ML13193A199: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(2 intermediate revisions by the same user not shown)
Line 3: Line 3:
| issue date = 07/12/2013
| issue date = 07/12/2013
| title = Order (Scheduling Initial Scheduling Conference)
| title = Order (Scheduling Initial Scheduling Conference)
| author name = Karlin A S
| author name = Karlin A
| author affiliation = NRC/ASLBP
| author affiliation = NRC/ASLBP
| addressee name =  
| addressee name =  
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION ATOMIC SAFETY AND LICENSING BOARD Before Administrative Judges:
{{#Wiki_filter:UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION ATOMIC SAFETY AND LICENSING BOARD Before Administrative Judges:
Alex S. Karlin, Chairman Dr. Paul B. Abramson Dr. Gary S. Arnold In the Matter of TENNESSEE VALLEY AUTHORITY (Sequoyah Nuclear Plant, Units 1 and 2)
Alex S. Karlin, Chairman Dr. Paul B. Abramson Dr. Gary S. Arnold In the Matter of                                         Docket Nos. 50-327-LR, 50-328-LR TENNESSEE VALLEY AUTHORITY                               ASLBP No. 13-927-01-LR-BD01 (Sequoyah Nuclear Plant, Units 1 and 2)                  July 12, 2013 ORDER (Scheduling Initial Scheduling Conference)
Docket Nos. 50-327-LR, 50-328-LR
This is to notify the Tennessee Valley Authority (TVA), the Blue Ridge Environmental Defense League (BREDL), and the Staff of the Nuclear Regulatory Commission (NRC) that, in accordance with 10 C.F.R. §§ 2.329 and 2.332, the Board will hold an initial scheduling conference call on August 8, 2013, at 9:00 AM EDT for the purpose of developing an initial scheduling order (ISO) to govern the conduct of this proceeding. Prior to the call, the parties should familiarize themselves with the relevant procedural rules of 10 C.F.R. Part 2, as amended.1 The posture of this case is unusual because no contentions are currently admitted.
Instead, one contention, which has neither been admitted nor denied, has been held in abeyance pending [the Commissions] further order as required by Calvert Cliffs Nuclear Project, LLC (Calvert Cliffs Nuclear Power Plant, Unit 3), CLI-12-16, 76 NRC 63, 69 (2012).
That contention - Contention B - is an environmental contention based on New York v. NRC, 1
See Amendments to Adjudicatory Process Rules and Related Requirements, NRC Final Rule, 77 Fed. Reg. 46,562 (Aug. 3, 2012).


