Commission Memorandum and Order (CLI-14-03) Dismissing Both TVA and Bredl'S Petition for Interlocutory Review
ML14043A418
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 02/12/2014
From: Annette Vietti-Cook
NRC/SECY
To:
NRC/OCM
SECY RAS
References
50-327-LR, 50-328-LR, ASLBP 13-927-01-LR-BD01, CLI-14-03, RAS 25577
Download: ML14043A418 (11)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION COMMISSIONERS:

Allison M. Macfarlane, Chairman Kristine L. Svinicki George Apostolakis William D. Magwood, IV William C. Ostendorff

)

In the Matter of )

)

TENNESSEE VALLEY AUTHORITY ) Docket Nos. 50-327-LR &

) 50-328-LR (Sequoyah Nuclear Plant, Units 1 and 2) )

)

CLI-14-03 MEMORANDUM AND ORDER The Tennessee Valley Authority (TVA) and the Blue Ridge Environmental Defense League (BREDL) have appealed the Atomic Safety and Licensing Boards order, LBP-13-8.1 The Board found that BREDL established standing.2 In addition, the Board found seven of BREDLs proposed contentions inadmissible, but held in abeyance a contention raising waste confidence matters. As a result, the Board neither granted nor denied the hearing request.3 As discussed in more detail below, because the intervention petition has not been fully ruled upon 1

LBP-13-8, 78 NRC 1 (2013).

2 Id. at 5.

3 Id.

by the Board, LBP-13-8 is not yet ripe for appeal. We dismiss the appeals as premature and provide further guidance with respect to the pending waste confidence contention.

I. BACKGROUND This matter involves TVAs license renewal application for two units on the Sequoyah site, located in Soddy-Daisy, Tennessee. The renewed operating licenses, if issued, would authorize TVA to operate Sequoyah Units 1 and 2 for an additional twenty years beyond the period specified in the current licenses, which expire on September 17, 2020, and September 15, 2021, respectively.4 Following publication of a notice of opportunity to request a hearing and petition for leave to intervene on TVAs license renewal application, BREDL filed an intervention petition and hearing request, submitting eight proposed contentions.5 The Board concluded that BREDL demonstrated standing.6 The Board rejected seven of BREDLs contentions and held that a portion of one, related to waste confidence, should be held in abeyance.7 4

Tennessee Valley Authority; Notice of Acceptance for Docketing of Application and Notice of Opportunity for Hearing Regarding Renewal of Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77, DPR-79 for an Additional 20-Year Period, 78 Fed. Reg.

14,362, 14,362-63 (Mar. 5, 2013).

5 See id.; Petition for Leave to Intervene and Request for Hearing by the Blue Ridge Environmental Defense League, Bellefonte Efficiency and Sustainability Team, and Mothers Against Tennessee River Radiation (May 6, 2013) (BREDL Intervention Petition).

6 LBP-13-8, 78 NRC at 5. The Board also found that two subsets of BREDL, Bellefonte Efficiency and Sustainability Team and Mothers Against Tennessee River Radiation, had not made sufficient showings to demonstrate standing. Id. BREDL did not challenge these two standing determinations. See Petition for Interlocutory Review by the Blue Ridge Environmental Defense League and Chapter Bellefonte Efficiency and Sustainability Team, and Mothers Against Tennessee River Radiation (July 30, 2013), at 1 n.1 (BREDL Petition).

7 LBP-13-8, 78 NRC at 5. Contention B asserts that NRC cannot grant the Sequoyah license renewal without conducting a thorough analysis of the risks of the long-term storage of irradiated nuclear fuel generated by Sequoyah Units 1 and 2. Id. at 15 (quoting BREDL (continued . . .)

