ML111240445: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(3 intermediate revisions by the same user not shown)
Line 1: Line 1:
#REDIRECT [[IR 05000250/2011008]]
{{Adams
| number = ML111240445
| issue date = 05/03/2011
| title = Notification of Turkey Point Nuclear Plant - Component Design Bases Inspection - NRC Inspection Report 05000250-11-08 & 05000251-11-008
| author name = Desai B
| author affiliation = NRC/RGN-II/DRS/EB1
| addressee name = Nazar M
| addressee affiliation = Florida Power & Light Co
| docket = 05000250, 05000251
| license number = DPR-031, DPR-041
| contact person =
| document report number = IR-11-008
| document type = Letter
| page count = 6
}}
See also: [[see also::IR 05000250/2011008]]
 
=Text=
{{#Wiki_filter:UNITED STATES
                                NUCLEAR REGULATORY COMMISSION
                                              REGION II
                            245 PEACHTREE CENTER AVENUE NE, SUITE 1200
                                      ATLANTA, GEORGIA 30303-1257
                                            May 3, 2011
Mr. Mano Nazar
Executive Vice President
  and Chief Nuclear Officer
Florida Power and Light Company
P.O. Box 14000
Juno Beach, FL 33408-0420
SUBJECT:        NOTIFICATION OF TURKEY POINT NUCLEAR PLANT - COMPONENT
                DESIGN BASES INSPECTION - NRC INSPECTION REPORT 05000250 &
                251/2011008
Dear Mr. Nazar:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II staff will conduct a component design bases inspection at your Turkey Point Nuclear
Power Plant during the weeks of July 11 - 15, July 25 - 29 and August 8 - 12, 2011. The
inspection team will be led by David Jones, a Senior Reactor Inspector from the NRC's Region
II Office. This inspection will be conducted in accordance with the baseline inspection
procedure, Procedure 71111.21, Component Design Bases Inspection, issued December 6,
2010.
The inspection will evaluate the capability of risk significant / low margin components to function
as designed and to support proper system operation. The inspection will also include a review
of selected risk significant components and operating experience items.
During a telephone conversation on April 20, 2011, Mr. Jones confirmed with Mr. R. Everett of
your staff, arrangements for an information gathering site visit and the three-week onsite
inspection. The schedule is as follows:
*        Information gathering visit: Week of June 27 - July 1, 2011
*        Onsite weeks: July 11 - 15, July 25 - 29 and August 8 - 12, 2011
The purpose of the information gathering visit is to meet with members of your staff to identify
risk-significant components and operator actions. Information and documentation needed to
support the inspection will also be identified. Mr. John Hanna, a Region II Senior Reactor
Analyst, will accompany Mr. Jones during the information gathering visit to review probabilistic
risk assessment data and identify risk significant components which will be examined during the
inspection.
The enclosure lists documents that will be needed prior to the information gathering visit.
Please provide the referenced information to the Region II office by June 6, 2011. Contact
 
FPL                                                2
Mr. Jones with any questions concerning the requested information. The inspectors will try to
minimize your administrative burden by specifically identifying only those documents required
for inspection preparation.
Additional documents will be requested during the information gathering visit. The additional
information will need to be made available to the team in the Region II office prior to the
inspection teams preparation week of July 5. Mr. Jones, will also discuss the following
inspection support administrative details: availability of knowledgeable plant engineering and
licensing personnel to serve as points of contact during the inspection; method of tracking
inspector requests during the inspection; licensee computer access; working space;
arrangements for site access; and other applicable information.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRC's document system
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Thank you for your cooperation in this matter. If you have any questions regarding the
information requested or the inspection, please contact Mr. Jones at (404) 997-4631 or me at
(404) 997-4519.
                                              Sincerely,
                                              /RA/
                                              Binoy B. Desai, Chief
                                              Engineering Branch 1
                                              Division of Reactor Safety
Docket Nos.: 50-250 & 251
License Nos.: DPR - 31 & 41
Enclosure:
Information Request for Turkey Point Nuclear Plant - Component Design Bases Inspection
cc w/enc/: (See page 3)
 
 
___ML111240445______________________          G SUNSI REVIEW COMPLETE
OFFICE            RII:DRS        RII:DRS
SIGNATURE          RA              RA
NAME              DJONES          BDESAI
DATE                  5/3/2011        5/3/2011
E-MAIL COPY?        YES        NO  YES        NO YES    NO  YES      NO  YES      NO  YES      NO  YES    NO
       
