperator Training & License Examination F-Administrative G-Dperational Error (R\.'J>lain)
: 2. Reporting Period                 May 1990
H-OthPr (J;'m l 'li n) LICENSE EVENT SYSTEM REIDRI' # CDDE 4 -------CH 3 Method: 1-Manual 2-Manual Scram 3-Autanatic Scram 4-COntinuation of Previous Outage 5-load Reduction 9--0ther ( DA'IE: 06-10-90 CiltPI.EI'ED BY: Art Orticelle TELEPHONE:
: 3. Licensed Thermal Power (MWt)             3411
339-2122 cmroNENT CAUSE AND CDRRFCTIVE ACTION 4 CDDE 0 'ID PREVENT RECURRENCE INSTRU #12 S.G. FEED PUMP Exhibit G -Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NURffi-0161) 5 Exhibit 1 -Same Source .* I I SAFETY RELATED MAINTENANCE MONTH: -MAY 1990 DOCKET NO: UNIT r.TAME: 50-272 SALEM 1 WO NO 890307143 900326142 900504117 900517136 900521058 900521068 900527061 UNIT 1 1 1 1 1 DATE: COMPLETED BY: TELEPHONE:
: 4. Nameplate Rating (Gross MWe)             1170
JUNE 10, 1990 M. MORRONI (609) 339-2068 EQUIPMENT IDENTIFICATION 11 SAFETY INJECTION PUMP FAILURE DESCRIPTION:
: 5. Design Electrical Rating (Net MWe)       1115
CHANGE OUT ROTATING ASSEMBLY REACTOR COOLANT WIDE RANGE PRESSURE INDICATION FAILURE DESCRIPTION:
: 6. Maximum Dependable Capacity(Gross MWe) 1149
HIGH INDICATION  
: 7. Maximum Dependable Capacity (Net MWe)   1106
-TROUBLESHOOT 11 CHARGING PUMP FAILURE DESCRIPTION:
: 8. If Changes Occur in Capacity Ratings (items 3 through 7) since Last Report, Give Reason     N/A
REWELD ALIGNING DOWEL AND CENTERING PIN BLOCK CABLE SEPARATION FAILURE DESCRIPTION:
                            ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
CORRECT CABLE SEPARATION CRITERIA VIOLATIONS 1RC41 REACTOR HEAD VENT SOLENOID FAILURE DESCRIPTION:
: 9. Power Level to Which Restricted, if any (Net MWe)   ~~-=N~/~A=--~~~~~~-
VALVE DOES NOT OPEN -INVESTIGATE 1 1 1RC43 REACTOR HEAD VENT FAILURE DESCRIPTION:
: 10. Reasons for Restrictions, if any   ~~N~/~A=--~~~~~~~~~~~~~~~~~-
VALVE DOES NOT OPEN -INVESTIGATE 12CV19 FAILURE DESCRIPTION:
This Month   Year to Date   Cumulative
NO OPEN OR CLOSE INDICATION  
: 11. Hours in Reporting Period               744           3623       113256
-TROUBLESHOOT AND REPAIR MAJOR PLANT MODIFICATIONS MONTH: -MAY 1990 *DCR PRINCIPAL SYSTEM lSC-2233 Main Transformer
: 12. No. of Hrs. Reactor was Critical           0         2162.7       73071.2
*DCR -Design Change Request DOCKET NO: 50-272 UNIT NAME: SALEM 1 DATE: COMPLETED BY: 'TELEPHONE:
: 13. Reactor Reserve Shutdown Hrs.             0             0             0
JUNE 10, 1990 M. MORRONI (609) 339-2068 DESCRIPTION This design change replaced the Main Generator Transformer Phases "A", "B", and "C" with transformers obtained from the Washington Public Power Supply System.
: 14. Hours Generator On-Line                     0         2102.8       70798.6
MAJOR PLANT MODIFICATIONS MONTH: -MAY 1990 DOCKET NO: UNIT NAME: 50-272 SALEM 1 *DCR lSC-2233 DATE: COMPLETED BY: TELEPHONE:
: 15. Unit Reserve Shutdown Hours                 0             0             0
SAFETY EVALUATION 10 CFR 50.59 JUNE 10, 1990 11. MORRONI (609) 339-2068 This design change replaced the Main Generator Transformer Phases "A", "B", and "C" with transformers obtained from the Washington Public Power Supply System. The replacement transformers have been analyzed and found to be acceptable for this application.
: 16. Gross Thermal Energy Generated (MWH)                             0       6892562.4   221993488.4
There is no change to any plant process or discharge or to the environmental impact of the plant. No unreviewed safety or environmental questions are involved.  
: 17. Gross Elec. Energy Generated (MWH)                             0       2290760     73752120
*DCR -Design Change Request SALEM UNIT NO. 1 SALEM GENERATING STATION MONTHLY OPERATING  
: 18. Net Elec. Energy Generated (MWH)     -10044       2193174     70204884
: 19. Unit Service Factor                       0           58.0         62.5
: 20. Unit Availability Factor                   0           58.0         62.5
: 21. Unit Capacity Factor
            -{using MDC Net)                       0           54.7         56.0
: 22. Unit Capacity Factor
{using DER Net)                       0           54.3         55.6
: 23. Unit Forced Outage Rate                 100             41. 9         22.3
: 24. Shutdowns scheduled over next 6 months (type, date and duration of each)
Unit #1 Ninth Refueling scheduled on October 6, 1990 and lasting 45 davs.
: 25. If shutdown at end of Report Period, Estimated Date of Startup:
Estimated start-up date of June 7, 1990.
8-l-7.R2
 