Regarding waste confidence, last year the U.S. Court of Appeals for the District of Columbia Circuit found that the NRC failed to comply with the National Environmental Policy Act in issuing its 2010 update to the Waste Confidence Decision and accompanying Temporary Storage Rule.8 The court vacated both the Decision and the Rule and remanded the case to the agency.9 Shortly thereafter, in the Calvert Cliffs decision, we responded to a series of petitions to suspend final licensing decisions in twenty-two reactor licensing proceedings.10 Because waste confidence undergirds certain agency licensing decisions, we held that the NRC should not issue licenses affected by the Waste Confidence Decision until the remanded issues are resolved.11 At that time, we and the licensing boards also had received several new contentions and associated filings concerning waste confidence.12 In view of the special circumstances presented by waste confidence, we directed that those contentionsand any related contentions filed in the near termbe held in abeyance pending our further order.13 In the instant case, the Board reasoned that the environmental portion of BREDLs waste confidence contention is substantially similar to the petitions that we responded to in the

(. . . continued)

Intervention Petition at 12). The Board rejected the safety portion of Contention B: To the extent that Contention B asserts that New York v. NRC undermines or invalidates the safety portion of the [License Renewal Application] for Sequoyah, we reject it. Id. at 16.

8 New York v. NRC, 681 F.3d 471, 473 (D.C. Cir. 2012).

9 Id.

10 Calvert Cliffs Nuclear Project, LLC (Calvert Cliffs Nuclear Power Plant, Unit 3), CLI-12-16, 76 NRC 63, 63-65 (2012).

11 Id. at 66-67.

12 Id. at 67 & n.10.

13 Id. at 68-69.

Calvert Cliffs decision.14 Accordingly, the Board held the contention in abeyance and, as a result, neither granted nor denied BREDLs request for a hearing.15 II. DISCUSSION Both TVA and BREDL now appeal the Board order pursuant to 10 C.F.R. § 2.311.16 TVA argues that the Board should have dismissed the waste confidence contention in its entirety, and therefore, BREDLs petition to intervene and request for hearing should have been wholly denied.17 BREDL requests that we review LBP-13-8 and grant its request for a hearing and petition to intervene.18 The Staff opposes both petitions for review; TVA opposes BREDLs petition for review.19 As an initial procedural matter, TVA seeks to reply to the Staffs answer, while the Staff opposes TVAs request.20 As TVA acknowledges, section 2.311 does not provide for the filing 14 LBP-13-8, 78 NRC at 16 (citing Calvert Cliffs, CLI-12-16, 76 NRC at 63).

15 Id. at 5, 16.

16 Tennessee Valley Authoritys Notice of Appeal of LBP-13-08 (July 30, 2013); BREDL Petition.

17 Tennessee Valley Authoritys Brief in Support of Appeal of LBP-13-08 (July 30, 2013), at 1 (TVA Brief).

18 BREDL Petition at 1.

19 NRC Staff Brief in Opposition to Tennessee Valley Authority Petition for Review of LBP-13-08 (Aug. 26, 2013) (Staff Answer to TVA Appeal); NRC Staff Brief in Opposition to Blue Ridge Environmental Defense League, Bellefonte Efficiency and Sustainability Team, and Mothers Against Tennessee River Radiation Petition for Interlocutory Review of LBP-13-08 (Aug. 26, 2013); Tennessee Valley Authoritys Brief in Opposition to BREDLs Appeal of LBP-13-08 (Aug.

26, 2013).

20 Tennessee Valley Authoritys Motion for Leave to Reply to NRC Staff Brief in Opposition to Tennessee Valley Authority Petition for Review of LBP-13-08 (Sept. 5, 2013) (TVA Motion to Reply); Tennessee Valley Authoritys Reply Brief on Appeal of LBP-13-08 (Sept. 5, 2013); NRC Staffs Answer to TVAs Motion for Leave to Reply (Sept. 16, 2013) (Staff Answer to TVA Motion to Reply).

