{{#Wiki_filter:2013 NRC In-Plant i: START AND LOAD THE DIESEL GENERATOR DURING CONTROL ROOM EVACUATIONCANDIDATE:EXAMINER:3 000-068-05-01SIMULATE20NODiesel started, field flashed, power is supplied to 1DA.PLANTTIME START:TIME FINISH:SAT:UNSAT:PERFORMANCE TIME:SIGNATUREDATE45.a.8PERFORM CONTROL ROOM EVACUATIONTOOLS:AOP-600.1, CONTROL ROOM EVACUATION, Attachment 3, LOCAL STARTING AND LOADING DIESEL GENERATOR A(B)CRS notified of 1DA status.
{{#Wiki_filter:V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO:        JPPF-013A 2013 NRC In-Plant i: START AND LOAD THE DIESEL GENERATOR DURING CONTROL ROOM EVACUATION APPROVAL:            APPROVAL DATE:
The CRS directs you to start the "A" Diesel Generator in accordance with AOP-600.1, Attachment 3, LOCAL STARTING AND LOADING DIESEL GENERATOR A(B)A control room evacuation has occurred. You as the BOP just completed AOP-600.1 Attachment 2, DUTIES OF THE BOP OPERATOR. During performance of the Attachment you determined that power was not available to 1DA.This JPM should only be run on a "A" train maintenance week and when the diesel rooms are not marked off as restricted areas due to EOOS. If it is a "B" train maintenance week use JPPF-013B.WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
REV NO: 3 CANDIDATE:
EXAMINER:
Saturday, August 03, 2013                                            Page 1 of 14


Ensure both of the following breakers are open (IB-463): XSW1DA 01, BUS 1DA NORMAL INCOMING BKR. XSW1DA 15, BUS 1DA EMERG INCOMING BKR.Evaluator Cue: Cue examinee that green light is lit and red light is off for XSW1DA 01, BUS 1DA NORMAL INCOMING BKR and XSW1DA 15, BUS 1DA EMERG INCOMING BKR.
TASK:
YesVerifies green light lit and red light off for both incoming breakers.No1Determine the cause of Diesel Generator start failure:Check alarms and indications at the local DG Control Panel. REFER TO ARP-004-XCX-5201.Verify problems found will NOT prevent starting the DG.Evaluator Cue: When asked which alarms are present on XCX-5201 report that no annunciators are in alarm.
000-068-05-01              PERFORM CONTROL ROOM EVACUATION TASK STANDARD:
YesDetermines that alarms do not indicate a problem that has to be fixed to start generator.No2 Place REMOTE/LOCAL/MAINT Switch in LOCAL.Evaluator Cue: When switch is taken to local indicate that XCX-5201 6-5, LOCAL CONTROL goes into alarm.
Diesel started, field flashed, power is supplied to 1DA.
YesREMOTE/LOCAL/MAINT Switch in LOCAL.Yes3Ensure the VOLT REG is in AUTO.Examiner Cue: Cue examinee that VOLT REG switch is in AUTO.
TERMINATING CUE:              CRS notified of 1DA status.
YesVerifies VOLT REG switch is in AUTO.No4 Depress the following reset pushbuttons: GEN RELAYS RESET. EXCITER RESET.Evaluator Cue: Cue applicant that there are no changes to indications.
PREFERRED EVALUATION LOCATION                                PREFERRED EVALUATION METHOD PLANT                                                        SIMULATE
YesDepresses GEN RELAYS RESET and EXCITER RESET.No5Attempt to start the Diesel Generator by depressing the ENGINE SHUT DOWN RESET Pushbutton.Examiner Cue: When button is pushed indicate that there are no change in indications.
 
YesENGINE SHUT DOWN RESET is pushed. When cued that there is no response, goes to step 9 as an alternative action.No6 Attempt to start the Diesel Generator:Momentarily depress the EMERG START Pushbutton. Verify the Diesel starts and accelerates to 514 rpm.Evaluator Cue: Cue applicant that there is no change in indications when button is pressed.
==REFERENCES:==
YesPushes EMERG START Pushbutton and notices that Diesel does not start. Goes to alternative action.No7
 
: b. Attempt to start the Diesel using the Main Air Start Valve:1) Using the attached spanner wrench, depress and hold the pushbutton on one of the following for five seconds (located at either end of the Diesel):
TOOLS:            AOP-600.1, CONTROL ROOM EVACUATION, Attachment 3, LOCAL STARTING AND LOADING DIESEL GENERATOR A(B)
EVALUATION TIME                      20          TIME CRITICAL    NO    10CFR55: 45.a.8 TIME START:                          TIME FINISH:                PERFORMANCE TIME:
PERFORMANCE RATING:                  SAT:            UNSAT:
CANDIDATE:
EXAMINER:
SIGNATURE          DATE Saturday, August 03, 2013                                                              Page 2 of 14
 
INSTRUCTIONS TO OPERATOR READ TO OPERATOR:
WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
SAFETY CONSIDERATIONS:                This JPM should only be run on a "A" train maintenance week and when the diesel rooms are not marked off as restricted areas due to EOOS. If it is a "B" train maintenance week use JPPF-013B.
INITIAL CONDITION: A control room evacuation has occurred. You as the BOP just completed AOP-600.1 Attachment 2, DUTIES OF THE BOP OPERATOR. During performance of the Attachment you determined that power was not available to 1DA.
INITIATING CUES: The CRS directs you to start the "A" Diesel Generator in accordance with AOP-600.1, Attachment 3, LOCAL STARTING AND LOADING DIESEL GENERATOR A(B)
HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!
AT NO TIME ARE YOU TO OPERATE ANY PLANT EQUIPMENT!
FOR ELECTRICAL MANIPULATIONS, AT NO TIME ARE YOU TO BREAK THE PLANE OF THE ELECTRICAL PANEL!
Saturday, August 03, 2013                                                                    Page 3 of 14
 
STEPS CRITICAL:          No        SEQUENCED: Yes                          SAT          UNSAT STEP:      1 Ensure both of the following breakers are open (IB-463):
XSW1DA 01, BUS 1DA NORMAL INCOMING BKR.
XSW1DA 15, BUS 1DA EMERG INCOMING BKR.
STEP STANDARD:
Verifies green light lit and red light off for both incoming breakers.
CUES:
Evaluator Cue: Cue examinee that green light is lit and red light is off for XSW1DA 01, BUS 1DA NORMAL INCOMING BKR and XSW1DA 15, BUS 1DA EMERG INCOMING BKR.
COMMENTS:
CRITICAL:          No        SEQUENCED: Yes                          SAT          UNSAT STEP:      2 Determine the cause of Diesel Generator start failure:
Check alarms and indications at the local DG Control Panel. REFER TO ARP-004-XCX-5201.
Verify problems found will NOT prevent starting the DG.
STEP STANDARD:
Determines that alarms do not indicate a problem that has to be fixed to start generator.
CUES:
Evaluator Cue: When asked which alarms are present on XCX-5201 report that no annunciators are in alarm.
COMMENTS:
Saturday, August 03, 2013                                                                    Page 4 of 14
 
CRITICAL:        Yes  SEQUENCED: Yes                          SAT          UNSAT STEP:      3 Place REMOTE/LOCAL/MAINT Switch in LOCAL.
STEP STANDARD:
REMOTE/LOCAL/MAINT Switch in LOCAL.
CUES:
Evaluator Cue: When switch is taken to local indicate that XCX-5201 6-5, LOCAL CONTROL goes into alarm.
COMMENTS:
CRITICAL:          No  SEQUENCED: Yes                          SAT          UNSAT STEP:      4 Ensure the VOLT REG is in AUTO.
STEP STANDARD:
Verifies VOLT REG switch is in AUTO.
CUES:
Examiner Cue: Cue examinee that VOLT REG switch is in AUTO.
COMMENTS:
Saturday, August 03, 2013                                                              Page 5 of 14
 
CRITICAL:          No      SEQUENCED: Yes                        SAT            UNSAT STEP:      5 Depress the following reset pushbuttons:
GEN RELAYS RESET.
EXCITER RESET.
STEP STANDARD:
Depresses GEN RELAYS RESET and EXCITER RESET.
CUES:
Evaluator Cue: Cue applicant that there are no changes to indications.
COMMENTS:
CRITICAL:          No      SEQUENCED: Yes                        SAT            UNSAT STEP:      6 Attempt to start the Diesel Generator by depressing the ENGINE SHUT DOWN RESET Pushbutton.
STEP STANDARD:
ENGINE SHUT DOWN RESET is pushed. When cued that there is no response, goes to step 9 as an alternative action.
CUES:
Examiner Cue: When button is pushed indicate that there are no change in indications.
COMMENTS:
Saturday, August 03, 2013                                                                Page 6 of 14
 
CRITICAL:          No      SEQUENCED: Yes                          SAT            UNSAT STEP:      7 Attempt to start the Diesel Generator:
Momentarily depress the EMERG START Pushbutton.
Verify the Diesel starts and accelerates to 514 rpm.
STEP STANDARD:
Pushes EMERG START Pushbutton and notices that Diesel does not start. Goes to alternative action.
CUES:
Evaluator Cue: Cue applicant that there is no change in indications when button is pressed.
COMMENTS:
Saturday, August 03, 2013                                                                    Page 7 of 14
 
CRITICAL:        Yes      SEQUENCED: Yes                        SAT            UNSAT STEP:      8
: b. Attempt to start the Diesel using the Main Air Start Valve:
: 1) Using the attached spanner wrench, depress and hold the pushbutton on one of the following for five seconds (located at either end of the Diesel):
XVM10996A-DG, DIESEL GEN A MAIN AIR START VALVE A.
XVM10996A-DG, DIESEL GEN A MAIN AIR START VALVE A.
ORXVM10996B-DG, DIESEL GEN A MAIN AIR START VALVE B.
OR XVM10996B-DG, DIESEL GEN A MAIN AIR START VALVE B.
: 2) Verify the Diesel starts and accelerates to 514 rpm.Evaluator Cue: Cue applicant that diesel is heard to start. Cue that RPM's indicate 514 rpm if meter is observed.
: 2) Verify the Diesel starts and accelerates to 514 rpm.
YesUses spanner wrench to push on one of the air start valves. Verifies that diesel accelerates to 514 rpm.Yes8Verify the Generator voltage indication increased to between 6800 Volts and 7600 Volts.Examiner Cue: Cue applicant that voltage remains at 0 volts.
STEP STANDARD:
YesDetermines that voltage has remained at 0 volts and goes to alternate action.No9 Perform a manual field flash:1) Momentarily place FIELD FLASH Switch to FLASH.2) Verify Generator voltage increases to between 6800 Volts and 7600 Volts.Examiner Cue: Cue applicant that voltage has increased to 7200 volts.
Uses spanner wrench to push on one of the air start valves. Verifies that diesel accelerates to 514 rpm.
YesPlaces FIELD FLASH Switch to FLASH. Verifies generator voltage increase to 7200 volts.Yes10Depress the EMERG START RESET Pushbutton.
CUES:
Evaluator Cue: Cue applicant that EMERG START light at top of board goes from lit to off.
Evaluator Cue: Cue applicant that diesel is heard to start. Cue that RPM's indicate 514 rpm if meter is observed.
YesEMERG START RESET Pushbutton depressed.No11 Reset all annunciators on XCX5201.Evaluator Cue: Cue applicant that only alarm in is 6-5, LOCAL CONTROL, before and after reset is pressed.Evaluator Note: Because there are no annunciators to reset the applicant may not press the reset pushbutton.
COMMENTS:
YesPresses reset on XCX5201.No12Procedure Caution: If any DG annunciator will NOT reset, it should be evaluated by the Shift Supervisor prior to performing Step 12, since it may cause the DG or its output breaker to trip.Depress the TEST START Pushbutton.Evaluator Cue: Cue applicant that there is no change in indication after button is depressed.
CRITICAL:          No      SEQUENCED: Yes                        SAT            UNSAT STEP:      9 Verify the Generator voltage indication increased to between 6800 Volts and 7600 Volts.
YesTEST START Pushbutton depressed.No13 Ensure BUS 1DA DG FEED is closed.Evaluator Cue: Cue applicant that BUS 1DA DG FEED indicates red light lit, green light off and voltage is 7200 KV on 1DA.
STEP STANDARD:
YesVerifies BUS 1DA DG FEED indicates red light lit, green light off and voltage is indicated on 1DA.No14Adjust Generator voltage to 7200 Volts using the AUTO VOLT CNTRL Switch.Evaluator Cue: Cue applicant that voltage is at 7200 volts. If AUTO VOLT CNTRL Switch is used indicate changing voltages.Evaluator Note:  This voltage band is that required for steady state operation in accordance with TSR 1068.YesGenerator Voltage is between 6840 and 7445 Volts.No15 Examiner ends JPM at this point.Adjust Generator frequency to 60 Hertz using the GOVERNOR Switch.Evaluator Cue:  Cue applicant that frequency is at 60 Hz. If the GOVERNOR Switch is used indicate changing frequency.Evaluator Note:  This frequency band is that required for steady state operation in accordance with TSR 1068.
Determines that voltage has remained at 0 volts and goes to alternate action.
YesGenerator frequency is 60 +/-0.6 Hz.No16Notify the Control Room Supervisor at the CREP of DG status.Evaluator Note: Cue applicant that CRS understands that the diesel is started and at normal operating voltage and frequency and that the BOP should report to the CREP and the intermediate building operator will take over operation of the diesel.
CUES:
YesNotifies CRS.No17 JPPF-013A2013 NRC In-Plant i: START AND LOAD THE DIESEL GENERATOR DURING CONTROL ROOM EVACUATIONN/AThis JPM should only be run on a "A" train maintenance week and when the diesel rooms are not marked off as restricted areas due to EOOS. If it is a "B" train maintenance week use JPPF-013B.
Examiner Cue: Cue applicant that voltage remains at 0 volts.
JPM SETUP SHEET The CRS directs you to start the "A" Diesel Generator in accordance with AOP-600.1, Attachment 3,  LOCAL STARTING AND LOADING DIESEL GENERATOR A(B)A control room evacuation has occurred. You as the BOP just completed AOP-600.1 Attachment 2, DUTIES OF THE BOP OPERATOR. During performance of the Attachment you determined that power was not available to 1DA.
COMMENTS:
2013 NRC In-Plant j: LOCALLY CLOSE AND DE-ENERGIZE MS LOOP "B" AND "C" TO TDEFPCANDIDATE:EXAMINER:2 000-169-05-04SIMULATE20NoTurbine driven emergency feed pump main steam loop "B" and "C" supply valve is manually closed and power removed from 2802A per EOP-3.0.PLANTTIME START:TIME FINISH:SAT:UNSAT:PERFORMANCE TIME:SIGNATUREDATE45.a.8Locally Isolate a Faulted Steam Generator per EOP-3.0.TOOLS:EOP-3.0, STEP 5.h. ALTERNATIVE ACTIONMVG-2802A and MVG-2802B are closed and deenergized per EOP-3.0.EOP-3.0FAULTED STEAM GENERATOR ISOLATION035000A406S/G isolation on steam leak or tube rupture/leak4.54.6A4.06061000K103Main steam system3.53.9K1.03000040A104Isolation of all steam lines from header4.34.3AA1.04000040A110 AFW System4.14.1AA1.10 RO directs you as the IB operator (Unit 7) to open breaker 05EH on XMC1DA2X and locally close valves XVG02802A-MS and XVG02802B-MS in accordance with EOP-3.0, Step 5.h, Alternative Action. The AB operator (Unit 6 upper) has already opened breaker 05EH on XMC1DB2Y. The shift supervisor has approved the waiving of ISP-027 requirements due to the emergency condition.The plant was at 100% power when a steamline break occurred inside containment.  "B" and "C" SGs are faulted as indicated by steam pressure dropping in an uncontrolled manner. The CRS has implemented EOP-3.0, FAULTED STEAM GENERATOR ISOLATION, out of EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION, following a Automatic SI. Both motor driven emergency feedwater pumps started. MVG-2802A, MS LOOP B TO TD EFP and MVG-2802B, MS LOOP C TO TD EFP will not close from the MCB.Burn HazardWHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
Saturday, August 03, 2013                                                                      Page 8 of 14
 
CRITICAL:        Yes    SEQUENCED: Yes                        SAT            UNSAT STEP:      10 Perform a manual field flash:
: 1) Momentarily place FIELD FLASH Switch to FLASH.
: 2) Verify Generator voltage increases to between 6800 Volts and 7600 Volts.
STEP STANDARD:
Places FIELD FLASH Switch to FLASH. Verifies generator voltage increase to 7200 volts.
CUES:
Examiner Cue: Cue applicant that voltage has increased to 7200 volts.
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                        SAT            UNSAT STEP:      11 Depress the EMERG START RESET Pushbutton.
STEP STANDARD:
EMERG START RESET Pushbutton depressed.
CUES:
Evaluator Cue: Cue applicant that EMERG START light at top of board goes from lit to off.
COMMENTS:
Saturday, August 03, 2013                                                                  Page 9 of 14
 
CRITICAL:          No    SEQUENCED: Yes                          SAT              UNSAT STEP:      12 Reset all annunciators on XCX5201.
STEP STANDARD:
Presses reset on XCX5201.
CUES:
Evaluator Cue: Cue applicant that only alarm in is 6-5, LOCAL CONTROL, before and after reset is pressed.
Evaluator Note: Because there are no annunciators to reset the applicant may not press the reset pushbutton.
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                          SAT              UNSAT STEP:      13 Procedure Caution: If any DG annunciator will NOT reset, it should be evaluated by the Shift Supervisor prior to performing Step 12, since it may cause the DG or its output breaker to trip.
Depress the TEST START Pushbutton.
STEP STANDARD:
TEST START Pushbutton depressed.
CUES:
Evaluator Cue: Cue applicant that there is no change in indication after button is depressed.
COMMENTS:
Saturday, August 03, 2013                                                                     Page 10 of 14


Locally deenergize and close the appropriate valve. If SG B is faulted:Open XMC1DA2X 05EH, EF PUMP MAIN STEAM BLOCK VLV XVG-2802A-MS (IB-463).Evaluator Note: The only sequence that is important is to open each breaker before closing each valve. If the examinee repositions a valve prior to opening the breaker the JPM is considered unsat.
CRITICAL:          No    SEQUENCED: Yes                            SAT              UNSAT STEP:       14 Ensure BUS 1DA DG FEED is closed.
YesOperator locates the power supply (1DA2X, 05EH) for XVG-02802A and opens the breaker by pullingthe breaker control lever down.Yes1Locally deenergize and close the appropriate valve. If SG C is faulted:
STEP STANDARD:
Open XMC1DB2Y 05EH, EMERG FEEDWATER PUMP MAIN STEAM BLOCK XVG2802B-MS (AB-463).Evaluator Note: The only sequence that is important is to open each breaker before closing each valve. If the examinee repositions a valve prior to opening the breaker the JPM is considered unsat.
Verifies BUS 1DA DG FEED indicates red light lit, green light off and voltage is indicated on 1DA.
YesDetermines that the AB operator has already opened XMC1DB2Y 05EH, EMERG FEEDWATER PUMP MAIN STEAM BLOCK XVG2802B-MS (AB-463).No2 Examiner ends JPM at this point.Close XVG02802A-MS, MS HEADER B EF PUMP TURBINE SUPPLY VLV (IB-436 East Pen).Evaluator Note: The only sequence that is important is to open each breaker before closing each valve. If the examinee repositions a valve prior to opening the breaker the JPM is considered unsat.
CUES:
YesOperator locates and closes XVG02802A-MS by pulling the manual engagement clutch lever down and turning the valve handwheel in the clockwise direction until the valve position arrow of the handwheel points to the right and the handwheel will no longer rotate.Yes3Close XVG02802B-MS, MS HEADER C EF PUMP TURBINE SUPPLY VLV (IB-436 East Pen).Evaluator Note: The only sequence that is important is to open each breaker before closing each valve. If the examinee repositions a valve prior to opening the breaker the JPM is considered unsat.
Evaluator Cue: Cue applicant that BUS 1DA DG FEED indicates red light lit, green light off and voltage is 7200 KV on 1DA.
YesOperator locates and closes XVG02802B-MS by pulling the manual engagement clutch lever down and turning the valve handwheel in the clockwise direction until the valve position arrow of the handwheel points to the right and the handwheel will no longer rotate.Yes4 JPP-107A2013 NRC In-Plant j: LOCALLY CLOSE AND DE-ENERGIZE MS LOOP "B" AND "C" TO TDEFPJPM SETUP SHEET RO directs you as the IB operator (Unit 7) to open breaker 05EH on XMC1DA2X and locally close valves XVG02802A-MS and XVG02802B-MS in accordance with EOP-3.0, Step 5.h, Alternative Action. The AB operator (Unit 6 upper) has already opened breaker 05EH on XMC1DB2Y. The shift supervisor has approved the waiving of ISP-027 requirements due to the emergency condition.The plant was at 100% power when a steamline break occurred inside containment.  "B" and "C" SGs are faulted as indicated by steam pressure dropping in an uncontrolled manner. The CRS has implemented EOP-3.0, FAULTED STEAM GENERATOR ISOLATION, out of EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION, following a Automatic SI. Both motor driven emergency feedwater pumps started. MVG-2802A, MS LOOP B TO TD EFP and MVG-2802B, MS LOOP C TO TD EFP will not close from the MCB.
COMMENTS:
2013 NRC In-Plant k: LOCALLY ISOLATE RCP SEALS DURING A TOTAL LOSS OF ESF POWERCANDIDATE:EXAMINER:3 000-175-05-04SIMULATE15NoSeal injection and return valves for RCP seals have been manually isolated per EOP-6.0 Att 9.PLANTTIME START:TIME FINISH:SAT:UNSAT:PERFORMANCE TIME:SIGNATUREDATE45.a.6 Locally Isolate RCP Seals per EOP-6.0.TOOLS:EOP-6.0, Attachment 9, LOCALLY OPERATED ISOLATION VALVES FLASHLIGHTRCP seals isolated per Att 9 of EOP-6.0.EOP-6.0LOSS OF ALL ESF AC POWER000055K302Actions contained in EOP for loss of offsite and onsite power4.34.6EK3.02 The RO calls and directs you to isolate RCP seals in accordance with Step 1 of Attachment 9 of EOP-6.0, LOCALLY OPERATED ISOLATION VALVES.A total loss of offsite power has occurred and both DG's have failed to start. Alternate Seal injection also failed to start on the loss of power.
CRITICAL:          No    SEQUENCED: Yes                            SAT              UNSAT STEP:      15 Adjust Generator voltage to 7200 Volts using the AUTO VOLT CNTRL Switch.
The CRS has implemented EOP-6.0, LOSS OF ALL ESF AC POWER, and is directing actions for locally isolating RCP seals.MVT-8100 is in the north end of the 412' West Penetration area, which is a Radiation Area. At the discretion of the examiner, have the examinee describe the general location of the valve. Operation of the valve is identical to MVT-8105 and MVG-9606. Ensure to view radiation surveys and to monitor EDs if entering Radiation area.WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
STEP STANDARD:
Generator Voltage is between 6840 and 7445 Volts.
CUES:
Evaluator Cue: Cue applicant that voltage is at 7200 volts. If AUTO VOLT CNTRL Switch is used indicate changing voltages.
Evaluator Note: This voltage band is that required for steady state operation in accordance with TSR 1068.
COMMENTS:
Saturday, August 03, 2013                                                                    Page 11 of 14


Locally isolate RCP Seals by closing the following (EOP-6.0 Step 13):XVT08100-CS, RC PUMP SEAL RETURN HDR ISOL VLV(ORC) (AB-412 West Pen)Evaluator Note: MVT-8100 is in the north end of the 412' West Penetration area, which is a Radiation Area. At the discretion of the examiner, have the examinee describe the general location of the valve. Operation of the valve is identical to MVT-8105 and MVG-9606. Ensure to view radiation surveys and to monitor EDs if entering Radiation area.Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.
CRITICAL:          No      SEQUENCED: Yes                        SAT              UNSAT STEP:      16 Adjust Generator frequency to 60 Hertz using the GOVERNOR Switch.
YesEngages manual handwheel by pressing down on the declutch lever on XVT08100-CS and turns handwheel fully clockwise.Yes1 Locally isolate RCP Seals by closing the following (EOP-6.0 Step 13):XVG09606-CC, RB CC RETURN HEADER VALVE (AB-436 West Pen)Evaluator Cue:  Cue applicant that valve moves in the clockwise direction and then stops.
STEP STANDARD:
YesEngages manual handwheel by pressing down on the declutch lever on XVG09606-CC and turns handwheel fully clockwise.Yes2Locally isolate RCP Seals by closing the following (EOP-6.0 Step 13):XVT08105-CS, SEAL INJECTION HEADER ISOLATION VALVE (AB-436)Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.
Generator frequency is 60 +/-0.6 Hz.
YesEngages manual handwheel by pressing down on the declutch lever on XVT08105-CS and turns handwheel fully clockwise.Yes3 Contact the Control Room to determine if the Alternate Seal Injection System has actuated.Evaluator Cue: If called as the control room reply that Alternate Seal Injection has not been actuated.
CUES:
YesDetermines from initial cue or from calling the control room that Alternate Seal Injection has not actuated and that the alternate action is necessary.No4If the Alternate Seal Injection System has not actuated, close all the following:XVT08102A-CS, RC PUMP A SEAL SUPPLY ISOL VALVE (ORC) (AB-412 West Pen).Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.
Evaluator Cue: Cue applicant that frequency is at 60 Hz. If the GOVERNOR Switch is used indicate changing frequency.
YesEngages manual handwheel by pressing down on the declutch lever on XVT08102A-CS and turns handwheel fully clockwise.Yes5 Examiner ends JPM at this point.If the Alternate Seal Injection System has not actuated, close all the following:XVT08102B-CS, RC PUMP B SEAL SUPPLY ISOL VALVE (ORC) (IB-412 East Pen).Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.Evaluator Note: When validated this valve did not have a CHAMPS tag, but did have a small metal OEM tag.YesEngages manual handwheel by pressing down on the declutch lever on XVT08102B-CS and turns handwheel fully clockwise.Yes6If the Alternate Seal Injection System has not actuated, close all the following:XVT08102C-CS, RC PUMP C SEAL SUPPLY ISOL VALVE (ORC) (IB-412 East Pen).Evaluator Cue:  Cue applicant that valve moves in the clockwise direction and then stops.
Evaluator Note: This frequency band is that required for steady state operation in accordance with TSR 1068.
YesEngages manual handwheel by pressing down on the declutch lever on XVT08102C-CS and turns handwheel fully clockwise.Yes7 JPPF-066A2013 NRC In-Plant k: LOCALLY ISOLATE RCP SEALS DURING A TOTAL LOSS OF ESF POWERJPM SETUP SHEET The RO calls and directs you to isolate RCP seals in accordance with Step 1 of Attachment 9 of EOP-6.0, LOCALLY OPERATED ISOLATION VALVES.A total loss of offsite power has occurred and both DG's have failed to start. Alternate Seal injection also failed to start on the loss of power.
COMMENTS:
CRITICAL:          No      SEQUENCED: Yes                        SAT              UNSAT STEP:      17 Notify the Control Room Supervisor at the CREP of DG status.
STEP STANDARD:
Notifies CRS.
CUES:
Evaluator Note: Cue applicant that CRS understands that the diesel is started and at normal operating voltage and frequency and that the BOP should report to the CREP and the intermediate building operator will take over operation of the diesel.
COMMENTS:
Examiner ends JPM at this point.
Saturday, August 03, 2013                                                                  Page 12 of 14
 
JPM SETUP SHEET JPM NO: JPPF-013A DESCRIPTION:          2013 NRC In-Plant i: START AND LOAD THE DIESEL GENERATOR DURING CONTROL ROOM EVACUATION IC SET: N/A INSTRUCTIONS:
COMMENTS:
This JPM should only be run on a "A" train maintenance week and when the diesel rooms are not marked off as restricted areas due to EOOS. If it is a "B" train maintenance week use JPPF-013B.
Saturday, August 03, 2013                                                                  Page 13 of 14
 
JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:
INITIAL CONDITION: A control room evacuation has occurred. You as the BOP just completed AOP-600.1 Attachment 2, DUTIES OF THE BOP OPERATOR. During performance of the Attachment you determined that power was not available to 1DA.
INITIATING CUES: The CRS directs you to start the "A" Diesel Generator in accordance with AOP-600.1, Attachment 3, LOCAL STARTING AND LOADING DIESEL GENERATOR A(B)
AT NO TIME ARE YOU TO OPERATE ANY PLANT EQUIPMENT!
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
Saturday, August 03, 2013
 
V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO:        JPP-107A 2013 NRC In-Plant j: LOCALLY CLOSE AND DE-ENERGIZE MS LOOP "B" AND "C" TO TDEFP APPROVAL:            APPROVAL DATE:
REV NO: 2 CANDIDATE:
EXAMINER:
Saturday, August 03, 2013                                                Page 1 of 7
 
TASK:
000-169-05-04            Locally Isolate a Faulted Steam Generator per EOP-3.0.
TASK STANDARD:
Turbine driven emergency feed pump main steam loop "B" and "C" supply valve is manually closed and power removed from 2802A per EOP-3.0.
TERMINATING CUE:            MVG-2802A and MVG-2802B are closed and deenergized per EOP-3.0.
PREFERRED EVALUATION LOCATION                                  PREFERRED EVALUATION METHOD PLANT                                                          SIMULATE
 
==REFERENCES:==
EOP-3.0                  FAULTED STEAM GENERATOR ISOLATION INDEX NO.            K/A NO.                                              RO        SRO 035000A406          A4.06    S/G isolation on steam leak or tube        4.5        4.6 rupture/leak 061000K103          K1.03    Main steam system                          3.5        3.9 000040A104          AA1.04    Isolation of all steam lines from header    4.3        4.3 000040A110          AA1.10    AFW System                                  4.1        4.1 TOOLS:            EOP-3.0, STEP 5.h. ALTERNATIVE ACTION EVALUATION TIME                    20          TIME CRITICAL        No    10CFR55: 45.a.8 TIME START:                        TIME FINISH:                    PERFORMANCE TIME:
PERFORMANCE RATING:                  SAT:            UNSAT:
CANDIDATE:
EXAMINER:
SIGNATURE          DATE Saturday, August 03, 2013                                                                    Page 2 of 7
 
INSTRUCTIONS TO OPERATOR READ TO OPERATOR:
WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
SAFETY CONSIDERATIONS:                  Burn Hazard INITIAL CONDITION: The plant was at 100% power when a steamline break occurred inside containment. "B" and "C" SGs are faulted as indicated by steam pressure dropping in an uncontrolled manner. The CRS has implemented EOP-3.0, FAULTED STEAM GENERATOR ISOLATION, out of EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION, following a Automatic SI. Both motor driven emergency feedwater pumps started. MVG-2802A, MS LOOP B TO TD EFP and MVG-2802B, MS LOOP C TO TD EFP will not close from the MCB.
INITIATING CUES: RO directs you as the IB operator (Unit 7) to open breaker 05EH on XMC1DA2X and locally close valves XVG02802A-MS and XVG02802B-MS in accordance with EOP-3.0, Step 5.h, Alternative Action. The AB operator (Unit 6 upper) has already opened breaker 05EH on XMC1DB2Y. The shift supervisor has approved the waiving of ISP-027 requirements due to the emergency condition.
HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!
AT NO TIME ARE YOU TO OPERATE ANY PLANT EQUIPMENT!
FOR ELECTRICAL MANIPULATIONS, AT NO TIME ARE YOU TO BREAK THE PLANE OF THE ELECTRICAL PANEL!
Saturday, August 03, 2013                                                                    Page 3 of 7
 