UNIT SHUTOOWN AND POWER REDUCTIONS                                   lXJCKEI'NO.:   _5~0-~~~,7=2_ _ __
                                                                    ~RI' r-uNTH ~MA=Y"--=19'""'9-'-0_ _ __                                UNIT NAME: Salem #1 DA'IE: 06-10-90 CiltPI.EI'ED BY: Art Orticelle TELEPHONE: 339-2122 MEI'HOD OF SHUTI'ING      LICENSE DURATION                      OOWN          EVENT                SYSTEM    cmroNENT             CAUSE AND CDRRFCTIVE ACTION NO.      DATE    '1YPE 1    (BOORS)            REASON 2  REACTOR        REIDRI' #          CDDE 4   CDDE 0                 'ID PREVENT RECURRENCE 0035      5-01-90      F        744                  A          3          -------              CH      INSTRU         #12 S.G. FEED PUMP I
(
i      i          i          I                  l          I                                                                                                              I 1                  2                                                    3                            4                              5 F: Forced          Reason:                                              Method:                      Exhibit G - Instructions       Exhibit 1 - Same S: Scheduled      A-F.quiprent Failure (Explain)                        1-Manual                    for Preparation of Data       Source B-Maintenance or Test                                  2-Manual Scram              Entry Sheets for Licensee C-Refueling                                          3-Autanatic Scram            Event Report (LER) File D-Regulatory Restriction                              4-COntinuation of            (NURffi-0161)
E-Dperator Training &License Examination                Previous Outage F-Administrative                                      5-load Reduction G-Dperational Error (R\.'J>lain)                      9--0ther H-OthPr  (J;'m l 'li n)
 
SAFETY RELATED MAINTENANCE                 DOCKET NO:  50-272 MONTH: - MAY 1990                           UNIT r.TAME: SALEM 1 DATE:   JUNE 10, 1990 COMPLETED BY:  M. MORRONI TELEPHONE:    (609) 339-2068 WO NO    UNIT                      EQUIPMENT IDENTIFICATION 890307143    1    11 SAFETY INJECTION PUMP FAILURE DESCRIPTION: CHANGE OUT ROTATING ASSEMBLY 900326142    1    REACTOR COOLANT WIDE RANGE PRESSURE INDICATION FAILURE DESCRIPTION: HIGH INDICATION - TROUBLESHOOT 900504117    1    11 CHARGING PUMP FAILURE DESCRIPTION: REWELD ALIGNING DOWEL AND CENTERING PIN BLOCK 900517136    1    CABLE SEPARATION FAILURE DESCRIPTION: CORRECT CABLE SEPARATION CRITERIA VIOLATIONS 900521058    1    1RC41 REACTOR HEAD VENT SOLENOID FAILURE DESCRIPTION:   VALVE DOES NOT OPEN - INVESTIGATE 900521068    1   1RC43 REACTOR HEAD VENT FAILURE DESCRIPTION: VALVE DOES NOT OPEN - INVESTIGATE 900527061    1    12CV19 FAILURE DESCRIPTION: NO OPEN OR CLOSE INDICATION -
TROUBLESHOOT AND REPAIR
 
MAJOR PLANT MODIFICATIONS             DOCKET NO:   50-272 MONTH: - MAY 1990                      UNIT NAME:   SALEM 1 DATE: JUNE 10, 1990 COMPLETED BY:  M. MORRONI
                                      'TELEPHONE:  (609) 339-2068
    *DCR          PRINCIPAL SYSTEM          DESCRIPTION lSC-2233      Main Transformer This design change replaced the Main Generator Transformer Phases "A",
                                  "B", and "C" with transformers obtained from the Washington Public Power Supply System.
  *DCR - Design Change Request
 