of replies.21 The Staff contends that TVA should have anticipated its arguments that (1) LBP-13-8 is not appealable under 10 C.F.R. § 2.311 and (2) because TVA did not raise the issue before the Board, TVA is foreclosed on appeal from arguing that Calvert Cliffs does not apply here because that decision only applies to contentions then pending or filed soon after its issuance one year ago.22 For its part, TVA argues that it should be allowed to file a reply due to compelling circumstances, including the unusual posture of this case and the unforeseeability of the Staffs arguments.23 We permit filings not otherwise authorized by our rules only where necessity or fairness dictates.24 We are not persuaded that TVA could not reasonably have anticipated the arguments contained in the Staffs brief opposing TVAs appeal. TVA filed its appeal under section 2.311. As an experienced litigant in our proceedings, TVA should reasonably have anticipated that the Staff might challenge its interpretation of section 2.311 in the first instance, particularly given recent Commission case law (discussed infra) clarifying the appealability of Board decisions that only partially disposition a hearing request. More critically, however, the 21 TVA Motion to Reply at 1; All Operating Boiling Water Reactor Licensees with Mark I and Mark II Containments: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents, CLI-13-2, 77 NRC 39, 44 n.20 (2013); Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), CLI-12-6, 75 NRC 352, 360 n.36 (2012).

22 Staff Answer to TVA Appeal at 14-15.

23 TVA Motion to Reply at 1-2.

24 Entergy Nuclear Operations, Inc. (Indian Point, Units 2 and 3), CLI-11-14, 74 NRC 801, 807 (2011) (citing U.S. Department of Energy (High-Level Waste Repository), CLI-08-12, 67 NRC 386, 393 (2008); AmerGen Energy Co., LLC (Oyster Creek Nuclear Generating Station),

CLI-08-28, 68 NRC 658, 677 (2008)).

record reflects that TVA was aware of the potential applicability of Calvert Cliffs to this matter.25 Because this very issue was raised earlier in this proceeding, TVA cannot claim surprise at the Staffs argument that it is precluded from raising the inapplicability of Calvert Cliffs for the first time on appeal.26 TVA has not shown that it could not have addressed these issues in its appeal, nor has it presented genuinely new information in its reply; therefore, neither necessity nor fairness dictates that its reply should be permitted.27 Moreover, we find that the arguments raised in TVAs reply are not necessary for our decision in this case. We therefore deny TVAs Motion to Reply.28 With respect to the appeals of the Board order, Section 2.311 of our rules of practice permits an appeal as of right from a boards ruling on an intervention petition in two limited circumstances: (1) upon the denial of a petition to intervene and/or request for hearing, on the question as to whether it should have been granted; or (2) upon the granting of a petition to 25 See Transcript (Scheduling Teleconference) (Aug. 8, 2013), at 46-47 (Judge Karlins exchange with TVA counsel on the potential applicability of Calvert Cliffs).

26 See Staff Answer to TVA Motion to Reply at 7 (citing Tr. at 46-47).

27 See Pilgrim, CLI-12-6, 75 NRC at 374 n.138. For the same reasons, even if TVAs reply were considered under our motions rule that it cites, 10 C.F.R. § 2.323(c), it would not satisfy the compelling circumstances standard.

28 BREDL replied to TVAs answer. Reply of the Blue Ridge Environmental Defense League (Sept. 5, 2013). TVA does not oppose BREDLs reply, but that reply likewise is not contemplated by our rules. BREDL does not address why its reply is proper, but even had BREDL done so, it would not have satisfied our standard. BREDLs reply does not raise new information or arguments that it could not have made when it filed its petition for review, and, as the reply relates to the merits of its appeal, which we do not reach today, it does not provide information necessary for our decision. As such, we likewise reject BREDLs reply.

We also note that BREDL did not submit its reply via the agencys E-filing system, as required by 10 C.F.R. § 2.302, nor did it seek an exemption from that rule. We remind adjudicatory participants that electronic filing is required unless we grant an exemption permitting an alternative filing method for good cause shown, or unless the filing falls within the scope of the exception identified in 10 C.F.R. § 2.302(g)(1).

intervene and/or request for hearing, on the question as to whether it should have been wholly denied.29 This limited interlocutory appeal right attaches only when the Board has fully ruled on the initial intervention petitionthat is, when it has admitted or rejected all proposed contentions. In South Texas and Catawba, we addressed circumstances similar to those herewhere a Board has ruled only partially on an initial intervention petition.30 These cases demonstrate that a Board must rule on all pending contentions before an appeal may be lodged pursuant to section 2.311(c) or (d)(1).31 Consistent with these cases, because the Board explicitly neither granted nor denied BREDLs hearing request and neither admitted nor denied BREDLs waste confidence contention, neither TVAs nor BREDLs appeal is yet ripe.32 We 29 See 10 C.F.R. § 2.311(c), (d)(1). An appeal of an order selecting a hearing procedure also is governed by section 2.311, on the question as to whether the selection of the particular hearing procedures was in clear contravention of the criteria set forth in § 2.310. 10 C.F.R. § 2.311(e).

