{{#Wiki_filter: | {{#Wiki_filter: E. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans Including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). | ||
The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled: "Diablo Canyon Power Plant, Units 1 and 2 Physical Security Plan, by Training and Qualification Plan, and Safeguards Contingency Plan," submitted by letter dated May 16, 2006. F.Deleted. | The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled: "Diablo Canyon Power Plant, Units 1 and 2 Physical Security Plan, by Training and Qualification Plan, and Safeguards Contingency Plan," submitted by letter dated May 16, 2006. | ||
G.Deleted. | F. Deleted. | ||
G. Deleted. l H. Financial Protection PG&E shall have and maintain financial protection of such type and in such amonts as the Commission shall require In accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims. | |||
I. Term of License This License is effective as of the date of Issuance and shall expire at midnight on November 2, 2024. | |||
FOR THE NUCLEAR REGULATORY COMMISSION Original Signed by: | |||
Edson G. Case for Harold R. Denton, Director Office of Nuclear Reactor Regulation Attachments: | |||
: 1. Appendix A - Technical Specifications | |||
: 2. Appendix B - Environmental Protection Plan | : 2. Appendix B - Environmental Protection Plan | ||
: 3. Appendix C - Deleted | : 3. Appendix C - Deleted | ||
: 4. Appendix D - Additional | : 4. Appendix D - Additional Conditions Date of Issuance: November 2, 1984 Amendment No. 82, 75, 97, 129, 188, 189, 193 Revised by letter dated December 11, 2006 | ||
F. Deleted. | |||
G. Deleted. l H. Financial Protection PG&E shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims. | |||
I. Term of License This License is effective as of the date of issuance and shall expire at midnight on August 26, 2025. | |||
FOR THE NUCLEAR REGULATORY COMMISSION Original Signed by: | |||
Harold R. Denton Harold R. Denton, Director Office of Nuclear Reactor Regulation Attachments: | |||
: 1. Appendix A Technical Specifications (NUREG-1151) | |||
: 2. Appendix B - Environmental Protection Plan | |||
: 3. Appendix C - Deleted | |||
: 4. Appendix D - Additional Conditions Date of Issuance: August 26, 1985 Amendment No. 96, 118, 190, 191, 194 Revised by letter dated December 11, 2006}} |
Latest revision as of 09:27, 23 November 2019
ML070440503 | |
Person / Time | |
---|---|
Site: | Diablo Canyon |
Issue date: | 03/19/2007 |
From: | Harold Denton Office of Nuclear Reactor Regulation |
To: | |
Wang A, NRR/DORL/LPL4, 301-415-1445 | |
Shared Package | |
ML070440500 | List: |
References | |
TAC MD3817, TAC MD3818 | |
Download: ML070440503 (2) | |
Text
E. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans Including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p).
The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled: "Diablo Canyon Power Plant, Units 1 and 2 Physical Security Plan, by Training and Qualification Plan, and Safeguards Contingency Plan," submitted by letter dated May 16, 2006.
F. Deleted.
G. Deleted. l H. Financial Protection PG&E shall have and maintain financial protection of such type and in such amonts as the Commission shall require In accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.
I. Term of License This License is effective as of the date of Issuance and shall expire at midnight on November 2, 2024.
FOR THE NUCLEAR REGULATORY COMMISSION Original Signed by:
Edson G. Case for Harold R. Denton, Director Office of Nuclear Reactor Regulation Attachments:
- 1. Appendix A - Technical Specifications
- 2. Appendix B - Environmental Protection Plan
- 3. Appendix C - Deleted
- 4. Appendix D - Additional Conditions Date of Issuance: November 2, 1984 Amendment No. 82, 75, 97, 129, 188, 189, 193 Revised by letter dated December 11, 2006
F. Deleted.
G. Deleted. l H. Financial Protection PG&E shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.
I. Term of License This License is effective as of the date of issuance and shall expire at midnight on August 26, 2025.
FOR THE NUCLEAR REGULATORY COMMISSION Original Signed by:
Harold R. Denton Harold R. Denton, Director Office of Nuclear Reactor Regulation Attachments:
- 1. Appendix A Technical Specifications (NUREG-1151)
- 2. Appendix B - Environmental Protection Plan
- 3. Appendix C - Deleted
- 4. Appendix D - Additional Conditions Date of Issuance: August 26, 1985 Amendment No. 96, 118, 190, 191, 194 Revised by letter dated December 11, 2006