ASLBP No. 13-927-01-LR-BD01 July 12, 2013 ORDER (Scheduling Initial Scheduling Conference)
681 F.3d 471 (D.C. Cir. 2012). See LBP-13-08, 78 NRC __, __ (slip op. at 14) (July 5, 2013).
This is to notify the Tennessee Valley Authority (TVA), the Blue Ridge Environmental Defense League (BREDL), and the Staff of the Nuclear Regulatory Commission (NRC) that, in accordance with 10 C.F.R. §§ 2.329 and 2.332, the Board will hold an initial scheduling conference call on August 8, 2013, at 9:00 AM EDT for the purpose of developing an initial scheduling order (ISO) to govern the conduct of this proceeding. Prior to the call, the parties should familiarize themselves with the relevant procedural rules of 10 C.F.R. Part 2, as amended.The posture of this case is unusual because no contentions are currently admitted. Instead, one contention, which has neither been admitted nor denied, has been held "in abeyance pending [the Commission's] further order" as required by Calvert Cliffs Nuclear Project, LLC (Calvert Cliffs Nuclear Power Plant, Unit 3), CLI-12-16, 76 NRC 63, 69 (2012). That contention - Contention B - is an environmental contention based on New York v. NRC ,
Contention B alleges that NRC cannot grant the Sequoyah license renewal without conducting a thorough analysis of the risks of long-term storage of irradiated nuclear fuel generated by Sequoyah Units 1 and 2. Id.
1 See Amendments to Adjudicatory Process Rules and Related Requirements, NRC Final Rule, 77 Fed. Reg. 46,562 (Aug. 3, 2012).
The purpose of the scheduling conference is to assist the Board in developing an ISO appropriate for the posture of this case. For example, given that no contentions have been admitted, it would appear that the current scheduling order does not need to address matters such as mandatory disclosures under 10 C.F.R. § 2.336; opportunities to clarify, simplify, or amend the pleadings in accordance with 10 C.F.R. § 2.329(c); or the timing and procedures for the filing of testimony and exhibits for the evidentiary hearing.
On the other hand, it would appear that the ISO may need to address matters such as:
: 1. The value and need to obtain regular reports from the Staff as to its projected schedule for completion of its safety and environmental evaluations.2
: 2. The advisability of requiring notification if a party believes that the Commission has issued an order or taken any action that affects the abeyance status of Contention B.
: 3. The value of setting time limits for the filing of timely motions for leave to file new or amended contentions under 10 C.F.R. § 2.309(c)(1)(iii).
: 4. The value of setting rules and time limits for the filing of dispositive motions, such as motions for summary disposition.
: 5. The requirement that all motions (except motions for new or amended contentions) be filed no later than ten days after the occurrence or circumstances from which the motion arises. 10 C.F.R. § 2.323(a).
2 The NRC regulations state, In establishing a schedule, the presiding officer shall take into consideration the NRC staffs projected schedule for completion of its safety and environmental evaluations. 10 C.F.R. § 2.332(d).
2
: 6. Whether it is necessary or appropriate for the Staff to file (and update) its hearing file at this time. See 10 C.F.R. § 2.1203(c).
: 7. Any other procedural or scheduling matters that the Board may deem appropriate.
In furtherance of the foregoing objectives, the parties shall take the following actions:
Prior to the conference, the parties shall jointly confer for the purpose of discussing the foregoing procedural matters (and any others that they deem appropriate) and, where possible, developing agreement, joint positions, or procedural proposals for the Board to consider.
On or before July 30, 2013, the NRC Staff shall submit to the Board, with copies to all of the parties, a written estimate of its projected schedule for completion of its safety and environmental evaluations, including but not limited to its current reasonable good faith estimate of the dates when it expects to issue the final safety evaluation report and the draft and final environmental impact statements relating to TVAs license renewal application.
On or before August 5, 2013, counsel for each of the parties and the Staff should contact Twana Ellis at 301-415-7703 to obtain the telephone number and pass code for the August 8, 2013, prehearing conference call. Members of the public or media who wish to listen to this conference call may do so, and should contact Ms. Ellis at the above number for the requisite information.
If the lead representative or lawyer for any party has a previously scheduled concrete conflict that would prevent him or her from participating in the initial scheduling conference call on August 8, 2013, at 9:00 AM EDT, then that party shall consult with the other parties and, on or before July 17, 2013, shall file a motion herein certifying that such a conflict exists and 3


2  681 F.3d 471 (D.C. Cir. 2012). See LBP-13-08, 78 NRC __, __ (slip op. at 14) (July 5, 2013). Contention B alleges that "NRC cannot grant the Sequoyah license renewal without conducting a thorough analysis of the risks of long-term storage of irradiated nuclear fuel generated by Sequoyah Units 1 and 2."  Id.
proposing at least two alternative dates and times, acceptable to all parties, for the conference call.
The purpose of the scheduling conference is to assist the Board in developing an ISO appropriate for the posture of this case. For example, given that no contentions have been admitted, it would appear that the current scheduling order does not need to address matters such as mandatory disclosures under 10 C.F.R. § 2.336; opportunities to clarify, simplify, or amend the pleadings in accordance with 10 C.F.R. § 2.329(c); or the timing and procedures for the filing of testimony and exhibits for the evidentiary hearing. On the other hand, it would appear that the ISO may need to address matters such as: 1. The value and need to obtain regular reports from the Staff as to its projected schedule for completion of its safety and environmental evaluations.
It is so ORDERED.
2  2. The advisability of requiring notification if a party believes that the Commission has issued an order or taken any action that affects the "abeyance" status of Contention
FOR THE ATOMIC SAFETY AND LICENSING BOARD
                                                              /RA/
Alex S. Karlin, Chairman ADMINISTRATIVE JUDGE Rockville, Maryland July 12, 2013 4