That provision is not at issue here.

30 South Texas Project Nuclear Operating Co. (South Texas Project, Units 3 and 4), CLI-09-18, 70 NRC 859 (2009); Duke Energy Corp. (Catawba Nuclear Station, Units 1 and 2), CLI-04-11, 59 NRC 203 (2004)). In these cases, the Boards found that the petitioners had standing and had submitted at least one admissible contention but did not rule on all of the outstanding contentions. South Texas Project, CLI-09-18, 70 NRC at 860; Catawba, CLI-04-11, 59 NRC at 205-207.

31 South Texas Project, CLI-09-18, 70 NRC at 862; Catawba, CLI-04-11, 59 NRC at 208 ([F]or a hearing petitioner to take an appeal pursuant to section 2.714a(b) [now section 2.311(c)], the petitioner must claim that, after considering all pending contentions, the Board has erroneously denied a hearing. And for a license applicant . . . to take an appeal under the counterpart regulation, section 2.714a(c) [now section 2.311(d)(1)], the applicant must contend that, after considering all pending contentions, the Board has erroneously granted a hearing to the petitioner.); see Changes to Adjudicatory Process, 69 Fed. Reg. 2182, 2218 (Jan. 14, 2004)

(Table 2 - Cross-References Between Old Provisions of Subpart G and New Subpart C); see also Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), CLI-07-2, 65 NRC 10, 11 (2007) (citing AmerGen Energy Co., LLC (Oyster Creek Nuclear Generating Station), CLI-06-24, 64 NRC 111, 119 (2006); Exelon Generation Co., LLC (Early Site Permit for Clinton ESP Site), CLI-04-31, 60 NRC 461, 468 (2004);

Catawba, CLI-04-11, 59 NRC at 208).

32 See LBP-13-8, 78 NRC at 5.

therefore dismiss those appeals without prejudice. Once the Board has finally dispositioned BREDLs intervention petition, TVA and BREDL may re-submit their appeals, as appropriate, consistent with the applicable rules.33 We do, however, take this opportunity to provide additional guidance on the question of the pending waste confidence contentionafter all, it was our direction in Calvert Cliffs that led the Board to rule only partially on BREDLs intervention petition. We issued Calvert Cliffs shortly after the court vacated our 2010 Waste Confidence Decision and Temporary Storage Rule.34 TVA correctly observes that, at that time, we had not set a course of action in response to the remand. Consistent with our direction in Calvert Cliffs to hold contentions related to waste confidence in abeyance, the Board correctly held the environmental portion of Contention B in abeyance.

Since the issuance of that decision, we have directed the Staff to proceed with development of a generic environmental impact statement and complete a final rule and environmental impact statement by Fall 2014.35 We will provide further direction regarding 33 We observe that, in its decision, the Board did note that its order was subject to appeal in accordance with the provisions of 10 C.F.R. § 2.311. Id. at 35. The Boards reference serves as a useful convenience to the participants, in that it advises them of the potentially applicable appeal provision. But the Boards reference does not guarantee an immediate automatic appeal; the rules requirements still must be satisfied.

34 See Calvert Cliffs, CLI-12-16, 76 NRC at 66.

35 See Staff RequirementsCOMSECY-12-0016Approach for Addressing Policy Issues Resulting from Court Decision to Vacate Waste Confidence Decision and Rule (Sept. 6, 2012)

(ADAMS accession number ML12250A032). We have since approved publication of a proposed rule and a draft Generic Environmental Impact Statement. See Staff Requirements SECY-13-0061Proposed Rule: Waste ConfidenceContinued Storage of Spent Nuclear Fuel (RIN 3150-AJ20) (Aug. 5, 2013) (ML13217A358); Waste ConfidenceContinued Storage of Spent Nuclear Fuel, 78 Fed. Reg. 56,776 (Sept. 13, 2013); Draft Waste Confidence Generic Environmental Impact Statement, 78 Fed. Reg. 56,621 (Sept. 13, 2013).

pending waste confidence contentions concurrent with issuance of the final rule. Thereafter, following the issuance of the Boards final dispositive decision in this matter, and consistent with our procedural rules, TVA and BREDL will have the opportunity to appeal the Boards decisions.36 In the meantime, the direction we provided in Calvert Cliffs remains in place.