STEPS CRITICAL:        Yes      SEQUENCED: Yes                          SAT            UNSAT STEP:      1 Locally deenergize and close the appropriate valve. If SG B is faulted:
Open XMC1DA2X 05EH, EF PUMP MAIN STEAM BLOCK VLV XVG-2802A-MS (IB-463).
STEP STANDARD:
Operator locates the power supply (1DA2X, 05EH) for XVG-02802A and opens the breaker by pulling the breaker control lever down.
CUES:
Evaluator Note: The only sequence that is important is to open each breaker before closing each valve. If the examinee repositions a valve prior to opening the breaker the JPM is considered unsat.
COMMENTS:
CRITICAL:          No      SEQUENCED: Yes                          SAT            UNSAT STEP:      2 Locally deenergize and close the appropriate valve. If SG C is faulted:
Open XMC1DB2Y 05EH, EMERG FEEDWATER PUMP MAIN STEAM BLOCK XVG2802B-MS (AB-463).
STEP STANDARD:
Determines that the AB operator has already opened XMC1DB2Y 05EH, EMERG FEEDWATER PUMP MAIN STEAM BLOCK XVG2802B-MS (AB-463).
CUES:
Evaluator Note: The only sequence that is important is to open each breaker before closing each valve. If the examinee repositions a valve prior to opening the breaker the JPM is considered unsat.
COMMENTS:
Saturday, August 03, 2013                                                                      Page 4 of 7
 
CRITICAL:        Yes    SEQUENCED: Yes                            SAT              UNSAT STEP:       3 Close XVG02802A-MS, MS HEADER B EF PUMP TURBINE SUPPLY VLV (IB-436 East Pen).
STEP STANDARD:
Operator locates and closes XVG02802A-MS by pulling the manual engagement clutch lever down and turning the valve handwheel in the clockwise direction until the valve position arrow of the handwheel points to the right and the handwheel will no longer rotate.
CUES:
Evaluator Note: The only sequence that is important is to open each breaker before closing each valve. If the examinee repositions a valve prior to opening the breaker the JPM is considered unsat.
COMMENTS:
CRITICAL:        Yes    SEQUENCED: Yes                            SAT              UNSAT STEP:       4 Close XVG02802B-MS, MS HEADER C EF PUMP TURBINE SUPPLY VLV (IB-436 East Pen).
STEP STANDARD:
Operator locates and closes XVG02802B-MS by pulling the manual engagement clutch lever down and turning the valve handwheel in the clockwise direction until the valve position arrow of the handwheel points to the right and the handwheel will no longer rotate.
CUES:
Evaluator Note: The only sequence that is important is to open each breaker before closing each valve. If the examinee repositions a valve prior to opening the breaker the JPM is considered unsat.
COMMENTS:
Examiner ends JPM at this point.
Saturday, August 03, 2013                                                                        Page 5 of 7
 
JPM SETUP SHEET JPM NO: JPP-107A DESCRIPTION:          2013 NRC In-Plant j: LOCALLY CLOSE AND DE-ENERGIZE MS LOOP "B" AND "C" TO TDEFP IC SET:
INSTRUCTIONS:
COMMENTS:
Saturday, August 03, 2013                                                          Page 6 of 7
 
JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:
INITIAL CONDITION: The plant was at 100% power when a steamline break occurred inside containment. "B" and "C" SGs are faulted as indicated by steam pressure dropping in an uncontrolled manner. The CRS has implemented EOP-3.0, FAULTED STEAM GENERATOR ISOLATION, out of EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION, following a Automatic SI. Both motor driven emergency feedwater pumps started. MVG-2802A, MS LOOP B TO TD EFP and MVG-2802B, MS LOOP C TO TD EFP will not close from the MCB.
INITIATING CUES: RO directs you as the IB operator (Unit 7) to open breaker 05EH on XMC1DA2X and locally close valves XVG02802A-MS and XVG02802B-MS in accordance with EOP-3.0, Step 5.h, Alternative Action. The AB operator (Unit 6 upper) has already opened breaker 05EH on XMC1DB2Y. The shift supervisor has approved the waiving of ISP-027 requirements due to the emergency condition.
AT NO TIME ARE YOU TO OPERATE ANY PLANT EQUIPMENT!
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
Saturday, August 03, 2013
 
V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO:      JPPF-066A 2013 NRC In-Plant k: LOCALLY ISOLATE RCP SEALS DURING A TOTAL LOSS OF ESF POWER APPROVAL:            APPROVAL DATE:
REV NO: 3 CANDIDATE:
EXAMINER:
Saturday, August 03, 2013                                              Page 1 of 9
 
TASK:
000-175-05-04            Locally Isolate RCP Seals per EOP-6.0.
TASK STANDARD:
Seal injection and return valves for RCP seals have been manually isolated per EOP-6.0 Att 9.
TERMINATING CUE:            RCP seals isolated per Att 9 of EOP-6.0.
PREFERRED EVALUATION LOCATION                                PREFERRED EVALUATION METHOD PLANT                                                          SIMULATE
 
==REFERENCES:==
EOP-6.0                  LOSS OF ALL ESF AC POWER INDEX NO.            K/A NO.                                            RO          SRO 000055K302          EK3.02    Actions contained in EOP for loss of       4.3        4.6 offsite and onsite power TOOLS:            EOP-6.0, Attachment 9, LOCALLY OPERATED ISOLATION VALVES FLASHLIGHT EVALUATION TIME                    15          TIME CRITICAL      No    10CFR55: 45.a.6 TIME START:                        TIME FINISH:                    PERFORMANCE TIME:
PERFORMANCE RATING:                  SAT:            UNSAT:
CANDIDATE:
EXAMINER:
SIGNATURE            DATE Saturday, August 03, 2013                                                                    Page 2 of 9
 
INSTRUCTIONS TO OPERATOR READ TO OPERATOR:
WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
SAFETY CONSIDERATIONS:                  MVT-8100 is in the north end of the 412' West Penetration area, which is a Radiation Area. At the discretion of the examiner, have the examinee describe the general location of the valve. Operation of the valve is identical to MVT-8105 and MVG-9606. Ensure to view radiation surveys and to monitor EDs if entering Radiation area.
INITIAL CONDITION: A total loss of offsite power has occurred and both DG's have failed to start. Alternate Seal injection also failed to start on the loss of power.
The CRS has implemented EOP-6.0, LOSS OF ALL ESF AC POWER, and is directing actions for locally isolating RCP seals.
The CRS has implemented EOP-6.0, LOSS OF ALL ESF AC POWER, and is directing actions for locally isolating RCP seals.
2013 NRC Sim a RO&SRO-I&SRO-U: CONTINUOUS ROD WITHDRAWALCANDIDATE:EXAMINER:3 000-006-05-01PERFORM10NoThe reactor is tripped per AOP-403.3, CONTINUOUS CONTROL ROD MOTION, to terminate the transient prior to exceeding Reactor trip setpoints. Immediate actions of EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION, are completed.SIMULATORTIME START:TIME FINISH:SAT:UNSAT:PERFORMANCE TIME:SIGNATUREDATE45.a.3RESPOND TO CONTINUOUS ROD MOTIONTOOLS:GOP-3, REACTOR STARTUP FROM HOT STANDBY TO STARTUP (MODE 3 TO MODE 2)
INITIATING CUES: The RO calls and directs you to isolate RCP seals in accordance with Step 1 of Attachment 9 of EOP-6.0, LOCALLY OPERATED ISOLATION VALVES.
AOP-403.3, CONTINUOUS CONTROL ROD MOTIONEOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATIONREP-109.002, Enclosure 9.2, Recommended Rod Positions for ICRR.Immediate actions of EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION are complete.0000012413Knowledge of crew roles and responsibilities during EOP usage.4.04.62.4.13 Increase reactor power to 10-3% per GOP-3 starting at Step 3.12. The Examiner will play the role of CRS and Reactor Engineering for this JPM. Reactor engineering has started REP-109.002, INVERSE COUNT RATE RATIO PLOT, and has taken all necessary data and is ready to collect data at 53 steps on Control Bank A.GOP-3, REACTOR STARTUP FROM HOT STANDBY TO STARTUP (MODE 3 TO MODE 2), is in progress after a short mini-outage.The shutdown banks have been fully withdrawn. Step 3.11 of GOP-3 is complete. Estimated critical position is 100 steps on bank "D".WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!
Review GOP Appendix A, Generic Operating Precautions, for Reactor Startup.Evaluator Note: This JPM can be briefed outside of the simulator and this step can occur outside of the simulator.
AT NO TIME ARE YOU TO OPERATE ANY PLANT EQUIPMENT!
YesReviews GOP Appendix A, Generic Operating Precautions, for Reactor Startup.No1Procedure Caution: To prevent any inadvertent inward rod motion the ROD CNTRL BANK SEL Switch should not be placed in or pass through AUTO.Place the ROD CNTRL BANK SEL Switch in MAN.
FOR ELECTRICAL MANIPULATIONS, AT NO TIME ARE YOU TO BREAK THE PLANE OF THE ELECTRICAL PANEL!
YesROD CNTROL BANK SEL Switch taken counter clockwise to MAN.Yes2 Procedure Note: A stable Startup Rate of one decade per minute should NOT be exceeded.Using ROD CONTROL ROD MOTION lever, commence Control Bank Rod withdrawal to ten steps on Bank A.
Saturday, August 03, 2013                                                                          Page 3 of 9
YesSteps indicate ten steps on Bank A.Yes3Procedure Caution: 12 steps should NOT be exceeded until all Rod Bottom lights are off. If all Control Bank A Rod Bottom lights are NOT off at ten steps, AOP-403.5, Stuck Or Misaligned Control Rod, should be entered.At ten steps on Control Bank A, stop and verify:1) Bank A RB lights clear.2) ONE ROD ON BOTTOM (XCP-621 3-1) annunciator clears.3) RODS ON BOTTOM (XCP-621 3-2) annunciator clears.
 
Yes1) Bank A RB lights clear.
STEPS CRITICAL:        Yes      SEQUENCED: Yes                        SAT            UNSAT STEP:      1 Locally isolate RCP Seals by closing the following (EOP-6.0 Step 13):
XVT08100-CS, RC PUMP SEAL RETURN HDR ISOL VLV(ORC) (AB-412 West Pen)
STEP STANDARD:
Engages manual handwheel by pressing down on the declutch lever on XVT08100-CS and turns handwheel fully clockwise.
CUES:
Evaluator Note: MVT-8100 is in the north end of the 412' West Penetration area, which is a Radiation Area. At the discretion of the examiner, have the examinee describe the general location of the valve. Operation of the valve is identical to MVT-8105 and MVG-9606. Ensure to view radiation surveys and to monitor EDs if entering Radiation area.
Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.
COMMENTS:
Saturday, August 03, 2013                                                                    Page 4 of 9
 
CRITICAL:        Yes    SEQUENCED: Yes                          SAT            UNSAT STEP:      2 Locally isolate RCP Seals by closing the following (EOP-6.0 Step 13):
XVG09606-CC, RB CC RETURN HEADER VALVE (AB-436 West Pen)
STEP STANDARD:
Engages manual handwheel by pressing down on the declutch lever on XVG09606-CC and turns handwheel fully clockwise.
CUES:
Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.
COMMENTS:
CRITICAL:        Yes    SEQUENCED: Yes                          SAT            UNSAT STEP:      3 Locally isolate RCP Seals by closing the following (EOP-6.0 Step 13):
XVT08105-CS, SEAL INJECTION HEADER ISOLATION VALVE (AB-436)
STEP STANDARD:
Engages manual handwheel by pressing down on the declutch lever on XVT08105-CS and turns handwheel fully clockwise.
CUES:
Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.
COMMENTS:
Saturday, August 03, 2013                                                                Page 5 of 9
 
CRITICAL:          No        SEQUENCED: Yes                          SAT              UNSAT STEP:      4 Contact the Control Room to determine if the Alternate Seal Injection System has actuated.
STEP STANDARD:
Determines from initial cue or from calling the control room that Alternate Seal Injection has not actuated and that the alternate action is necessary.
CUES:
Evaluator Cue: If called as the control room reply that Alternate Seal Injection has not been actuated.
COMMENTS:
CRITICAL:        Yes        SEQUENCED: Yes                          SAT              UNSAT STEP:      5 If the Alternate Seal Injection System has not actuated, close all the following:
XVT08102A-CS, RC PUMP A SEAL SUPPLY ISOL VALVE (ORC) (AB-412 West Pen).
STEP STANDARD:
Engages manual handwheel by pressing down on the declutch lever on XVT08102A-CS and turns handwheel fully clockwise.
CUES:
Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.
COMMENTS:
Saturday, August 03, 2013                                                                        Page 6 of 9
 
CRITICAL:        Yes        SEQUENCED: Yes                          SAT          UNSAT STEP:      6 If the Alternate Seal Injection System has not actuated, close all the following:
XVT08102B-CS, RC PUMP B SEAL SUPPLY ISOL VALVE (ORC) (IB-412 East Pen).
STEP STANDARD:
Engages manual handwheel by pressing down on the declutch lever on XVT08102B-CS and turns handwheel fully clockwise.
CUES:
Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.
Evaluator Note: When validated this valve did not have a CHAMPS tag, but did have a small metal OEM tag.
COMMENTS:
CRITICAL:        Yes        SEQUENCED: Yes                          SAT          UNSAT STEP:      7 If the Alternate Seal Injection System has not actuated, close all the following:
XVT08102C-CS, RC PUMP C SEAL SUPPLY ISOL VALVE (ORC) (IB-412 East Pen).
STEP STANDARD:
Engages manual handwheel by pressing down on the declutch lever on XVT08102C-CS and turns handwheel fully clockwise.
CUES:
Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.
COMMENTS:
Examiner ends JPM at this point.
Saturday, August 03, 2013                                                                  Page 7 of 9
 
JPM SETUP SHEET JPM NO: JPPF-066A DESCRIPTION:          2013 NRC In-Plant k: LOCALLY ISOLATE RCP SEALS DURING A TOTAL LOSS OF ESF POWER IC SET:
INSTRUCTIONS:
COMMENTS:
Saturday, August 03, 2013                                                          Page 8 of 9
 
JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:
INITIAL CONDITION: A total loss of offsite power has occurred and both DG's have failed to start. Alternate Seal injection also failed to start on the loss of power.
The CRS has implemented EOP-6.0, LOSS OF ALL ESF AC POWER, and is directing actions for locally isolating RCP seals.
INITIATING CUES: The RO calls and directs you to isolate RCP seals in accordance with Step 1 of Attachment 9 of EOP-6.0, LOCALLY OPERATED ISOLATION VALVES.
AT NO TIME ARE YOU TO OPERATE ANY PLANT EQUIPMENT!
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
Saturday, August 03, 2013
 
V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO:    NJPSF-141A 2013 NRC Sim a RO&SRO-I&SRO-U: CONTINUOUS ROD WITHDRAWAL APPROVAL:          APPROVAL DATE:
REV NO: 3 CANDIDATE:
EXAMINER:
Thursday, August 01, 2013                                              Page 1 of 12
 
TASK:
000-006-05-01            RESPOND TO CONTINUOUS ROD MOTION TASK STANDARD:
The reactor is tripped per AOP-403.3, CONTINUOUS CONTROL ROD MOTION, to terminate the transient prior to exceeding Reactor trip setpoints.
Immediate actions of EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION, are completed.
TERMINATING CUE:             Immediate actions of EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION are complete.
PREFERRED EVALUATION LOCATION                                PREFERRED EVALUATION METHOD SIMULATOR                                                        PERFORM
 
==REFERENCES:==
 
INDEX NO.            K/A NO.                                              RO        SRO 0000012413          2.4.13    Knowledge of crew roles and                4.0        4.6 responsibilities during EOP usage.
TOOLS:           GOP-3, REACTOR STARTUP FROM HOT STANDBY TO STARTUP (MODE 3 TO MODE 2)
AOP-403.3, CONTINUOUS CONTROL ROD MOTION EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION REP-109.002, Enclosure 9.2, Recommended Rod Positions for ICRR.
EVALUATION TIME                    10          TIME CRITICAL      No      10CFR55: 45.a.3 TIME START:                        TIME FINISH:                    PERFORMANCE TIME:
PERFORMANCE RATING:                  SAT:            UNSAT:
CANDIDATE:
EXAMINER:
SIGNATURE          DATE Thursday, August 01, 2013                                                                  Page 2 of 12
 
INSTRUCTIONS TO OPERATOR READ TO OPERATOR:
WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
SAFETY CONSIDERATIONS:
INITIAL CONDITION: GOP-3, REACTOR STARTUP FROM HOT STANDBY TO STARTUP (MODE 3 TO MODE 2), is in progress after a short mini-outage.
The shutdown banks have been fully withdrawn. Step 3.11 of GOP-3 is complete. Estimated critical position is 100 steps on bank "D".
INITIATING CUES: Increase reactor power to 10-3% per GOP-3 starting at Step 3.12. The Examiner will play the role of CRS and Reactor Engineering for this JPM. Reactor engineering has started REP-109.002, INVERSE COUNT RATE RATIO PLOT, and has taken all necessary data and is ready to collect data at 53 steps on Control Bank A.
HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!
Thursday, August 01, 2013                                                                      Page 3 of 12
 
STEPS CRITICAL:          No    SEQUENCED: Yes                          SAT            UNSAT STEP:      1 Review GOP Appendix A, Generic Operating Precautions, for Reactor Startup.
STEP STANDARD:
Reviews GOP Appendix A, Generic Operating Precautions, for Reactor Startup.
CUES:
Evaluator Note: This JPM can be briefed outside of the simulator and this step can occur outside of the simulator.
COMMENTS:
CRITICAL:        Yes    SEQUENCED: Yes                          SAT            UNSAT STEP:      2 Procedure Caution: To prevent any inadvertent inward rod motion the ROD CNTRL BANK SEL Switch should not be placed in or pass through AUTO.
Place the ROD CNTRL BANK SEL Switch in MAN.
STEP STANDARD:
ROD CNTROL BANK SEL Switch taken counter clockwise to MAN.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                                    Page 4 of 12
 
CRITICAL:        Yes      SEQUENCED: Yes                        SAT            UNSAT STEP:      3 Procedure Note: A stable Startup Rate of one decade per minute should NOT be exceeded.
Using ROD CONTROL ROD MOTION lever, commence Control Bank Rod withdrawal to ten steps on Bank A.
STEP STANDARD:
Steps indicate ten steps on Bank A.
CUES:
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                        SAT            UNSAT STEP:      4 Procedure Caution: 12 steps should NOT be exceeded until all Rod Bottom lights are off. If all Control Bank A Rod Bottom lights are NOT off at ten steps, AOP-403.5, Stuck Or Misaligned Control Rod, should be entered.
At ten steps on Control Bank A, stop and verify:
: 1) Bank A RB lights clear.
: 2) ONE ROD ON BOTTOM (XCP-621 3-1) annunciator clears.
: 2) ONE ROD ON BOTTOM (XCP-621 3-1) annunciator clears.
: 3) RODS ON BOTTOM (XCP-621 3-2) annunciator clears.No4 Recommence withdrawing rods while observing that the groups sequence properly.Evaluator Cue: The examinee should stop pulling rods at 53 steps to collect data for inverse count rate ratio plot. Once the examinee determines that count rates are stable then cue the examinee that the estimated critical condition (ECC) is at 230 steps on Bank "D". Evaluator Note: When rods are >53 steps on Bank A then the continuous rod motion will occur.
: 3) RODS ON BOTTOM (XCP-621 3-2) annunciator clears.
YesContinues to pull rods.No5Enters AOP-403.3, CONTINUOUS CONTROL ROD MOTION.Evaluator Note: The applicant is not expected to pull out the procedure, but may perform the actions of this procedure from memory and trip the unit.
STEP STANDARD:
YesEnters AOP-403.3, CONTINUOUS CONTROL ROD MOTION.No6 Verify rod motion is NOT required:Tavg is within 1.5 °F of Tref.AND No load rejection has occurred (C7A OR C7B).Evaluator Note: This is an immediate operator action.
: 1) Bank A RB lights clear.
YesNotes that rod motion is not required.No7Verify rod motion is stopped.
: 2) ONE ROD ON BOTTOM (XCP-621 3-1) annunciator clears.
Evaluator Note: This is an immediate operator action.
: 3) RODS ON BOTTOM (XCP-621 3-2) annunciator clears.
YesNotes that rod motion has not stopped.No8 Perform the following:a) Trip the Reactor. b) GO TO EOP-1.0. REACTOR TRIP/SAFETY INJECTION ACTUATION.Evaluator Note: This is an immediate operator action.
CUES:
YesTurns reactor trip switch to trip.Yes9 Procedure Note: Steps 1 through 5 are Immediate Operator Actions. The EOP REFERENCE PAGE should be monitored throughout the use of this procedure.Conditions for implementing Emergency Plan Procedures should be evaluated using EPP-001, ACTIVATION AND IMPLEMENTATION OF EMERGENCY PLAN.Verify Reactor Trip:Trip the Reactor using either Reactor Trip Switch.
COMMENTS:
Verify all Reactor Trip and Bypass Breakers are open.Verify all Rod Bottom Lights are lit.Verify Reactor Power level is decreasing.Evaluator Note: This is an immediate operator action.
Thursday, August 01, 2013                                                                    Page 5 of 12
YesReactor Trip and Bypass Breakers indicate green light lit red light off.Rod Bottom Lights are lit.
 
Reactor Power level is decreasing.No10 Examiner ends JPM at this point.Verify Turbine/Generator Trip:a. Verify all Turbine STM STOP VLVs are closed.b. Ensure Generator Trip (after 30 second delay):  
CRITICAL:          No      SEQUENCED: Yes                        SAT            UNSAT STEP:      5 Recommence withdrawing rods while observing that the groups sequence properly.
: 1) Ensure the GEN BKR is open. 2) Ensure the GEN FIELD BKR is open.3) Ensure the EXC FIELD CNTRL is tripped.Evaluator Note: This is an immediate operator action.
STEP STANDARD:
YesGEN BKR, GEN FIELD BKR, and EXC FIELD CNTRL indicate green light lit and red light off.No11Verify both ESF buses are energized.
Continues to pull rods.
Evaluator Note: This is an immediate operator action.
CUES:
YesPotential lights on 1DA and 1DB are lit for all three phases.No12 NJPSF-141A2013 NRC Sim a RO&SRO-I&SRO-U: CONTINUOUS ROD WITHDRAWAL330/15IC 15 MAL-PCS009AB REACTOR TRIP BREAKER A FAILURE (FAIL TO OPEN) Delay=0, Ramp=0, Final=AUTO_(UV)
Evaluator Cue: The examinee should stop pulling rods at 53 steps to collect data for inverse count rate ratio plot. Once the examinee determines that count rates are stable then cue the examinee that the estimated critical condition (ECC) is at 230 steps on Bank "D".
MAL-PCS009BB REACTOR TRIP BREAKER B FAILURE (FAIL TO OPEN) Delay=0, Ramp=0, Final=AUTO_(UV)Event #1Mcrfpa(5) >53Trigger #1 MAL-CRF006B UNCONTROLLED MANUAL ROD MOTION Delay=0, Ramp=0, Final=ActiveJPM is terminated after the reactor is tripped and immediate operator actions of EOP-1.0 are completed.Ensure Audio Count Rate (step 3.4.e), HIGH FLUX AT SHUTDOWN is blocked (step 3.11.b), IPCS indicates MODE 2 (step 3.11.f), NR-45 is in HI speed (Audio count rate and NR-45 should be the two that are not saved with the snap). Reactivity is returned to service (see REP-109.002).
Evaluator Note: When rods are >53 steps on Bank A then the continuous rod motion will occur.
JPM SETUP SHEET Increase reactor power to 10-3% per GOP-3 starting at Step 3.12. The Examiner will play the role of CRS and Reactor Engineering for this JPM. Reactor engineering has started REP-109.002, INVERSE COUNT RATE RATIO PLOT, and has taken all necessary data and is ready to collect data at 53 steps on Control Bank A.GOP-3, REACTOR STARTUP FROM HOT STANDBY TO STARTUP (MODE 3 TO MODE 2), is in progress after a short mini-outage.
COMMENTS:
CRITICAL:          No      SEQUENCED: Yes                        SAT            UNSAT STEP:      6 Enters AOP-403.3, CONTINUOUS CONTROL ROD MOTION.
STEP STANDARD:
Enters AOP-403.3, CONTINUOUS CONTROL ROD MOTION.
CUES:
Evaluator Note: The applicant is not expected to pull out the procedure, but may perform the actions of this procedure from memory and trip the unit.
COMMENTS:
Thursday, August 01, 2013                                                                    Page 6 of 12
 
CRITICAL:          No      SEQUENCED: Yes            SAT UNSAT STEP:      7 Verify rod motion is NOT required:
Tavg is within 1.5 °F of Tref.
AND No load rejection has occurred (C7A OR C7B).
STEP STANDARD:
Notes that rod motion is not required.
CUES:
Evaluator Note: This is an immediate operator action.
COMMENTS:
CRITICAL:          No      SEQUENCED: Yes            SAT UNSAT STEP:      8 Verify rod motion is stopped.
STEP STANDARD:
Notes that rod motion has not stopped.
CUES:
Evaluator Note: This is an immediate operator action.
COMMENTS:
Thursday, August 01, 2013                                        Page 7 of 12
 
CRITICAL:        Yes        SEQUENCED: Yes          SAT  UNSAT STEP:      9 Perform the following:
a) Trip the Reactor.
b) GO TO EOP-1.0. REACTOR TRIP/SAFETY INJECTION ACTUATION.
STEP STANDARD:
Turns reactor trip switch to trip.
CUES:
Evaluator Note: This is an immediate operator action.
COMMENTS:
Thursday, August 01, 2013                                        Page 8 of 12
 
CRITICAL:          No      SEQUENCED: Yes                            SAT      UNSAT STEP:      10 Procedure Note: Steps 1 through 5 are Immediate Operator Actions.
The EOP REFERENCE PAGE should be monitored throughout the use of this procedure.
Conditions for implementing Emergency Plan Procedures should be evaluated using EPP-001, ACTIVATION AND IMPLEMENTATION OF EMERGENCY PLAN.
Verify Reactor Trip:
Trip the Reactor using either Reactor Trip Switch.
Verify all Reactor Trip and Bypass Breakers are open.
Verify all Rod Bottom Lights are lit.
Verify Reactor Power level is decreasing.
STEP STANDARD:
Reactor Trip and Bypass Breakers indicate green light lit red light off.
Rod Bottom Lights are lit.
Reactor Power level is decreasing.
CUES:
Evaluator Note: This is an immediate operator action.
COMMENTS:
Thursday, August 01, 2013                                                              Page 9 of 12
 
CRITICAL:          No    SEQUENCED: Yes                    SAT          UNSAT STEP:      11 Verify Turbine/Generator Trip:
: a. Verify all Turbine STM STOP VLVs are closed.
: b. Ensure Generator Trip (after 30 second delay):
: 1) Ensure the GEN BKR is open.
: 2) Ensure the GEN FIELD BKR is open.
: 3) Ensure the EXC FIELD CNTRL is tripped.
STEP STANDARD:
GEN BKR, GEN FIELD BKR, and EXC FIELD CNTRL indicate green light lit and red light off.
CUES:
Evaluator Note: This is an immediate operator action.
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                    SAT          UNSAT STEP:      12 Verify both ESF buses are energized.
STEP STANDARD:
Potential lights on 1DA and 1DB are lit for all three phases.
CUES:
Evaluator Note: This is an immediate operator action.
COMMENTS:
Examiner ends JPM at this point.
Thursday, August 01, 2013                                                            Page 10 of 12
 
JPM SETUP SHEET JPM NO: NJPSF-141A DESCRIPTION:          2013 NRC Sim a RO&SRO-I&SRO-U: CONTINUOUS ROD WITHDRAWAL IC SET: 330/15 INSTRUCTIONS:
IC 15 MAL-PCS009AB REACTOR TRIP BREAKER A FAILURE (FAIL TO OPEN) Delay=0, Ramp=0, Final=AUTO_(UV)
MAL-PCS009BB REACTOR TRIP BREAKER B FAILURE (FAIL TO OPEN) Delay=0, Ramp=0, Final=AUTO_(UV)
Event #1 Mcrfpa(5) >53 Trigger #1 MAL-CRF006B UNCONTROLLED MANUAL ROD MOTION Delay=0, Ramp=0, Final=Active COMMENTS:
JPM is terminated after the reactor is tripped and immediate operator actions of EOP-1.0 are completed.
Ensure Audio Count Rate (step 3.4.e), HIGH FLUX AT SHUTDOWN is blocked (step 3.11.b), IPCS indicates MODE 2 (step 3.11.f), NR-45 is in HI speed (Audio count rate and NR-45 should be the two that are not saved with the snap). Reactivity is returned to service (see REP-109.002).
Thursday, August 01, 2013                                                                  Page 11 of 12
 
JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:
INITIAL CONDITION: GOP-3, REACTOR STARTUP FROM HOT STANDBY TO STARTUP (MODE 3 TO MODE 2), is in progress after a short mini-outage.
The shutdown banks have been fully withdrawn. Step 3.11 of GOP-3 is complete. Estimated critical position is 100 steps on bank "D".
The shutdown banks have been fully withdrawn. Step 3.11 of GOP-3 is complete. Estimated critical position is 100 steps on bank "D".
2013 NRC Sim b RO&SRO-I&SRO-U: SWAP RUNNING RBCU'SCANDIDATE:EXAMINER:4 022-003-01-01PERFORM5NOXFN-64A, XFN-064B, and XFN-65A are running in fast/norm speed and RBCU TRAIN B EMER Gis selected to XFN-064B.SIMULATORTIME START:TIME FINISH:SAT:UNSAT:PERFORMANCE TIME:SIGNATUREDATE45.a.4START THE REACTOR BUILDING VENTILATION SYSTEM PER SOP114.TOOLS:SOP-114 IV. D. SHIFTING REACTOR BUILDING COOLING UNITS FAN SPEEDSOP-114 IV. D. SHIFTING REACTOR BUILDING COOLING UNITS FA NSPEED complete.SOP-114REACTOR BUILDING VENTILATION SYSTEM022000A401 CCS fans3.63.6A4.01 The CRS directs you as the RO to start XFN-64A, XFN-64B, and XFN-65B in NORM speed in accordance with SOP-114 Section IV. D.
INITIATING CUES: Increase reactor power to 10-3% per GOP-3 starting at Step 3.12. The Examiner will play the role of CRS and Reactor Engineering for this JPM. Reactor engineering has started REP-109.002, INVERSE COUNT RATE RATIO PLOT, and has taken all necessary data and is ready to collect data at 53 steps on Control Bank A.
SHIFTING REACTOR BUILDING COOLING UNITS FAN SPEED, in order to align the plant for a normal preferred at power lineup.Mode 3.The current lineup of the RBCU's is as follows: XFN-64A and XFN-64B are running in slow speed.It is desired to run XFN-64A, XFN-64B, and XFN-65B in NORM speed in order to prepare for reactor startup.None.WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
Shift RBCU's as follows:a. Shutdown RBCUs by placing appropriate switch(es) in STOP:1) XFN 0064A-AH, 1A NORM.2) XFN 0064A-AH, 1A SLOW.
Thursday, August 01, 2013
 
V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO:    NJPSF-159 2013 NRC Sim b RO&SRO-I&SRO-U: SWAP RUNNING RBCU'S APPROVAL:           APPROVAL DATE:
REV NO: 4 CANDIDATE:
EXAMINER:
Sunday, August 04, 2013                                        Page 1 of 12
 