B. 3. The value of setting time limits for the filing of "timely" motions for leave to file new or amended contentions under 10 C.F.R. § 2.309(c)(1)(iii). 4. The value of setting rules and time limits for the filing of dispositive motions, such as motions for summary disposition. 5. The requirement that all motions (except motions for new or amended contentions) be filed no later than ten days after the occurrence or circumstances from which the motion arises. 10 C.F.R. § 2.323(a).
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of                               )
2 The NRC regulations state, "In establishing a schedule, the presiding officer shall take into consideration the NRC staff's projected schedule for completion of its safety and environmental evaluations."  10 C.F.R. § 2.332(d).  
                                              )
TENNESSEE VALEY AUTHORITY                      )
                                              )
SEQUOYAH NUCLEAR PLANT,                        )    Docket Nos. 50-327-LR and 50-328-LR UNITS 1 AND 2 (License Renewal)               )
                                              )
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing ORDER (Scheduling Initial Scheduling Conference) have been served upon the following persons by Electronic Information Exchange.
Office of Commission Appellate                  U.S. Nuclear Regulatory Commission Adjudication                                  Office of the Secretary of the Commission U.S. Nuclear Regulatory Commission              Mail Stop O-16C1 Washington, DC 20555-0001                        Washington, DC 20555-0001 E-mail: ocaamail@nrc.gov                        Hearing Docket E-mail: hearingdocket@nrc.gov U.S. Nuclear Regulatory Commission.
Atomic Safety and Licensing Board Panel          Louis A. Zeller Mail Stop T-3F23                                Blue Ridge Environmental Defense League Washington, DC 20555-0001                        E-mail: bredl@skybest.com Alex S. Karlin, Chairman Administrative Judge                            Tennessee Valley Authority E-mail: alex.karlin@nrc.gov                      400 W Summit Hill Drive, WT 6A-K Knoxville, TN 37902 Dr. Paul B. Abramson                            Office of the General Counsel Administrative Judge                            Scott A. Vance, Nuclear Licensing Attorney E-mail: paul.abramson@nrc.gov                    Edward J. Vigluicci, Associate General Counsel, Nuclear Licensing Dr. Gary S. Arnold                              Blake Nelson, Attorney Administrative Judge                            E-mail:
E-mail: gary.arnold@nrc.gov                      savance@tva.gov ejvigluicci@tva.gov Matthew E. Flyntz, Law Clerk                    bjnelson@tva.gov E-mail: matthew.flyntz@nrc.gov


3  6. Whether it is necessary or appropriate for the Staff to file (and update) its hearing file at this time. See 10 C.F.R. § 2.1203(c). 7. Any other procedural or scheduling matters that the Board may deem appropriate. In furtherance of the foregoing objectives, the parties shall take the following actions:
2 Docket Nos. 50-327-LR and 50-328-LR ORDER (Scheduling Initial Scheduling Conference)
Prior to the conference, the parties shall jointly confer for the purpose of discussing the foregoing procedural matters (and any others that they deem appropriate) and, where possible, developing agreement, joint positions, or procedural proposals for the Board to consider. On or before July 30, 2013, the NRC Staff shall submit to the Board, with copies to all of the parties, a written estimate of its projected schedule for completion of its safety and environmental evaluations, including but not limited to its current reasonable good faith estimate of the dates when it expects to issue the final safety evaluation report and the draft and final environmental impact statements relating to TVA's license renewal application. On or before August 5, 2013, counsel for each of the parties and the Staff should contact Twana Ellis at 301-415-7703 to obtain the telephone number and pass code for the August 8, 2013, prehearing conference call. Members of the public or media who wish to listen to this conference call may do so, and should contact Ms. Ellis at the above number for the requisite information. If the lead representative or lawyer for any party has a previously scheduled concrete conflict that would prevent him or her from participating in the initial scheduling conference call on August 8, 2013, at 9:00 AM EDT, then that party shall consult with the other parties and, on or before July 17, 2013, shall file a motion herein certifying that such a conflict exists and
U.S. Nuclear Regulatory Commission       Counsel for Tennessee Valley Authority Office of the General Counsel             Pillsbury, Winthrop, Shaw, Pittman, LLP Mail Stop O-15D21                         2300 N Street, N.W.
 