III. CONCLUSION For the reasons set forth above, we dismiss both TVAs appeal and BREDLs petition for interlocutory review, without prejudice to their ability to appeal the Boards rulings following the issuance of the Boards final dispositive decision in this matter.

IT IS SO ORDERED.

For the Commission NRC SEAL

/RA/

Annette L. Vietti-Cook Secretary of the Commission Dated at Rockville, Maryland, this 12th day of February, 2014.

36 See South Texas Project Nuclear Operating Co. (South Texas Project, Units 3 and 4),

CLI-10-16, 71 NRC 486, 491 (2010) (citing 10 C.F.R. § 2.341(a), (b); Crow Butte Resources, Inc. (In Situ Leach Facility, Crawford, Nebraska), CLI-09-9, 69 NRC 331, 365 & n.180 (2009)).

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )

)

TENNESSEE VALLEY AUTHORITY )

)

SEQUOYAH NUCLEAR PLANT, ) Docket Nos. 50-327-LR and 50-328-LR UNITS 1 AND 2 (License Renewal) )

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing COMMISSION MEMORANDUM AND ORDER (CLI-14-03) have been served upon the following persons by Electronic Information Exchange.

Office of Commission Appellate U.S. Nuclear Regulatory Commission Adjudication Office of the Secretary of the Commission U.S. Nuclear Regulatory Commission Mail Stop O-16C1 Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail: ocaamail@nrc.gov Hearing Docket E-mail: hearingdocket@nrc.gov U.S. Nuclear Regulatory Commission.

Atomic Safety and Licensing Board Panel Louis A. Zeller Mail Stop T-3F23 Blue Ridge Environmental Defense League Washington, DC 20555-0001 E-mail: bredl@skybest.com Alex S. Karlin, Chairman Administrative Judge Tennessee Valley Authority E-mail: alex.karlin@nrc.gov 400 W Summit Hill Drive, WT 6A-K Knoxville, TN 37902 Dr. Paul B. Abramson Office of the General Counsel Administrative Judge Scott A. Vance, Nuclear Licensing Attorney E-mail: paul.abramson@nrc.gov Blake Nelson, Attorney E-mail:

Dr. Gary S. Arnold savance@tva.gov Administrative Judge bjnelson@tva.gov E-mail: gary.arnold@nrc.gov

2 Docket Nos. 50-327-LR and 50-328-LR COMMISSION MEMORANDUM AND ORDER (CLI-14-03)

U.S. Nuclear Regulatory Commission Counsel for Tennessee Valley Authority Office of the General Counsel Pillsbury, Winthrop, Shaw, Pittman, LLP Mail Stop O-15D21 2300 N Street, N.W.

Washington, DC 20555-0001 Washington, DC 20037 Christina England, Esq. Michael G. Lepre, Esq.

Brian Harris, Esq. David Lewis, Esq.

Beth Mizuno, Esq. Robert Ross Mary Spencer, Esq. Maria Webb Edward Williamson, Esq. Email:

Mitzi Young, Esq. michael.lewis@pillsburylaw.com John Tibbetts, Paralegal david.lewis@pillsburylaw.com E-mail: robert.ross@pillsburylaw.com christina.england@nrc.gov maria.webb@pillsburylaw.com brian.harris@nrc.gov beth.mizuno@nrc.gov mary.spencer@nrc.gov john.tibbetts@nrc.gov edward.williamson@nrc.gov mitzi.young@nrc.gov OGC Mail Center: OGCMailCenter@nrc.gov

[Original signed by Clara Sola ]

Office of the Secretary of the Commission Dated at Rockville, Maryland, this 12th day of February 2014