TASK:
022-003-01-01            START THE REACTOR BUILDING VENTILATION SYSTEM PER SOP 114.
TASK STANDARD:
XFN-64A, XFN-064B, and XFN-65A are running in fast/norm speed and RBCU TRAIN B EMERG is selected to XFN-064B.
TERMINATING CUE:             SOP-114 IV. D. SHIFTING REACTOR BUILDING COOLING UNITS FAN SPEED complete.
PREFERRED EVALUATION LOCATION                              PREFERRED EVALUATION METHOD SIMULATOR                                                  PERFORM
 
==REFERENCES:==
SOP-114                REACTOR BUILDING VENTILATION SYSTEM INDEX NO.             K/A NO.                                         RO        SRO 022000A401          A4.01     CCS fans                              3.6        3.6 TOOLS:            SOP-114 IV. D. SHIFTING REACTOR BUILDING COOLING UNITS FAN SPEED EVALUATION TIME                      5          TIME CRITICAL    NO    10CFR55: 45.a.4 TIME START:                        TIME FINISH:                PERFORMANCE TIME:
PERFORMANCE RATING:                SAT:            UNSAT:
CANDIDATE:
EXAMINER:
SIGNATURE          DATE Sunday, August 04, 2013                                                                Page 2 of 12
 
INSTRUCTIONS TO OPERATOR READ TO OPERATOR:
WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
SAFETY CONSIDERATIONS:                  None.
INITIAL CONDITION: Mode 3.
The current lineup of the RBCU's is as follows: XFN-64A and XFN-64B are running in slow speed.
It is desired to run XFN-64A, XFN-64B, and XFN-65B in NORM speed in order to prepare for reactor startup.
INITIATING CUES: The CRS directs you as the RO to start XFN-64A, XFN-64B, and XFN-65B in NORM speed in accordance with SOP-114 Section IV. D.
SHIFTING REACTOR BUILDING COOLING UNITS FAN SPEED, in order to align the plant for a normal preferred at power lineup.
HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!
Sunday, August 04, 2013                                                                    Page 3 of 12
 
STEPS CRITICAL:        Yes  SEQUENCED: Yes                      SAT          UNSAT STEP:      1 Shift RBCUs as follows:
: a. Shutdown RBCUs by placing appropriate switch(es) in STOP:
: 1) XFN 0064A-AH, 1A NORM.
: 2) XFN 0064A-AH, 1A SLOW.
: 3) XFN 0064B-AH, 1B NORM.
: 3) XFN 0064B-AH, 1B NORM.
: 4) XFN 0064B-AH, 1B SLOW.5) XFN 0065A-AH, 2A NORM.6) XFN 0065A-AH, 2A SLOW.
: 4) XFN 0064B-AH, 1B SLOW.
: 5) XFN 0065A-AH, 2A NORM.
: 6) XFN 0065A-AH, 2A SLOW.
: 7) XFN 0065B-AH, 2B NORM.
: 7) XFN 0065B-AH, 2B NORM.
: 8) XFN 0065B-AH, 2B SLOW.
: 8) XFN 0065B-AH, 2B SLOW.
YesTakes XFN 0064A-AH, 1A SLOW and XFN 0064B-AH, 1B SLOW to stop. Verifies red light off and green light on.Yes1 Ensure the RBCU dampers are in BYP:1) XDP-110A, RBCU 64A HEPA FLTR BYP DMPR.2) XDP-111A, RBCU 65A HEPA FLTR BYP DMPR.
STEP STANDARD:
: 3) XDP-110B, RBCU 64B HEPA FLTR BYP DMPR4) XDP-111B, RBCU 65B HEPA FLTR BYP DMPR.
Takes XFN 0064A-AH, 1A SLOW and XFN 0064B-AH, 1B SLOW to stop. Verifies red light off and green light on.
YesTakes XDP-110A, RBCU 64A HEPA FLTR BYP DMPR and XDP-110B, RBCU 64B HEPA FLTR BYP DMPRto BYP. Verifies red light lit and green light off.Yes2 Procedure Note: a. Due to eddy current brakes, RBCU control switches must be held in START position until the red beaker closed light is lit and starting current is indicated on appropriate meter.B. Normal and preferred lineup is three RBCUs running in NORM (fast speed).C. To increase stay times for teams entering containment, four RBCUs may be placed in service in NORM (fast speed).Place RBCUs in service by starting three or four RBCUs in SLOW or NORM as follows: For XFN0064A-AH, REACTOR BLDG COOLING UNIT 1A EMERG FAN, start one of the following:a) XFN 0064A-AH, 1A NORM.For XFN0064B-AH, REACTOR BLDG COOLING UNIT 1B EMERG FAN, start one of the following:a) XFN 0064B-AH, 1B NORM.For XFN0065B-AH, REACTOR BLDG COOLING UNIT 2B EMERG FAN, start one of the following: a) XFN 0065B-AH, 2B NORM.
CUES:
YesTakes and holds XFN 0064A-AH, 1A NORM, 0064B-AH, 1B NORM, and 0065B, 2B NORM to START until red breaker closed light is lit and starting current is indicated.Yes3 Procedure Note: Contact PSE to evaluate, if RBCU fan motor amps exceed the values given.Verify RBCU Fan motor amps return to normal operating range: 1) For fast speed operation, 275 amps to 300 amps. Remove RBCU fan from service due to above normal amps.
COMMENTS:
YesDetermines normal amps for XFN0064A and XFN0064BYes4 Determines that XFN0065B has tripped.Enters XCP-607, 1-1, RBCU 1B/2B FAN TRIP CORRECTIVE ACTIONS:1. Determine which fan tripped and place the control switch in Normal After Stop.
Sunday, August 04, 2013                                                            Page 4 of 12
 
CRITICAL:        Yes        SEQUENCED: Yes          SAT          UNSAT STEP:      2 Ensure the RBCU dampers are in BYP:
: 1) XDP-110A, RBCU 64A HEPA FLTR BYP DMPR.
: 2) XDP-111A, RBCU 65A HEPA FLTR BYP DMPR.
: 3) XDP-110B, RBCU 64B HEPA FLTR BYP DMPR
: 4) XDP-111B, RBCU 65B HEPA FLTR BYP DMPR.
STEP STANDARD:
Takes XDP-110A, RBCU 64A HEPA FLTR BYP DMPR and XDP-110B, RBCU 64B HEPA FLTR BYP DMPR to BYP. Verifies red light lit and green light off.
CUES:
COMMENTS:
Sunday, August 04, 2013                                                  Page 5 of 12
 
CRITICAL:        Yes      SEQUENCED: Yes                            SAT        UNSAT STEP:      3 Procedure Note:
: a. Due to eddy current brakes, RBCU control switches must be held in START position until the red beaker closed light is lit and starting current is indicated on appropriate meter.
B. Normal and preferred lineup is three RBCUs running in NORM (fast speed).
C. To increase stay times for teams entering containment, four RBCUs may be placed in service in NORM (fast speed).
Place RBCUs in service by starting three or four RBCUs in SLOW or NORM as follows:
For XFN0064A-AH, REACTOR BLDG COOLING UNIT 1A EMERG FAN, start one of the following:
a) XFN 0064A-AH, 1A NORM.
For XFN0064B-AH, REACTOR BLDG COOLING UNIT 1B EMERG FAN, start one of the following:
a) XFN 0064B-AH, 1B NORM.
For XFN0065B-AH, REACTOR BLDG COOLING UNIT 2B EMERG FAN, start one of the following:
a) XFN 0065B-AH, 2B NORM.
STEP STANDARD:
Takes and holds XFN 0064A-AH, 1A NORM, 0064B-AH, 1B NORM, and 0065B, 2B NORM to START until red breaker closed light is lit and starting current is indicated.
CUES:
COMMENTS:
Sunday, August 04, 2013                                                                    Page 6 of 12
 
CRITICAL:        Yes  SEQUENCED: Yes                          SAT            UNSAT STEP:      4 Procedure Note: Contact PSE to evaluate, if RBCU fan motor amps exceed the values given.
Verify RBCU Fan motor amps return to normal operating range: 1) For fast speed operation, 275 amps to 300 amps. Remove RBCU fan from service due to above normal amps.
STEP STANDARD:
Determines normal amps for XFN0064A and XFN0064B CUES:
COMMENTS:
Sunday, August 04, 2013                                                                    Page 7 of 12
 
CRITICAL:          No    SEQUENCED: Yes                            SAT            UNSAT STEP:      5 Determines that XFN0065B has tripped.
Enters XCP-607, 1-1, RBCU 1B/2B FAN TRIP CORRECTIVE ACTIONS:
: 1. Determine which fan tripped and place the control switch in Normal After Stop.
: 2. Start the non-running Reactor Building Cooling Unit fan after ensuring cooling water is lined up.
: 2. Start the non-running Reactor Building Cooling Unit fan after ensuring cooling water is lined up.
: 3. Dispatch an operator to XPN7077 (CB-436, TSC Equipment Room) to select the RACK RESET and reset the alarm.SUPPLEMENTAL ACTIONS:1. Determine the cause of the fan trip, correct and return to service as soon as possible.2. Continued normal operation is allowed when one fan per group in slow speed is operable per Technical Specification 3.6.2.3.
: 3. Dispatch an operator to XPN7077 (CB-436, TSC Equipment Room) to select the RACK RESET and reset the alarm.
: 3. Notify PSE (Predictive Maintenance) for further assistance.Evaluator Note: This is where the JPM becomes alternate path.Booth Operator Cue: If called to go to XPN7077 (CB-436, TSC Equipment Room) and to select the RACK RESET and reset the alarm, report that it is complete after 5 minutes.
SUPPLEMENTAL ACTIONS:
YesTakes XFN 0065B-AH, 2B NORM to stop.No5 From ARP:2. Start the non-running Reactor Building Cooling Unit fan after ensuring cooling water is lined up.From SOP:Place RBCUs in service by starting three or four RBCUs in SLOW or NORM as follows:For XFN0065A-AH, REACTOR BLDG COOLING UNIT 2A EMERG FAN, start one of the following:a) XFN 0065A-AH, 2A NORM.
: 1. Determine the cause of the fan trip, correct and return to service as soon as possible.
YesTakes and holds XFN 0065A, 2A NORM to START until red breaker closed light is lit and starting current is indicated.Yes6Verify RBCU Fan motor amps return to normal operating range: 1) For fast speed operation, 275 amps to 300 amps YesVerifies RBCU motor amps return to normal operating range.No7 Examiner ends JPM at this point.Procedure Note: The RBCU TRAIN A (B) EMERG switch must be selected to an operable RBCU.Verify the following switches are in the desired position:1) XFN-64A/XFN 65A - RBCU TRAIN A EMERG.2) XFN-64B/XFN 65B - RBCU TRAIN B EMERG.Evaluator Cue:  If applicant reports that an inoperable RBCU is selected for start, ask for a recommendation and approve it.Evaluator Note:  The section of XFN-64B causes XCP-6103 5-6, RB RECRIC UNIT C 3108C/ 3109C MISALIGN and XCP-6103 5-7, RB RECRIC UNIT D 3108D/ 3109D to change condition (dim/bright).
: 2. Continued normal operation is allowed when one fan per group in slow speed is operable per Technical Specification 3.6.2.3.
YesTakes XFN-64B/XFN 65B - RBCU TRAIN B EMERG to XFN-64B position.Yes8 NJPSF-1592013 NRC Sim b RO&SRO-I&SRO-U: SWAP RUNNING RBCU'S331/4IC 4. Pre-Event LoadSelect RBCU TRAIN A EMERG to XFN-65A and select RBCU TRAIN B EMERG to XFN-65B.Stop all RBCUsStart XFN-64A and XFN-64B in slow.Take XDP-110A, RBCU 64A HEPA FLTR BYP DMPR and XDP-110B, RBCU 64B HEPA FLTR BYP DMPR to FILTER.
: 3. Notify PSE (Predictive Maintenance) for further assistance.
PMP-AH049B  XFN0065BH RB CLG RAN HIGH BRG FAILURE  Final=1.2Event 1:X02O104R==1 (red light lit for XFN-65BTrigger 1:PMP-AH049T  Delay=2 seconds Trip of XFN-65B. Saved to IC 331.Need to provide copies of procedure since is not laminated in the simulator.
STEP STANDARD:
JPM SETUP SHEET The CRS directs you as the RO to start XFN-64A, XFN-64B, and XFN-65B in NORM speed in accordance with SOP-114 Section IV. D. SHIFTING REACTOR BUILDING COOLING UNITS FAN SPEED, in order to align the plant for a normal preferred at power lineup.Mode 3.The current lineup of the RBCU's is as follows: XFN-64A and XFN-64B are running in slow speed.It is desired to run XFN-64A, XFN-64B, and XFN-65B in NORM speed in order to prepare for reactor startup.
Takes XFN 0065B-AH, 2B NORM to stop.
2013 NRC Sim JPM c RO&SRO-I: INCREASE LETDOWN FLOW TO A MAXIMUM TO IMPROVE CHEMISTRYCANDIDATE:EXAMINER:4 044-031-01-01PERFORM5NoLetdown flow is increased to about 120 gpm without ever exceeding 120 gpm. Letdown pressure controlled such that the letdown relief valve does not open.SIMULATORTIME START:TIME FINISH:SAT:UNSAT:PERFORMANCE TIME:SIGNATUREDATE45.a.6Adjust Letdown Flowrate per SOP-102.TOOLS:SOP-102 Section IV. R. SHIFTING LETDOWN ORIFICES WITH NORMAL LETDOWN IN SERVICELetdown flow at 120 gpm with PCV-145 returned to AUTO.004000A419CVCS letdown orifice isolation valve and valve control switches3.12.8A4.19 The CRS directs you as the RO to increase letdown flow to the maximum in accordance with SOP-102, Section IV.R. SHIFTING LETDOWN ORIFICES WITH NORMAL LETDOWN IN SERVICE.100% power. Chemistry has called and wants to maximize letdown to improve primary chemistry.None.WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
CUES:
Verify Initial Conditions:1.1 Letdown is in service (Letdown flow rate of 60 gpm to 120 gpm).1.2 Pressurizer level is greater than 18%.Procedure Note:  More than two Letdown Orifices may be placed in service when RCS pressure is less than or equal to 1000 psig as long as a Letdown flow rate of 120 gpm is not exceeded.Evaluator Cue:  The applicant may request further direction about what it means to raise letdown to a maximum (which valves are desired to be open). Ask for a recommendation and approve the recommendation given. The desired line up will be PVT-8149B and PVT-8149C open and PVT8149A closed.YesVerifies current letdown flow at 95 gpm.Verifies current pressurizer level is 60%.No1Place PCV-145, LO PRESS LTDN, in MAN and open to 70%.
Evaluator Note: This is where the JPM becomes alternate path.
YesPCV-145, LO PRESS LTDN, indicates MAN and open to 70%.Yes2 If necessary, close the desired Orifice Isolation Valve:a. PVT-8149A, LTDN ORIFICE A ISOL (45 gpm).B. PVT-8149B, LTDN ORIFICE B ISOL (60 gpm).
Booth Operator Cue: If called to go to XPN7077 (CB-436, TSC Equipment Room) and to select the RACK RESET and reset the alarm, report that it is complete after 5 minutes.
C. PVT-8149C, LTDN ORIFICE C ISOL (60 gpm).Evaluator Note:  PVT-8149A,  LTDN ORIFICE A ISOL (45 gpm) must be closed before PVT-8149C, LTDN ORIFICE C ISOL (60 gpm) is opened to preclude damage to the demins. If flow is allowed to exceed 120 gpm it constitutes a failure.
COMMENTS:
YesTakes  PVT-8149A, LTDN ORIFICE A ISOL (45 gpm) to CLOSE. Verifies green light lit and red light dim.Yes3Open the desired Orifice Isolation Valve:
Sunday, August 04, 2013                                                                        Page 8 of 12
: a. PVT-8149A, LTDN ORIFICE A ISOL (45 gpm).b. PVT-8149B, LTDN ORIFICE B ISOL (60 gpm).c. PVT-8149C, LTDN ORIFICE C ISOL (60 gpm).
YesTakes PVT-8149C, LTDN ORIFICE C ISOL (60 gpm), to OPEN. Verifies red light and green light dim.Yes4 Adjust PCV-145, LO PRESS LTDN, to maintain PI-145, LO PRESS LTDN PRESS PSIG, between 300 psig and 400 psig.Evaluator Note:  This step is critical in that the applicant must do it so that pressure does not exceed the letdown relief setpoint. This will be evidenced by annunciator XCP-613 2-2, LP LTDN RLF TEMP HI.YesPCV-145, LO PRESS LTDN, adjusted to maintain 300-400 psig as indicated on PI-145.Yes5Ensure PCV-145 Setpoint Pot is set between 5.0 and 6.7.
YesPCV-145 Setpoint Pot is between 5.0 and 6.7.No6 Examiner ends JPM at this point.Place PCV-145, LO PRESS LTDN, in AUTO.
YesPCV-145, LO PRESS LTDN, indicates AUTO.No7 NJPS-034A2013 NRC Sim JPM c RO&SRO-I: INCREASE LETDOWN FLOW TO A MAXIMUM TO IMPROVE CHEMISTRY10No special instructions,  Just reset to IC-10.Need to provide copies of procedure since it is not laminated in the simulator. Allow students to mark up procedure in books and then replace after JPM.
JPM SETUP SHEET The CRS directs you as the RO to increase letdown flow to the maximum in accordance with SOP-102, Section IV.R. SHIFTING LETDOWN ORIFICES WITH NORMAL LETDOWN IN SERVICE.100% power. Chemistry has called and wants to maximize letdown to improve primary chemistry.


CANDIDATE:EXAMINER:
CRITICAL:         Yes    SEQUENCED: Yes                          SAT              UNSAT STEP:      6 From ARP:
TIME START:TIME FINISH:SAT:UNSAT:PERFORMANCE TIME:SIGNATUREDATETOOLS:  
: 2. Start the non-running Reactor Building Cooling Unit fan after ensuring cooling water is lined up.
From SOP:
Place RBCUs in service by starting three or four RBCUs in SLOW or NORM as follows:
For XFN0065A-AH, REACTOR BLDG COOLING UNIT 2A EMERG FAN, start one of the following:
a) XFN 0065A-AH, 2A NORM.
STEP STANDARD:
Takes and holds XFN 0065A, 2A NORM to START until red breaker closed light is lit and starting current is indicated.
CUES:
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                          SAT             UNSAT STEP:       7 Verify RBCU Fan motor amps return to normal operating range: 1) For fast speed operation, 275 amps to 300 amps STEP STANDARD:
Verifies RBCU motor amps return to normal operating range.
CUES:
COMMENTS:
Sunday, August 04, 2013                                                                        Page 9 of 12


JPM SETUP SHEET
CRITICAL:        Yes      SEQUENCED: Yes                        SAT              UNSAT STEP:      8 Procedure Note: The RBCU TRAIN A (B) EMERG switch must be selected to an operable RBCU.
Verify the following switches are in the desired position:
: 1) XFN-64A/XFN 65A - RBCU TRAIN A EMERG.
: 2) XFN-64B/XFN 65B - RBCU TRAIN B EMERG.
STEP STANDARD:
Takes XFN-64B/XFN 65B - RBCU TRAIN B EMERG to XFN-64B position.
CUES:
Evaluator Cue: If applicant reports that an inoperable RBCU is selected for start, ask for a recommendation and approve it.
Evaluator Note: The section of XFN-64B causes XCP-6103 5-6, RB RECRIC UNIT C 3108C/ 3109C MISALIGN and XCP-6103 5-7, RB RECRIC UNIT D 3108D/ 3109D to change condition (dim/bright).
COMMENTS:
Examiner ends JPM at this point.
Sunday, August 04, 2013                                                                      Page 10 of 12


CANDIDATE:EXAMINER:
JPM SETUP SHEET JPM NO: NJPSF-159 DESCRIPTION:         2013 NRC Sim b RO&SRO-I&SRO-U: SWAP RUNNING RBCU'S IC SET: 331/4 INSTRUCTIONS:
TIME START:TIME FINISH:SAT:UNSAT:PERFORMANCE TIME:SIGNATUREDATETOOLS:  
IC 4.
Pre-Event Load Select RBCU TRAIN A EMERG to XFN-65A and select RBCU TRAIN B EMERG to XFN-65B.
Stop all RBCUs Start XFN-64A and XFN-64B in slow.
Take XDP-110A, RBCU 64A HEPA FLTR BYP DMPR and XDP-110B, RBCU 64B HEPA FLTR BYP DMPR to FILTER.
PMP-AH049B XFN0065BH RB CLG RAN HIGH BRG FAILURE Final=1.2 Event 1:
X02O104R==1 (red light lit for XFN-65B Trigger 1:
PMP-AH049T Delay=2 seconds Trip of XFN-65B.
Saved to IC 331.
COMMENTS:
Need to provide copies of procedure since is not laminated in the simulator.
Sunday, August 04, 2013                                                      Page 11 of 12


JPM SETUP SHEET  
JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:
INITIAL CONDITION: Mode 3.
The current lineup of the RBCU's is as follows: XFN-64A and XFN-64B are running in slow speed.
It is desired to run XFN-64A, XFN-64B, and XFN-65B in NORM speed in order to prepare for reactor startup.
INITIATING CUES: The CRS directs you as the RO to start XFN-64A, XFN-64B, and XFN-65B in NORM speed in accordance with SOP-114 Section IV. D.
SHIFTING REACTOR BUILDING COOLING UNITS FAN SPEED, in order to align the plant for a normal preferred at power lineup.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
Sunday, August 04, 2013


CANDIDATE:EXAMINER:
V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO:     NJPS-034A 2013 NRC Sim JPM c RO&SRO-I: INCREASE LETDOWN FLOW TO A MAXIMUM TO IMPROVE CHEMISTRY APPROVAL:           APPROVAL DATE:
TIME START:TIME FINISH:SAT:UNSAT:PERFORMANCE TIME:SIGNATUREDATE TOOLS:  
REV NO: 4 CANDIDATE:
EXAMINER:
Thursday, August 01, 2013                                          Page 1 of 9


JPM SETUP SHEET
TASK:
044-031-01-01            Adjust Letdown Flowrate per SOP-102.
TASK STANDARD:
Letdown flow is increased to about 120 gpm without ever exceeding 120 gpm.
Letdown pressure controlled such that the letdown relief valve does not open.
TERMINATING CUE:            Letdown flow at 120 gpm with PCV-145 returned to AUTO.
PREFERRED EVALUATION LOCATION                              PREFERRED EVALUATION METHOD SIMULATOR                                                      PERFORM


CANDIDATE:EXAMINER:
==REFERENCES:==
TIME START:TIME FINISH:SAT:UNSAT:PERFORMANCE TIME:SIGNATUREDATE TOOLS:  


JPM SETUP SHEET
INDEX NO.            K/A NO.                                            RO        SRO 004000A419          A4.19    CVCS letdown orifice isolation valve and  3.1        2.8 valve control switches TOOLS:            SOP-102 Section IV. R. SHIFTING LETDOWN ORIFICES WITH NORMAL LETDOWN IN SERVICE EVALUATION TIME                    5          TIME CRITICAL        No    10CFR55: 45.a.6 TIME START:                      TIME FINISH:                    PERFORMANCE TIME:
PERFORMANCE RATING:                SAT:            UNSAT:
CANDIDATE:
EXAMINER:
SIGNATURE          DATE Thursday, August 01, 2013                                                                  Page 2 of 9


2013 NRC Sim JPM h RO: RESPOND TO HIGH REACTOR BUILDING PRESSURECANDIDATE:EXAMINER:NJPS-15215 029-004-01-01PERFORM15NoRB pressure is reduced  <+0.05 and >-0.05 psig on PI-8254, RB NR PRESS PSI.Containment isolation is restored by closing the purge exhaust valves.SIMULATORTIME START:TIME FINISH:SAT:UNSAT:PERFORMANCE TIME:SIGNATUREDATE45.a.5VENT THE REACTOR BUILDINGTOOLS:SOP-114, REACTOR BUILDING VENTILATION SYSTEMHPP-709, Attachment VI, REACTOR BUILDING PURGE RELEASE PERMIT.RB purge is secured.SOP-114REACTOR BUILDING VENTILATION SYSTEM028000A401 HRPS controls4.04.0A4.01 Lower RB pressure as required in accordance with SOP-114, REACTOR BUILDING VENTILATION SYSTEM, III.P. LOWERING REACTOR BUILDING PRESSURE USING NORMAL PRESSURE CONTROL starting at step 2.5.Plant is at 100% power. Preparations are underway to conduct maintenance on the Personnel Access inner door.SOP-114,  REACTOR BUILDING VENTILATION SYSTEM, III.P. LOWERING REACTOR BUILDING PRESSURE USING NORMAL PRESSURE CONTROL is being used to lower RB pressure. All initial conditions have been met. A reactor building purge release permit has been issued in accordance with HPP-709. RM-A4 and RM-A2 are in service. RM-A4's setpoint has been adjusted in accordance with the Release Permit and step 2.4 of SOP-114, III.P. FI-8252, H2 PURGE FLOW CFM is out of service. The CRS has completed 702 Attachment VI.S-3, 6" RB PURGE OPERATING WITH IFT08252 AND/OR RMA-4 INOPERABLE, which requires that the release flowrate be estimated every 4 hours. The CRS has determined that the flow rate will be estimated at 600 cfm for the duration of the release.WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
INSTRUCTIONS TO OPERATOR READ TO OPERATOR:
Procedure Caution: To prevent damage to Alternate Purge System ducting, Alternate Purge must not be placed in service if RB pressure is greater than 3 psi.Open the following:1) PVG-6066, CNTMT PUR EXH ISOL VLV.
WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
SAFETY CONSIDERATIONS:                None.
INITIAL CONDITION: 100% power. Chemistry has called and wants to maximize letdown to improve primary chemistry.
INITIATING CUES: The CRS directs you as the RO to increase letdown flow to the maximum in accordance with SOP-102, Section IV.R. SHIFTING LETDOWN ORIFICES WITH NORMAL LETDOWN IN SERVICE.
HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!
Thursday, August 01, 2013                                                            Page 3 of 9
 
STEPS CRITICAL:          No      SEQUENCED: Yes                          SAT            UNSAT STEP:        1 Verify Initial Conditions:
1.1 Letdown is in service (Letdown flow rate of 60 gpm to 120 gpm).
1.2 Pressurizer level is greater than 18%.
Procedure Note: More than two Letdown Orifices may be placed in service when RCS pressure is less than or equal to 1000 psig as long as a Letdown flow rate of 120 gpm is not exceeded.
STEP STANDARD:
Verifies current letdown flow at 95 gpm.
Verifies current pressurizer level is 60%.
CUES:
Evaluator Cue: The applicant may request further direction about what it means to raise letdown to a maximum (which valves are desired to be open). Ask for a recommendation and approve the recommendation given. The desired line up will be PVT-8149B and PVT-8149C open and PVT8149A closed.
COMMENTS:
CRITICAL:        Yes      SEQUENCED: Yes                          SAT            UNSAT STEP:        2 Place PCV-145, LO PRESS LTDN, in MAN and open to 70%.
STEP STANDARD:
PCV-145, LO PRESS LTDN, indicates MAN and open to 70%.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                                    Page 4 of 9
 
CRITICAL:        Yes      SEQUENCED: Yes                  SAT              UNSAT STEP:      3 If necessary, close the desired Orifice Isolation Valve:
: a. PVT-8149A, LTDN ORIFICE A ISOL (45 gpm).
B. PVT-8149B, LTDN ORIFICE B ISOL (60 gpm).
C. PVT-8149C, LTDN ORIFICE C ISOL (60 gpm).
STEP STANDARD:
Takes PVT-8149A, LTDN ORIFICE A ISOL (45 gpm) to CLOSE. Verifies green light lit and red light dim.
CUES:
Evaluator Note: PVT-8149A, LTDN ORIFICE A ISOL (45 gpm) must be closed before PVT-8149C, LTDN ORIFICE C ISOL (60 gpm) is opened to preclude damage to the demins. If flow is allowed to exceed 120 gpm it constitutes a failure.
COMMENTS:
CRITICAL:        Yes      SEQUENCED: Yes                  SAT              UNSAT STEP:      4 Open the desired Orifice Isolation Valve:
: a. PVT-8149A, LTDN ORIFICE A ISOL (45 gpm).
: b. PVT-8149B, LTDN ORIFICE B ISOL (60 gpm).
: c. PVT-8149C, LTDN ORIFICE C ISOL (60 gpm).
STEP STANDARD:
Takes PVT-8149C, LTDN ORIFICE C ISOL (60 gpm), to OPEN. Verifies red light and green light dim.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                                Page 5 of 9
 
CRITICAL:        Yes        SEQUENCED: Yes                            SAT            UNSAT STEP:      5 Adjust PCV-145, LO PRESS LTDN, to maintain PI-145, LO PRESS LTDN PRESS PSIG, between 300 psig and 400 psig.
STEP STANDARD:
PCV-145, LO PRESS LTDN, adjusted to maintain 300-400 psig as indicated on PI-145.
CUES:
Evaluator Note: This step is critical in that the applicant must do it so that pressure does not exceed the letdown relief setpoint. This will be evidenced by annunciator XCP-613 2-2, LP LTDN RLF TEMP HI.
COMMENTS:
CRITICAL:          No      SEQUENCED: Yes                            SAT            UNSAT STEP:      6 Ensure PCV-145 Setpoint Pot is set between 5.0 and 6.7.
STEP STANDARD:
PCV-145 Setpoint Pot is between 5.0 and 6.7.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                                          Page 6 of 9
 
CRITICAL:          No  SEQUENCED: Yes SAT UNSAT STEP:      7 Place PCV-145, LO PRESS LTDN, in AUTO.
STEP STANDARD:
PCV-145, LO PRESS LTDN, indicates AUTO.
CUES:
COMMENTS:
Examiner ends JPM at this point.
Thursday, August 01, 2013                          Page 7 of 9
 
JPM SETUP SHEET JPM NO: NJPS-034A DESCRIPTION:          2013 NRC Sim JPM c RO&SRO-I: INCREASE LETDOWN FLOW TO A MAXIMUM TO IMPROVE CHEMISTRY IC SET: 10 INSTRUCTIONS:
No special instructions, Just reset to IC-10.
COMMENTS:
Need to provide copies of procedure since it is not laminated in the simulator. Allow students to mark up procedure in books and then replace after JPM.
Thursday, August 01, 2013                                                                      Page 8 of 9
 
JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:
INITIAL CONDITION: 100% power. Chemistry has called and wants to maximize letdown to improve primary chemistry.
INITIATING CUES: The CRS directs you as the RO to increase letdown flow to the maximum in accordance with SOP-102, Section IV.R. SHIFTING LETDOWN ORIFICES WITH NORMAL LETDOWN IN SERVICE.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
Thursday, August 01, 2013
 
V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO:    NJPSF-059B 2013 NRC Sim JPM d RO&SRO-I: ALTERNATE ISOLATION OF RUPTURED SG ("C" MSIV FAILS TO CLOSE)
APPROVAL:          APPROVAL DATE:
REV NO: 15 CANDIDATE:
EXAMINER:
Thursday, August 01, 2013                                            Page 1 of 18
 
TASK:
000-504-05-01            Perform Ruptured Steam Generator Isolation.
TASK STANDARD:
The "C" SG is completely isolated from the "A" and "B" SG's per EOP-4.0, steps 3.a - 3h, and step 3.i alternate actions.
TERMINATING CUE:            EOP-4.0, step 3.i complete.
PREFERRED EVALUATION LOCATION                                PREFERRED EVALUATION METHOD SIMULATOR                                                    PERFORM
 