FPL                                  3
cc w/encl:                            Ruben D. Almaguer
Alison Brown                          Director
Nuclear Licensing                      Division of Emergency Preparedness
Florida Power & Light Company          Department of Community Affairs
Electronic Mail Distribution          Electronic Mail Distribution
Larry Nicholson                        Mano Nazar
Director                              Executive Vice President and Chief Nuclear
Licensing                              Officer
Florida Power & Light Company          Nuclear Division
Electronic Mail Distribution          Florida Power & Light Company
                                      P.O. Box 14000
Michael Kiley                          Juno Beach, FL 33408
Site Vice President
Turkey Point Nuclear Plant            Senior Resident Inspector
Florida Power and Light Company        Turkey Point Nuclear Generating Station
Electronic Mail Distribution          U.S. Nuclear Regulatory Commission
                                      9762 SW 344th St.
Niel Batista                          Florida City, FL 33035
Emergency Management Coordinator
Department of Emergency Management    Attorney General
and Homeland Security                  Department of Legal Affairs
Electronic Mail Distribution          The Capitol PL-01
                                      Tallahassee, FL 32399-1050
Robert J. Tomonto
Licensing Manager                      Mike A. Shehadeh, P.E.
Turkey Point Nuclear Plant            City Manager
Florida Power & Light Company          City of Homestead
Electronic Mail Distribution          Electronic Mail Distribution
Paul Rubin                            County Manager of Miami-Dade County
Plant General Manager                  111 NW 1st Street, 29th Floor
Turkey Point Nuclear Plant            Miami, FL 33128
Florida Power and Light Company
Electronic Mail Distribution          Gene St. Pierre
                                      Vice President, Fleet Support
Mitch S. Ross                          Florida Power & Light Company
Vice President and Associate General  Electronic Mail Distribution
Counsel
Florida Power & Light Company
Electronic Mail Distribution
Marjan Mashhadi
Senior Attorney
Florida Power & Light Company
Electronic Mail Distribution
William A. Passetti
Chief
Florida Bureau of Radiation Control
Department of Health
Electronic Mail Distribution
 
        INFORMATION REQUEST FOR TURKEY POINT NUCLEAR POWER PLANT
                            COMPONENT DESIGN BASES INSPECTION
Please provide the information electronically in .pdf files, Excel, or other searchable format on
CDROM. The CDROM should be indexed and hyperlinked to facilitate ease of use.
1.  From your most-recent probabilistic safety analysis (PSA) excluding external events and
    fires:
        a.      Two risk rankings of components from your site-specific probabilistic safety
                analysis (PSA): one sorted by Risk Achievement Worth (RAW), and the other
                sorted by Birnbaum Importance.
        b.      A list of the top 500 cutsets.
2.  From your most-recent probabilistic safety analysis (PSA) including external events and
    fires:
        a.      Two risk rankings of components from your site-specific probabilistic safety
                analysis (PSA): one sorted by Risk Achievement Worth (RAW), and the other
                sorted by Birnbaum Importance.
        b.      A list of the top 500 cutsets.
3.  Risk ranking of operator actions from your site specific PSA sorted by RAW. Provide
    human reliability worksheets for these items.
4.  Contact information for a person to discuss PRA information prior to the information
    gathering trip (name, title, phone number, and e-mail address)
5.  List of time critical operator actions with a brief description of each action.
6.  List of Emergency and Abnormal Operating Procedures revised (significant) since January
    1, 2008 with a brief description of each revision.
7.  List of components with low design margins (i.e., pumps closest to the design limit for flow
    or pressure, diesel generator close to design required output, heat exchangers close to
    rated design heat removal, MOV risk-margin rankings, etc.) and associated evaluations or
    calculations.
8.  List of station operating experience evaluations/reviews performed and documented in the
    stations corrective action program for industry events and safety-related equipment
    failures/vulnerabilities [as communicated by NRC generic communications, industry
    communications, 10 CFR part 21 notifications, etc.] since January 1, 2008.
9.  List and brief description of safety-related SSC design modifications implemented since
    January 1, 2008.
10. List and brief description of common-cause component failures that have occurred since
    January 1, 2008.
11. Operability Determination Procedure(s)
12. List and brief description of operability evaluations completed since January 1, 2008.
                                                                                          Enclosure
 
                                            2
13. List of equipment on the sites Station Equipment Reliability Issues List, including a
    description of the reason(s) why each component is on that list and summaries (if available)
    of your plans to address the issue(s).
14. List and brief description of equipment currently in degraded or nonconforming status as
    described in RIS 05-020.
15. List and reason for equipment classified in maintenance rule (a)(1) status since January 1,
    2008 to present.
16. Copy of UFSAR(s)
17. Copy of Technical Specification(s)
18. Copy of Technical Specifications Bases
19. Copy of Technical Requirements Manual(s)
20. Corrective Action Program Procedure(s)
21. Condition reports associated with findings from NRC Inspection Report 2008006
22. List and brief description of Root Cause Evaluations that have been performed since
    January 1, 2008.
23. In-service Testing Program Procedure(s)
24. Copies of System Descriptions (or the like) for safety-related systems (mechanical &
    electrical)
25. Design bases documents for safety-related systems (mechanical & electrical)
26. Primary AC calculation(s) for safety-related buses
27. Primary DC calculation(s) for safety-related buses
28. One line diagram of electrical plant (electronic and full size)
29. Index and legend for electrical plant one-line diagrams
30. PI&Ds for ECCS systems (electronic and 1/2 size)
31. Index and Legend for PI&Ds
                                                                                        Enclosure
}}