Washington, DC 20555-0001                 Washington, DC 20037 Christina England, Esq.                   Michael G. Lepre, Esq.
4  proposing at least two alternative dates and times, acceptable to all parties, for the conference call. It is so ORDERED.
Brian Harris, Esq.                       David Lewis, Esq.
FOR THE ATOMIC SAFETY          AND LICENSING BOARD
Beth Mizuno, Esq.                         Robert Ross Mary Spencer, Esq.                       Maria Webb Edward Williamson, Esg.                   Email:
 
Mitzi Young, Esq.                         michael.lewis@pillsburylaw.com John Tibbetts, Paralegal                 david.lewis@pillsburylaw.com E-mail:                                   robert.ross@pillsburylaw.com christina.england@nrc.gov                 maria.webb@pillsburylaw.com brian.harris@nrc.gov beth.mizuno@nrc.gov mary.spencer@nrc.gov john.tibbetts@nrc.gov edward.williamson@nrc.gov mitzi.young@nrc.gov OGC Mail Center: OGCMailCenter@nrc.gov
Alex S. Karlin, Chairman ADMINISTRATIVE JUDGE
[Original signed by Clara I. Sola       ]
 
Office of the Secretary of the Commission Dated at Rockville, Maryland, this 12th day of July 2013.}}
Rockville, Maryland July 12, 2013 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of    )
      )
TENNESSEE VALEY AUTHORITY  )
      )
SEQUOYAH NUCLEAR PLANT,  ) Docket Nos. 50-327-LR and 50-328-LR UNITS 1 AND 2 (License Renewal)  )      )
 
CERTIFICATE OF SERVICE
 
I hereby certify that copies of the foregoing ORDER (Scheduling Initial Scheduling Conference) have been served upon the following persons by Electronic Information Exchange.
 
Office of Commission Appellate 
 
Adjudication U.S. Nuclear Regulatory Commission Washington, DC  20555-0001
 
E-mail:  ocaamail@nrc.gov U.S. Nuclear Regulatory Commission.
Atomic Safety and Licensing Board Panel
 
Mail Stop T-3F23 Washington, DC  20555-0001 Alex S. Karlin, Chairman
 
Administrative Judge
 
E-mail:  alex.karlin@nrc.gov
 
Dr. Paul B. Abramson Administrative Judge E-mail:  paul.abramson@nrc.gov
 
Dr. Gary S. Arnold
 
Administrative Judge E-mail:  gary.arnold@nrc.gov Matthew E. Flyntz, Law Clerk
 
E-mail:  matthew.flyntz@nrc.gov
 
U.S. Nuclear Regulatory Commission Office of the Secretary of the Commission
 
Mail Stop O-16C1 Washington, DC  20555-0001
 
Hearing Docket
 
E-mail:  hearingdocket@nrc.gov
 
Louis A. Zeller Blue Ridge Environmental Defense League
 
E-mail:  bredl@skybest.com
 
Tennessee Valley Authority  
 
400 W Summit Hill Drive, WT 6A-K
 
Knoxville, TN 37902 Office of the General Counsel Scott A. Vance, Nuclear Licensing Attorney Edward J. Vigluicci, Associate General Counsel, Nuclear Licensing Blake Nelson, Attorney
 
E-mail: savance@tva.gov ejvigluicci@tva.gov bjnelson@tva.gov
 
2  Docket Nos. 50-327-LR and 50-328-LR ORDER (Scheduling Initial Scheduling Conference)
 
U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop O-15D21 Washington, DC 20555-0001 Christina England, Esq.  
 
Brian Harris, Esq.  
 
Beth Mizuno, Esq. Mary Spencer, Esq. Edward Williamson, Esg.  
 
Mitzi Young, Esq.
John Tibbetts, Paralegal  
 
E-mail: christina.england@nrc.gov brian.harris@nrc.gov beth.mizuno@nrc.gov mary.spencer@nrc.gov john.tibbetts@nrc.gov edward.williamson@nrc.gov mitzi.young@nrc.gov OGC Mail Center:
OGCMailCenter@nrc.gov
 
Counsel for Tennessee Valley Authority Pillsbury, Winthrop, Shaw, Pittman, LLP 2300 N Street, N.W. Washington, DC 20037
 
Michael G. Lepre, Esq.
 
David Lewis, Esq.
 