==REFERENCES:==
EOP-4.0                  STEAM GENERATOR TUBE RUPTURE INDEX NO.            K/A NO.                                            RO            SRO 000038A132          EA1.32    Isolation of a ruptured S/G              4.6            4.7 TOOLS:            EOP-4.0, STEAM GENERATOR TUBE RUPTURE EVALUATION TIME                    15          TIME CRITICAL    NO    10CFR55: 45.a.6 TIME START:                        TIME FINISH:                  PERFORMANCE TIME:
PERFORMANCE RATING:                  SAT:            UNSAT:
CANDIDATE:
EXAMINER:
SIGNATURE              DATE Thursday, August 01, 2013                                                                    Page 2 of 18
 
INSTRUCTIONS TO OPERATOR READ TO OPERATOR:
WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SAFETY CONSIDERATIONS:
INITIAL CONDITION: The "C" Steam Generator has experienced a tube rupture. The crew has taken actions through step 2 of EOP-4.0, STEAM GENERATOR TUBE RUPTURE. The RO has been assigned to monitor RCP trip criteria of step 1.
INITIATING CUES: The CRS has directed you as the BOP to isolate the "C" SG in accordance with EOP-4.0, STEAM GENERATOR TUBE RUPTURE, step 3.
HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!
Thursday, August 01, 2013                                                              Page 3 of 18
 
STEPS CRITICAL:          No    SEQUENCED: Yes                        SAT            UNSAT STEP:      1 Procedure Caution: At least one SG must be maintained available for RCS cooldown.
Place the Steamline PWR RELIEF A(B)(C) SETPT Controller(s) in MAN and closed.
STEP STANDARD:
"C" Steamline PWR RELIEF SETPT controller MAN pushbutton is depressed and decrease pushbutton is depressed so that both MAN and decrease pushbuttons are illuminated. Controller output will also read 0.
CUES:
Evaluator Note: There is not a demand for the PORV to be open and so taking the controller to MAN and closed is not critical.
COMMENTS:
CRITICAL:        Yes      SEQUENCED: Yes                        SAT            UNSAT STEP:      2 Adjust the PWR RELIEF A(B)(C) SETPT Controller(s) to 8.85 (1150 psig).
STEP STANDARD:
"C" Steamline PWR RELIEF SETPT controller turned so that it indicates 8.85 (1150 psig).
CUES:
COMMENTS:
Thursday, August 01, 2013                                                                  Page 4 of 18
 
CRITICAL:          No      SEQUENCED: Yes                              SAT              UNSAT STEP:      3 Place the Steamline Power Relief A(B)(C) Mode Switch(s) in PWR RLF.
STEP STANDARD:
"C" Steamline Power Relief mode switch taken to PWR RLF.
CUES:
COMMENTS:
CRITICAL:        Yes      SEQUENCED: Yes                              SAT              UNSAT STEP:      4 Place the PWR RELIEF A(B)(C) SETPT Controller(s) in AUTO.
STEP STANDARD:
"C" Steamline PWR RELIEF SETPT controller AUTO pushbutton is pressed. AUTO pushbutton illuminates.
CUES:
Evaluator Note: It is only critical that the controller be left in AUTO at the end of the JPM. If the controller was never taken to Manual and Closed then this step is not critical.
COMMENTS:
Thursday, August 01, 2013                                                                          Page 5 of 18
 
CRITICAL:          No    SEQUENCED: Yes                          SAT              UNSAT STEP:      5 WHEN RCS Tavg is LESS THAN P-12 (552&deg;F), THEN place both STM DUMP INTERLOCK Switches to BYP INTLK.
STEP STANDARD:
Both STM DUMP INTERLOCK switches indicate BYP INTLK (red flag) when RCS Tavg <552&deg;F.
CUES:
Evaluator Note: If RCS Tavg is >552&deg;F then this step is not performed at this time.
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                          SAT              UNSAT STEP:      6 Verify the Steamline PORV closed.
STEP STANDARD:
PCV-2020 indicates red light off, green light on. Demand on controller is zero.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                                  Page 6 of 18
 
CRITICAL:        Yes        SEQUENCED: Yes                      SAT              UNSAT STEP:      7 Procedure Caution: If the TD EFW Pump is the only available source of feed flow, the steam supply to the TD EFW Pump must be maintained from at least one SG, to maintain a secondary heat sink.
Procedure Note: If the TD EFW Pump is tripped, it should be reset as time permits.
IF SG B OR SG C is RUPTURED, THEN perform the following:
: 1) IF at least one MD EFW Pump is running, THEN isolate the TD EFW Pump by placing PVG-2030, STM SPLY TO TD EFP TRN A(B), to CLOSE.
STEP STANDARD:
Both switches for PVG-2030 are taken to close. PVG-2030 STM SPLY TO TD EFP TRN A (B) indicates red light off and green light on.
CUES:
Evaluator Note: Both PVG-2030 switches must be taken to close before the valve closes.
Booth Operator Cue: When called to reset the TD EFW Pump use the LOA resets page or trigger
#1 to reset TD EFW Pump after it comes to a stop.
COMMENTS:
Thursday, August 01, 2013                                                                  Page 7 of 18
 
CRITICAL:          No      SEQUENCED: Yes                          SAT              UNSAT STEP:      8 Notify local Operators to perform Alternate Action Step 3.g, while continuing with this procedure.
STEP STANDARD:
Calls local operator to perform Alternate Action Step 3.g CUES:
Booth Operator Cue: When called to perform Alternate Action Step 3.g use trigger #2 and #3 to do so.
Booth Operator Note: If called for repeat back of Alternate Action Step 3.g it is as follows for SG C:
: 1) Open XMC1DB2Y 05EH, EMERG FEEDWATER PUMP MAIN STEAM BLOCK XVG2802B-MS (AB-463). Trigger #2 Unit 6U
: 2) Close XVG02802B-MS, MS HEADER C EF PUMP TURBINE SUPPLY VLV (IB-436 East Pen).
Trigger #3 Unit 7.
COMMENTS:
Thursday, August 01, 2013                                                                        Page 8 of 18
 
CRITICAL:          No    SEQUENCED: Yes                      SAT              UNSAT STEP:      9 Close the following for each RUPTURED SG:
SG Blowdown, PVG-503A(B)(C).
STEP STANDARD:
PVG-503C indicates red light off, green light on.
CUES:
Evaluator Note: PVG-503C is already closed on EFW pump start and so there is no action here.
COMMENTS:
CRITICAL:        Yes      SEQUENCED: Yes                      SAT              UNSAT STEP:      10 Close the following for each RUPTURED SG:
MS Drain Isolation, PVT-2843A(B)(C).
STEP STANDARD:
Takes PVT-2843C to close. PVT-2843C indicates red light OFF, green light ON.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                                Page 9 of 18
 
CRITICAL:        Yes      SEQUENCED: Yes                      SAT          UNSAT STEP:      11 Close the following for each RUPTURED SG:
MS Drain Isolation, PVT-2877A for SG A PVT-2877B for SG C.
STEP STANDARD:
Takes PVT-2877B to close. PVT-2877B indicates red light OFF, green light ON.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                          Page 10 of 18
 
CRITICAL:          No      SEQUENCED: Yes                          SAT              UNSAT STEP:      12 Close the following for each RUPTURED SG:
- MS Isolation Valve, PVM-2801A(B)(C).
- MS Isolation Bypass Valve, PVM-2869A(B)(C).
STEP STANDARD:
Takes PVM-2801C to close.
Notes MS Isolation Valve, PVM-2801C still indicates red light on, green light off (MSIV failed to close).
MS Isolation Bypass Valve, PVM-2869C indicates red light off, green light on.
CUES:
Evaluator Note: Operator may send someone out to locally close the "C" MSIV while proceeding.
Evaluator Note: This is when the JPM becomes alternate path.
Booth Operator Cue: If called to locally close the "C" MSIV wait 5 minutes and report that you have bleed air off the "C" MSIV but it did not go closed.
COMMENTS:
Thursday, August 01, 2013                                                                    Page 11 of 18
 
CRITICAL:        Yes      SEQUENCED: Yes                        SAT            UNSAT STEP:      13
: 1) Close the following:
All remaining MS Isolation and MS Isolation Bypass Valves.
STEP STANDARD:
Takes individual MSIV switches PVM-2801A&B, A(B) ISOL VLV or common switch PVM-2801A,B,C, MS LINES ISOL VLVS to close. MS PVM-2801A&B, MS ISOLATION VALVE, PVM-2869A&B, MS ISOLATION BYPASS VALVE, indicate red light off and green light on.
CUES:
Evaluator Note: This step can be accomplished in two ways. The individual MSIVs can be closed or the common switch can be used. The bypass valves are already closed and so its not critical to close them.
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                        SAT            UNSAT STEP:      14
: 1) Close the following:
PCV-2058, MS TO AUX STM STEP STANDARD:
PCV-2058, MS TO AUX STM, indicates red light off and green light on.
CUES:
Evaluator Note: PCV-2058, MS TO AUX STM is already closed and so this requires no action.
COMMENTS:
Thursday, August 01, 2013                                                                Page 12 of 18
 
CRITICAL:        Yes        SEQUENCED: Yes                SAT            UNSAT STEP:      15
: 1) Close the following:
MVG-1701, STEAM SEAL FEED VLV STEP STANDARD:
MVG-1701 is taken to close. MVG-1701, STEAM SEAL FEED VLV, indicates red light off and green light on.
CUES:
COMMENTS:
CRITICAL:        Yes        SEQUENCED: Yes                SAT            UNSAT STEP:      16
: 1) Close the following:
MVG-2896A, SV-1 BSD.
MVG-2896B, SV-2 BSD.
MVG-2896C, SV-3 BSD.
MVG-2896D, SV-4 BSD.
STEP STANDARD:
Takes MVG-2896A-D, SV-1 (2,3,4) BSD to close. MVG-2896A-D, SV-1 (2,3,4) BSD, indicates red light off and green light on.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                            Page 13 of 18
 
CRITICAL:          No      SEQUENCED: Yes                          SAT            UNSAT STEP:      17
: 1) Close the following:
IPV-2231, MS/PEGGING STM TO DEAERATOR.
STEP STANDARD:
Places IPV-2231, MS/PEGGING STM TO DEAERATOR, controller in MAN and output of 0%.
CUES:
Evaluator Note: IPV-2231 is already closed and so this step is not critical.
COMMENTS:
CRITICAL:          No      SEQUENCED: Yes                          SAT            UNSAT STEP:      18
: 2) At the Digital Control Station for the MSRs, ensure the following are closed:
MVG-2811.
XVG-2807.
STEP STANDARD:
At MSR DCS terminal, MVG-2811 and XVG-2807 indicate closed.
CUES:
Evaluator Note: These valves are in there required positions and so action is taken.
COMMENTS:
Thursday, August 01, 2013                                                                  Page 14 of 18
 
CRITICAL:        Yes      SEQUENCED: Yes                            SAT            UNSAT STEP:      19
: 3) Place the STM DUMP CNTRL Controller in MAN and closed.
STEP STANDARD:
Pushes STM DUMP CNTRL controller MAN pushbutton. Pushes decrease pushbutton as necessary to set controller to 0. MAN and decrease pushbuttons illuminated with 0% output on controller.
CUES:
COMMENTS:
CRITICAL:          No      SEQUENCED: Yes                            SAT            UNSAT STEP:      20
: 4) Place the STM DUMP MODE SELECT Switch in STM PRESS.
STEP STANDARD:
STM DUMP MODE SELECT Switch in STM PRESS.
CUES:
Evaluator Note: This step is not critical if the steam dumps are already taken to manual and closed.
COMMENTS:
Thursday, August 01, 2013                                                                    Page 15 of 18
 
CRITICAL:          No      SEQUENCED: Yes                            SAT            UNSAT STEP:      21
: 5) Place the following in AUTO and ensure the valves are closed (REFER TO ATTACHMENT 1, ALTERNATE ISOLATION OF RUPTURED STEAM GENERATORS, if necessary to locally isolate valves):
PVT-2870, TO MSR A & B DRN.
PVT-2875, TO MSR A & B DRN.
PVT-2851A,B,C,D, MS LINES TO TURB DRN.
PVT-2713A,B,C,D, STM DUMP DRN BYP.
PVT-2838A,B, HDR DRNS.
: 6) Direct the Turbine Building Operator to complete ATTACHMENT 1, ALTERNATE ISOLATION OF RUPTURED STEAM GENERATORS.
STEP STANDARD:
Notes PVT-2870, To MSR A&B DRN indicates mid-position with red and green light on.
Directs Turbine Building Operator to complete ATTACHMENT 1, ALTERNATE ISOLATION OF RUPTURED STEAM GENERATORS. Including alternate isolation for PVT-2870 by closing XVT02871A-MS, MSR A&B MS SUP HDR DRAIN POT OUTLET VLV at TB-412-G-02.
The following valve switches are in AUTO with red light OFF and green light ON:
- PVT-2875, TO MSR A&B DRN
- PVT-2851A-D, MS LINES TO TURB DRN
- PVT-2713A-D, STEAM DUMP DRN BYP
- PVT-2838A,B, HDR DRNS.
CUES:
Evaluator Note: Step one of Attachment 1 is always done and step two contains backup valves for any valves that fail to close. The TB operator will be called to close XVT02871A-MS, MSR A&B MS SUP HDR DRAIN POT OUTLET VLV at TB-412-G-02 as well as to perform step one of Attachment 1.
Evaluator Note: Due to the complexity of this task the applicant may call an auxiliary operator to the control room to effectively communicate the desired local actions.
Evaluator Note: The JPM can be stopped once the order to complete Attachment 1 is given. There are no observable actions here other than ordering the local operator to complete the necessary tasks.
COMMENTS:
Examiner ends JPM at this point.
Thursday, August 01, 2013                                                                    Page 16 of 18
 
JPM SETUP SHEET JPM NO: NJPSF-059B DESCRIPTION:          2013 NRC Sim JPM d RO&SRO-I: ALTERNATE ISOLATION OF RUPTURED SG ("C" MSIV FAILS TO CLOSE)
IC SET: 333/ 10 INSTRUCTIONS:
Start at IC 10: Saved to IC 333 for 2013 NRC exam.
MAL-RCS002C STEAM GENERATOR C TUBE LEAK Final=400 RAMP=00:00:30 (SGTR ON
'C' S/G)
MAL-MSS006C MAIN STEAM ISOLATION VALVE (S/G C) FAILURE Final= FAIL TO CLOSE (C MSIV FAIL TO CLOSE)
VLV-MS041P XVT02870-MS MS LINE TO MOSS SEP DEP DRN FAIL POSITION Final = 80 (2870 Failed 80% open)
Manual SI and perform actions of EOP-1.0 & EOP-4.0 up through step 2.
Throttle EFW flow to 'C' S/G when > 40% level.
Silence HVAC alarms.
This is where IC is saved.
RUN 5 seconds day of and acknowledge annunciators When student is ready: RUN Local Operator Actions when instructed:
Trigger #1: EOP-4.0, STEAM GENERATOR TUBE RUPTURE, 3.g LOA-MSS026 EMERGENCY FW TDFP MN STM THROTTLE VLV 2865 RESET Final=RESET (Reset TDEFW pump once RPMs reach 0.0.
Trigger #2: EOP-4.0, STEAM GENERATOR TUBE RUPTURE, Alternate action 3.g LOA-MSS033 TDEFP STM SUP VLV 2802B BRK Final=OPEN (Open XMC1DB2Y 05EH, EF PUMP MAIN STEAM BLOCK XVG2802B-MS (AB-463)
Trigger #3: EOP-4.0, STEAM GENERATOR TUBE RUPTURE, Alternate action 3.g VLV-MS009P XVG02802B-MS MS LP C TO TD EF PMP FAIL POSITION Final=0, Ramp=00:00:30 (CLOSE XVG02802B-MS, MS HEADER C EF PUMP TURBINE SUPPLY VLV (IB-436 East Pen).
EOP-4.0, STEAM GENERATOR TUBE RUPTURE, Alternate Action 3.i.5) refer to Attachment 1, ALTERNATE ISOLATION OF RUPTURED STEAM GENERATORS PVT-2870, TO MSR A & B DRN.
Currently there is no modeling of XVT02871A-MS MSR A&B MS SUP HDR DRAIN POT OUTLET VLV (TB-412) but report that it is closed .
COMMENTS:
Circle and slash up to step 3.0 of EOP-4.0, STEAM GENERATOR TUBE RUPTURE.
Thursday, August 01, 2013                                                        Page 17 of 18
 
JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:
INITIAL CONDITION: The "C" Steam Generator has experienced a tube rupture. The crew has taken actions through step 2 of EOP-4.0, STEAM GENERATOR TUBE RUPTURE. The RO has been assigned to monitor RCP trip criteria of step 1.
INITIATING CUES: The CRS has directed you as the BOP to isolate the "C" SG in accordance with EOP-4.0, STEAM GENERATOR TUBE RUPTURE, step 3.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
Thursday, August 01, 2013
 
V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO:    NJPS-151 2013 NRC Sim JPM e RO&SRO-I: SHIFT RHR LOOPS WITH RHR IN SERVICE APPROVAL:          APPROVAL DATE:
REV NO: 4 CANDIDATE:
EXAMINER:
Thursday, August 01, 2013                                          Page 1 of 15
 
TASK:
005-001-01-01            Perform Lineups of the Residual Heat Removal System TASK STANDARD:
RHR train "A" is providing core cooling. RHR Train "B" is secured. RCS temperatures remain less than 200&deg;F to preclude unplanned/allowed entry into MODE 4.
TERMINATING CUE:            RHR Train "A" is in service with RHR Train "B" shut down.
PREFERRED EVALUATION LOCATION                              PREFERRED EVALUATION METHOD SIMULATOR                                                      PERFORM
 
==REFERENCES:==
SOP-115                RESIDUAL HEAT REMOVAL INDEX NO.            K/A NO.                                            RO          SRO 005000A401          A4.01    Controls and indication for RHR pumps      3.6        3.4 TOOLS:            SOP-115, RESIDUAL HEAT REMOVAL EVALUATION TIME                    20          TIME CRITICAL      NO      10CFR55: 45.a.7 TIME START:                      TIME FINISH:                    PERFORMANCE TIME:
PERFORMANCE RATING:                SAT:            UNSAT:
CANDIDATE:
EXAMINER:
SIGNATURE            DATE Thursday, August 01, 2013                                                                  Page 2 of 15
 
INSTRUCTIONS TO OPERATOR READ TO OPERATOR:
WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
SAFETY CONSIDERATIONS:
INITIAL CONDITION: Plant heatup is in progress in accordance with GOP-2, PLANT STARTUP AND HEATUP (MODE 5 TO MODE 3).
The crew has performed all steps up to step 3.4 of GOP-2 and is currently drawing a bubble with pressurizer level on scale on wide range level.
The ABLL has reported that the "B" RHR Pump bearing is making loud unusual noises and is worried about damage to the pump since it is vibrating excessively.
The CRS and Shift Supervisor have determined that "A" RHR loop be placed in service and the plant maintained in Mode 5.
INITIATING CUES: The CRS directs you as the RO to shift from RHR Train "B" to RHR Train "A" running in accordance with SOP-115, RESIDUAL HEAT REMOVAL, section III.E, SHIFTING FROM RHR TRAIN B TO RHR TRAIN A RUNNING, starting with step 2.1.
                          "A" CCW will remain the active loop.
HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!
Thursday, August 01, 2013                                                                    Page 3 of 15
 
STEPS CRITICAL:          No      SEQUENCED: Yes                          SAT            UNSAT STEP:      1 Procedure Caution:
: a. Performance of this procedure while RCS Hot Leg temperatures are greater than or equal to 200&deg;F renders both RHR Loops incapable of being aligned to the RWST (reference Technical Specification 3.5.3.d) until the Hot Leg temperatures are reduced to less than 200&deg;F.
: b. Unless Plant conditions absolutely require shifting trains of RHR, this procedure should not normally be utilized in Mode 4.
: c. PCV-145, LO PRESS LTDN, must be in MAN if starting or stopping an RHR Pump with the primary system solid with RHR letdown flow via HCV-142, LTDN FROM RHR.
Ensure the following valves are energized and open per GOP-6, Plant Shutdown From Hot Standby To Cold Shutdown (Mode 3 To Mode 5):
: a. MVG-8701A, RCS LP A TO PUMP A.
B. MVG-8702A, RCS LP A TO PUMP A.
STEP STANDARD:
Verifies MVG-8701A and MVG-8702A are energized and open - Red lights ON, green lights OFF CUES:
COMMENTS:
Thursday, August 01, 2013                                                                      Page 4 of 15
 
CRITICAL:          No    SEQUENCED: Yes                        SAT          UNSAT STEP:      2 Ensure Train "A" Component Cooling is aligned to supply RHR Heat Exchanger "A" per SOP-118 STEP STANDARD:
Determines that "A" Component Cooling is aligned to supply the "A" RHR heat exchanger by verifying that MVB-9503A, CC TO RHR HX A, is open and that flow is indicated on FI-7034, HX A FLOW GPM.
CUES:
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                        SAT          UNSAT STEP:      3 Close HCV-603A, A Outlet STEP STANDARD:
Rotates controller for HCV-603A fully counter-clockwise CUES:
COMMENTS:
Thursday, August 01, 2013                                                                Page 5 of 15
 
CRITICAL:          No    SEQUENCED: Yes                      SAT UNSAT STEP:      4 Place FCV-605A, A BYP, in MAN and adjust to 100%
STEP STANDARD:
Places controller for FCV-605A in MANUAL and adjusts output to 100%
CUES:
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                      SAT UNSAT STEP:      5 Readjust FCV-605A, A BYP, in MAN to 40%.
STEP STANDARD:
Adjusts output for FCV-605A to 40%
CUES:
COMMENTS:
Thursday, August 01, 2013                                                  Page 6 of 15
 
CRITICAL:            No      SEQUENCED: Yes                            SAT            UNSAT STEP:        6 Place PCV-145, LO PRESS LTDN, in MAN STEP STANDARD:
Places controller for PCV-145 in MANUAL CUES:
COMMENTS:
CRITICAL:          Yes      SEQUENCED: Yes                            SAT            UNSAT STEP:        7 Procedure Note:
: a. RHR Pump run time on miniflow should not be permitted to exceed 30 minutes.
: b. After each RHR Pump start, IFI00602A (AB-374) indication should be evaluated to verify proper operation of IFV0602A.
Start XPP-0031A, Pump A STEP STANDARD:
Places RHR Pump "A" control switch in START. Verifies amps and control switch indication turns red.
CUES:
Booth Operator Cue: If called to check out the RHR pump for start report that the pump is good for start. If called to investigate the pump after start, report that the pump looks good after start. When called to investigate IFI00602A report that flow is 1000 gpm.
Evaluator Note: Applicant will ask for a peer check as required by the procedure. Acknowledge that the applicant would ask for a peer check.
COMMENTS:
Thursday, August 01, 2013                                                                          Page 7 of 15
 
CRITICAL:          No      SEQUENCED: Yes                          SAT                UNSAT STEP:      8 Place PCV-145, LO PRESS LTDN, in AUTO STEP STANDARD:
Places controller for PCV-145 in AUTOMATIC CUES:
COMMENTS:
CRITICAL:        Yes        SEQUENCED: Yes                          SAT                UNSAT STEP:      9 Equalize flow between the two RHR loops by slowly opening FCV-605A, A BYP.
STEP STANDARD:
Observing flow, slowly increases the output of the controller for FCV-605A until flows are approximately equal.
CUES:
Evaluator Note: Flow will not totally equalize between the two loops. It is critical that "A" loop RHR flow is established not that flows are brought to be equal.
COMMENTS:
Thursday, August 01, 2013                                                                        Page 8 of 15
 
CRITICAL:          No      SEQUENCED: Yes                        SAT            UNSAT STEP:      10 Place FCV-605A, A BYP, in AUTO.
STEP STANDARD:
FCV-605A, A BYP, in AUTO CUES:
COMMENTS:
CRITICAL:          No      SEQUENCED: Yes                        SAT            UNSAT STEP:      11 Procedure Caution: In Mode 6, RHR flow must be greater than 2800 gpm per Technical Specifications 3.9.7.1 and 3.9.7.2.
Procedure Note: If RCPs or two trains of RHR are running, RHR flow may be less than 3750 gpm.
FCV-605A controller setpoint may need to be adjusted to less than the normal flow setpoint to improve temperature control while cooling down.
Ensure FCV-605A, A BYP, modulates to maintain between 2000 GPM and 3750 GPM as indicated on FI-605A, PUMP A FLOW GPM.
STEP STANDARD:
Verifies indicated flow on FI-605A is between 2000 and 3750 GPM.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                                    Page 9 of 15
 
CRITICAL:          No      SEQUENCED: Yes                          SAT              UNSAT STEP:      12 Shift Letdown from RHR Train B to RHR Train A as follows (AB-412):
Open XVT08720A-RH, LETDOWN HDR RH RETURN HDR A INLET VALVE Close XVT08720B-RH, LETDOWN HDR RH RETURN HDR B INLET VALVE STEP STANDARD:
Directs operator to perform valve alignment CUES:
Booth Operator Cue: When called to Open XVT-8702A use Trigger 1 to open the valve.
When called to close XVT8702B use Trigger 2 to close the valve.
COMMENTS:
CRITICAL:        Yes        SEQUENCED: Yes                          SAT              UNSAT STEP:      13 Align RHR Loop B for Standby Operation as follows:
Shift all heat removal to Loop A by slowly opening HCV-603A, A OUTLET, while adjusting HCV-603B, B OUTLET, closed STEP STANDARD:
Adjusts HCV-603A in the clockwise direction and HCV-603B in the counter clockwise direction while maintaining approximately the same total RHR flow.
Continues to throttle HCV-603A open and HCV-603B closed until all flow is on Train "A" CUES:
Evaluator Note: It is critical that RCS temperature at the RHR inlet is not allowed to increase above 200&deg;F because this would be an unplanned mode change into MODE 4.
COMMENTS:
Thursday, August 01, 2013                                                                      Page 10 of 15
 
CRITICAL:          No    SEQUENCED: No                        SAT          UNSAT STEP:      14 Close HCV-603B, B OUTLET STEP STANDARD:
Rotates controller for HCV-603B fully counter clockwise CUES:
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                        SAT          UNSAT STEP:      15 Place FCV-605B, B BYP, in MAN and adjust to 40%
STEP STANDARD:
Places controller for FCV-605B in MANUAL and adjusts controller output to 40%
CUES:
COMMENTS:
Thursday, August 01, 2013                                                          Page 11 of 15
 
CRITICAL:          Yes      SEQUENCED: Yes                        SAT          UNSAT STEP:        16 Secure the RHR Pump B as follows:
: 1) If the primary system is solid, a) Place PCV-145, LO PRESS LTDN, in MAN.
b) Stop XPP-0031B, PUMP B.
c) Place PCV-145, LO PRESS LTDN, in AUTO.
: 2) If there is a steam bubble in the Pressurizer, stop XPP-0031B, PUMP B.
STEP STANDARD:
Places "B" RHR Pump Control Switch in STOP. Observes green light on, red light off. Amps go to zero.
CUES:
Evaluator Note: There is a bubble in the Pressurizer.
Evaluator Cue: Cue the applicant as the CRS to place the B RHR pump control switch in PTL for maintenance to look at the pump.
COMMENTS:
CRITICAL:          No      SEQUENCED: Yes                        SAT          UNSAT STEP:        17 Close FCV-605B, B BYP STEP STANDARD:
Adjusts the controller for FCV-605B to 0%
CUES:
COMMENTS:
Thursday, August 01, 2013                                                              Page 12 of 15
 
CRITICAL:          No      SEQUENCED: No          SAT UNSAT STEP:      18 Open HCV-603B, B OUTLET STEP STANDARD:
Adjusts the controller for HCV-603B fully clockwise CUES:
COMMENTS:
Examiner ends JPM at this point.
Thursday, August 01, 2013                                    Page 13 of 15
 
JPM SETUP SHEET JPM NO: NJPS-151 DESCRIPTION:          2013 NRC Sim JPM e RO&SRO-I: SHIFT RHR LOOPS WITH RHR IN SERVICE IC SET: 334/2 INSTRUCTIONS:
Start with IC 2. IC set 2 is collapsing the bubble. Change parameters to slowly draw a bubble.
Stabilize RCS pressure 350-400 psig and RCS temperature at ~188&deg;F (Open CCW "A" to RHR HX).
Saved to IC 334.
Trigger 1:8720A (open) LOA-RHR001 Final=1 Trigger 2: 8702B (close) LOA-RHR002 Final =0 COMMENTS:
Thursday, August 01, 2013                                                                  Page 14 of 15
 
JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:
INITIAL CONDITION: Plant heatup is in progress in accordance with GOP-2, PLANT STARTUP AND HEATUP (MODE 5 TO MODE 3).
The crew has performed all steps up to step 3.4 of GOP-2 and is currently drawing a bubble with pressurizer level on scale on wide range level.
The ABLL has reported that the "B" RHR Pump bearing is making loud unusual noises and is worried about damage to the pump since it is vibrating excessively.
The CRS and Shift Supervisor have determined that "A" RHR loop be placed in service and the plant maintained in Mode 5.
INITIATING CUES: The CRS directs you as the RO to shift from RHR Train "B" to RHR Train "A" running in accordance with SOP-115, RESIDUAL HEAT REMOVAL, section III.E, SHIFTING FROM RHR TRAIN B TO RHR TRAIN A RUNNING, starting with step 2.1.
                          "A" CCW will remain the active loop.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
Thursday, August 01, 2013
 
V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO:    NJPSF-161 2013 NRC Sim JPM f RO&SRO-I: RESPOND TO A FEED REGULATING VALVE CLOSURE AT LOW POWER APPROVAL:          APPROVAL DATE:
REV NO: 3 CANDIDATE:
EXAMINER:
Thursday, August 01, 2013                                              Page 1 of 10
 
TASK:
000-147-05-01            Respond to Feedwater Flow Control Valve Failure per AOP-201.1.
TASK STANDARD:
    "A" steam generator level is controlled by the operator without causing an automatic reactor trip.
TERMINATING CUE:            "A" S/G level is under control of the operator with the main feed reg bypass valve.
PREFERRED EVALUATION LOCATION                                PREFERRED EVALUATION METHOD SIMULATOR                                                        PERFORM
 
==REFERENCES:==
 
INDEX NO.            K/A NO.                                              RO              SRO 059000A212          A2.12    Failure of feedwater regulating valves      3.1            3.4 TOOLS:            AOP-210.1, FEEDWATER FLOW CONTROL VALVE FAILURE EVALUATION TIME                      5          TIME CRITICAL        NO    10CFR55: 45.a.3 TIME START:                        TIME FINISH:                      PERFORMANCE TIME:
PERFORMANCE RATING:                SAT:            UNSAT:
CANDIDATE:
EXAMINER:
SIGNATURE                DATE Thursday, August 01, 2013                                                                        Page 2 of 10
 
INSTRUCTIONS TO OPERATOR READ TO OPERATOR:
WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
SAFETY CONSIDERATIONS:              None.
INITIAL CONDITION: 15% power BOL.
INITIATING CUES: Respond to developing plant conditions as the BOP operator.
HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!
Thursday, August 01, 2013                                                    Page 3 of 10
 