Latest revision as of 01:12, 13 November 2019

Notification of Turkey Point Nuclear Plant - Component Design Bases Inspection - NRC Inspection Report 05000250-11-08 & 05000251-11-008
ML111240445
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 05/03/2011
From: Binoy Desai
NRC/RGN-II/DRS/EB1
To: Nazar M
Florida Power & Light Co
References
IR-11-008
Download: ML111240445 (6)


See also: IR 05000250/2011008

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

245 PEACHTREE CENTER AVENUE NE, SUITE 1200

ATLANTA, GEORGIA 30303-1257

May 3, 2011

Mr. Mano Nazar

Executive Vice President

and Chief Nuclear Officer

Florida Power and Light Company

P.O. Box 14000

Juno Beach, FL 33408-0420

SUBJECT: NOTIFICATION OF TURKEY POINT NUCLEAR PLANT - COMPONENT

DESIGN BASES INSPECTION - NRC INSPECTION REPORT 05000250 &

251/2011008

Dear Mr. Nazar:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)

Region II staff will conduct a component design bases inspection at your Turkey Point Nuclear

Power Plant during the weeks of July 11 - 15, July 25 - 29 and August 8 - 12, 2011. The

inspection team will be led by David Jones, a Senior Reactor Inspector from the NRC's Region

II Office. This inspection will be conducted in accordance with the baseline inspection

procedure, Procedure 71111.21, Component Design Bases Inspection, issued December 6,

2010.

The inspection will evaluate the capability of risk significant / low margin components to function

as designed and to support proper system operation. The inspection will also include a review

of selected risk significant components and operating experience items.

During a telephone conversation on April 20, 2011, Mr. Jones confirmed with Mr. R. Everett of

your staff, arrangements for an information gathering site visit and the three-week onsite

inspection. The schedule is as follows:

  • Information gathering visit: Week of June 27 - July 1, 2011
  • Onsite weeks: July 11 - 15, July 25 - 29 and August 8 - 12, 2011

The purpose of the information gathering visit is to meet with members of your staff to identify

risk-significant components and operator actions. Information and documentation needed to

support the inspection will also be identified. Mr. John Hanna, a Region II Senior Reactor

Analyst, will accompany Mr. Jones during the information gathering visit to review probabilistic

risk assessment data and identify risk significant components which will be examined during the

inspection.

The enclosure lists documents that will be needed prior to the information gathering visit.

Please provide the referenced information to the Region II office by June 6, 2011. Contact

FPL 2

Mr. Jones with any questions concerning the requested information. The inspectors will try to

minimize your administrative burden by specifically identifying only those documents required

for inspection preparation.

Additional documents will be requested during the information gathering visit. The additional

information will need to be made available to the team in the Region II office prior to the

inspection teams preparation week of July 5. Mr. Jones, will also discuss the following

inspection support administrative details: availability of knowledgeable plant engineering and

licensing personnel to serve as points of contact during the inspection; method of tracking

inspector requests during the inspection; licensee computer access; working space;

arrangements for site access; and other applicable information.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions regarding the

information requested or the inspection, please contact Mr. Jones at (404) 997-4631 or me at

(404) 997-4519.

Sincerely,

/RA/

Binoy B. Desai, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos.: 50-250 & 251

License Nos.: DPR - 31 & 41

Enclosure:

Information Request for Turkey Point Nuclear Plant - Component Design Bases Inspection

cc w/enc/: (See page 3)

___ML111240445______________________ G SUNSI REVIEW COMPLETE

OFFICE RII:DRS RII:DRS

SIGNATURE RA RA

NAME DJONES BDESAI

DATE 5/3/2011 5/3/2011

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

FPL 3

cc w/encl: Ruben D. Almaguer

Alison Brown Director

Nuclear Licensing Division of Emergency Preparedness

Florida Power & Light Company Department of Community Affairs

Electronic Mail Distribution Electronic Mail Distribution

Larry Nicholson Mano Nazar

Director Executive Vice President and Chief Nuclear

Licensing Officer

Florida Power & Light Company Nuclear Division

Electronic Mail Distribution Florida Power & Light Company

P.O. Box 14000

Michael Kiley Juno Beach, FL 33408

Site Vice President

Turkey Point Nuclear Plant Senior Resident Inspector

Florida Power and Light Company Turkey Point Nuclear Generating Station

Electronic Mail Distribution U.S. Nuclear Regulatory Commission

9762 SW 344th St.

Niel Batista Florida City, FL 33035

Emergency Management Coordinator

Department of Emergency Management Attorney General

and Homeland Security Department of Legal Affairs

Electronic Mail Distribution The Capitol PL-01

Tallahassee, FL 32399-1050

Robert J. Tomonto

Licensing Manager Mike A. Shehadeh, P.E.

