{{#Wiki_filter:P. Chowdhury                                                                          January 13, 2020 Dr. Partha Chowdhury, Director Nuclear Radiation Laboratory University of Massachusetts-Lowell One University Avenue Lowell, MA 01854
 
==SUBJECT:==
UNIVERSITY OF MASSACHUSETTS LOWELL - RESPONSE TO REQUEST FOR EXTENSION OF TIME TO RESPOND TO REQUEST FOR ADDITIONAL INFORMATION REGARDING THE RENEWAL OF FACILITY OPERATING LICENSE NO. R-125 (EPID NO. L-2015-RNW-0001)
 
==Dear Dr. Chowdhury:==
 
The University of Massachusetts Lowell (UML) holds U.S. Nuclear Regulatory Commission (NRC) Facility Operating License No. R-125 for the operation of the UML Research Reactor (UMLRR). By application dated October 20, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16042A015), as supplemented, UML applied for renewal of the UMLRR operating license.
On July 19, 2019 (ADAMS Accession No. ML18092B090), the NRC staff sent UML a letter enclosing requests for additional information (RAIs) identifying additional information needed for the NRC staff to continue its review of UMLs renewal application. The NRC staffs letter requested that UML provide responses to the RAIs by October 21, 2019, and stated that based on this response date, the NRC staff expected to complete its review and make a final determination on the renewal request by June 30, 2020.
By letter dated October 18, 2019 (ADAMS Accession No. ML19291C293), UML provided responses to the NRC staffs RAIs, but requested an additional 60 days beyond the deadline in the NRC staffs July 19, 2019, letter to provide additional information to complete its responses to RAI-7.4.c, RAI-7.4.d, and RAI-7.5.a (RAI numbers corrected by UML in a follow-up letter dated October 24, 2019 (ADAMS Accession No. ML19297F433)). The NRC staff accepted UMLs extension request by letter dated October 30, 2019 (ADAMS Accession No. ML19296E279).
By letters dated December 19 and 20, 2019 (ADAMS Accession Nos. ML19353C523 and ML19354A610, respectively), UML provided a response to RAI-7.4.d. In its letter dated December 19, 2019, UML also requested an additional 60 days beyond the updated deadline in the NRC staffs October 30, 2019, letter to complete its responses to RAI-7.4.c and RAI-7.5.a.
The NRC staff accepts UMLs extension request dated December 19, 2019, such that the deadline for UML to complete its responses to RAI-7.4.c and RAI-7.5.a is now February 18, 2020.
 
P. Chowdhury                                Based on the information that UML requested additional time to provide, and the new response date, the NRC staff continues to expect to complete its review and make a final determination on the renewal request by June 30, 2020. However, this date could still change due to several factors including a need for further RAIs, unanticipated changes to the scope of the review, unsolicited supplements to the application for the renewal, and others. If the forecasted date changes, the NRC staff will notify you in writing of the new date and an explanation of the reason for the change.
If you have any questions, or need additional time to respond to the NRC staffs original July 19, 2019, request, please contact me at 301-415-4067, or by electronic mail at Edward.Helvenston@nrc.gov.
Sincerely,
                                                /RA/
Edward Helvenston, Project Manager Non-Power Production and Utilization Facility Licensing Branch Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation Docket No. 50-223 License No. R-125 cc: See next page
 
University of Massachusetts - Lowell      Docket No. 50-223 cc:
Mayor of Lowell City Hall Lowell, MA 01852 Mr. Leo Bobek Reactor Supervisor University of Massachusetts - Lowell One University Avenue Lowell, MA 01854 Department of Environmental Protection One Winter Street Boston, MA 02108 Jack Priest, Director Radiation Control Program Department of Public Health Schrafft Center, Suite 1M2A 529 Main Street Charlestown, MA 02129 John Giarrusso, Planning and Preparedness Division Chief Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702-5399 Test, Research and Training Reactor Newsletter Attention: Ms. Amber Johnson Department of Materials Science and Engineering University of Maryland 4418 Stadium Drive College Park, MD 20742-2115
 
ML120009E848              *concurred via email      NRR-106 OFFICE  NRR/DANU/UNPL/PM NRR/DANU/UNPL/LA* NRR/DANU/UNPL/BC NRR/DANU/UNPL/PM NAME    EHelvenston        NParker              GCasto              EHelvenston DATE    1/13/2020          1/10/2020            1/13/2020          1/13/2020}}