STEPS CRITICAL:          No      SEQUENCED: Yes                          SAT              UNSAT STEP:      1 Diagnose entry into AOP-210.1, FEEDWATER FLOW CONTROL VALVE FAILURE.
Procedure Note: Throughout this procedure, "AFFECTED" refers to any Feedwater Flow Control Valve that has failed open, closed, or does NOT respond to demand.
: 1. Abnormal indication on the associated Feedwater Flow Control Valve controller:
PVT-478, SG A FWF.
PVT-488, SG B FWF.
PVT-498, SG C FWF.
: 2. Any of the following Main Control Board annunciators in alarm:
SG A(B)(C) STF>FWF MISMATCH (XCP-624 4-3(5-3)(6-3)).
SG A(B)(C) FWF>STF MISMATCH (XCP-624 4-4(5-4)(6-4)).
SG A(B)(C) LVL DEV (XCP-624 1-5(2-5)(3-5)).
SG A(B)(C) LVL LO (XCP-624 1-3(2-3)(3-3)).
SG A(B)(C) LVL HI-HI (XCP-624 1-1(2-1)(3-1)).
SG A(B)(C) LVL LO-LO (XCP-624 1-2(2-2)(3-2)).
STEP STANDARD:
Diagnoses that PVT-478, SG A FWF is closing and enters AOP-210.1, FEEDWATER FLOW CONTROL VALVE FAILURE.
CUES:
Evaluator Note: The applicant may attempt to utilize the ARP actions to correct the level deviations but opening of the bypass valve is unique to the AOP.
Evaluator Note: Allow the applicant to pick the desired procedure from the list of AOPs and then provide AOP-210.1 from the drawer.
COMMENTS:
Thursday, August 01, 2013                                                                    Page 4 of 10
 
CRITICAL:          No    SEQUENCED: Yes                            SAT              UNSAT STEP:      2 Manually adjust the AFFECTED Feedwater Flow Control Valve as necessary to maintain Narrow Range SG level between 60% and 65%:
PVT-478, SG A FWF.
STEP STANDARD:
Attempts to take manual control of PVT-478, SG A FWF, but determines that the valve will not open manually.
CUES:
Evaluator Note: This is an immediate operator action and applicant may do this step without aid of the procedure although that is not required as long as the plant is brought to a stable condition.
COMMENTS:
Thursday, August 01, 2013                                                                        Page 5 of 10
 
CRITICAL:          No    SEQUENCED: Yes                            SAT              UNSAT STEP:      3 Adjust Feedwater Pump speed and Main Turbine load as necessary to maintain SG level. Do NOT exceed 1600 psig Feedwater Pump discharge pressure.
STEP STANDARD:
Raises MFP speed. Does not exceed 1600 psig Feedwater Pump discharge pressure.
CUES:
Evaluator Note: This is an immediate operator action and applicant may do this step without aid of the procedure although that is not required as long as the plant is brought to a stable condition.
Evaluator Note: Note if 1600 psig Feedwater Pump discharge pressure is exceeded the MFP's will trip.
Evaluator Note: With the malfunction that is present this action will not be effective and the applicant may skip this step and go directly to the bypass valve.
COMMENTS:
Thursday, August 01, 2013                                                                        Page 6 of 10
 
CRITICAL:        Yes      SEQUENCED: Yes                            SAT              UNSAT STEP:      4 If feed flow remains low, THEN perform the following:
Open the associated bypass valve as necessary to control SG level:
FCV-3321, LOOP A MAIN FW BYP.
FCV-3331, LOOP B MAIN FW BYP.
FCV-3341, LOOP C MAIN FW BYP.
STEP STANDARD:
FCV-3321, LOOP A MAIN FW BYP is in manual and open. S/G level is controlled between 60% and 65%.
CUES:
Evaluator Note: This is an immediate operator action and applicant may do this steps without aid of the procedure although that is not required as the plant is brought to a stable condition.
COMMENTS:
Thursday, August 01, 2013                                                                    Page 7 of 10
 
CRITICAL:          No    SEQUENCED: Yes                            SAT              UNSAT STEP:      5 Procedure Note: If the Feedwater Flow Control Valve is closed, the maximum flow attainable with the bypass valve is 20% to 30%.
Reduce plant load as necessary to control SG level using the bypass valve. REFER TO GOP-4, POWER OPERATION (MODE 1).
STEP STANDARD:
Determines that "A" SG level can be maintained at current power level.
CUES:
Evaluator Note: This is an immediate operator action and applicant may do this steps without aid of the procedure although that is not required as the plant is brought to a stable condition.
COMMENTS:
Examiner ends JPM at this point.
Thursday, August 01, 2013                                                                    Page 8 of 10
 
JPM SETUP SHEET JPM NO: NJPSF-161 DESCRIPTION:          2013 NRC Sim JPM f RO&SRO-I: RESPOND TO A FEED REGULATING VALVE CLOSURE AT LOW POWER IC SET: 335/44 INSTRUCTIONS:
Saved to IC 335 from IC 44 When examiner is ready insert Trigger #1.
Trigger # 1 VLV-FW001P IFV00478-FW SG A FW CTRL VLV FAIL POSITION Delay=0, Ramp=00:01:00, Final=5.
COMMENTS:
Thursday, August 01, 2013                                                      Page 9 of 10
 
JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:
INITIAL CONDITION: 15% power BOL.
INITIATING CUES: Respond to developing plant conditions as the BOP operator.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
Thursday, August 01, 2013
 
V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO:    NJPS-162 2013 NRC Sim JPM g RO&SRO-I: START AND LOAD THE MAIN GENERATOR APPROVAL:          APPROVAL DATE:
REV NO: 3 CANDIDATE:
EXAMINER:
Thursday, August 01, 2013                                          Page 1 of 14
 
TASK:
045-005-01-01            Synchronize Turbine Generator with Grid at Minimum Load Per SOP-201/SOP-207/SOP-214/SOP-218/SOP-217 TASK STANDARD:
Main Generator is synchronized with the grid without causing damage to the main generator breaker (closing out of phase) and loaded to 50 MW.
TERMINATING CUE:            Main Generator is synchronized with grid and is carrying at least 50 MW.
PREFERRED EVALUATION LOCATION                              PREFERRED EVALUATION METHOD SIMULATOR                                                      PERFORM
 
==REFERENCES:==
 
INDEX NO.            K/A NO.                                            RO              SRO 062000A401          A4.01    All breakers (including available          3.3            3.1 switchyard)
TOOLS:            SOP-301, MAIN GENERATOR SYSTEM.
EVALUATION TIME                    15          TIME CRITICAL      NO      10CFR55: 45.a.6 TIME START:                        TIME FINISH:                  PERFORMANCE TIME:
PERFORMANCE RATING:                SAT:            UNSAT:
CANDIDATE:
EXAMINER:
SIGNATURE                DATE Thursday, August 01, 2013                                                                      Page 2 of 14
 
INSTRUCTIONS TO OPERATOR READ TO OPERATOR:
WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
SAFETY CONSIDERATIONS:                None.
INITIAL CONDITION: 15% power. The Main Generator is being synchronized in accordance with SOP-301 Section III. A. STARTUP. Step 2.2 has just been completed.
INITIATING CUES: The CRS directs you as the BOP to synchronize the Main Generator in accordance with SOP-301 Section III. A. STARTUP starting at step 2.3.
HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!
Thursday, August 01, 2013                                                                  Page 3 of 14
 
STEPS CRITICAL:          No      SEQUENCED: Yes                            SAT        UNSAT STEP:      1 Procedure Note: The System Controller should be notified as soon as practical, but within 30 minutes if Automatic Regulation is not achieved.
Place the GEN VOLT REG XFER Switch, in MAN.
STEP STANDARD:
GEN VOLT REG XFER Switch, in MAN.
CUES:
Evaluator Note: The GEN VOLT REG XFER will already be in MAN and so this step is not critical.
Booth Operator Cue: If called as the system controller respond that you understand they are putting the voltage adjust in Manual and to notify that condition exists for >30 minutes.
Booth Operator Cue: If asked for a switching order respond that your switching order is 1.
COMMENTS:
CRITICAL:        Yes      SEQUENCED: Yes                            SAT        UNSAT STEP:      2 Close the GEN FIELD BKR.
STEP STANDARD:
GEN FIELD BKR take to CLOSE. Red light lit. Green light off.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                                    Page 4 of 14
 
CRITICAL:        Yes    SEQUENCED: Yes                          SAT              UNSAT STEP:      3 Using the EXC FIELD CNTRL Switch, energize the Exciter and Main Generator by placing the switch to CLOSE and verifying the red light illuminates.
STEP STANDARD:
EXC FIELD CNTRL taken to CLOSE Red light lit. Green light off.
CUES:
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                          SAT              UNSAT STEP:      4 Procedure Note: To prevent inadvertently over or under exciting the Main Generator, the controls for both the Manual and Automatic Regulators are only activated for an interval of 1.0 second per adjustment.
Using the EXC FIELD VOLT ADJ (MAN) Control Switch adjust Generator KILOVOLTS to 22 KV (normal band 20.9 to 23.1 KV).
STEP STANDARD:
EXC FIELD VOLT ADJ (MAN) used. KILOVOLTS are between 20.9 and 23.1 KV.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                                    Page 5 of 14
 
CRITICAL:          No    SEQUENCED: Yes                          SAT              UNSAT STEP:      5 Using the GEN VOLT SEL Switch, check phase voltages on KILOVOLTS Meter.
STEP STANDARD:
All positions of GEN VOLT SEL show voltage between 20.9 and 23.1 KV.
CUES:
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                          SAT              UNSAT STEP:      6 Procedure Note: Failure of one regulation mode to track with the other is indicative of a problem with the in-service Core. I&C should be contacted to investigate the problem.
Verify the Automatic Regulator tracks to match the Manual Regulator by observing the EXCITER VOLTS Meter trends to 0%.
STEP STANDARD:
EXCITER VOLTS meter is at 0%.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                                      Page 6 of 14
 
CRITICAL:        Yes    SEQUENCED: Yes                            SAT              UNSAT STEP:      7 Transfer the GEN VOLT REG XFER Switch, to AUTO.
STEP STANDARD:
GEN VOLT REG XFER Switch in AUTO.
CUES:
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                            SAT              UNSAT STEP:      8 Using the GEN FIELD VOLT ADJ (AUTO) Control Switch, cycle Main Generator voltage above and below 22 KV (normal band 20.9 to 23.1 KV) sufficiently to verify control while monitoring that the EXCITER VOLTS Meter trends toward 0% following each cycle.
STEP STANDARD:
Voltage raised and lowered. EXCITER VOLTS Meter trends toward 0%.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                                      Page 7 of 14
 
CRITICAL:          No      SEQUENCED: Yes                            SAT            UNSAT STEP:      9 Procedure Note: In order to get the light to change state on any of the active OC2000 Pushbuttons, the button itself must be depressed.
Ensure the PSS CNTRL ENABLE Pushbutton is lit (TB-436, OC2000).
STEP STANDARD:
Calls local operator to ensure PSS CNTRL ENABLE Pushbutton is lit (TB-436, OC2000).
CUES:
Booth Operator Cue: When called to ensure PSS CNTRL ENABLE Pushbutton is lit (TB-436, OC2000) respond that it is lit.
COMMENTS:
CRITICAL:          No      SEQUENCED: Yes                            SAT            UNSAT STEP:      10 Notify the System Controller that the unit is ready to be paralleled and obtain a Switching Order.
STEP STANDARD:
Calls System Controller for Switching Order.
CUES:
Booth Operator Cue: When called as System Controller for a Switching Order respond "Parallel to the Grid, Your Switching Order is 1."
COMMENTS:
Thursday, August 01, 2013                                                                      Page 8 of 14
 
CRITICAL:        Yes    SEQUENCED: Yes                      SAT          UNSAT STEP:      11 Place the GEN SYNC NORM FEED Switch, to MAN.
STEP STANDARD:
GEN SYNC NORM FEED Switch, in MAN.
CUES:
COMMENTS:
CRITICAL:        Yes    SEQUENCED: Yes                      SAT          UNSAT STEP:      12 Using the GEN FIELD VOLT ADJ (AUTO) Control Switch, adjust GEN VOLTS equal to or slightly higher than SYS VOLTS.
STEP STANDARD:
GEN VOLTS equal or slightly higher than SYS VOLTS.
CUES:
COMMENTS:
Thursday, August 01, 2013                                                            Page 9 of 14
 
CRITICAL:        Yes      SEQUENCED: Yes                        SAT            UNSAT STEP:      13 Using the Raise Lower Pushbuttons on the Main Control Board at the Turbine EHC HMI adjust Turbine speed until the SYNCHROSCOPE rotates slowly in the FAST (clockwise) direction.
STEP STANDARD:
SYNCHROSCOPE rotates slowly in the FAST (clockwise) direction.
CUES:
COMMENTS:
CRITICAL:        Yes      SEQUENCED: Yes                        SAT            UNSAT STEP:      14 When the SYNCHROSCOPE indicator passes 11 oclock and slowly approaches 12 oclock, close the GEN BKR. (PEER check)
STEP STANDARD:
GEN BKR is closed in phase.
CUES:
Evaluator Note: This step requires a peer check. Respond that you understand that applicant desires a peer check.
COMMENTS:
Thursday, August 01, 2013                                                                Page 10 of 14
 
CRITICAL:          No    SEQUENCED: Yes                          SAT            UNSAT STEP:      15 Verify the GEN BKR is closed.
STEP STANDARD:
GEN BKR is CLOSED. Red light lit. Green light off.
CUES:
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                          SAT            UNSAT STEP:      16 On the EHC HMI, Control/Load screen, select Ramp Rate and enter desired rate of 1% or less.
G. Raise Turbine load to 50 MW by one of the following methods:
: 1) Using the EHC HMI, Control/Load screen, select Manual Adj, Raise.
: 2) Using the Raise Pushbutton on the Main Control Board at the Turbine EHC HMI.
STEP STANDARD:
MW indicate ~ 50 MW.
CUES:
Evaluator Note: The new EHC system now loads the generator to ~50 MW automatically.
Evaluator Cue: If asked as SS what the desired rate of load increase is respond 0.5 %/min.
COMMENTS:
Thursday, August 01, 2013                                                                  Page 11 of 14
 
CRITICAL:          No  SEQUENCED: Yes      SAT UNSAT STEP:      17 Place the GEN SYNCH NORM FEED Switch in OFF.
STEP STANDARD:
GEN SYNCH NORM FEED Switch in OFF.
CUES:
COMMENTS:
Examiner ends JPM at this point.
Thursday, August 01, 2013                              Page 12 of 14
 
JPM SETUP SHEET JPM NO: NJPS-162 DESCRIPTION:          2013 NRC Sim JPM g RO&SRO-I: START AND LOAD THE MAIN GENERATOR IC SET: 336/44 INSTRUCTIONS:
Saved to IC-336. Build from IC-44.
IC-44.
Ensure IR and PR low trip setpoints are blocked.
Roll Main Turbine to 1800 RPM, per SOP-214, Main Turbine And Controls.
Freeze.
When applicant is ready go to run.
COMMENTS:
Ensure that the GEN VOLT REG XFER Switch is at the 45&deg; angle and not 90&deg; where it points at nothing.
Thursday, August 01, 2013                                                              Page 13 of 14
 
JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:
INITIAL CONDITION: 15% power. The Main Generator is being synchronized in accordance with SOP-301 Section III. A. STARTUP. Step 2.2 has just been completed.
INITIATING CUES: The CRS directs you as the BOP to synchronize the Main Generator in accordance with SOP-301 Section III. A. STARTUP starting at step 2.3.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
Thursday, August 01, 2013
 
V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO:    NJPS-152 2013 NRC Sim JPM h RO: RESPOND TO HIGH REACTOR BUILDING PRESSURE APPROVAL:          APPROVAL DATE:
REV NO: 15 CANDIDATE:
EXAMINER:
Saturday, August 03, 2013                                            Page 1 of 10
 
TASK:
029-004-01-01            VENT THE REACTOR BUILDING TASK STANDARD:
RB pressure is reduced <+0.05 and >-0.05 psig on PI-8254, RB NR PRESS PSI.
Containment isolation is restored by closing the purge exhaust valves.
TERMINATING CUE:            RB purge is secured.
PREFERRED EVALUATION LOCATION                              PREFERRED EVALUATION METHOD SIMULATOR                                                    PERFORM
 
==REFERENCES:==
SOP-114                REACTOR BUILDING VENTILATION SYSTEM INDEX NO.            K/A NO.                                            RO        SRO 028000A401          A4.01    HRPS controls                              4.0        4.0 TOOLS:            SOP-114, REACTOR BUILDING VENTILATION SYSTEM HPP-709, Attachment VI, REACTOR BUILDING PURGE RELEASE PERMIT.
EVALUATION TIME                    15          TIME CRITICAL      No      10CFR55: 45.a.5 TIME START:                        TIME FINISH:                    PERFORMANCE TIME:
PERFORMANCE RATING:                SAT:            UNSAT:
CANDIDATE:
EXAMINER:
SIGNATURE            DATE Saturday, August 03, 2013                                                                  Page 2 of 10
 
INSTRUCTIONS TO OPERATOR READ TO OPERATOR:
WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.
SAFETY CONSIDERATIONS:
INITIAL CONDITION: Plant is at 100% power.
Preparations are underway to conduct maintenance on the Personnel Access inner door.
SOP-114, REACTOR BUILDING VENTILATION SYSTEM, III.P.
LOWERING REACTOR BUILDING PRESSURE USING NORMAL PRESSURE CONTROL is being used to lower RB pressure.
All initial conditions have been met. A reactor building purge release permit has been issued in accordance with HPP-709. RM-A4 and RM-A2 are in service.
RM-A4's setpoint has been adjusted in accordance with the Release Permit and step 2.4 of SOP-114, III.P.
FI-8252, H2 PURGE FLOW CFM is out of service. The CRS has completed 702 Attachment VI.S-3, 6" RB PURGE OPERATING WITH IFT08252 AND/OR RMA-4 INOPERABLE, which requires that the release flowrate be estimated every 4 hours. The CRS has determined that the flow rate will be estimated at 600 cfm for the duration of the release.
INITIATING CUES: Lower RB pressure as required in accordance with SOP-114, REACTOR BUILDING VENTILATION SYSTEM, III.P. LOWERING REACTOR BUILDING PRESSURE USING NORMAL PRESSURE CONTROL starting at step 2.5.
HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!
Saturday, August 03, 2013                                                                      Page 3 of 10
 
STEPS CRITICAL:        Yes      SEQUENCED: Yes                          SAT                UNSAT STEP:      1 Procedure Caution: To prevent damage to Alternate Purge System ducting, Alternate Purge must not be placed in service if RB pressure is greater than 3 psi.
Open the following:
: 1) PVG-6066, CNTMT PUR EXH ISOL VLV.
: 2) PVG-6067, CNTMT PUR EXH ISOL VLV.
: 2) PVG-6067, CNTMT PUR EXH ISOL VLV.
YesPlaces PVG-6066, CNTMT PUR EXH ISOL VLV and PVG-6067, CNTMT PUR EXH ISOL VLV.
STEP STANDARD:
switch in the OPEN position. Verifies the valve opens by observing the red light lit and the green light off.Yes1 Start XFN-96, ALT PUR EXH FAN.Examiner Cue: Cue the applicant that "Time Compression" will be used to expedite the administration of the JPM.Evaluator Note: The procedure requires a peer check at this step. Acknowledge that you understandthat the applicant will obtain a peer check.
Places PVG-6066, CNTMT PUR EXH ISOL VLV and PVG-6067, CNTMT PUR EXH ISOL VLV.
YesPlaces switch for XFN-96 ALT PUR EXH FAN in START. Observes red light ON and green light OFF.Yes2 Record time release was started and flow rate as indicated on FI-8252, H2 PURGE FLOW CFM, in the following places:1) Reactor Building Purge Release Permit.
switch in the OPEN position. Verifies the valve opens by observing the red light lit and the green light off.
: 2) Station Log Book.Examiner Cue: Cue the applicant that the start time and flow rate will be transferred to the station log book.Examiner Note: Initial conditions indicate that the flowrate of the release is estimated at 500 cfm.
CUES:
YesRecords start time and flowrate estimate of 600 cfm in the Station Log Book and on the Continuous Waste Release Permit.No3Records release readings from RM-A2 and RM-A4.
COMMENTS:
YesRecords release readings from RM-A2 and RM-A4.No4 If RB pressure is being lowered to support door maintenance, simultaneousopening of both personnel hatch doors or opening of equipment hatch door,perform the following:
Saturday, August 03, 2013                                                                      Page 4 of 10
: a. Monitor PI-8254, RB NR PRESS PSI.b. When RB pressure is between negative 0.05 psi and positive 0.05 psi, stop XFN-96, ALT PUR EXH FAN.YesChecks RB pressure <+0.05 and >-0.05 psig on PI-8254, RB NR PRESS PSI.No5Stop XFN-96, ALT PUR EXH FAN.
 
YesStops XFN-96, ALT PUR EXH FAN.Yes6 Examiner ends JPM at this point.
CRITICAL:        Yes      SEQUENCED: Yes                      SAT            UNSAT STEP:      2 Start XFN-96, ALT PUR EXH FAN.
Close the following:a. PVG-6066, CNTMT PUR EXH ISOL VLV.b. PVG-6067, CNTMT PUR EXH ISOL VLV.
STEP STANDARD:
YesPlaces PVG-6066 CNTMT PUR EXH ISOL VLV and PVG-6067 CNTMT PUR EXH ISOL VLV switches in the CLOSE position and verifies the valves go close by verifying green light lit and red light off.Yes7Record time release was stopped in the following places:
Places switch for XFN-96 ALT PUR EXH FAN in START. Observes red light ON and green light OFF.
: a. Reactor Building Purge Release Permit.b. Station Log Book.Examiner Cue: Cue the applicant that the release time will be recorded in the station log book and the continuous waste release permit.
CUES:
YesRecords time in the Station Log Book and on the Continuous Waste Release Permit.No8 NJPS-1522013 NRC Sim JPM h RO: RESPOND TO HIGH REACTOR BUILDING PRESSURE363/10Run when applicant is ready.If IC-363 is not available:Reset to IC 10Event #1 x15i355t>0 Enter MALF RMS004C, CONT BREACH FHB436; Set = 2 SCFT, when examinee starts XFN-96.Event #2 x15i355s>0&&jmlrms4c>0 (Deletes Malf RMS004C when the examinee secures XFN-96)Hang an Orange R&R tag on FI-8252, H2 PURGE FLOW CFM.
Examiner Cue: Cue the applicant that "Time Compression" will be used to expedite the administration of the JPM.
Evaluator Note: The procedure requires a peer check at this step. Acknowledge that you understand that the applicant will obtain a peer check.
COMMENTS:
Saturday, August 03, 2013                                                                Page 5 of 10
 
CRITICAL:          No    SEQUENCED: Yes                              SAT            UNSAT STEP:      3 Record time release was started and flow rate as indicated on FI-8252, H2 PURGE FLOW CFM, in the following places:
: 1) Reactor Building Purge Release Permit.
: 2) Station Log Book.
STEP STANDARD:
Records start time and flowrate estimate of 600 cfm in the Station Log Book and on the Continuous Waste Release Permit.
CUES:
Examiner Cue: Cue the applicant that the start time and flow rate will be transferred to the station log book.
Examiner Note: Initial conditions indicate that the flowrate of the release is estimated at 500 cfm.
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                              SAT            UNSAT STEP:      4 Records release readings from RM-A2 and RM-A4.
STEP STANDARD:
Records release readings from RM-A2 and RM-A4.
CUES:
COMMENTS:
Saturday, August 03, 2013                                                                        Page 6 of 10
 
CRITICAL:          No    SEQUENCED: Yes                          SAT          UNSAT STEP:      5 If RB pressure is being lowered to support door maintenance, simultaneous opening of both personnel hatch doors or opening of equipment hatch door, perform the following:
: a. Monitor PI-8254, RB NR PRESS PSI.
: b. When RB pressure is between negative 0.05 psi and positive 0.05 psi, stop XFN-96, ALT PUR EXH FAN.
STEP STANDARD:
Checks RB pressure <+0.05 and >-0.05 psig on PI-8254, RB NR PRESS PSI.
CUES:
COMMENTS:
CRITICAL:        Yes    SEQUENCED: Yes                          SAT          UNSAT STEP:      6 Stop XFN-96, ALT PUR EXH FAN.
STEP STANDARD:
Stops XFN-96, ALT PUR EXH FAN.
CUES:
COMMENTS:
Saturday, August 03, 2013                                                                Page 7 of 10
 
CRITICAL:        Yes    SEQUENCED: Yes                          SAT              UNSAT STEP:      7 Close the following:
: a. PVG-6066, CNTMT PUR EXH ISOL VLV.
: b. PVG-6067, CNTMT PUR EXH ISOL VLV.
STEP STANDARD:
Places PVG-6066 CNTMT PUR EXH ISOL VLV and PVG-6067 CNTMT PUR EXH ISOL VLV switches in the CLOSE position and verifies the valves go close by verifying green light lit and red light off.
CUES:
COMMENTS:
CRITICAL:          No    SEQUENCED: Yes                          SAT              UNSAT STEP:      8 Record time release was stopped in the following places:
: a. Reactor Building Purge Release Permit.
: b. Station Log Book.
STEP STANDARD:
Records time in the Station Log Book and on the Continuous Waste Release Permit.
CUES:
Examiner Cue: Cue the applicant that the release time will be recorded in the station log book and the continuous waste release permit.
COMMENTS:
Examiner ends JPM at this point.
Saturday, August 03, 2013                                                                      Page 8 of 10
 
JPM SETUP SHEET JPM NO: NJPS-152 DESCRIPTION:          2013 NRC Sim JPM h RO: RESPOND TO HIGH REACTOR BUILDING PRESSURE IC SET: 363/10 INSTRUCTIONS:
Run when applicant is ready.
If IC-363 is not available:
Reset to IC 10 Event #1 x15i355t>0 Enter MALF RMS004C, CONT BREACH FHB436; Set = 2 SCFT, when examinee starts XFN-96.
Event #2 x15i355s>0&&jmlrms4c>0 (Deletes Malf RMS004C when the examinee secures XFN-96)
COMMENTS:
Hang an Orange R&R tag on FI-8252, H2 PURGE FLOW CFM.
Provide an operator to silence alarms and have operator silence alarms from the MCB while the applicant is conducting the realease from the HVAC panel.
Provide an operator to silence alarms and have operator silence alarms from the MCB while the applicant is conducting the realease from the HVAC panel.
JPM SETUP SHEET Lower RB pressure as required in accordance with SOP-114, REACTOR BUILDING VENTILATION SYSTEM, III.P. LOWERING REACTOR BUILDING PRESSURE USING NORMAL PRESSURE CONTROL starting at step 2.5.Plant is at 100% power.
Saturday, August 03, 2013                                                                Page 9 of 10
Preparations are underway to conduct maintenance on the Personnel Access inner door.SOP-114, REACTOR BUILDING VENTILATION SYSTEM, III.P. LOWERING REACTOR BUILDING PRESSURE USING NORMAL PRESSURE CONTROL is being used to lower RB pressure. All initial conditions have been met. A reactor building purge release permit has been issued in accordance with HPP-709. RM-A4 and RM-A2 are in service. RM-A4's setpoint has been adjusted in accordance with the Release Permit and step 2.4 of SOP-114, III.P. FI-8252, H2 PURGE FLOW CFM is out of service. The CRS has completed 702 Attachment VI.S-3, 6" RB PURGE OPERATING WITH IFT08252 AND/OR RMA-4 INOPERABLE, which requires that the release flowrate be estimated every 4 hours. The CRS has determined that the flow rate will be estimated at 600 cfm for the duration of the release.HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.}}
 
JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:
INITIAL CONDITION: Plant is at 100% power.
Preparations are underway to conduct maintenance on the Personnel Access inner door.
SOP-114, REACTOR BUILDING VENTILATION SYSTEM, III.P.
LOWERING REACTOR BUILDING PRESSURE USING NORMAL PRESSURE CONTROL is being used to lower RB pressure.
All initial conditions have been met. A reactor building purge release permit has been issued in accordance with HPP-709. RM-A4 and RM-A2 are in service.
RM-A4's setpoint has been adjusted in accordance with the Release Permit and step 2.4 of SOP-114, III.P.
FI-8252, H2 PURGE FLOW CFM is out of service. The CRS has completed 702 Attachment VI.S-3, 6" RB PURGE OPERATING WITH IFT08252 AND/OR RMA-4 INOPERABLE, which requires that the release flowrate be estimated every 4 hours. The CRS has determined that the flow rate will be estimated at 600 cfm for the duration of the release.
INITIATING CUES: Lower RB pressure as required in accordance with SOP-114, REACTOR BUILDING VENTILATION SYSTEM, III.P. LOWERING REACTOR BUILDING PRESSURE USING NORMAL PRESSURE CONTROL starting at step 2.5.
HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.
Saturday, August 03, 2013}}

Latest revision as of 13:04, 4 November 2019

VC Summer Initial Exam 2013-301 Final Sim IN-Plant Jpmss
ML13301A739
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 10/23/2013
From:
NRC/RGN-II
To:
South Carolina Electric & Gas Co
References
JPPF-013A
Download: ML13301A739 (130)


Text

V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO: JPPF-013A 2013 NRC In-Plant i: START AND LOAD THE DIESEL GENERATOR DURING CONTROL ROOM EVACUATION APPROVAL: APPROVAL DATE:

REV NO: 3 CANDIDATE:

EXAMINER:

Saturday, August 03, 2013 Page 1 of 14

TASK:

000-068-05-01 PERFORM CONTROL ROOM EVACUATION TASK STANDARD:

Diesel started, field flashed, power is supplied to 1DA.

TERMINATING CUE: CRS notified of 1DA status.

PREFERRED EVALUATION LOCATION PREFERRED EVALUATION METHOD PLANT SIMULATE

REFERENCES:

TOOLS: AOP-600.1, CONTROL ROOM EVACUATION, Attachment 3, LOCAL STARTING AND LOADING DIESEL GENERATOR A(B)

EVALUATION TIME 20 TIME CRITICAL NO 10CFR55: 45.a.8 TIME START: TIME FINISH: PERFORMANCE TIME:

PERFORMANCE RATING: SAT: UNSAT:

CANDIDATE:

EXAMINER:

SIGNATURE DATE Saturday, August 03, 2013 Page 2 of 14

INSTRUCTIONS TO OPERATOR READ TO OPERATOR:

WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.

SAFETY CONSIDERATIONS: This JPM should only be run on a "A" train maintenance week and when the diesel rooms are not marked off as restricted areas due to EOOS. If it is a "B" train maintenance week use JPPF-013B.

INITIAL CONDITION: A control room evacuation has occurred. You as the BOP just completed AOP-600.1 Attachment 2, DUTIES OF THE BOP OPERATOR. During performance of the Attachment you determined that power was not available to 1DA.

INITIATING CUES: The CRS directs you to start the "A" Diesel Generator in accordance with AOP-600.1, Attachment 3, LOCAL STARTING AND LOADING DIESEL GENERATOR A(B)

HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!

AT NO TIME ARE YOU TO OPERATE ANY PLANT EQUIPMENT!

FOR ELECTRICAL MANIPULATIONS, AT NO TIME ARE YOU TO BREAK THE PLANE OF THE ELECTRICAL PANEL!

Saturday, August 03, 2013 Page 3 of 14

STEPS CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 1 Ensure both of the following breakers are open (IB-463):

XSW1DA 01, BUS 1DA NORMAL INCOMING BKR.

XSW1DA 15, BUS 1DA EMERG INCOMING BKR.

STEP STANDARD:

Verifies green light lit and red light off for both incoming breakers.

CUES:

Evaluator Cue: Cue examinee that green light is lit and red light is off for XSW1DA 01, BUS 1DA NORMAL INCOMING BKR and XSW1DA 15, BUS 1DA EMERG INCOMING BKR.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 2 Determine the cause of Diesel Generator start failure:

Check alarms and indications at the local DG Control Panel. REFER TO ARP-004-XCX-5201.

Verify problems found will NOT prevent starting the DG.

STEP STANDARD:

Determines that alarms do not indicate a problem that has to be fixed to start generator.

CUES:

Evaluator Cue: When asked which alarms are present on XCX-5201 report that no annunciators are in alarm.

COMMENTS:

Saturday, August 03, 2013 Page 4 of 14

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 3 Place REMOTE/LOCAL/MAINT Switch in LOCAL.