MAJOR PLANT MODIFICATIONS                   DOCKET NO:  50-272 MONTH: - MAY 1990                           UNIT NAME: SALEM 1 DATE: JUNE 10, 1990 COMPLETED BY: 11. MORRONI TELEPHONE:   (609) 339-2068
    *DCR          SAFETY EVALUATION 10 CFR 50.59 lSC-2233      This design change replaced the Main Generator Transformer Phases "A", "B", and "C" with transformers obtained from the Washington Public Power Supply System. The replacement transformers have been analyzed and found to be acceptable for this application. There is no change to any plant process or discharge or to the environmental impact of the plant. No unreviewed safety or environmental questions are involved.
  *DCR - Design Change Request
 
SALEM GENERATING STATION MONTHLY OPERATING  


==SUMMARY==
==SUMMARY==
  -UNIT 1 MAY 1990 The Unit remained shutdown throughout the period for investigation and resolution of Emergency Core Cooling System (ECCS) issues. During this period, issues related to cable separation criteria and Residual Heat Removal (RHR) problems, were also addressed.
  - UNIT 1 MAY 1990 SALEM UNIT NO. 1 The Unit remained shutdown throughout the period for investigation and resolution of Emergency Core Cooling System (ECCS) issues. During this period, issues related to cable separation criteria and Residual Heat Removal (RHR) problems, were also addressed.
J ' . , , REFUELING INFORMATION MONTH: -MAY 1990 MONTH MAY 1990 DOCKET NO: UNIT NAME: DATE: COMPLETED BY: TELEPHONE:
 
: 1. Refueling information has changed from last month: YES x NO 50-272 SALEH 1 JUNE 10, 1990 11. MORRONI (609) 339-2068 2 . Scheduled date for next refueling:
J '
October 2Q, 1990 3. Scheduled date for restart following refueling:
REFUELING INFORMATION                             DOCKET NO:  50-272 MONTH: - MAY 1990                                 UNIT NAME:   SALEH 1 DATE:   JUNE 10, 1990 COMPLETED BY:   11. MORRONI TELEPHONE:   (609) 339-2068 MONTH MAY 1990
December 13, 1990 4. a) Will Technical Specification changes or other license amendments be required?:
: 1. Refueling information has changed from last month:
YES NO l\TO'I' DETERMINED TO DATE -=x __ b) Has the reload fuel design been reviewed by the Station Operating Review Committee?:
YES       x           NO
YES NO If no, when is it scheduled?:
: 2. Scheduled date for next refueling:       October 2Q, 1990
Se-otember 1990 5. Scheduled date(s) for submitting proposed licensing action: N/A 6. Important licensing considerations associated with refueling:
: 3. Scheduled date for restart following refueling:       December 13, 1990
: 4. a) Will Technical Specification changes or other license amendments be required?:
YES                   NO l\TO'I' DETERMINED TO DATE -=x__
b) Has the reload fuel design been reviewed by the Station Operating Review Committee?:
YES                   NO If no, when is it scheduled?:       Se-otember 1990
: 5. Scheduled date(s)     for submitting proposed licensing action:
N/A
: 6. Important licensing considerations associated with refueling:
: 7. Number of Fuel Assemblies:
: 7. Number of Fuel Assemblies:
: a. In core 193 b. In Spent Fuel Storage 540 8. Present licensed spent fuel storage capacity:
: a. In core                                                           193
1170 Future spent fuel storage capacity:
: b. In Spent Fuel Storage                                             540
1170 9. Date of last refueling that can be discharged to the spent fuel pool assuming the present licensed capacity:
: 8. Present licensed spent fuel storage capacity:                         1170 Future spent fuel storage capacity:                                   1170
September 2001 8-1-7.R4}}
: 9. Date of last refueling that can be discharged to the spent fuel pool assuming the present licensed capacity:                                           September 2001 8-1-7.R4}}

Latest revision as of 07:00, 3 February 2020

Monthly Operating Rept for May 1990 for Salem Unit 1. W/900612 Ltr
ML18095A282
Person / Time
Site: Salem PSEG icon.png
Issue date: 05/31/1990
From: Miller L, Morroni M, Orticelle A
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9006190091
Download: ML18095A282 (9)


Text

{{#Wiki_filter:., . e

  *ops~G Public Service Electric and Gas Company P.O. Box E Hancocks Bridge, New Jersey 08038 Salem Generating Station June 12, 1990 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC                20555

Dear Sir:

MONTHLY OPERATING REPORT SALEM NO. 1 DOCKET NO. 50-272 In compliance with Section 6.9.1.6, Reporting Requirements for the Salem Technical Specifications, the original copy of the monthly operating reports for the month of May 1990 are being sent to you. Average Daily Unit Power Level Operating Data Report Unit Shutdowns and Power Reductions Safety Related Maintenance Major Plant Modifications Operating Summary Refueling Information Sincerely yours, L. K. Miller General Manager - Salem Operations RH:pc cc: Mr. Thomas T. Martin Regional Administrator USNRC Region I 631 Park Avenue King of Prussia, PA 19046 Enclosures 8-1-7.R4 The Energy People 9006190091- 900531 PDR R ADOCK 05000272 PDC pf.I

                                                                                        ' / / 95-2189 (11 M) 12-84

AVERAGE DAILY UNIT POWER LEVEL Docket No. 50-272 Unit Name Salem # 1 Date 06-10-90 Completed by Art Orticelle Telephone 609-339-2122 Month MAY, 1990 Day Average Daily Power Level Day Average Daily Power Level (MWe-NET) (MWe-NET) 1 0 17 0 2 0 18 0 3 0 19 0 4 0 20 0 5 0 21 0 6 0 22 0 7 0 23 0 8 0 24 0 9 0 25 0 10 0 26 0 11 0 27 0 12 0 28 0 13 0 29 0 14 0 30 0 15 0 31 0 16 0 P. 8.1-7 Rl

OPERATING DATA REPORT Docket No: 50-272 Date: 06-10-90 Completed by: Art Orticelle Telephone: 609-339-2122 Operating Status

1. Unit Name Salem No. 1 Notes
2. Reporting Period May 1990
3. Licensed Thermal Power (MWt) 3411
4. Nameplate Rating (Gross MWe) 1170
5. Design Electrical Rating (Net MWe) 1115
6. Maximum Dependable Capacity(Gross MWe) 1149
7. Maximum Dependable Capacity (Net MWe) 1106
8. If Changes Occur in Capacity Ratings (items 3 through 7) since Last Report, Give Reason N/A
                            ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
9. Power Level to Which Restricted, if any (Net MWe) ~~-=N~/~A=--~~~~~~-
10. Reasons for Restrictions, if any ~~N~/~A=--~~~~~~~~~~~~~~~~~-

This Month Year to Date Cumulative

11. Hours in Reporting Period 744 3623 113256
12. No. of Hrs. Reactor was Critical 0 2162.7 73071.2
13. Reactor Reserve Shutdown Hrs. 0 0 0
14. Hours Generator On-Line 0 2102.8 70798.6
15. Unit Reserve Shutdown Hours 0 0 0
16. Gross Thermal Energy Generated (MWH) 0 6892562.4 221993488.4
17. Gross Elec. Energy Generated (MWH) 0 2290760 73752120
18. Net Elec. Energy Generated (MWH) -10044 2193174 70204884
19. Unit Service Factor 0 58.0 62.5
20. Unit Availability Factor 0 58.0 62.5
21. Unit Capacity Factor
           -{using MDC Net)                       0            54.7          56.0
22. Unit Capacity Factor

{using DER Net) 0 54.3 55.6

23. Unit Forced Outage Rate 100 41. 9 22.3
24. Shutdowns scheduled over next 6 months (type, date and duration of each)

Unit #1 Ninth Refueling scheduled on October 6, 1990 and lasting 45 davs.

25. If shutdown at end of Report Period, Estimated Date of Startup:

Estimated start-up date of June 7, 1990. 8-l-7.R2

UNIT SHUTOOWN AND POWER REDUCTIONS lXJCKEI'NO.: _5~0-~~~,7=2_ _ __

                                                                   ~RI' r-uNTH ~MA=Y"--=19'""'9-'-0_ _ __                                 UNIT NAME: Salem #1 DA'IE: 06-10-90 CiltPI.EI'ED BY: Art Orticelle TELEPHONE: 339-2122 MEI'HOD OF SHUTI'ING      LICENSE DURATION                      OOWN          EVENT                SYSTEM    cmroNENT             CAUSE AND CDRRFCTIVE ACTION NO.       DATE     '1YPE 1     (BOORS)            REASON 2   REACTOR        REIDRI' #           CDDE 4    CDDE 0                  'ID PREVENT RECURRENCE 0035      5-01-90       F         744                  A           3          -------               CH      INSTRU          #12 S.G. FEED PUMP I

