ML021620166

From kanterella
Jump to navigation Jump to search
Memorandum Stating That the Decision the Licensing Board Had Hoped to Issue in May, on Intervention Petitions Will Now Be Issued by July 3, 2002
ML021620166
Person / Time
Site: Watts Bar, Sequoyah  Tennessee Valley Authority icon.png
Issue date: 06/07/2002
From: Moore T
Atomic Safety and Licensing Board Panel
To:
Byrdsong A T
References
+adjud/ruledam200506, 50-327-OLA, 50-328-OLA, 50-390-OLA, ASLBP 02-796-01-OLA, RAS 4505
Download: ML021620166 (3)


Text

RAS 4505 UNITED STATES OF AMERICA DOCKETED 06/07/02 NUCLEAR REGULATORY COMMISSION SERVED 06/07/02 ATOMIC SAFETY AND LICENSING BOARD Before Administrative Judges:

Thomas S. Moore, Chairman Dr. Peter S. Lam Dr. Thomas S. Elleman In the Matter of Docket Nos. 50-327-OLA, 50-328-OLA, 50-390-OLA TENNESSEE VALLEY AUTHORITY ASLBP No. 02-796-01-OLA (Sequoyah Nuclear Plant, Units 1 & 2; Watts Bar Nuclear Plant, Unit 1) June 7, 2002 MEMORANDUM The Licensing Board had hoped to issue a decision by the end of May ruling on the intervention petitions filed in this consolidated proceeding. The conflicting schedules of the judges on the Board, however, have made that impossible. It now appears that the Boards decision will be delayed until the first week of July. Judge Elleman, a part-time member of the Atomic Safety and Licensing Board Panel and a member of this Board, is on extended travel and is unavailable until after June 25. Judge Lam, as a member of the Private Fuel Storage Licensing Board, has been in a hearing in Salt Lake City, and his duties in that proceeding have made him unavailable. Accordingly, barring any additional unforeseen eventualities, the Licensing Boards decision on the intervention petitions will be issued by July 3, 2002.

FOR THE ATOMIC SAFETY AND LICENSING BOARD1

/RA/

Thomas S. Moore ADMINISTRATIVE JUDGE Rockville, Maryland June 7, 2002 1

Copies of this Memorandum were sent this date by Internet e-mail or facsimile transmission to (1) GANE; (2) BREDL; (3) DCS; and (4) the NRC Staff.

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )

)

TENNESSEE VALLEY AUTHORITY ) Docket Nos. 50-327-OLA, 50-328-OLA,

) and 50-390-OLA (Sequoyah Nuclear Plant, Units 1 & 2 and )

Watts Bar Nuclear Plant, Unit 1) )

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing LB MEMORANDUM DATED JUNE 7, 2002 have been served upon the following persons by U.S. mail, first class, or through NRC internal distribution.

Office of Commission Appellate Administrative Judge Adjudication Thomas S. Moore, Chair U.S. Nuclear Regulatory Commission Atomic Safety and Licensing Board Panel Washington, DC 20555-0001 Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Administrative Judge Administrative Judge Peter S. Lam Thomas S. Elleman Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel Mail Stop - T-3 F23 Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Washington, DC 20555-0001 Steven R. Hom, Esq. Ann Pickel Harris, Director Antonio Fernández, Esq. We The People, Inc., Tennessee Jared K. Heck, Esq. 341 Swing Loop Road Office of the General Counsel Rockwood, TN 37854 Mail Stop - O-15 D21 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Donald J. Moniak Jeannine Honicker Blue Ridge Environmental Defense League 704 Camellia Dr.

P.O. Box 3487 LaGrange, GA 30240 Aiken, SC 29802

2 Docket Nos. 50-327-OLA, 50-328-OLA, and 50-390-OLA LB MEMORANDUM DATED JUNE 7, 2002 Edward J. Vigluicci, Esq. David A. Repka, Esq.

Harriet A. Cooper, Esq. Kathryn M. Sutton, Esq.

Tennessee Valley Authority Winston & Strawn 400 West Summit Hill Drive 1400 L Street, NW Knoxville, TN 37902-1499 Washington, DC 20005

[Original signed by Evangeline S. Ngbea]

Office of the Secretary of the Commission Dated at Rockville, Maryland, this 7th day of June 2002