STEP STANDARD:

REMOTE/LOCAL/MAINT Switch in LOCAL.

CUES:

Evaluator Cue: When switch is taken to local indicate that XCX-5201 6-5, LOCAL CONTROL goes into alarm.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 4 Ensure the VOLT REG is in AUTO.

STEP STANDARD:

Verifies VOLT REG switch is in AUTO.

CUES:

Examiner Cue: Cue examinee that VOLT REG switch is in AUTO.

COMMENTS:

Saturday, August 03, 2013 Page 5 of 14

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 5 Depress the following reset pushbuttons:

GEN RELAYS RESET.

EXCITER RESET.

STEP STANDARD:

Depresses GEN RELAYS RESET and EXCITER RESET.

CUES:

Evaluator Cue: Cue applicant that there are no changes to indications.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 6 Attempt to start the Diesel Generator by depressing the ENGINE SHUT DOWN RESET Pushbutton.

STEP STANDARD:

ENGINE SHUT DOWN RESET is pushed. When cued that there is no response, goes to step 9 as an alternative action.

CUES:

Examiner Cue: When button is pushed indicate that there are no change in indications.

COMMENTS:

Saturday, August 03, 2013 Page 6 of 14

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 7 Attempt to start the Diesel Generator:

Momentarily depress the EMERG START Pushbutton.

Verify the Diesel starts and accelerates to 514 rpm.

STEP STANDARD:

Pushes EMERG START Pushbutton and notices that Diesel does not start. Goes to alternative action.

CUES:

Evaluator Cue: Cue applicant that there is no change in indications when button is pressed.

COMMENTS:

Saturday, August 03, 2013 Page 7 of 14

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 8

b. Attempt to start the Diesel using the Main Air Start Valve:
1) Using the attached spanner wrench, depress and hold the pushbutton on one of the following for five seconds (located at either end of the Diesel):

XVM10996A-DG, DIESEL GEN A MAIN AIR START VALVE A.

OR XVM10996B-DG, DIESEL GEN A MAIN AIR START VALVE B.

2) Verify the Diesel starts and accelerates to 514 rpm.

STEP STANDARD:

Uses spanner wrench to push on one of the air start valves. Verifies that diesel accelerates to 514 rpm.

CUES:

Evaluator Cue: Cue applicant that diesel is heard to start. Cue that RPM's indicate 514 rpm if meter is observed.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 9 Verify the Generator voltage indication increased to between 6800 Volts and 7600 Volts.

STEP STANDARD:

Determines that voltage has remained at 0 volts and goes to alternate action.

CUES:

Examiner Cue: Cue applicant that voltage remains at 0 volts.

COMMENTS:

Saturday, August 03, 2013 Page 8 of 14

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 10 Perform a manual field flash:

1) Momentarily place FIELD FLASH Switch to FLASH.
2) Verify Generator voltage increases to between 6800 Volts and 7600 Volts.

STEP STANDARD:

Places FIELD FLASH Switch to FLASH. Verifies generator voltage increase to 7200 volts.

CUES:

Examiner Cue: Cue applicant that voltage has increased to 7200 volts.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 11 Depress the EMERG START RESET Pushbutton.

STEP STANDARD:

EMERG START RESET Pushbutton depressed.

CUES:

Evaluator Cue: Cue applicant that EMERG START light at top of board goes from lit to off.

COMMENTS:

Saturday, August 03, 2013 Page 9 of 14

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 12 Reset all annunciators on XCX5201.

STEP STANDARD:

Presses reset on XCX5201.

CUES:

Evaluator Cue: Cue applicant that only alarm in is 6-5, LOCAL CONTROL, before and after reset is pressed.

Evaluator Note: Because there are no annunciators to reset the applicant may not press the reset pushbutton.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 13 Procedure Caution: If any DG annunciator will NOT reset, it should be evaluated by the Shift Supervisor prior to performing Step 12, since it may cause the DG or its output breaker to trip.

Depress the TEST START Pushbutton.

STEP STANDARD:

TEST START Pushbutton depressed.

CUES:

Evaluator Cue: Cue applicant that there is no change in indication after button is depressed.

COMMENTS:

Saturday, August 03, 2013 Page 10 of 14

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 14 Ensure BUS 1DA DG FEED is closed.

STEP STANDARD:

Verifies BUS 1DA DG FEED indicates red light lit, green light off and voltage is indicated on 1DA.

CUES:

Evaluator Cue: Cue applicant that BUS 1DA DG FEED indicates red light lit, green light off and voltage is 7200 KV on 1DA.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 15 Adjust Generator voltage to 7200 Volts using the AUTO VOLT CNTRL Switch.

STEP STANDARD:

Generator Voltage is between 6840 and 7445 Volts.

CUES:

Evaluator Cue: Cue applicant that voltage is at 7200 volts. If AUTO VOLT CNTRL Switch is used indicate changing voltages.

Evaluator Note: This voltage band is that required for steady state operation in accordance with TSR 1068.

COMMENTS:

Saturday, August 03, 2013 Page 11 of 14

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 16 Adjust Generator frequency to 60 Hertz using the GOVERNOR Switch.

STEP STANDARD:

Generator frequency is 60 +/-0.6 Hz.

CUES:

Evaluator Cue: Cue applicant that frequency is at 60 Hz. If the GOVERNOR Switch is used indicate changing frequency.

Evaluator Note: This frequency band is that required for steady state operation in accordance with TSR 1068.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 17 Notify the Control Room Supervisor at the CREP of DG status.

STEP STANDARD:

Notifies CRS.

CUES:

Evaluator Note: Cue applicant that CRS understands that the diesel is started and at normal operating voltage and frequency and that the BOP should report to the CREP and the intermediate building operator will take over operation of the diesel.

COMMENTS:

Examiner ends JPM at this point.

Saturday, August 03, 2013 Page 12 of 14

JPM SETUP SHEET JPM NO: JPPF-013A DESCRIPTION: 2013 NRC In-Plant i: START AND LOAD THE DIESEL GENERATOR DURING CONTROL ROOM EVACUATION IC SET: N/A INSTRUCTIONS:

COMMENTS:

This JPM should only be run on a "A" train maintenance week and when the diesel rooms are not marked off as restricted areas due to EOOS. If it is a "B" train maintenance week use JPPF-013B.

Saturday, August 03, 2013 Page 13 of 14

JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:

INITIAL CONDITION: A control room evacuation has occurred. You as the BOP just completed AOP-600.1 Attachment 2, DUTIES OF THE BOP OPERATOR. During performance of the Attachment you determined that power was not available to 1DA.

INITIATING CUES: The CRS directs you to start the "A" Diesel Generator in accordance with AOP-600.1, Attachment 3, LOCAL STARTING AND LOADING DIESEL GENERATOR A(B)

AT NO TIME ARE YOU TO OPERATE ANY PLANT EQUIPMENT!

HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.

Saturday, August 03, 2013

V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO: JPP-107A 2013 NRC In-Plant j: LOCALLY CLOSE AND DE-ENERGIZE MS LOOP "B" AND "C" TO TDEFP APPROVAL: APPROVAL DATE:

REV NO: 2 CANDIDATE:

EXAMINER:

Saturday, August 03, 2013 Page 1 of 7

TASK:

000-169-05-04 Locally Isolate a Faulted Steam Generator per EOP-3.0.

TASK STANDARD:

Turbine driven emergency feed pump main steam loop "B" and "C" supply valve is manually closed and power removed from 2802A per EOP-3.0.

TERMINATING CUE: MVG-2802A and MVG-2802B are closed and deenergized per EOP-3.0.

PREFERRED EVALUATION LOCATION PREFERRED EVALUATION METHOD PLANT SIMULATE

REFERENCES:

EOP-3.0 FAULTED STEAM GENERATOR ISOLATION INDEX NO. K/A NO. RO SRO 035000A406 A4.06 S/G isolation on steam leak or tube 4.5 4.6 rupture/leak 061000K103 K1.03 Main steam system 3.5 3.9 000040A104 AA1.04 Isolation of all steam lines from header 4.3 4.3 000040A110 AA1.10 AFW System 4.1 4.1 TOOLS: EOP-3.0, STEP 5.h. ALTERNATIVE ACTION EVALUATION TIME 20 TIME CRITICAL No 10CFR55: 45.a.8 TIME START: TIME FINISH: PERFORMANCE TIME:

PERFORMANCE RATING: SAT: UNSAT:

CANDIDATE:

EXAMINER:

SIGNATURE DATE Saturday, August 03, 2013 Page 2 of 7

INSTRUCTIONS TO OPERATOR READ TO OPERATOR:

WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.

SAFETY CONSIDERATIONS: Burn Hazard INITIAL CONDITION: The plant was at 100% power when a steamline break occurred inside containment. "B" and "C" SGs are faulted as indicated by steam pressure dropping in an uncontrolled manner. The CRS has implemented EOP-3.0, FAULTED STEAM GENERATOR ISOLATION, out of EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION, following a Automatic SI. Both motor driven emergency feedwater pumps started. MVG-2802A, MS LOOP B TO TD EFP and MVG-2802B, MS LOOP C TO TD EFP will not close from the MCB.

INITIATING CUES: RO directs you as the IB operator (Unit 7) to open breaker 05EH on XMC1DA2X and locally close valves XVG02802A-MS and XVG02802B-MS in accordance with EOP-3.0, Step 5.h, Alternative Action. The AB operator (Unit 6 upper) has already opened breaker 05EH on XMC1DB2Y. The shift supervisor has approved the waiving of ISP-027 requirements due to the emergency condition.

HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!

AT NO TIME ARE YOU TO OPERATE ANY PLANT EQUIPMENT!

FOR ELECTRICAL MANIPULATIONS, AT NO TIME ARE YOU TO BREAK THE PLANE OF THE ELECTRICAL PANEL!

Saturday, August 03, 2013 Page 3 of 7

STEPS CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 1 Locally deenergize and close the appropriate valve. If SG B is faulted:

Open XMC1DA2X 05EH, EF PUMP MAIN STEAM BLOCK VLV XVG-2802A-MS (IB-463).

STEP STANDARD:

Operator locates the power supply (1DA2X, 05EH) for XVG-02802A and opens the breaker by pulling the breaker control lever down.

CUES:

Evaluator Note: The only sequence that is important is to open each breaker before closing each valve. If the examinee repositions a valve prior to opening the breaker the JPM is considered unsat.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 2 Locally deenergize and close the appropriate valve. If SG C is faulted:

Open XMC1DB2Y 05EH, EMERG FEEDWATER PUMP MAIN STEAM BLOCK XVG2802B-MS (AB-463).

STEP STANDARD:

Determines that the AB operator has already opened XMC1DB2Y 05EH, EMERG FEEDWATER PUMP MAIN STEAM BLOCK XVG2802B-MS (AB-463).

CUES:

Evaluator Note: The only sequence that is important is to open each breaker before closing each valve. If the examinee repositions a valve prior to opening the breaker the JPM is considered unsat.

COMMENTS:

Saturday, August 03, 2013 Page 4 of 7

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 3 Close XVG02802A-MS, MS HEADER B EF PUMP TURBINE SUPPLY VLV (IB-436 East Pen).

STEP STANDARD:

Operator locates and closes XVG02802A-MS by pulling the manual engagement clutch lever down and turning the valve handwheel in the clockwise direction until the valve position arrow of the handwheel points to the right and the handwheel will no longer rotate.

CUES:

Evaluator Note: The only sequence that is important is to open each breaker before closing each valve. If the examinee repositions a valve prior to opening the breaker the JPM is considered unsat.

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 4 Close XVG02802B-MS, MS HEADER C EF PUMP TURBINE SUPPLY VLV (IB-436 East Pen).

STEP STANDARD:

Operator locates and closes XVG02802B-MS by pulling the manual engagement clutch lever down and turning the valve handwheel in the clockwise direction until the valve position arrow of the handwheel points to the right and the handwheel will no longer rotate.

CUES:

Evaluator Note: The only sequence that is important is to open each breaker before closing each valve. If the examinee repositions a valve prior to opening the breaker the JPM is considered unsat.

COMMENTS:

Examiner ends JPM at this point.

Saturday, August 03, 2013 Page 5 of 7

JPM SETUP SHEET JPM NO: JPP-107A DESCRIPTION: 2013 NRC In-Plant j: LOCALLY CLOSE AND DE-ENERGIZE MS LOOP "B" AND "C" TO TDEFP IC SET:

INSTRUCTIONS:

COMMENTS:

Saturday, August 03, 2013 Page 6 of 7

JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:

INITIAL CONDITION: The plant was at 100% power when a steamline break occurred inside containment. "B" and "C" SGs are faulted as indicated by steam pressure dropping in an uncontrolled manner. The CRS has implemented EOP-3.0, FAULTED STEAM GENERATOR ISOLATION, out of EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION, following a Automatic SI. Both motor driven emergency feedwater pumps started. MVG-2802A, MS LOOP B TO TD EFP and MVG-2802B, MS LOOP C TO TD EFP will not close from the MCB.

INITIATING CUES: RO directs you as the IB operator (Unit 7) to open breaker 05EH on XMC1DA2X and locally close valves XVG02802A-MS and XVG02802B-MS in accordance with EOP-3.0, Step 5.h, Alternative Action. The AB operator (Unit 6 upper) has already opened breaker 05EH on XMC1DB2Y. The shift supervisor has approved the waiving of ISP-027 requirements due to the emergency condition.

AT NO TIME ARE YOU TO OPERATE ANY PLANT EQUIPMENT!

HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.

Saturday, August 03, 2013

V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO: JPPF-066A 2013 NRC In-Plant k: LOCALLY ISOLATE RCP SEALS DURING A TOTAL LOSS OF ESF POWER APPROVAL: APPROVAL DATE:

REV NO: 3 CANDIDATE:

EXAMINER:

Saturday, August 03, 2013 Page 1 of 9

TASK:

000-175-05-04 Locally Isolate RCP Seals per EOP-6.0.

TASK STANDARD:

Seal injection and return valves for RCP seals have been manually isolated per EOP-6.0 Att 9.

TERMINATING CUE: RCP seals isolated per Att 9 of EOP-6.0.

PREFERRED EVALUATION LOCATION PREFERRED EVALUATION METHOD PLANT SIMULATE

REFERENCES:

EOP-6.0 LOSS OF ALL ESF AC POWER INDEX NO. K/A NO. RO SRO 000055K302 EK3.02 Actions contained in EOP for loss of 4.3 4.6 offsite and onsite power TOOLS: EOP-6.0, Attachment 9, LOCALLY OPERATED ISOLATION VALVES FLASHLIGHT EVALUATION TIME 15 TIME CRITICAL No 10CFR55: 45.a.6 TIME START: TIME FINISH: PERFORMANCE TIME:

PERFORMANCE RATING: SAT: UNSAT:

CANDIDATE:

EXAMINER:

SIGNATURE DATE Saturday, August 03, 2013 Page 2 of 9

INSTRUCTIONS TO OPERATOR READ TO OPERATOR:

WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.

SAFETY CONSIDERATIONS: MVT-8100 is in the north end of the 412' West Penetration area, which is a Radiation Area. At the discretion of the examiner, have the examinee describe the general location of the valve. Operation of the valve is identical to MVT-8105 and MVG-9606. Ensure to view radiation surveys and to monitor EDs if entering Radiation area.

INITIAL CONDITION: A total loss of offsite power has occurred and both DG's have failed to start. Alternate Seal injection also failed to start on the loss of power.

The CRS has implemented EOP-6.0, LOSS OF ALL ESF AC POWER, and is directing actions for locally isolating RCP seals.

INITIATING CUES: The RO calls and directs you to isolate RCP seals in accordance with Step 1 of Attachment 9 of EOP-6.0, LOCALLY OPERATED ISOLATION VALVES.

HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!

AT NO TIME ARE YOU TO OPERATE ANY PLANT EQUIPMENT!

FOR ELECTRICAL MANIPULATIONS, AT NO TIME ARE YOU TO BREAK THE PLANE OF THE ELECTRICAL PANEL!

Saturday, August 03, 2013 Page 3 of 9

STEPS CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 1 Locally isolate RCP Seals by closing the following (EOP-6.0 Step 13):

XVT08100-CS, RC PUMP SEAL RETURN HDR ISOL VLV(ORC) (AB-412 West Pen)

STEP STANDARD:

Engages manual handwheel by pressing down on the declutch lever on XVT08100-CS and turns handwheel fully clockwise.

CUES:

Evaluator Note: MVT-8100 is in the north end of the 412' West Penetration area, which is a Radiation Area. At the discretion of the examiner, have the examinee describe the general location of the valve. Operation of the valve is identical to MVT-8105 and MVG-9606. Ensure to view radiation surveys and to monitor EDs if entering Radiation area.

Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.

COMMENTS:

Saturday, August 03, 2013 Page 4 of 9

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 2 Locally isolate RCP Seals by closing the following (EOP-6.0 Step 13):

XVG09606-CC, RB CC RETURN HEADER VALVE (AB-436 West Pen)

STEP STANDARD:

Engages manual handwheel by pressing down on the declutch lever on XVG09606-CC and turns handwheel fully clockwise.

CUES:

Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 3 Locally isolate RCP Seals by closing the following (EOP-6.0 Step 13):

XVT08105-CS, SEAL INJECTION HEADER ISOLATION VALVE (AB-436)

STEP STANDARD:

Engages manual handwheel by pressing down on the declutch lever on XVT08105-CS and turns handwheel fully clockwise.

CUES:

Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.

COMMENTS:

Saturday, August 03, 2013 Page 5 of 9

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 4 Contact the Control Room to determine if the Alternate Seal Injection System has actuated.

STEP STANDARD:

Determines from initial cue or from calling the control room that Alternate Seal Injection has not actuated and that the alternate action is necessary.

CUES:

Evaluator Cue: If called as the control room reply that Alternate Seal Injection has not been actuated.

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 5 If the Alternate Seal Injection System has not actuated, close all the following:

XVT08102A-CS, RC PUMP A SEAL SUPPLY ISOL VALVE (ORC) (AB-412 West Pen).

STEP STANDARD:

Engages manual handwheel by pressing down on the declutch lever on XVT08102A-CS and turns handwheel fully clockwise.

CUES:

Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.

COMMENTS:

Saturday, August 03, 2013 Page 6 of 9

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 6 If the Alternate Seal Injection System has not actuated, close all the following:

XVT08102B-CS, RC PUMP B SEAL SUPPLY ISOL VALVE (ORC) (IB-412 East Pen).

STEP STANDARD:

Engages manual handwheel by pressing down on the declutch lever on XVT08102B-CS and turns handwheel fully clockwise.

CUES:

Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.

Evaluator Note: When validated this valve did not have a CHAMPS tag, but did have a small metal OEM tag.

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 7 If the Alternate Seal Injection System has not actuated, close all the following:

XVT08102C-CS, RC PUMP C SEAL SUPPLY ISOL VALVE (ORC) (IB-412 East Pen).

STEP STANDARD:

Engages manual handwheel by pressing down on the declutch lever on XVT08102C-CS and turns handwheel fully clockwise.

CUES:

Evaluator Cue: Cue applicant that valve moves in the clockwise direction and then stops.

COMMENTS:

Examiner ends JPM at this point.

Saturday, August 03, 2013 Page 7 of 9

JPM SETUP SHEET JPM NO: JPPF-066A DESCRIPTION: 2013 NRC In-Plant k: LOCALLY ISOLATE RCP SEALS DURING A TOTAL LOSS OF ESF POWER IC SET:

INSTRUCTIONS:

COMMENTS:

Saturday, August 03, 2013 Page 8 of 9

JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:

INITIAL CONDITION: A total loss of offsite power has occurred and both DG's have failed to start. Alternate Seal injection also failed to start on the loss of power.

The CRS has implemented EOP-6.0, LOSS OF ALL ESF AC POWER, and is directing actions for locally isolating RCP seals.

INITIATING CUES: The RO calls and directs you to isolate RCP seals in accordance with Step 1 of Attachment 9 of EOP-6.0, LOCALLY OPERATED ISOLATION VALVES.

AT NO TIME ARE YOU TO OPERATE ANY PLANT EQUIPMENT!

HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.

Saturday, August 03, 2013

V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO: NJPSF-141A 2013 NRC Sim a RO&SRO-I&SRO-U: CONTINUOUS ROD WITHDRAWAL APPROVAL: APPROVAL DATE:

REV NO: 3 CANDIDATE:

EXAMINER:

Thursday, August 01, 2013 Page 1 of 12

TASK:

000-006-05-01 RESPOND TO CONTINUOUS ROD MOTION TASK STANDARD:

The reactor is tripped per AOP-403.3, CONTINUOUS CONTROL ROD MOTION, to terminate the transient prior to exceeding Reactor trip setpoints.

Immediate actions of EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION, are completed.

TERMINATING CUE: Immediate actions of EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION are complete.

PREFERRED EVALUATION LOCATION PREFERRED EVALUATION METHOD SIMULATOR PERFORM

REFERENCES:

INDEX NO. K/A NO. RO SRO 0000012413 2.4.13 Knowledge of crew roles and 4.0 4.6 responsibilities during EOP usage.

TOOLS: GOP-3, REACTOR STARTUP FROM HOT STANDBY TO STARTUP (MODE 3 TO MODE 2)

AOP-403.3, CONTINUOUS CONTROL ROD MOTION EOP-1.0, REACTOR TRIP/SAFETY INJECTION ACTUATION REP-109.002, Enclosure 9.2, Recommended Rod Positions for ICRR.

EVALUATION TIME 10 TIME CRITICAL No 10CFR55: 45.a.3 TIME START: TIME FINISH: PERFORMANCE TIME:

PERFORMANCE RATING: SAT: UNSAT:

CANDIDATE:

EXAMINER:

SIGNATURE DATE Thursday, August 01, 2013 Page 2 of 12

INSTRUCTIONS TO OPERATOR READ TO OPERATOR:

WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.

SAFETY CONSIDERATIONS:

INITIAL CONDITION: GOP-3, REACTOR STARTUP FROM HOT STANDBY TO STARTUP (MODE 3 TO MODE 2), is in progress after a short mini-outage.

The shutdown banks have been fully withdrawn. Step 3.11 of GOP-3 is complete. Estimated critical position is 100 steps on bank "D".

INITIATING CUES: Increase reactor power to 10-3% per GOP-3 starting at Step 3.12. The Examiner will play the role of CRS and Reactor Engineering for this JPM. Reactor engineering has started REP-109.002, INVERSE COUNT RATE RATIO PLOT, and has taken all necessary data and is ready to collect data at 53 steps on Control Bank A.

HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!

Thursday, August 01, 2013 Page 3 of 12

STEPS CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 1 Review GOP Appendix A, Generic Operating Precautions, for Reactor Startup.

STEP STANDARD:

Reviews GOP Appendix A, Generic Operating Precautions, for Reactor Startup.

CUES:

Evaluator Note: This JPM can be briefed outside of the simulator and this step can occur outside of the simulator.

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 2 Procedure Caution: To prevent any inadvertent inward rod motion the ROD CNTRL BANK SEL Switch should not be placed in or pass through AUTO.

Place the ROD CNTRL BANK SEL Switch in MAN.

STEP STANDARD:

ROD CNTROL BANK SEL Switch taken counter clockwise to MAN.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 4 of 12

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 3 Procedure Note: A stable Startup Rate of one decade per minute should NOT be exceeded.

Using ROD CONTROL ROD MOTION lever, commence Control Bank Rod withdrawal to ten steps on Bank A.

STEP STANDARD:

Steps indicate ten steps on Bank A.

CUES:

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 4 Procedure Caution: 12 steps should NOT be exceeded until all Rod Bottom lights are off. If all Control Bank A Rod Bottom lights are NOT off at ten steps, AOP-403.5, Stuck Or Misaligned Control Rod, should be entered.

At ten steps on Control Bank A, stop and verify:

1) Bank A RB lights clear.
2) ONE ROD ON BOTTOM (XCP-621 3-1) annunciator clears.
3) RODS ON BOTTOM (XCP-621 3-2) annunciator clears.

STEP STANDARD:

1) Bank A RB lights clear.
2) ONE ROD ON BOTTOM (XCP-621 3-1) annunciator clears.
3) RODS ON BOTTOM (XCP-621 3-2) annunciator clears.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 5 of 12

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 5 Recommence withdrawing rods while observing that the groups sequence properly.

STEP STANDARD:

Continues to pull rods.

CUES:

Evaluator Cue: The examinee should stop pulling rods at 53 steps to collect data for inverse count rate ratio plot. Once the examinee determines that count rates are stable then cue the examinee that the estimated critical condition (ECC) is at 230 steps on Bank "D".

Evaluator Note: When rods are >53 steps on Bank A then the continuous rod motion will occur.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 6 Enters AOP-403.3, CONTINUOUS CONTROL ROD MOTION.

STEP STANDARD:

Enters AOP-403.3, CONTINUOUS CONTROL ROD MOTION.

CUES:

Evaluator Note: The applicant is not expected to pull out the procedure, but may perform the actions of this procedure from memory and trip the unit.

COMMENTS:

Thursday, August 01, 2013 Page 6 of 12

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 7 Verify rod motion is NOT required:

Tavg is within 1.5 °F of Tref.

AND No load rejection has occurred (C7A OR C7B).

STEP STANDARD:

Notes that rod motion is not required.

CUES:

Evaluator Note: This is an immediate operator action.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 8 Verify rod motion is stopped.

STEP STANDARD:

Notes that rod motion has not stopped.

CUES:

Evaluator Note: This is an immediate operator action.

COMMENTS:

Thursday, August 01, 2013 Page 7 of 12

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 9 Perform the following:

a) Trip the Reactor.

b) GO TO EOP-1.0. REACTOR TRIP/SAFETY INJECTION ACTUATION.

STEP STANDARD:

Turns reactor trip switch to trip.

CUES:

Evaluator Note: This is an immediate operator action.

COMMENTS:

Thursday, August 01, 2013 Page 8 of 12

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 10 Procedure Note: Steps 1 through 5 are Immediate Operator Actions.

The EOP REFERENCE PAGE should be monitored throughout the use of this procedure.

Conditions for implementing Emergency Plan Procedures should be evaluated using EPP-001, ACTIVATION AND IMPLEMENTATION OF EMERGENCY PLAN.

Verify Reactor Trip:

Trip the Reactor using either Reactor Trip Switch.

Verify all Reactor Trip and Bypass Breakers are open.

Verify all Rod Bottom Lights are lit.

Verify Reactor Power level is decreasing.

STEP STANDARD:

Reactor Trip and Bypass Breakers indicate green light lit red light off.

Rod Bottom Lights are lit.

Reactor Power level is decreasing.

CUES:

Evaluator Note: This is an immediate operator action.

COMMENTS:

Thursday, August 01, 2013 Page 9 of 12

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 11 Verify Turbine/Generator Trip:

a. Verify all Turbine STM STOP VLVs are closed.
b. Ensure Generator Trip (after 30 second delay):
1) Ensure the GEN BKR is open.
2) Ensure the GEN FIELD BKR is open.
3) Ensure the EXC FIELD CNTRL is tripped.

STEP STANDARD:

GEN BKR, GEN FIELD BKR, and EXC FIELD CNTRL indicate green light lit and red light off.

CUES:

Evaluator Note: This is an immediate operator action.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 12 Verify both ESF buses are energized.

STEP STANDARD:

Potential lights on 1DA and 1DB are lit for all three phases.

CUES:

Evaluator Note: This is an immediate operator action.

COMMENTS:

Examiner ends JPM at this point.

Thursday, August 01, 2013 Page 10 of 12

JPM SETUP SHEET JPM NO: NJPSF-141A DESCRIPTION: 2013 NRC Sim a RO&SRO-I&SRO-U: CONTINUOUS ROD WITHDRAWAL IC SET: 330/15 INSTRUCTIONS:

IC 15 MAL-PCS009AB REACTOR TRIP BREAKER A FAILURE (FAIL TO OPEN) Delay=0, Ramp=0, Final=AUTO_(UV)

MAL-PCS009BB REACTOR TRIP BREAKER B FAILURE (FAIL TO OPEN) Delay=0, Ramp=0, Final=AUTO_(UV)

Event #1 Mcrfpa(5) >53 Trigger #1 MAL-CRF006B UNCONTROLLED MANUAL ROD MOTION Delay=0, Ramp=0, Final=Active COMMENTS:

JPM is terminated after the reactor is tripped and immediate operator actions of EOP-1.0 are completed.

Ensure Audio Count Rate (step 3.4.e), HIGH FLUX AT SHUTDOWN is blocked (step 3.11.b), IPCS indicates MODE 2 (step 3.11.f), NR-45 is in HI speed (Audio count rate and NR-45 should be the two that are not saved with the snap). Reactivity is returned to service (see REP-109.002).

Thursday, August 01, 2013 Page 11 of 12

JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:

INITIAL CONDITION: GOP-3, REACTOR STARTUP FROM HOT STANDBY TO STARTUP (MODE 3 TO MODE 2), is in progress after a short mini-outage.

The shutdown banks have been fully withdrawn. Step 3.11 of GOP-3 is complete. Estimated critical position is 100 steps on bank "D".

INITIATING CUES: Increase reactor power to 10-3% per GOP-3 starting at Step 3.12. The Examiner will play the role of CRS and Reactor Engineering for this JPM. Reactor engineering has started REP-109.002, INVERSE COUNT RATE RATIO PLOT, and has taken all necessary data and is ready to collect data at 53 steps on Control Bank A.

HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.

Thursday, August 01, 2013

V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO: NJPSF-159 2013 NRC Sim b RO&SRO-I&SRO-U: SWAP RUNNING RBCU'S APPROVAL: APPROVAL DATE:

REV NO: 4 CANDIDATE:

EXAMINER:

Sunday, August 04, 2013 Page 1 of 12

TASK:

022-003-01-01 START THE REACTOR BUILDING VENTILATION SYSTEM PER SOP 114.

TASK STANDARD:

XFN-64A, XFN-064B, and XFN-65A are running in fast/norm speed and RBCU TRAIN B EMERG is selected to XFN-064B.

TERMINATING CUE: SOP-114 IV. D. SHIFTING REACTOR BUILDING COOLING UNITS FAN SPEED complete.

PREFERRED EVALUATION LOCATION PREFERRED EVALUATION METHOD SIMULATOR PERFORM

REFERENCES:

SOP-114 REACTOR BUILDING VENTILATION SYSTEM INDEX NO. K/A NO. RO SRO 022000A401 A4.01 CCS fans 3.6 3.6 TOOLS: SOP-114 IV. D. SHIFTING REACTOR BUILDING COOLING UNITS FAN SPEED EVALUATION TIME 5 TIME CRITICAL NO 10CFR55: 45.a.4 TIME START: TIME FINISH: PERFORMANCE TIME:

PERFORMANCE RATING: SAT: UNSAT:

CANDIDATE:

EXAMINER:

SIGNATURE DATE Sunday, August 04, 2013 Page 2 of 12

INSTRUCTIONS TO OPERATOR READ TO OPERATOR:

WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.

SAFETY CONSIDERATIONS: None.

INITIAL CONDITION: Mode 3.

The current lineup of the RBCU's is as follows: XFN-64A and XFN-64B are running in slow speed.

It is desired to run XFN-64A, XFN-64B, and XFN-65B in NORM speed in order to prepare for reactor startup.

INITIATING CUES: The CRS directs you as the RO to start XFN-64A, XFN-64B, and XFN-65B in NORM speed in accordance with SOP-114 Section IV. D.

SHIFTING REACTOR BUILDING COOLING UNITS FAN SPEED, in order to align the plant for a normal preferred at power lineup.

HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!