( i i i I l I I 1 2 3 4 5 F: Forced Reason: Method: Exhibit G - Instructions Exhibit 1 - Same S: Scheduled A-F.quiprent Failure (Explain) 1-Manual for Preparation of Data Source B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Autanatic Scram Event Report (LER) File D-Regulatory Restriction 4-COntinuation of (NURffi-0161) E-Dperator Training &License Examination Previous Outage F-Administrative 5-load Reduction G-Dperational Error (R\.'J>lain) 9--0ther H-OthPr (J;'m l 'li n)

SAFETY RELATED MAINTENANCE DOCKET NO: 50-272 MONTH: - MAY 1990 UNIT r.TAME: SALEM 1 DATE: JUNE 10, 1990 COMPLETED BY: M. MORRONI TELEPHONE: (609) 339-2068 WO NO UNIT EQUIPMENT IDENTIFICATION 890307143 1 11 SAFETY INJECTION PUMP FAILURE DESCRIPTION: CHANGE OUT ROTATING ASSEMBLY 900326142 1 REACTOR COOLANT WIDE RANGE PRESSURE INDICATION FAILURE DESCRIPTION: HIGH INDICATION - TROUBLESHOOT 900504117 1 11 CHARGING PUMP FAILURE DESCRIPTION: REWELD ALIGNING DOWEL AND CENTERING PIN BLOCK 900517136 1 CABLE SEPARATION FAILURE DESCRIPTION: CORRECT CABLE SEPARATION CRITERIA VIOLATIONS 900521058 1 1RC41 REACTOR HEAD VENT SOLENOID FAILURE DESCRIPTION: VALVE DOES NOT OPEN - INVESTIGATE 900521068 1 1RC43 REACTOR HEAD VENT FAILURE DESCRIPTION: VALVE DOES NOT OPEN - INVESTIGATE 900527061 1 12CV19 FAILURE DESCRIPTION: NO OPEN OR CLOSE INDICATION - TROUBLESHOOT AND REPAIR

MAJOR PLANT MODIFICATIONS DOCKET NO: 50-272 MONTH: - MAY 1990 UNIT NAME: SALEM 1 DATE: JUNE 10, 1990 COMPLETED BY: M. MORRONI

                                      'TELEPHONE:   (609) 339-2068
   *DCR          PRINCIPAL SYSTEM           DESCRIPTION lSC-2233       Main Transformer This design change replaced the Main Generator Transformer Phases "A",
                                  "B", and "C" with transformers obtained from the Washington Public Power Supply System.
  *DCR - Design Change Request

MAJOR PLANT MODIFICATIONS DOCKET NO: 50-272 MONTH: - MAY 1990 UNIT NAME: SALEM 1 DATE: JUNE 10, 1990 COMPLETED BY: 11. MORRONI TELEPHONE: (609) 339-2068

   *DCR          SAFETY EVALUATION 10 CFR 50.59 lSC-2233       This design change replaced the Main Generator Transformer Phases "A", "B", and "C" with transformers obtained from the Washington Public Power Supply System. The replacement transformers have been analyzed and found to be acceptable for this application. There is no change to any plant process or discharge or to the environmental impact of the plant. No unreviewed safety or environmental questions are involved.
  *DCR - Design Change Request

SALEM GENERATING STATION MONTHLY OPERATING

SUMMARY

- UNIT 1 MAY 1990 SALEM UNIT NO. 1 The Unit remained shutdown throughout the period for investigation and resolution of Emergency Core Cooling System (ECCS) issues. During this period, issues related to cable separation criteria and Residual Heat Removal (RHR) problems, were also addressed.

J ' REFUELING INFORMATION DOCKET NO: 50-272 MONTH: - MAY 1990 UNIT NAME: SALEH 1 DATE: JUNE 10, 1990 COMPLETED BY: 11. MORRONI TELEPHONE: (609) 339-2068 MONTH MAY 1990

1. Refueling information has changed from last month:

YES x NO

2. Scheduled date for next refueling: October 2Q, 1990
3. Scheduled date for restart following refueling: December 13, 1990
4. a) Will Technical Specification changes or other license amendments be required?:

YES NO l\TO'I' DETERMINED TO DATE -=x__ b) Has the reload fuel design been reviewed by the Station Operating Review Committee?: YES NO If no, when is it scheduled?: Se-otember 1990

5. Scheduled date(s) for submitting proposed licensing action:

N/A

6. Important licensing considerations associated with refueling:
7. Number of Fuel Assemblies:
a. In core 193
b. In Spent Fuel Storage 540
8. Present licensed spent fuel storage capacity: 1170 Future spent fuel storage capacity: 1170
9. Date of last refueling that can be discharged to the spent fuel pool assuming the present licensed capacity: September 2001 8-1-7.R4}}