Robert Ross Maria Webb Email:
michael.lewis@pillsburylaw.com david.lewis@pillsburylaw.com robert.ross@pillsburylaw.com maria.webb@pillsburylaw.com
 
[Original signed by Clara I. Sola               ]       Office of the Secretary of the Commission  
 
Dated at Rockville, Maryland, this 12 th day of July 2013.}}

Latest revision as of 17:04, 4 November 2019

Order (Scheduling Initial Scheduling Conference)
ML13193A199
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 07/12/2013
From: Karlin A
Atomic Safety and Licensing Board Panel
To:
SECY RAS
References
50-327-LR, 50-328-LR, ASLBP 13-927-01-LR-BD01, RAS 24814
Download: ML13193A199 (6)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION ATOMIC SAFETY AND LICENSING BOARD Before Administrative Judges:

Alex S. Karlin, Chairman Dr. Paul B. Abramson Dr. Gary S. Arnold In the Matter of Docket Nos. 50-327-LR, 50-328-LR TENNESSEE VALLEY AUTHORITY ASLBP No. 13-927-01-LR-BD01 (Sequoyah Nuclear Plant, Units 1 and 2) July 12, 2013 ORDER (Scheduling Initial Scheduling Conference)

This is to notify the Tennessee Valley Authority (TVA), the Blue Ridge Environmental Defense League (BREDL), and the Staff of the Nuclear Regulatory Commission (NRC) that, in accordance with 10 C.F.R. §§ 2.329 and 2.332, the Board will hold an initial scheduling conference call on August 8, 2013, at 9:00 AM EDT for the purpose of developing an initial scheduling order (ISO) to govern the conduct of this proceeding. Prior to the call, the parties should familiarize themselves with the relevant procedural rules of 10 C.F.R. Part 2, as amended.1 The posture of this case is unusual because no contentions are currently admitted.

Instead, one contention, which has neither been admitted nor denied, has been held in abeyance pending [the Commissions] further order as required by Calvert Cliffs Nuclear Project, LLC (Calvert Cliffs Nuclear Power Plant, Unit 3), CLI-12-16, 76 NRC 63, 69 (2012).

That contention - Contention B - is an environmental contention based on New York v. NRC, 1

See Amendments to Adjudicatory Process Rules and Related Requirements, NRC Final Rule, 77 Fed. Reg. 46,562 (Aug. 3, 2012).

681 F.3d 471 (D.C. Cir. 2012). See LBP-13-08, 78 NRC __, __ (slip op. at 14) (July 5, 2013).

Contention B alleges that NRC cannot grant the Sequoyah license renewal without conducting a thorough analysis of the risks of long-term storage of irradiated nuclear fuel generated by Sequoyah Units 1 and 2. Id.

The purpose of the scheduling conference is to assist the Board in developing an ISO appropriate for the posture of this case. For example, given that no contentions have been admitted, it would appear that the current scheduling order does not need to address matters such as mandatory disclosures under 10 C.F.R. § 2.336; opportunities to clarify, simplify, or amend the pleadings in accordance with 10 C.F.R. § 2.329(c); or the timing and procedures for the filing of testimony and exhibits for the evidentiary hearing.

On the other hand, it would appear that the ISO may need to address matters such as:

1. The value and need to obtain regular reports from the Staff as to its projected schedule for completion of its safety and environmental evaluations.2
2. The advisability of requiring notification if a party believes that the Commission has issued an order or taken any action that affects the abeyance status of Contention B.
3. The value of setting time limits for the filing of timely motions for leave to file new or amended contentions under 10 C.F.R. § 2.309(c)(1)(iii).
4. The value of setting rules and time limits for the filing of dispositive motions, such as motions for summary disposition.
5. The requirement that all motions (except motions for new or amended contentions) be filed no later than ten days after the occurrence or circumstances from which the motion arises. 10 C.F.R. § 2.323(a).

2 The NRC regulations state, In establishing a schedule, the presiding officer shall take into consideration the NRC staffs projected schedule for completion of its safety and environmental evaluations. 10 C.F.R. § 2.332(d).

2

6. Whether it is necessary or appropriate for the Staff to file (and update) its hearing file at this time. See 10 C.F.R. § 2.1203(c).
7. Any other procedural or scheduling matters that the Board may deem appropriate.

In furtherance of the foregoing objectives, the parties shall take the following actions:

Prior to the conference, the parties shall jointly confer for the purpose of discussing the foregoing procedural matters (and any others that they deem appropriate) and, where possible, developing agreement, joint positions, or procedural proposals for the Board to consider.