Sunday, August 04, 2013 Page 3 of 12

STEPS CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 1 Shift RBCUs as follows:

a. Shutdown RBCUs by placing appropriate switch(es) in STOP:
1) XFN 0064A-AH, 1A NORM.
2) XFN 0064A-AH, 1A SLOW.
3) XFN 0064B-AH, 1B NORM.
4) XFN 0064B-AH, 1B SLOW.
5) XFN 0065A-AH, 2A NORM.
6) XFN 0065A-AH, 2A SLOW.
7) XFN 0065B-AH, 2B NORM.
8) XFN 0065B-AH, 2B SLOW.

STEP STANDARD:

Takes XFN 0064A-AH, 1A SLOW and XFN 0064B-AH, 1B SLOW to stop. Verifies red light off and green light on.

CUES:

COMMENTS:

Sunday, August 04, 2013 Page 4 of 12

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 2 Ensure the RBCU dampers are in BYP:

1) XDP-110A, RBCU 64A HEPA FLTR BYP DMPR.
2) XDP-111A, RBCU 65A HEPA FLTR BYP DMPR.
3) XDP-110B, RBCU 64B HEPA FLTR BYP DMPR
4) XDP-111B, RBCU 65B HEPA FLTR BYP DMPR.

STEP STANDARD:

Takes XDP-110A, RBCU 64A HEPA FLTR BYP DMPR and XDP-110B, RBCU 64B HEPA FLTR BYP DMPR to BYP. Verifies red light lit and green light off.

CUES:

COMMENTS:

Sunday, August 04, 2013 Page 5 of 12

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 3 Procedure Note:

a. Due to eddy current brakes, RBCU control switches must be held in START position until the red beaker closed light is lit and starting current is indicated on appropriate meter.

B. Normal and preferred lineup is three RBCUs running in NORM (fast speed).

C. To increase stay times for teams entering containment, four RBCUs may be placed in service in NORM (fast speed).

Place RBCUs in service by starting three or four RBCUs in SLOW or NORM as follows:

For XFN0064A-AH, REACTOR BLDG COOLING UNIT 1A EMERG FAN, start one of the following:

a) XFN 0064A-AH, 1A NORM.

For XFN0064B-AH, REACTOR BLDG COOLING UNIT 1B EMERG FAN, start one of the following:

a) XFN 0064B-AH, 1B NORM.

For XFN0065B-AH, REACTOR BLDG COOLING UNIT 2B EMERG FAN, start one of the following:

a) XFN 0065B-AH, 2B NORM.

STEP STANDARD:

Takes and holds XFN 0064A-AH, 1A NORM, 0064B-AH, 1B NORM, and 0065B, 2B NORM to START until red breaker closed light is lit and starting current is indicated.

CUES:

COMMENTS:

Sunday, August 04, 2013 Page 6 of 12

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 4 Procedure Note: Contact PSE to evaluate, if RBCU fan motor amps exceed the values given.

Verify RBCU Fan motor amps return to normal operating range: 1) For fast speed operation, 275 amps to 300 amps. Remove RBCU fan from service due to above normal amps.

STEP STANDARD:

Determines normal amps for XFN0064A and XFN0064B CUES:

COMMENTS:

Sunday, August 04, 2013 Page 7 of 12

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 5 Determines that XFN0065B has tripped.

Enters XCP-607, 1-1, RBCU 1B/2B FAN TRIP CORRECTIVE ACTIONS:

1. Determine which fan tripped and place the control switch in Normal After Stop.
2. Start the non-running Reactor Building Cooling Unit fan after ensuring cooling water is lined up.
3. Dispatch an operator to XPN7077 (CB-436, TSC Equipment Room) to select the RACK RESET and reset the alarm.

SUPPLEMENTAL ACTIONS:

1. Determine the cause of the fan trip, correct and return to service as soon as possible.
2. Continued normal operation is allowed when one fan per group in slow speed is operable per Technical Specification 3.6.2.3.
3. Notify PSE (Predictive Maintenance) for further assistance.

STEP STANDARD:

Takes XFN 0065B-AH, 2B NORM to stop.

CUES:

Evaluator Note: This is where the JPM becomes alternate path.

Booth Operator Cue: If called to go to XPN7077 (CB-436, TSC Equipment Room) and to select the RACK RESET and reset the alarm, report that it is complete after 5 minutes.

COMMENTS:

Sunday, August 04, 2013 Page 8 of 12

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 6 From ARP:

2. Start the non-running Reactor Building Cooling Unit fan after ensuring cooling water is lined up.

From SOP:

Place RBCUs in service by starting three or four RBCUs in SLOW or NORM as follows:

For XFN0065A-AH, REACTOR BLDG COOLING UNIT 2A EMERG FAN, start one of the following:

a) XFN 0065A-AH, 2A NORM.

STEP STANDARD:

Takes and holds XFN 0065A, 2A NORM to START until red breaker closed light is lit and starting current is indicated.

CUES:

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 7 Verify RBCU Fan motor amps return to normal operating range: 1) For fast speed operation, 275 amps to 300 amps STEP STANDARD:

Verifies RBCU motor amps return to normal operating range.

CUES:

COMMENTS:

Sunday, August 04, 2013 Page 9 of 12

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 8 Procedure Note: The RBCU TRAIN A (B) EMERG switch must be selected to an operable RBCU.

Verify the following switches are in the desired position:

1) XFN-64A/XFN 65A - RBCU TRAIN A EMERG.
2) XFN-64B/XFN 65B - RBCU TRAIN B EMERG.

STEP STANDARD:

Takes XFN-64B/XFN 65B - RBCU TRAIN B EMERG to XFN-64B position.

CUES:

Evaluator Cue: If applicant reports that an inoperable RBCU is selected for start, ask for a recommendation and approve it.

Evaluator Note: The section of XFN-64B causes XCP-6103 5-6, RB RECRIC UNIT C 3108C/ 3109C MISALIGN and XCP-6103 5-7, RB RECRIC UNIT D 3108D/ 3109D to change condition (dim/bright).

COMMENTS:

Examiner ends JPM at this point.

Sunday, August 04, 2013 Page 10 of 12

JPM SETUP SHEET JPM NO: NJPSF-159 DESCRIPTION: 2013 NRC Sim b RO&SRO-I&SRO-U: SWAP RUNNING RBCU'S IC SET: 331/4 INSTRUCTIONS:

IC 4.

Pre-Event Load Select RBCU TRAIN A EMERG to XFN-65A and select RBCU TRAIN B EMERG to XFN-65B.

Stop all RBCUs Start XFN-64A and XFN-64B in slow.

Take XDP-110A, RBCU 64A HEPA FLTR BYP DMPR and XDP-110B, RBCU 64B HEPA FLTR BYP DMPR to FILTER.

PMP-AH049B XFN0065BH RB CLG RAN HIGH BRG FAILURE Final=1.2 Event 1:

X02O104R==1 (red light lit for XFN-65B Trigger 1:

PMP-AH049T Delay=2 seconds Trip of XFN-65B.

Saved to IC 331.

COMMENTS:

Need to provide copies of procedure since is not laminated in the simulator.

Sunday, August 04, 2013 Page 11 of 12

JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:

INITIAL CONDITION: Mode 3.

The current lineup of the RBCU's is as follows: XFN-64A and XFN-64B are running in slow speed.

It is desired to run XFN-64A, XFN-64B, and XFN-65B in NORM speed in order to prepare for reactor startup.

INITIATING CUES: The CRS directs you as the RO to start XFN-64A, XFN-64B, and XFN-65B in NORM speed in accordance with SOP-114 Section IV. D.

SHIFTING REACTOR BUILDING COOLING UNITS FAN SPEED, in order to align the plant for a normal preferred at power lineup.

HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.

Sunday, August 04, 2013

V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO: NJPS-034A 2013 NRC Sim JPM c RO&SRO-I: INCREASE LETDOWN FLOW TO A MAXIMUM TO IMPROVE CHEMISTRY APPROVAL: APPROVAL DATE:

REV NO: 4 CANDIDATE:

EXAMINER:

Thursday, August 01, 2013 Page 1 of 9

TASK:

044-031-01-01 Adjust Letdown Flowrate per SOP-102.

TASK STANDARD:

Letdown flow is increased to about 120 gpm without ever exceeding 120 gpm.

Letdown pressure controlled such that the letdown relief valve does not open.

TERMINATING CUE: Letdown flow at 120 gpm with PCV-145 returned to AUTO.

PREFERRED EVALUATION LOCATION PREFERRED EVALUATION METHOD SIMULATOR PERFORM

REFERENCES:

INDEX NO. K/A NO. RO SRO 004000A419 A4.19 CVCS letdown orifice isolation valve and 3.1 2.8 valve control switches TOOLS: SOP-102 Section IV. R. SHIFTING LETDOWN ORIFICES WITH NORMAL LETDOWN IN SERVICE EVALUATION TIME 5 TIME CRITICAL No 10CFR55: 45.a.6 TIME START: TIME FINISH: PERFORMANCE TIME:

PERFORMANCE RATING: SAT: UNSAT:

CANDIDATE:

EXAMINER:

SIGNATURE DATE Thursday, August 01, 2013 Page 2 of 9

INSTRUCTIONS TO OPERATOR READ TO OPERATOR:

WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.

SAFETY CONSIDERATIONS: None.

INITIAL CONDITION: 100% power. Chemistry has called and wants to maximize letdown to improve primary chemistry.

INITIATING CUES: The CRS directs you as the RO to increase letdown flow to the maximum in accordance with SOP-102,Section IV.R. SHIFTING LETDOWN ORIFICES WITH NORMAL LETDOWN IN SERVICE.

HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!

Thursday, August 01, 2013 Page 3 of 9

STEPS CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 1 Verify Initial Conditions:

1.1 Letdown is in service (Letdown flow rate of 60 gpm to 120 gpm).

1.2 Pressurizer level is greater than 18%.

Procedure Note: More than two Letdown Orifices may be placed in service when RCS pressure is less than or equal to 1000 psig as long as a Letdown flow rate of 120 gpm is not exceeded.

STEP STANDARD:

Verifies current letdown flow at 95 gpm.

Verifies current pressurizer level is 60%.

CUES:

Evaluator Cue: The applicant may request further direction about what it means to raise letdown to a maximum (which valves are desired to be open). Ask for a recommendation and approve the recommendation given. The desired line up will be PVT-8149B and PVT-8149C open and PVT8149A closed.

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 2 Place PCV-145, LO PRESS LTDN, in MAN and open to 70%.

STEP STANDARD:

PCV-145, LO PRESS LTDN, indicates MAN and open to 70%.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 4 of 9

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 3 If necessary, close the desired Orifice Isolation Valve:

a. PVT-8149A, LTDN ORIFICE A ISOL (45 gpm).

B. PVT-8149B, LTDN ORIFICE B ISOL (60 gpm).

C. PVT-8149C, LTDN ORIFICE C ISOL (60 gpm).

STEP STANDARD:

Takes PVT-8149A, LTDN ORIFICE A ISOL (45 gpm) to CLOSE. Verifies green light lit and red light dim.

CUES:

Evaluator Note: PVT-8149A, LTDN ORIFICE A ISOL (45 gpm) must be closed before PVT-8149C, LTDN ORIFICE C ISOL (60 gpm) is opened to preclude damage to the demins. If flow is allowed to exceed 120 gpm it constitutes a failure.

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 4 Open the desired Orifice Isolation Valve:

a. PVT-8149A, LTDN ORIFICE A ISOL (45 gpm).
b. PVT-8149B, LTDN ORIFICE B ISOL (60 gpm).
c. PVT-8149C, LTDN ORIFICE C ISOL (60 gpm).

STEP STANDARD:

Takes PVT-8149C, LTDN ORIFICE C ISOL (60 gpm), to OPEN. Verifies red light and green light dim.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 5 of 9

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 5 Adjust PCV-145, LO PRESS LTDN, to maintain PI-145, LO PRESS LTDN PRESS PSIG, between 300 psig and 400 psig.

STEP STANDARD:

PCV-145, LO PRESS LTDN, adjusted to maintain 300-400 psig as indicated on PI-145.

CUES:

Evaluator Note: This step is critical in that the applicant must do it so that pressure does not exceed the letdown relief setpoint. This will be evidenced by annunciator XCP-613 2-2, LP LTDN RLF TEMP HI.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 6 Ensure PCV-145 Setpoint Pot is set between 5.0 and 6.7.

STEP STANDARD:

PCV-145 Setpoint Pot is between 5.0 and 6.7.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 6 of 9

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 7 Place PCV-145, LO PRESS LTDN, in AUTO.

STEP STANDARD:

PCV-145, LO PRESS LTDN, indicates AUTO.

CUES:

COMMENTS:

Examiner ends JPM at this point.

Thursday, August 01, 2013 Page 7 of 9

JPM SETUP SHEET JPM NO: NJPS-034A DESCRIPTION: 2013 NRC Sim JPM c RO&SRO-I: INCREASE LETDOWN FLOW TO A MAXIMUM TO IMPROVE CHEMISTRY IC SET: 10 INSTRUCTIONS:

No special instructions, Just reset to IC-10.

COMMENTS:

Need to provide copies of procedure since it is not laminated in the simulator. Allow students to mark up procedure in books and then replace after JPM.

Thursday, August 01, 2013 Page 8 of 9

JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:

INITIAL CONDITION: 100% power. Chemistry has called and wants to maximize letdown to improve primary chemistry.

INITIATING CUES: The CRS directs you as the RO to increase letdown flow to the maximum in accordance with SOP-102,Section IV.R. SHIFTING LETDOWN ORIFICES WITH NORMAL LETDOWN IN SERVICE.

HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.

Thursday, August 01, 2013

V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO: NJPSF-059B 2013 NRC Sim JPM d RO&SRO-I: ALTERNATE ISOLATION OF RUPTURED SG ("C" MSIV FAILS TO CLOSE)

APPROVAL: APPROVAL DATE:

REV NO: 15 CANDIDATE:

EXAMINER:

Thursday, August 01, 2013 Page 1 of 18

TASK:

000-504-05-01 Perform Ruptured Steam Generator Isolation.

TASK STANDARD:

The "C" SG is completely isolated from the "A" and "B" SG's per EOP-4.0, steps 3.a - 3h, and step 3.i alternate actions.

TERMINATING CUE: EOP-4.0, step 3.i complete.

PREFERRED EVALUATION LOCATION PREFERRED EVALUATION METHOD SIMULATOR PERFORM

REFERENCES:

EOP-4.0 STEAM GENERATOR TUBE RUPTURE INDEX NO. K/A NO. RO SRO 000038A132 EA1.32 Isolation of a ruptured S/G 4.6 4.7 TOOLS: EOP-4.0, STEAM GENERATOR TUBE RUPTURE EVALUATION TIME 15 TIME CRITICAL NO 10CFR55: 45.a.6 TIME START: TIME FINISH: PERFORMANCE TIME:

PERFORMANCE RATING: SAT: UNSAT:

CANDIDATE:

EXAMINER:

SIGNATURE DATE Thursday, August 01, 2013 Page 2 of 18

INSTRUCTIONS TO OPERATOR READ TO OPERATOR:

WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SAFETY CONSIDERATIONS:

INITIAL CONDITION: The "C" Steam Generator has experienced a tube rupture. The crew has taken actions through step 2 of EOP-4.0, STEAM GENERATOR TUBE RUPTURE. The RO has been assigned to monitor RCP trip criteria of step 1.

INITIATING CUES: The CRS has directed you as the BOP to isolate the "C" SG in accordance with EOP-4.0, STEAM GENERATOR TUBE RUPTURE, step 3.

HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!

Thursday, August 01, 2013 Page 3 of 18

STEPS CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 1 Procedure Caution: At least one SG must be maintained available for RCS cooldown.

Place the Steamline PWR RELIEF A(B)(C) SETPT Controller(s) in MAN and closed.

STEP STANDARD:

"C" Steamline PWR RELIEF SETPT controller MAN pushbutton is depressed and decrease pushbutton is depressed so that both MAN and decrease pushbuttons are illuminated. Controller output will also read 0.

CUES:

Evaluator Note: There is not a demand for the PORV to be open and so taking the controller to MAN and closed is not critical.

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 2 Adjust the PWR RELIEF A(B)(C) SETPT Controller(s) to 8.85 (1150 psig).

STEP STANDARD:

"C" Steamline PWR RELIEF SETPT controller turned so that it indicates 8.85 (1150 psig).

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 4 of 18

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 3 Place the Steamline Power Relief A(B)(C) Mode Switch(s) in PWR RLF.

STEP STANDARD:

"C" Steamline Power Relief mode switch taken to PWR RLF.

CUES:

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 4 Place the PWR RELIEF A(B)(C) SETPT Controller(s) in AUTO.

STEP STANDARD:

"C" Steamline PWR RELIEF SETPT controller AUTO pushbutton is pressed. AUTO pushbutton illuminates.

CUES:

Evaluator Note: It is only critical that the controller be left in AUTO at the end of the JPM. If the controller was never taken to Manual and Closed then this step is not critical.

COMMENTS:

Thursday, August 01, 2013 Page 5 of 18

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 5 WHEN RCS Tavg is LESS THAN P-12 (552°F), THEN place both STM DUMP INTERLOCK Switches to BYP INTLK.

STEP STANDARD:

Both STM DUMP INTERLOCK switches indicate BYP INTLK (red flag) when RCS Tavg <552°F.

CUES:

Evaluator Note: If RCS Tavg is >552°F then this step is not performed at this time.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 6 Verify the Steamline PORV closed.

STEP STANDARD:

PCV-2020 indicates red light off, green light on. Demand on controller is zero.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 6 of 18

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 7 Procedure Caution: If the TD EFW Pump is the only available source of feed flow, the steam supply to the TD EFW Pump must be maintained from at least one SG, to maintain a secondary heat sink.

Procedure Note: If the TD EFW Pump is tripped, it should be reset as time permits.

IF SG B OR SG C is RUPTURED, THEN perform the following:

1) IF at least one MD EFW Pump is running, THEN isolate the TD EFW Pump by placing PVG-2030, STM SPLY TO TD EFP TRN A(B), to CLOSE.

STEP STANDARD:

Both switches for PVG-2030 are taken to close. PVG-2030 STM SPLY TO TD EFP TRN A (B) indicates red light off and green light on.

CUES:

Evaluator Note: Both PVG-2030 switches must be taken to close before the valve closes.

Booth Operator Cue: When called to reset the TD EFW Pump use the LOA resets page or trigger

  1. 1 to reset TD EFW Pump after it comes to a stop.

COMMENTS:

Thursday, August 01, 2013 Page 7 of 18

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 8 Notify local Operators to perform Alternate Action Step 3.g, while continuing with this procedure.

STEP STANDARD:

Calls local operator to perform Alternate Action Step 3.g CUES:

Booth Operator Cue: When called to perform Alternate Action Step 3.g use trigger #2 and #3 to do so.

Booth Operator Note: If called for repeat back of Alternate Action Step 3.g it is as follows for SG C:

1) Open XMC1DB2Y 05EH, EMERG FEEDWATER PUMP MAIN STEAM BLOCK XVG2802B-MS (AB-463). Trigger #2 Unit 6U
2) Close XVG02802B-MS, MS HEADER C EF PUMP TURBINE SUPPLY VLV (IB-436 East Pen).

Trigger #3 Unit 7.

COMMENTS:

Thursday, August 01, 2013 Page 8 of 18

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 9 Close the following for each RUPTURED SG:

SG Blowdown, PVG-503A(B)(C).

STEP STANDARD:

PVG-503C indicates red light off, green light on.

CUES:

Evaluator Note: PVG-503C is already closed on EFW pump start and so there is no action here.

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 10 Close the following for each RUPTURED SG:

MS Drain Isolation, PVT-2843A(B)(C).

STEP STANDARD:

Takes PVT-2843C to close. PVT-2843C indicates red light OFF, green light ON.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 9 of 18

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 11 Close the following for each RUPTURED SG:

MS Drain Isolation, PVT-2877A for SG A PVT-2877B for SG C.

STEP STANDARD:

Takes PVT-2877B to close. PVT-2877B indicates red light OFF, green light ON.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 10 of 18

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 12 Close the following for each RUPTURED SG:

- MS Isolation Valve, PVM-2801A(B)(C).

- MS Isolation Bypass Valve, PVM-2869A(B)(C).

STEP STANDARD:

Takes PVM-2801C to close.

Notes MS Isolation Valve, PVM-2801C still indicates red light on, green light off (MSIV failed to close).

MS Isolation Bypass Valve, PVM-2869C indicates red light off, green light on.

CUES:

Evaluator Note: Operator may send someone out to locally close the "C" MSIV while proceeding.

Evaluator Note: This is when the JPM becomes alternate path.

Booth Operator Cue: If called to locally close the "C" MSIV wait 5 minutes and report that you have bleed air off the "C" MSIV but it did not go closed.

COMMENTS:

Thursday, August 01, 2013 Page 11 of 18

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 13

1) Close the following:

All remaining MS Isolation and MS Isolation Bypass Valves.

STEP STANDARD:

Takes individual MSIV switches PVM-2801A&B, A(B) ISOL VLV or common switch PVM-2801A,B,C, MS LINES ISOL VLVS to close. MS PVM-2801A&B, MS ISOLATION VALVE, PVM-2869A&B, MS ISOLATION BYPASS VALVE, indicate red light off and green light on.

CUES:

Evaluator Note: This step can be accomplished in two ways. The individual MSIVs can be closed or the common switch can be used. The bypass valves are already closed and so its not critical to close them.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 14

1) Close the following:

PCV-2058, MS TO AUX STM STEP STANDARD:

PCV-2058, MS TO AUX STM, indicates red light off and green light on.

CUES:

Evaluator Note: PCV-2058, MS TO AUX STM is already closed and so this requires no action.

COMMENTS:

Thursday, August 01, 2013 Page 12 of 18

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 15

1) Close the following:

MVG-1701, STEAM SEAL FEED VLV STEP STANDARD:

MVG-1701 is taken to close. MVG-1701, STEAM SEAL FEED VLV, indicates red light off and green light on.

CUES:

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 16

1) Close the following:

MVG-2896A, SV-1 BSD.

MVG-2896B, SV-2 BSD.

MVG-2896C, SV-3 BSD.

MVG-2896D, SV-4 BSD.

STEP STANDARD:

Takes MVG-2896A-D, SV-1 (2,3,4) BSD to close. MVG-2896A-D, SV-1 (2,3,4) BSD, indicates red light off and green light on.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 13 of 18

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 17

1) Close the following:

IPV-2231, MS/PEGGING STM TO DEAERATOR.

STEP STANDARD:

Places IPV-2231, MS/PEGGING STM TO DEAERATOR, controller in MAN and output of 0%.

CUES:

Evaluator Note: IPV-2231 is already closed and so this step is not critical.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 18

2) At the Digital Control Station for the MSRs, ensure the following are closed:

MVG-2811.

XVG-2807.

STEP STANDARD:

At MSR DCS terminal, MVG-2811 and XVG-2807 indicate closed.

CUES:

Evaluator Note: These valves are in there required positions and so action is taken.

COMMENTS:

Thursday, August 01, 2013 Page 14 of 18

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 19

3) Place the STM DUMP CNTRL Controller in MAN and closed.

STEP STANDARD:

Pushes STM DUMP CNTRL controller MAN pushbutton. Pushes decrease pushbutton as necessary to set controller to 0. MAN and decrease pushbuttons illuminated with 0% output on controller.

CUES:

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 20

4) Place the STM DUMP MODE SELECT Switch in STM PRESS.

STEP STANDARD:

STM DUMP MODE SELECT Switch in STM PRESS.

CUES:

Evaluator Note: This step is not critical if the steam dumps are already taken to manual and closed.

COMMENTS:

Thursday, August 01, 2013 Page 15 of 18

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 21

5) Place the following in AUTO and ensure the valves are closed (REFER TO ATTACHMENT 1, ALTERNATE ISOLATION OF RUPTURED STEAM GENERATORS, if necessary to locally isolate valves):

PVT-2870, TO MSR A & B DRN.

PVT-2875, TO MSR A & B DRN.

PVT-2851A,B,C,D, MS LINES TO TURB DRN.

PVT-2713A,B,C,D, STM DUMP DRN BYP.

PVT-2838A,B, HDR DRNS.

6) Direct the Turbine Building Operator to complete ATTACHMENT 1, ALTERNATE ISOLATION OF RUPTURED STEAM GENERATORS.

STEP STANDARD:

Notes PVT-2870, To MSR A&B DRN indicates mid-position with red and green light on.

Directs Turbine Building Operator to complete ATTACHMENT 1, ALTERNATE ISOLATION OF RUPTURED STEAM GENERATORS. Including alternate isolation for PVT-2870 by closing XVT02871A-MS, MSR A&B MS SUP HDR DRAIN POT OUTLET VLV at TB-412-G-02.

The following valve switches are in AUTO with red light OFF and green light ON:

- PVT-2875, TO MSR A&B DRN

- PVT-2851A-D, MS LINES TO TURB DRN

- PVT-2713A-D, STEAM DUMP DRN BYP

- PVT-2838A,B, HDR DRNS.

CUES:

Evaluator Note: Step one of Attachment 1 is always done and step two contains backup valves for any valves that fail to close. The TB operator will be called to close XVT02871A-MS, MSR A&B MS SUP HDR DRAIN POT OUTLET VLV at TB-412-G-02 as well as to perform step one of Attachment 1.

Evaluator Note: Due to the complexity of this task the applicant may call an auxiliary operator to the control room to effectively communicate the desired local actions.

Evaluator Note: The JPM can be stopped once the order to complete Attachment 1 is given. There are no observable actions here other than ordering the local operator to complete the necessary tasks.

COMMENTS:

Examiner ends JPM at this point.

Thursday, August 01, 2013 Page 16 of 18

JPM SETUP SHEET JPM NO: NJPSF-059B DESCRIPTION: 2013 NRC Sim JPM d RO&SRO-I: ALTERNATE ISOLATION OF RUPTURED SG ("C" MSIV FAILS TO CLOSE)

IC SET: 333/ 10 INSTRUCTIONS:

Start at IC 10: Saved to IC 333 for 2013 NRC exam.

MAL-RCS002C STEAM GENERATOR C TUBE LEAK Final=400 RAMP=00:00:30 (SGTR ON

'C' S/G)

MAL-MSS006C MAIN STEAM ISOLATION VALVE (S/G C) FAILURE Final= FAIL TO CLOSE (C MSIV FAIL TO CLOSE)

VLV-MS041P XVT02870-MS MS LINE TO MOSS SEP DEP DRN FAIL POSITION Final = 80 (2870 Failed 80% open)

Manual SI and perform actions of EOP-1.0 & EOP-4.0 up through step 2.

Throttle EFW flow to 'C' S/G when > 40% level.

Silence HVAC alarms.

This is where IC is saved.

RUN 5 seconds day of and acknowledge annunciators When student is ready: RUN Local Operator Actions when instructed:

Trigger #1: EOP-4.0, STEAM GENERATOR TUBE RUPTURE, 3.g LOA-MSS026 EMERGENCY FW TDFP MN STM THROTTLE VLV 2865 RESET Final=RESET (Reset TDEFW pump once RPMs reach 0.0.

Trigger #2: EOP-4.0, STEAM GENERATOR TUBE RUPTURE, Alternate action 3.g LOA-MSS033 TDEFP STM SUP VLV 2802B BRK Final=OPEN (Open XMC1DB2Y 05EH, EF PUMP MAIN STEAM BLOCK XVG2802B-MS (AB-463)

Trigger #3: EOP-4.0, STEAM GENERATOR TUBE RUPTURE, Alternate action 3.g VLV-MS009P XVG02802B-MS MS LP C TO TD EF PMP FAIL POSITION Final=0, Ramp=00:00:30 (CLOSE XVG02802B-MS, MS HEADER C EF PUMP TURBINE SUPPLY VLV (IB-436 East Pen).

EOP-4.0, STEAM GENERATOR TUBE RUPTURE, Alternate Action 3.i.5) refer to Attachment 1, ALTERNATE ISOLATION OF RUPTURED STEAM GENERATORS PVT-2870, TO MSR A & B DRN.

Currently there is no modeling of XVT02871A-MS MSR A&B MS SUP HDR DRAIN POT OUTLET VLV (TB-412) but report that it is closed .

COMMENTS:

Circle and slash up to step 3.0 of EOP-4.0, STEAM GENERATOR TUBE RUPTURE.

Thursday, August 01, 2013 Page 17 of 18

JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:

INITIAL CONDITION: The "C" Steam Generator has experienced a tube rupture. The crew has taken actions through step 2 of EOP-4.0, STEAM GENERATOR TUBE RUPTURE. The RO has been assigned to monitor RCP trip criteria of step 1.

INITIATING CUES: The CRS has directed you as the BOP to isolate the "C" SG in accordance with EOP-4.0, STEAM GENERATOR TUBE RUPTURE, step 3.

HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.

Thursday, August 01, 2013

V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO: NJPS-151 2013 NRC Sim JPM e RO&SRO-I: SHIFT RHR LOOPS WITH RHR IN SERVICE APPROVAL: APPROVAL DATE:

REV NO: 4 CANDIDATE:

EXAMINER:

Thursday, August 01, 2013 Page 1 of 15

TASK:

005-001-01-01 Perform Lineups of the Residual Heat Removal System TASK STANDARD:

RHR train "A" is providing core cooling. RHR Train "B" is secured. RCS temperatures remain less than 200°F to preclude unplanned/allowed entry into MODE 4.

TERMINATING CUE: RHR Train "A" is in service with RHR Train "B" shut down.

PREFERRED EVALUATION LOCATION PREFERRED EVALUATION METHOD SIMULATOR PERFORM

REFERENCES:

SOP-115 RESIDUAL HEAT REMOVAL INDEX NO. K/A NO. RO SRO 005000A401 A4.01 Controls and indication for RHR pumps 3.6 3.4 TOOLS: SOP-115, RESIDUAL HEAT REMOVAL EVALUATION TIME 20 TIME CRITICAL NO 10CFR55: 45.a.7 TIME START: TIME FINISH: PERFORMANCE TIME:

PERFORMANCE RATING: SAT: UNSAT:

CANDIDATE:

EXAMINER:

SIGNATURE DATE Thursday, August 01, 2013 Page 2 of 15

INSTRUCTIONS TO OPERATOR READ TO OPERATOR:

WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.

SAFETY CONSIDERATIONS:

INITIAL CONDITION: Plant heatup is in progress in accordance with GOP-2, PLANT STARTUP AND HEATUP (MODE 5 TO MODE 3).

The crew has performed all steps up to step 3.4 of GOP-2 and is currently drawing a bubble with pressurizer level on scale on wide range level.

The ABLL has reported that the "B" RHR Pump bearing is making loud unusual noises and is worried about damage to the pump since it is vibrating excessively.

The CRS and Shift Supervisor have determined that "A" RHR loop be placed in service and the plant maintained in Mode 5.

INITIATING CUES: The CRS directs you as the RO to shift from RHR Train "B" to RHR Train "A" running in accordance with SOP-115, RESIDUAL HEAT REMOVAL, section III.E, SHIFTING FROM RHR TRAIN B TO RHR TRAIN A RUNNING, starting with step 2.1.

"A" CCW will remain the active loop.

HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!

Thursday, August 01, 2013 Page 3 of 15

STEPS CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 1 Procedure Caution:

a. Performance of this procedure while RCS Hot Leg temperatures are greater than or equal to 200°F renders both RHR Loops incapable of being aligned to the RWST (reference Technical Specification 3.5.3.d) until the Hot Leg temperatures are reduced to less than 200°F.
b. Unless Plant conditions absolutely require shifting trains of RHR, this procedure should not normally be utilized in Mode 4.
c. PCV-145, LO PRESS LTDN, must be in MAN if starting or stopping an RHR Pump with the primary system solid with RHR letdown flow via HCV-142, LTDN FROM RHR.