Turkey Point Nuclear Plant City Manager

Florida Power & Light Company City of Homestead

Electronic Mail Distribution Electronic Mail Distribution

Paul Rubin County Manager of Miami-Dade County

Plant General Manager 111 NW 1st Street, 29th Floor

Turkey Point Nuclear Plant Miami, FL 33128

Florida Power and Light Company

Electronic Mail Distribution Gene St. Pierre

Vice President, Fleet Support

Mitch S. Ross Florida Power & Light Company

Vice President and Associate General Electronic Mail Distribution

Counsel

Florida Power & Light Company

Electronic Mail Distribution

Marjan Mashhadi

Senior Attorney

Florida Power & Light Company

Electronic Mail Distribution

William A. Passetti

Chief

Florida Bureau of Radiation Control

Department of Health

Electronic Mail Distribution

INFORMATION REQUEST FOR TURKEY POINT NUCLEAR POWER PLANT

COMPONENT DESIGN BASES INSPECTION

Please provide the information electronically in .pdf files, Excel, or other searchable format on

CDROM. The CDROM should be indexed and hyperlinked to facilitate ease of use.

1. From your most-recent probabilistic safety analysis (PSA) excluding external events and

fires:

a. Two risk rankings of components from your site-specific probabilistic safety

analysis (PSA): one sorted by Risk Achievement Worth (RAW), and the other

sorted by Birnbaum Importance.

b. A list of the top 500 cutsets.

2. From your most-recent probabilistic safety analysis (PSA) including external events and

fires:

a. Two risk rankings of components from your site-specific probabilistic safety

analysis (PSA): one sorted by Risk Achievement Worth (RAW), and the other

sorted by Birnbaum Importance.

b. A list of the top 500 cutsets.

3. Risk ranking of operator actions from your site specific PSA sorted by RAW. Provide

human reliability worksheets for these items.

4. Contact information for a person to discuss PRA information prior to the information

gathering trip (name, title, phone number, and e-mail address)

5. List of time critical operator actions with a brief description of each action.

6. List of Emergency and Abnormal Operating Procedures revised (significant) since January

1, 2008 with a brief description of each revision.

7. List of components with low design margins (i.e., pumps closest to the design limit for flow

or pressure, diesel generator close to design required output, heat exchangers close to

rated design heat removal, MOV risk-margin rankings, etc.) and associated evaluations or

calculations.

8. List of station operating experience evaluations/reviews performed and documented in the

stations corrective action program for industry events and safety-related equipment

failures/vulnerabilities [as communicated by NRC generic communications, industry

communications, 10 CFR part 21 notifications, etc.] since January 1, 2008.

9. List and brief description of safety-related SSC design modifications implemented since

January 1, 2008.

10. List and brief description of common-cause component failures that have occurred since

January 1, 2008.

11. Operability Determination Procedure(s)

12. List and brief description of operability evaluations completed since January 1, 2008.

Enclosure

2

13. List of equipment on the sites Station Equipment Reliability Issues List, including a

description of the reason(s) why each component is on that list and summaries (if available)

of your plans to address the issue(s).

14. List and brief description of equipment currently in degraded or nonconforming status as

described in RIS 05-020.

15. List and reason for equipment classified in maintenance rule (a)(1) status since January 1,

2008 to present.

16. Copy of UFSAR(s)

17. Copy of Technical Specification(s)

18. Copy of Technical Specifications Bases

19. Copy of Technical Requirements Manual(s)

20. Corrective Action Program Procedure(s)

21. Condition reports associated with findings from NRC Inspection Report 2008006

22. List and brief description of Root Cause Evaluations that have been performed since

January 1, 2008.

23. In-service Testing Program Procedure(s)

24. Copies of System Descriptions (or the like) for safety-related systems (mechanical &

electrical)

25. Design bases documents for safety-related systems (mechanical & electrical)

26. Primary AC calculation(s) for safety-related buses

27. Primary DC calculation(s) for safety-related buses

28. One line diagram of electrical plant (electronic and full size)

29. Index and legend for electrical plant one-line diagrams

30. PI&Ds for ECCS systems (electronic and 1/2 size)

31. Index and Legend for PI&Ds

Enclosure