On or before July 30, 2013, the NRC Staff shall submit to the Board, with copies to all of the parties, a written estimate of its projected schedule for completion of its safety and environmental evaluations, including but not limited to its current reasonable good faith estimate of the dates when it expects to issue the final safety evaluation report and the draft and final environmental impact statements relating to TVAs license renewal application.

On or before August 5, 2013, counsel for each of the parties and the Staff should contact Twana Ellis at 301-415-7703 to obtain the telephone number and pass code for the August 8, 2013, prehearing conference call. Members of the public or media who wish to listen to this conference call may do so, and should contact Ms. Ellis at the above number for the requisite information.

If the lead representative or lawyer for any party has a previously scheduled concrete conflict that would prevent him or her from participating in the initial scheduling conference call on August 8, 2013, at 9:00 AM EDT, then that party shall consult with the other parties and, on or before July 17, 2013, shall file a motion herein certifying that such a conflict exists and 3

proposing at least two alternative dates and times, acceptable to all parties, for the conference call.

It is so ORDERED.

FOR THE ATOMIC SAFETY AND LICENSING BOARD

/RA/

Alex S. Karlin, Chairman ADMINISTRATIVE JUDGE Rockville, Maryland July 12, 2013 4

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )

)

TENNESSEE VALEY AUTHORITY )

)

SEQUOYAH NUCLEAR PLANT, ) Docket Nos. 50-327-LR and 50-328-LR UNITS 1 AND 2 (License Renewal) )

)

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing ORDER (Scheduling Initial Scheduling Conference) have been served upon the following persons by Electronic Information Exchange.

Office of Commission Appellate U.S. Nuclear Regulatory Commission Adjudication Office of the Secretary of the Commission U.S. Nuclear Regulatory Commission Mail Stop O-16C1 Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail: ocaamail@nrc.gov Hearing Docket E-mail: hearingdocket@nrc.gov U.S. Nuclear Regulatory Commission.

Atomic Safety and Licensing Board Panel Louis A. Zeller Mail Stop T-3F23 Blue Ridge Environmental Defense League Washington, DC 20555-0001 E-mail: bredl@skybest.com Alex S. Karlin, Chairman Administrative Judge Tennessee Valley Authority E-mail: alex.karlin@nrc.gov 400 W Summit Hill Drive, WT 6A-K Knoxville, TN 37902 Dr. Paul B. Abramson Office of the General Counsel Administrative Judge Scott A. Vance, Nuclear Licensing Attorney E-mail: paul.abramson@nrc.gov Edward J. Vigluicci, Associate General Counsel, Nuclear Licensing Dr. Gary S. Arnold Blake Nelson, Attorney Administrative Judge E-mail:

E-mail: gary.arnold@nrc.gov savance@tva.gov ejvigluicci@tva.gov Matthew E. Flyntz, Law Clerk bjnelson@tva.gov E-mail: matthew.flyntz@nrc.gov

2 Docket Nos. 50-327-LR and 50-328-LR ORDER (Scheduling Initial Scheduling Conference)

U.S. Nuclear Regulatory Commission Counsel for Tennessee Valley Authority Office of the General Counsel Pillsbury, Winthrop, Shaw, Pittman, LLP Mail Stop O-15D21 2300 N Street, N.W.

Washington, DC 20555-0001 Washington, DC 20037 Christina England, Esq. Michael G. Lepre, Esq.

Brian Harris, Esq. David Lewis, Esq.

Beth Mizuno, Esq. Robert Ross Mary Spencer, Esq. Maria Webb Edward Williamson, Esg. Email:

Mitzi Young, Esq. michael.lewis@pillsburylaw.com John Tibbetts, Paralegal david.lewis@pillsburylaw.com E-mail: robert.ross@pillsburylaw.com christina.england@nrc.gov maria.webb@pillsburylaw.com brian.harris@nrc.gov beth.mizuno@nrc.gov mary.spencer@nrc.gov john.tibbetts@nrc.gov edward.williamson@nrc.gov mitzi.young@nrc.gov OGC Mail Center: OGCMailCenter@nrc.gov

[Original signed by Clara I. Sola ]

Office of the Secretary of the Commission Dated at Rockville, Maryland, this 12th day of July 2013.