Ensure the following valves are energized and open per GOP-6, Plant Shutdown From Hot Standby To Cold Shutdown (Mode 3 To Mode 5):

a. MVG-8701A, RCS LP A TO PUMP A.

B. MVG-8702A, RCS LP A TO PUMP A.

STEP STANDARD:

Verifies MVG-8701A and MVG-8702A are energized and open - Red lights ON, green lights OFF CUES:

COMMENTS:

Thursday, August 01, 2013 Page 4 of 15

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 2 Ensure Train "A" Component Cooling is aligned to supply RHR Heat Exchanger "A" per SOP-118 STEP STANDARD:

Determines that "A" Component Cooling is aligned to supply the "A" RHR heat exchanger by verifying that MVB-9503A, CC TO RHR HX A, is open and that flow is indicated on FI-7034, HX A FLOW GPM.

CUES:

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 3 Close HCV-603A, A Outlet STEP STANDARD:

Rotates controller for HCV-603A fully counter-clockwise CUES:

COMMENTS:

Thursday, August 01, 2013 Page 5 of 15

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 4 Place FCV-605A, A BYP, in MAN and adjust to 100%

STEP STANDARD:

Places controller for FCV-605A in MANUAL and adjusts output to 100%

CUES:

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 5 Readjust FCV-605A, A BYP, in MAN to 40%.

STEP STANDARD:

Adjusts output for FCV-605A to 40%

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 6 of 15

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 6 Place PCV-145, LO PRESS LTDN, in MAN STEP STANDARD:

Places controller for PCV-145 in MANUAL CUES:

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 7 Procedure Note:

a. RHR Pump run time on miniflow should not be permitted to exceed 30 minutes.
b. After each RHR Pump start, IFI00602A (AB-374) indication should be evaluated to verify proper operation of IFV0602A.

Start XPP-0031A, Pump A STEP STANDARD:

Places RHR Pump "A" control switch in START. Verifies amps and control switch indication turns red.

CUES:

Booth Operator Cue: If called to check out the RHR pump for start report that the pump is good for start. If called to investigate the pump after start, report that the pump looks good after start. When called to investigate IFI00602A report that flow is 1000 gpm.

Evaluator Note: Applicant will ask for a peer check as required by the procedure. Acknowledge that the applicant would ask for a peer check.

COMMENTS:

Thursday, August 01, 2013 Page 7 of 15

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 8 Place PCV-145, LO PRESS LTDN, in AUTO STEP STANDARD:

Places controller for PCV-145 in AUTOMATIC CUES:

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 9 Equalize flow between the two RHR loops by slowly opening FCV-605A, A BYP.

STEP STANDARD:

Observing flow, slowly increases the output of the controller for FCV-605A until flows are approximately equal.

CUES:

Evaluator Note: Flow will not totally equalize between the two loops. It is critical that "A" loop RHR flow is established not that flows are brought to be equal.

COMMENTS:

Thursday, August 01, 2013 Page 8 of 15

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 10 Place FCV-605A, A BYP, in AUTO.

STEP STANDARD:

FCV-605A, A BYP, in AUTO CUES:

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 11 Procedure Caution: In Mode 6, RHR flow must be greater than 2800 gpm per Technical Specifications 3.9.7.1 and 3.9.7.2.

Procedure Note: If RCPs or two trains of RHR are running, RHR flow may be less than 3750 gpm.

FCV-605A controller setpoint may need to be adjusted to less than the normal flow setpoint to improve temperature control while cooling down.

Ensure FCV-605A, A BYP, modulates to maintain between 2000 GPM and 3750 GPM as indicated on FI-605A, PUMP A FLOW GPM.

STEP STANDARD:

Verifies indicated flow on FI-605A is between 2000 and 3750 GPM.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 9 of 15

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 12 Shift Letdown from RHR Train B to RHR Train A as follows (AB-412):

Open XVT08720A-RH, LETDOWN HDR RH RETURN HDR A INLET VALVE Close XVT08720B-RH, LETDOWN HDR RH RETURN HDR B INLET VALVE STEP STANDARD:

Directs operator to perform valve alignment CUES:

Booth Operator Cue: When called to Open XVT-8702A use Trigger 1 to open the valve.

When called to close XVT8702B use Trigger 2 to close the valve.

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 13 Align RHR Loop B for Standby Operation as follows:

Shift all heat removal to Loop A by slowly opening HCV-603A, A OUTLET, while adjusting HCV-603B, B OUTLET, closed STEP STANDARD:

Adjusts HCV-603A in the clockwise direction and HCV-603B in the counter clockwise direction while maintaining approximately the same total RHR flow.

Continues to throttle HCV-603A open and HCV-603B closed until all flow is on Train "A" CUES:

Evaluator Note: It is critical that RCS temperature at the RHR inlet is not allowed to increase above 200°F because this would be an unplanned mode change into MODE 4.

COMMENTS:

Thursday, August 01, 2013 Page 10 of 15

CRITICAL: No SEQUENCED: No SAT UNSAT STEP: 14 Close HCV-603B, B OUTLET STEP STANDARD:

Rotates controller for HCV-603B fully counter clockwise CUES:

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 15 Place FCV-605B, B BYP, in MAN and adjust to 40%

STEP STANDARD:

Places controller for FCV-605B in MANUAL and adjusts controller output to 40%

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 11 of 15

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 16 Secure the RHR Pump B as follows:

1) If the primary system is solid, a) Place PCV-145, LO PRESS LTDN, in MAN.

b) Stop XPP-0031B, PUMP B.

c) Place PCV-145, LO PRESS LTDN, in AUTO.

2) If there is a steam bubble in the Pressurizer, stop XPP-0031B, PUMP B.

STEP STANDARD:

Places "B" RHR Pump Control Switch in STOP. Observes green light on, red light off. Amps go to zero.

CUES:

Evaluator Note: There is a bubble in the Pressurizer.

Evaluator Cue: Cue the applicant as the CRS to place the B RHR pump control switch in PTL for maintenance to look at the pump.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 17 Close FCV-605B, B BYP STEP STANDARD:

Adjusts the controller for FCV-605B to 0%

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 12 of 15

CRITICAL: No SEQUENCED: No SAT UNSAT STEP: 18 Open HCV-603B, B OUTLET STEP STANDARD:

Adjusts the controller for HCV-603B fully clockwise CUES:

COMMENTS:

Examiner ends JPM at this point.

Thursday, August 01, 2013 Page 13 of 15

JPM SETUP SHEET JPM NO: NJPS-151 DESCRIPTION: 2013 NRC Sim JPM e RO&SRO-I: SHIFT RHR LOOPS WITH RHR IN SERVICE IC SET: 334/2 INSTRUCTIONS:

Start with IC 2. IC set 2 is collapsing the bubble. Change parameters to slowly draw a bubble.

Stabilize RCS pressure 350-400 psig and RCS temperature at ~188°F (Open CCW "A" to RHR HX).

Saved to IC 334.

Trigger 1:8720A (open) LOA-RHR001 Final=1 Trigger 2: 8702B (close) LOA-RHR002 Final =0 COMMENTS:

Thursday, August 01, 2013 Page 14 of 15

JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:

INITIAL CONDITION: Plant heatup is in progress in accordance with GOP-2, PLANT STARTUP AND HEATUP (MODE 5 TO MODE 3).

The crew has performed all steps up to step 3.4 of GOP-2 and is currently drawing a bubble with pressurizer level on scale on wide range level.

The ABLL has reported that the "B" RHR Pump bearing is making loud unusual noises and is worried about damage to the pump since it is vibrating excessively.

The CRS and Shift Supervisor have determined that "A" RHR loop be placed in service and the plant maintained in Mode 5.

INITIATING CUES: The CRS directs you as the RO to shift from RHR Train "B" to RHR Train "A" running in accordance with SOP-115, RESIDUAL HEAT REMOVAL, section III.E, SHIFTING FROM RHR TRAIN B TO RHR TRAIN A RUNNING, starting with step 2.1.

"A" CCW will remain the active loop.

HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.

Thursday, August 01, 2013

V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO: NJPSF-161 2013 NRC Sim JPM f RO&SRO-I: RESPOND TO A FEED REGULATING VALVE CLOSURE AT LOW POWER APPROVAL: APPROVAL DATE:

REV NO: 3 CANDIDATE:

EXAMINER:

Thursday, August 01, 2013 Page 1 of 10

TASK:

000-147-05-01 Respond to Feedwater Flow Control Valve Failure per AOP-201.1.

TASK STANDARD:

"A" steam generator level is controlled by the operator without causing an automatic reactor trip.

TERMINATING CUE: "A" S/G level is under control of the operator with the main feed reg bypass valve.

PREFERRED EVALUATION LOCATION PREFERRED EVALUATION METHOD SIMULATOR PERFORM

REFERENCES:

INDEX NO. K/A NO. RO SRO 059000A212 A2.12 Failure of feedwater regulating valves 3.1 3.4 TOOLS: AOP-210.1, FEEDWATER FLOW CONTROL VALVE FAILURE EVALUATION TIME 5 TIME CRITICAL NO 10CFR55: 45.a.3 TIME START: TIME FINISH: PERFORMANCE TIME:

PERFORMANCE RATING: SAT: UNSAT:

CANDIDATE:

EXAMINER:

SIGNATURE DATE Thursday, August 01, 2013 Page 2 of 10

INSTRUCTIONS TO OPERATOR READ TO OPERATOR:

WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.

SAFETY CONSIDERATIONS: None.

INITIAL CONDITION: 15% power BOL.

INITIATING CUES: Respond to developing plant conditions as the BOP operator.

HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!

Thursday, August 01, 2013 Page 3 of 10

STEPS CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 1 Diagnose entry into AOP-210.1, FEEDWATER FLOW CONTROL VALVE FAILURE.

Procedure Note: Throughout this procedure, "AFFECTED" refers to any Feedwater Flow Control Valve that has failed open, closed, or does NOT respond to demand.

1. Abnormal indication on the associated Feedwater Flow Control Valve controller:

PVT-478, SG A FWF.

PVT-488, SG B FWF.

PVT-498, SG C FWF.

2. Any of the following Main Control Board annunciators in alarm:

SG A(B)(C) STF>FWF MISMATCH (XCP-624 4-3(5-3)(6-3)).

SG A(B)(C) FWF>STF MISMATCH (XCP-624 4-4(5-4)(6-4)).

SG A(B)(C) LVL DEV (XCP-624 1-5(2-5)(3-5)).

SG A(B)(C) LVL LO (XCP-624 1-3(2-3)(3-3)).

SG A(B)(C) LVL HI-HI (XCP-624 1-1(2-1)(3-1)).

SG A(B)(C) LVL LO-LO (XCP-624 1-2(2-2)(3-2)).

STEP STANDARD:

Diagnoses that PVT-478, SG A FWF is closing and enters AOP-210.1, FEEDWATER FLOW CONTROL VALVE FAILURE.

CUES:

Evaluator Note: The applicant may attempt to utilize the ARP actions to correct the level deviations but opening of the bypass valve is unique to the AOP.

Evaluator Note: Allow the applicant to pick the desired procedure from the list of AOPs and then provide AOP-210.1 from the drawer.

COMMENTS:

Thursday, August 01, 2013 Page 4 of 10

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 2 Manually adjust the AFFECTED Feedwater Flow Control Valve as necessary to maintain Narrow Range SG level between 60% and 65%:

PVT-478, SG A FWF.

STEP STANDARD:

Attempts to take manual control of PVT-478, SG A FWF, but determines that the valve will not open manually.

CUES:

Evaluator Note: This is an immediate operator action and applicant may do this step without aid of the procedure although that is not required as long as the plant is brought to a stable condition.

COMMENTS:

Thursday, August 01, 2013 Page 5 of 10

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 3 Adjust Feedwater Pump speed and Main Turbine load as necessary to maintain SG level. Do NOT exceed 1600 psig Feedwater Pump discharge pressure.

STEP STANDARD:

Raises MFP speed. Does not exceed 1600 psig Feedwater Pump discharge pressure.

CUES:

Evaluator Note: This is an immediate operator action and applicant may do this step without aid of the procedure although that is not required as long as the plant is brought to a stable condition.

Evaluator Note: Note if 1600 psig Feedwater Pump discharge pressure is exceeded the MFP's will trip.

Evaluator Note: With the malfunction that is present this action will not be effective and the applicant may skip this step and go directly to the bypass valve.

COMMENTS:

Thursday, August 01, 2013 Page 6 of 10

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 4 If feed flow remains low, THEN perform the following:

Open the associated bypass valve as necessary to control SG level:

FCV-3321, LOOP A MAIN FW BYP.

FCV-3331, LOOP B MAIN FW BYP.

FCV-3341, LOOP C MAIN FW BYP.

STEP STANDARD:

FCV-3321, LOOP A MAIN FW BYP is in manual and open. S/G level is controlled between 60% and 65%.

CUES:

Evaluator Note: This is an immediate operator action and applicant may do this steps without aid of the procedure although that is not required as the plant is brought to a stable condition.

COMMENTS:

Thursday, August 01, 2013 Page 7 of 10

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 5 Procedure Note: If the Feedwater Flow Control Valve is closed, the maximum flow attainable with the bypass valve is 20% to 30%.

Reduce plant load as necessary to control SG level using the bypass valve. REFER TO GOP-4, POWER OPERATION (MODE 1).

STEP STANDARD:

Determines that "A" SG level can be maintained at current power level.

CUES:

Evaluator Note: This is an immediate operator action and applicant may do this steps without aid of the procedure although that is not required as the plant is brought to a stable condition.

COMMENTS:

Examiner ends JPM at this point.

Thursday, August 01, 2013 Page 8 of 10

JPM SETUP SHEET JPM NO: NJPSF-161 DESCRIPTION: 2013 NRC Sim JPM f RO&SRO-I: RESPOND TO A FEED REGULATING VALVE CLOSURE AT LOW POWER IC SET: 335/44 INSTRUCTIONS:

Saved to IC 335 from IC 44 When examiner is ready insert Trigger #1.

Trigger # 1 VLV-FW001P IFV00478-FW SG A FW CTRL VLV FAIL POSITION Delay=0, Ramp=00:01:00, Final=5.

COMMENTS:

Thursday, August 01, 2013 Page 9 of 10

JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:

INITIAL CONDITION: 15% power BOL.

INITIATING CUES: Respond to developing plant conditions as the BOP operator.

HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.

Thursday, August 01, 2013

V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO: NJPS-162 2013 NRC Sim JPM g RO&SRO-I: START AND LOAD THE MAIN GENERATOR APPROVAL: APPROVAL DATE:

REV NO: 3 CANDIDATE:

EXAMINER:

Thursday, August 01, 2013 Page 1 of 14

TASK:

045-005-01-01 Synchronize Turbine Generator with Grid at Minimum Load Per SOP-201/SOP-207/SOP-214/SOP-218/SOP-217 TASK STANDARD:

Main Generator is synchronized with the grid without causing damage to the main generator breaker (closing out of phase) and loaded to 50 MW.

TERMINATING CUE: Main Generator is synchronized with grid and is carrying at least 50 MW.

PREFERRED EVALUATION LOCATION PREFERRED EVALUATION METHOD SIMULATOR PERFORM

REFERENCES:

INDEX NO. K/A NO. RO SRO 062000A401 A4.01 All breakers (including available 3.3 3.1 switchyard)

TOOLS: SOP-301, MAIN GENERATOR SYSTEM.

EVALUATION TIME 15 TIME CRITICAL NO 10CFR55: 45.a.6 TIME START: TIME FINISH: PERFORMANCE TIME:

PERFORMANCE RATING: SAT: UNSAT:

CANDIDATE:

EXAMINER:

SIGNATURE DATE Thursday, August 01, 2013 Page 2 of 14

INSTRUCTIONS TO OPERATOR READ TO OPERATOR:

WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.

SAFETY CONSIDERATIONS: None.

INITIAL CONDITION: 15% power. The Main Generator is being synchronized in accordance with SOP-301 Section III. A. STARTUP. Step 2.2 has just been completed.

INITIATING CUES: The CRS directs you as the BOP to synchronize the Main Generator in accordance with SOP-301 Section III. A. STARTUP starting at step 2.3.

HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!

Thursday, August 01, 2013 Page 3 of 14

STEPS CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 1 Procedure Note: The System Controller should be notified as soon as practical, but within 30 minutes if Automatic Regulation is not achieved.

Place the GEN VOLT REG XFER Switch, in MAN.

STEP STANDARD:

GEN VOLT REG XFER Switch, in MAN.

CUES:

Evaluator Note: The GEN VOLT REG XFER will already be in MAN and so this step is not critical.

Booth Operator Cue: If called as the system controller respond that you understand they are putting the voltage adjust in Manual and to notify that condition exists for >30 minutes.

Booth Operator Cue: If asked for a switching order respond that your switching order is 1.

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 2 Close the GEN FIELD BKR.

STEP STANDARD:

GEN FIELD BKR take to CLOSE. Red light lit. Green light off.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 4 of 14

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 3 Using the EXC FIELD CNTRL Switch, energize the Exciter and Main Generator by placing the switch to CLOSE and verifying the red light illuminates.

STEP STANDARD:

EXC FIELD CNTRL taken to CLOSE Red light lit. Green light off.

CUES:

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 4 Procedure Note: To prevent inadvertently over or under exciting the Main Generator, the controls for both the Manual and Automatic Regulators are only activated for an interval of 1.0 second per adjustment.

Using the EXC FIELD VOLT ADJ (MAN) Control Switch adjust Generator KILOVOLTS to 22 KV (normal band 20.9 to 23.1 KV).

STEP STANDARD:

EXC FIELD VOLT ADJ (MAN) used. KILOVOLTS are between 20.9 and 23.1 KV.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 5 of 14

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 5 Using the GEN VOLT SEL Switch, check phase voltages on KILOVOLTS Meter.

STEP STANDARD:

All positions of GEN VOLT SEL show voltage between 20.9 and 23.1 KV.

CUES:

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 6 Procedure Note: Failure of one regulation mode to track with the other is indicative of a problem with the in-service Core. I&C should be contacted to investigate the problem.

Verify the Automatic Regulator tracks to match the Manual Regulator by observing the EXCITER VOLTS Meter trends to 0%.

STEP STANDARD:

EXCITER VOLTS meter is at 0%.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 6 of 14

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 7 Transfer the GEN VOLT REG XFER Switch, to AUTO.

STEP STANDARD:

GEN VOLT REG XFER Switch in AUTO.

CUES:

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 8 Using the GEN FIELD VOLT ADJ (AUTO) Control Switch, cycle Main Generator voltage above and below 22 KV (normal band 20.9 to 23.1 KV) sufficiently to verify control while monitoring that the EXCITER VOLTS Meter trends toward 0% following each cycle.

STEP STANDARD:

Voltage raised and lowered. EXCITER VOLTS Meter trends toward 0%.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 7 of 14

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 9 Procedure Note: In order to get the light to change state on any of the active OC2000 Pushbuttons, the button itself must be depressed.

Ensure the PSS CNTRL ENABLE Pushbutton is lit (TB-436, OC2000).

STEP STANDARD:

Calls local operator to ensure PSS CNTRL ENABLE Pushbutton is lit (TB-436, OC2000).

CUES:

Booth Operator Cue: When called to ensure PSS CNTRL ENABLE Pushbutton is lit (TB-436, OC2000) respond that it is lit.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 10 Notify the System Controller that the unit is ready to be paralleled and obtain a Switching Order.

STEP STANDARD:

Calls System Controller for Switching Order.

CUES:

Booth Operator Cue: When called as System Controller for a Switching Order respond "Parallel to the Grid, Your Switching Order is 1."

COMMENTS:

Thursday, August 01, 2013 Page 8 of 14

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 11 Place the GEN SYNC NORM FEED Switch, to MAN.

STEP STANDARD:

GEN SYNC NORM FEED Switch, in MAN.

CUES:

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 12 Using the GEN FIELD VOLT ADJ (AUTO) Control Switch, adjust GEN VOLTS equal to or slightly higher than SYS VOLTS.

STEP STANDARD:

GEN VOLTS equal or slightly higher than SYS VOLTS.

CUES:

COMMENTS:

Thursday, August 01, 2013 Page 9 of 14

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 13 Using the Raise Lower Pushbuttons on the Main Control Board at the Turbine EHC HMI adjust Turbine speed until the SYNCHROSCOPE rotates slowly in the FAST (clockwise) direction.

STEP STANDARD:

SYNCHROSCOPE rotates slowly in the FAST (clockwise) direction.

CUES:

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 14 When the SYNCHROSCOPE indicator passes 11 oclock and slowly approaches 12 oclock, close the GEN BKR. (PEER check)

STEP STANDARD:

GEN BKR is closed in phase.

CUES:

Evaluator Note: This step requires a peer check. Respond that you understand that applicant desires a peer check.

COMMENTS:

Thursday, August 01, 2013 Page 10 of 14

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 15 Verify the GEN BKR is closed.

STEP STANDARD:

GEN BKR is CLOSED. Red light lit. Green light off.

CUES:

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 16 On the EHC HMI, Control/Load screen, select Ramp Rate and enter desired rate of 1% or less.

G. Raise Turbine load to 50 MW by one of the following methods:

1) Using the EHC HMI, Control/Load screen, select Manual Adj, Raise.
2) Using the Raise Pushbutton on the Main Control Board at the Turbine EHC HMI.

STEP STANDARD:

MW indicate ~ 50 MW.

CUES:

Evaluator Note: The new EHC system now loads the generator to ~50 MW automatically.

Evaluator Cue: If asked as SS what the desired rate of load increase is respond 0.5 %/min.

COMMENTS:

Thursday, August 01, 2013 Page 11 of 14

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 17 Place the GEN SYNCH NORM FEED Switch in OFF.

STEP STANDARD:

GEN SYNCH NORM FEED Switch in OFF.

CUES:

COMMENTS:

Examiner ends JPM at this point.

Thursday, August 01, 2013 Page 12 of 14

JPM SETUP SHEET JPM NO: NJPS-162 DESCRIPTION: 2013 NRC Sim JPM g RO&SRO-I: START AND LOAD THE MAIN GENERATOR IC SET: 336/44 INSTRUCTIONS:

Saved to IC-336. Build from IC-44.

IC-44.

Ensure IR and PR low trip setpoints are blocked.

Roll Main Turbine to 1800 RPM, per SOP-214, Main Turbine And Controls.

Freeze.

When applicant is ready go to run.

COMMENTS:

Ensure that the GEN VOLT REG XFER Switch is at the 45° angle and not 90° where it points at nothing.

Thursday, August 01, 2013 Page 13 of 14

JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:

INITIAL CONDITION: 15% power. The Main Generator is being synchronized in accordance with SOP-301 Section III. A. STARTUP. Step 2.2 has just been completed.

INITIATING CUES: The CRS directs you as the BOP to synchronize the Main Generator in accordance with SOP-301 Section III. A. STARTUP starting at step 2.3.

HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.

Thursday, August 01, 2013

V.C. SUMMER NUCLEAR STATION JOB PERFORMANCE MEASURE JPM NO: NJPS-152 2013 NRC Sim JPM h RO: RESPOND TO HIGH REACTOR BUILDING PRESSURE APPROVAL: APPROVAL DATE:

REV NO: 15 CANDIDATE:

EXAMINER:

Saturday, August 03, 2013 Page 1 of 10

TASK:

029-004-01-01 VENT THE REACTOR BUILDING TASK STANDARD:

RB pressure is reduced <+0.05 and >-0.05 psig on PI-8254, RB NR PRESS PSI.

Containment isolation is restored by closing the purge exhaust valves.

TERMINATING CUE: RB purge is secured.

PREFERRED EVALUATION LOCATION PREFERRED EVALUATION METHOD SIMULATOR PERFORM

REFERENCES:

SOP-114 REACTOR BUILDING VENTILATION SYSTEM INDEX NO. K/A NO. RO SRO 028000A401 A4.01 HRPS controls 4.0 4.0 TOOLS: SOP-114, REACTOR BUILDING VENTILATION SYSTEM HPP-709, Attachment VI, REACTOR BUILDING PURGE RELEASE PERMIT.

EVALUATION TIME 15 TIME CRITICAL No 10CFR55: 45.a.5 TIME START: TIME FINISH: PERFORMANCE TIME:

PERFORMANCE RATING: SAT: UNSAT:

CANDIDATE:

EXAMINER:

SIGNATURE DATE Saturday, August 03, 2013 Page 2 of 10

INSTRUCTIONS TO OPERATOR READ TO OPERATOR:

WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE INITIATING CUES. I WILL DESCRIBE THE GENERAL CONDITIONS UNDER WHICH THIS TASK IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THIS JOB PERFORMANCE MEASURE WILL BE SATISFIED.

SAFETY CONSIDERATIONS:

INITIAL CONDITION: Plant is at 100% power.

Preparations are underway to conduct maintenance on the Personnel Access inner door.

SOP-114, REACTOR BUILDING VENTILATION SYSTEM, III.P.

LOWERING REACTOR BUILDING PRESSURE USING NORMAL PRESSURE CONTROL is being used to lower RB pressure.

All initial conditions have been met. A reactor building purge release permit has been issued in accordance with HPP-709. RM-A4 and RM-A2 are in service.

RM-A4's setpoint has been adjusted in accordance with the Release Permit and step 2.4 of SOP-114, III.P.

FI-8252, H2 PURGE FLOW CFM is out of service. The CRS has completed 702 Attachment VI.S-3, 6" RB PURGE OPERATING WITH IFT08252 AND/OR RMA-4 INOPERABLE, which requires that the release flowrate be estimated every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. The CRS has determined that the flow rate will be estimated at 600 cfm for the duration of the release.

INITIATING CUES: Lower RB pressure as required in accordance with SOP-114, REACTOR BUILDING VENTILATION SYSTEM, III.P. LOWERING REACTOR BUILDING PRESSURE USING NORMAL PRESSURE CONTROL starting at step 2.5.

HAND JPM BRIEFING SHEET TO OPERATOR AT THIS TIME!

Saturday, August 03, 2013 Page 3 of 10

STEPS CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 1 Procedure Caution: To prevent damage to Alternate Purge System ducting, Alternate Purge must not be placed in service if RB pressure is greater than 3 psi.

Open the following:

1) PVG-6066, CNTMT PUR EXH ISOL VLV.
2) PVG-6067, CNTMT PUR EXH ISOL VLV.

STEP STANDARD:

Places PVG-6066, CNTMT PUR EXH ISOL VLV and PVG-6067, CNTMT PUR EXH ISOL VLV.

switch in the OPEN position. Verifies the valve opens by observing the red light lit and the green light off.

CUES:

COMMENTS:

Saturday, August 03, 2013 Page 4 of 10

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 2 Start XFN-96, ALT PUR EXH FAN.

STEP STANDARD:

Places switch for XFN-96 ALT PUR EXH FAN in START. Observes red light ON and green light OFF.

CUES:

Examiner Cue: Cue the applicant that "Time Compression" will be used to expedite the administration of the JPM.

Evaluator Note: The procedure requires a peer check at this step. Acknowledge that you understand that the applicant will obtain a peer check.

COMMENTS:

Saturday, August 03, 2013 Page 5 of 10

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 3 Record time release was started and flow rate as indicated on FI-8252, H2 PURGE FLOW CFM, in the following places:

1) Reactor Building Purge Release Permit.
2) Station Log Book.

STEP STANDARD:

Records start time and flowrate estimate of 600 cfm in the Station Log Book and on the Continuous Waste Release Permit.

CUES:

Examiner Cue: Cue the applicant that the start time and flow rate will be transferred to the station log book.

Examiner Note: Initial conditions indicate that the flowrate of the release is estimated at 500 cfm.

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 4 Records release readings from RM-A2 and RM-A4.

STEP STANDARD:

Records release readings from RM-A2 and RM-A4.

CUES:

COMMENTS:

Saturday, August 03, 2013 Page 6 of 10

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 5 If RB pressure is being lowered to support door maintenance, simultaneous opening of both personnel hatch doors or opening of equipment hatch door, perform the following:

a. Monitor PI-8254, RB NR PRESS PSI.
b. When RB pressure is between negative 0.05 psi and positive 0.05 psi, stop XFN-96, ALT PUR EXH FAN.

STEP STANDARD:

Checks RB pressure <+0.05 and >-0.05 psig on PI-8254, RB NR PRESS PSI.

CUES:

COMMENTS:

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 6 Stop XFN-96, ALT PUR EXH FAN.

STEP STANDARD:

Stops XFN-96, ALT PUR EXH FAN.

CUES:

COMMENTS:

Saturday, August 03, 2013 Page 7 of 10

CRITICAL: Yes SEQUENCED: Yes SAT UNSAT STEP: 7 Close the following:

a. PVG-6066, CNTMT PUR EXH ISOL VLV.
b. PVG-6067, CNTMT PUR EXH ISOL VLV.

STEP STANDARD:

Places PVG-6066 CNTMT PUR EXH ISOL VLV and PVG-6067 CNTMT PUR EXH ISOL VLV switches in the CLOSE position and verifies the valves go close by verifying green light lit and red light off.

CUES:

COMMENTS:

CRITICAL: No SEQUENCED: Yes SAT UNSAT STEP: 8 Record time release was stopped in the following places:

a. Reactor Building Purge Release Permit.
b. Station Log Book.

STEP STANDARD:

Records time in the Station Log Book and on the Continuous Waste Release Permit.

CUES:

Examiner Cue: Cue the applicant that the release time will be recorded in the station log book and the continuous waste release permit.

COMMENTS:

Examiner ends JPM at this point.

Saturday, August 03, 2013 Page 8 of 10

JPM SETUP SHEET JPM NO: NJPS-152 DESCRIPTION: 2013 NRC Sim JPM h RO: RESPOND TO HIGH REACTOR BUILDING PRESSURE IC SET: 363/10 INSTRUCTIONS:

Run when applicant is ready.

If IC-363 is not available:

Reset to IC 10 Event #1 x15i355t>0 Enter MALF RMS004C, CONT BREACH FHB436; Set = 2 SCFT, when examinee starts XFN-96.

Event #2 x15i355s>0&&jmlrms4c>0 (Deletes Malf RMS004C when the examinee secures XFN-96)

COMMENTS:

Hang an Orange R&R tag on FI-8252, H2 PURGE FLOW CFM.

Provide an operator to silence alarms and have operator silence alarms from the MCB while the applicant is conducting the realease from the HVAC panel.

Saturday, August 03, 2013 Page 9 of 10

JPM BRIEFING SHEET OPERATOR INSTRUCTIONS:

INITIAL CONDITION: Plant is at 100% power.

Preparations are underway to conduct maintenance on the Personnel Access inner door.

SOP-114, REACTOR BUILDING VENTILATION SYSTEM, III.P.

LOWERING REACTOR BUILDING PRESSURE USING NORMAL PRESSURE CONTROL is being used to lower RB pressure.

All initial conditions have been met. A reactor building purge release permit has been issued in accordance with HPP-709. RM-A4 and RM-A2 are in service.

RM-A4's setpoint has been adjusted in accordance with the Release Permit and step 2.4 of SOP-114, III.P.

FI-8252, H2 PURGE FLOW CFM is out of service. The CRS has completed 702 Attachment VI.S-3, 6" RB PURGE OPERATING WITH IFT08252 AND/OR RMA-4 INOPERABLE, which requires that the release flowrate be estimated every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. The CRS has determined that the flow rate will be estimated at 600 cfm for the duration of the release.

INITIATING CUES: Lower RB pressure as required in accordance with SOP-114, REACTOR BUILDING VENTILATION SYSTEM, III.P. LOWERING REACTOR BUILDING PRESSURE USING NORMAL PRESSURE CONTROL starting at step 2.5.

HAND THIS PAPER BACK TO YOUR EVALUATOR WHEN YOU FEEL THAT YOU HAVE SATISFACTORILY COMPLETED THE ASSIGNED TASK.