Latest revision as of 15:39, 28 January 2020

University of Massachusetts Lowell, Response to Request for Extension of Time to Respond to Request for Additional Information Regarding the Renewal of Facility Operating License No. R-125
ML20009E848
Person / Time
Site: University of Lowell
Issue date: 01/13/2020
From: Edward Helvenston
NRC/NRR/DANU
To: Prosanta Chowdhury
Univ of Massachusetts - Lowell
Ed Helvenston , NRR/DANU 415-4067
References
EPID L-2015-RNW-0001
Download: ML20009E848 (4)


Text

P. Chowdhury January 13, 2020 Dr. Partha Chowdhury, Director Nuclear Radiation Laboratory University of Massachusetts-Lowell One University Avenue Lowell, MA 01854

SUBJECT:

UNIVERSITY OF MASSACHUSETTS LOWELL - RESPONSE TO REQUEST FOR EXTENSION OF TIME TO RESPOND TO REQUEST FOR ADDITIONAL INFORMATION REGARDING THE RENEWAL OF FACILITY OPERATING LICENSE NO. R-125 (EPID NO. L-2015-RNW-0001)

Dear Dr. Chowdhury:

The University of Massachusetts Lowell (UML) holds U.S. Nuclear Regulatory Commission (NRC) Facility Operating License No. R-125 for the operation of the UML Research Reactor (UMLRR). By application dated October 20, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16042A015), as supplemented, UML applied for renewal of the UMLRR operating license.

On July 19, 2019 (ADAMS Accession No. ML18092B090), the NRC staff sent UML a letter enclosing requests for additional information (RAIs) identifying additional information needed for the NRC staff to continue its review of UMLs renewal application. The NRC staffs letter requested that UML provide responses to the RAIs by October 21, 2019, and stated that based on this response date, the NRC staff expected to complete its review and make a final determination on the renewal request by June 30, 2020.

By letter dated October 18, 2019 (ADAMS Accession No. ML19291C293), UML provided responses to the NRC staffs RAIs, but requested an additional 60 days beyond the deadline in the NRC staffs July 19, 2019, letter to provide additional information to complete its responses to RAI-7.4.c, RAI-7.4.d, and RAI-7.5.a (RAI numbers corrected by UML in a follow-up letter dated October 24, 2019 (ADAMS Accession No. ML19297F433)). The NRC staff accepted UMLs extension request by letter dated October 30, 2019 (ADAMS Accession No. ML19296E279).

By letters dated December 19 and 20, 2019 (ADAMS Accession Nos. ML19353C523 and ML19354A610, respectively), UML provided a response to RAI-7.4.d. In its letter dated December 19, 2019, UML also requested an additional 60 days beyond the updated deadline in the NRC staffs October 30, 2019, letter to complete its responses to RAI-7.4.c and RAI-7.5.a.

The NRC staff accepts UMLs extension request dated December 19, 2019, such that the deadline for UML to complete its responses to RAI-7.4.c and RAI-7.5.a is now February 18, 2020.

P. Chowdhury Based on the information that UML requested additional time to provide, and the new response date, the NRC staff continues to expect to complete its review and make a final determination on the renewal request by June 30, 2020. However, this date could still change due to several factors including a need for further RAIs, unanticipated changes to the scope of the review, unsolicited supplements to the application for the renewal, and others. If the forecasted date changes, the NRC staff will notify you in writing of the new date and an explanation of the reason for the change.

If you have any questions, or need additional time to respond to the NRC staffs original July 19, 2019, request, please contact me at 301-415-4067, or by electronic mail at Edward.Helvenston@nrc.gov.

Sincerely,

/RA/

Edward Helvenston, Project Manager Non-Power Production and Utilization Facility Licensing Branch Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation Docket No. 50-223 License No. R-125 cc: See next page

University of Massachusetts - Lowell Docket No. 50-223 cc:

Mayor of Lowell City Hall Lowell, MA 01852 Mr. Leo Bobek Reactor Supervisor University of Massachusetts - Lowell One University Avenue Lowell, MA 01854 Department of Environmental Protection One Winter Street Boston, MA 02108 Jack Priest, Director Radiation Control Program Department of Public Health Schrafft Center, Suite 1M2A 529 Main Street Charlestown, MA 02129 John Giarrusso, Planning and Preparedness Division Chief Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702-5399 Test, Research and Training Reactor Newsletter Attention: Ms. Amber Johnson Department of Materials Science and Engineering University of Maryland 4418 Stadium Drive College Park, MD 20742-2115

ML120009E848 *concurred via email NRR-106 OFFICE NRR/DANU/UNPL/PM NRR/DANU/UNPL/LA* NRR/DANU/UNPL/BC NRR/DANU/UNPL/PM NAME EHelvenston NParker GCasto EHelvenston DATE 1/13/2020 1/10/2020 1/13/2020 1/13/2020