MONTHYEARML22125A1762022-05-0505 May 2022 Preparation and Scheduling of Operator Licensing. ML21279A2222021-10-0606 October 2021 301 RO NRC Exam ML21279A2282021-10-0606 October 2021 301 SRO NRC Exam ML21279A2192021-10-0606 October 2021 301 Post Exam Comments ML24053A1822021-09-13013 September 2021 301 ADAMS 2A-2 ML24053A1862021-09-13013 September 2021 301 ADAMS 2A-3 ML24053A1942021-09-0303 September 2021 V.C. Summer 2021-301 ADAMS 2B ML24053A1892021-08-26026 August 2021 301 ADAMS 2B ML21074A2712021-03-12012 March 2021 VCS 2021-301 Corporate Notification Letter Aka 210-day Letter ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 ML24053A1802020-09-0808 September 2020 301 ADAMS 2A-1 ML20105A4342020-04-14014 April 2020 (Vcsns), Unit 1 - NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations ML20043F0942020-02-11011 February 2020 (2) VC Summer 2019-301 Exam Report Items - SRO Written Exam ML20043F0932020-02-11011 February 2020 (1) VC Summer 2019-301 Exam Report Items - RO Written Exam ML20007F7572020-01-0707 January 2020 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2020 ML19352G6942019-12-16016 December 2019 VC Summer 2019-301 Written Exam Approval Letter ML19340A0612019-12-0606 December 2019 VC Summer 2019-301 Exam Approval Letter ML19022A2132019-01-18018 January 2019 VCS 2019 Corporate Notification Letter Aka 210-Day Letter ML19018A0882019-01-17017 January 2019 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2019 ML18226A3442018-08-14014 August 2018 VC Summer U2 2017-302 Exam Administrative Items ML18116A6892018-04-26026 April 2018 (Vcsns), Unit 1 - Regulatory Issue Summary, RIS 2018-02: Preparation and Scheduling of Operator Licensing Examinations ML18057B5102018-02-26026 February 2018 V. C. Summer 05000395/2011301 Exam Draft Items 2A ML18057A9362018-02-26026 February 2018 301 Exam Administrative Items ML18057B5352018-02-26026 February 2018 VC Summer 05000395/2011301 Exam Administrative Items 2C ML18057A7672018-02-26026 February 2018 301 Exam Final Items (Delayed Release-2 Year) ML18057A7402018-02-26026 February 2018 VCS Unit 1 2017-301 Exam Draft Items (Delayed Release-2 Years) ML18057A8142018-02-26026 February 2018 301 Exam Administrative Items (Delayed Release-2 Year) ML18086B0442018-02-16016 February 2018 Facility Cover Letter - Rii - March 2018 - GFE ML18032A2372018-02-0101 February 2018 Form ES-201 Vogtle 3&4, V.C. Summer 2&3 Initial NRC Written Exam Sample Plan - ADAMS 2A - Public Exam Draft Items - Delay Release 2 Years ML17298B9692017-10-25025 October 2017 /2016-301 Public Draft Items (ADAMS-2A)- Delay Release 2 Yrs ML17298C0122017-10-25025 October 2017 V. C. Summer, Unit 2, 05200027/2016301 Public Administrative Items (ADAMS-2C)- Delay Release 2 Yrs ML17298A5532017-10-25025 October 2017 VC Summer 05000395/2017301 Exam Report Items RO As-Given Written Exam ML17263B2132017-09-14014 September 2017 V. C. Summer Nuclear Power Plant - Operator Licensing Examination Approval 05000395/2017301 ML17193A9242017-07-12012 July 2017 (U1) 2016-301 Exam Final Items - Delay Release ML17193A9262017-07-12012 July 2017 (U1) 2016-301 Exam Administrative Items - Delay Release ML17181A3672017-06-30030 June 2017 V.C. Summer 2015-301 Exam Administrative Items for ADAMS 2C ML17181A3622017-06-30030 June 2017 V.C. Summer 2015-301 Exam Final Items for ADAMS 2B ML17181A3542017-06-30030 June 2017 V.C. Summer 2015-301 Exam Draft Items for ADAMS 2A ML17181A3762017-06-30030 June 2017 V.C. Summer 2015-301 Exam Administrative Items for ADAMS 2D IR 05000395/20173012017-04-0505 April 2017 Notification of Licensed Operator Initial Examination 05000395/2017301 ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 ML16279A3232016-10-0303 October 2016 September 2016 - Summer Unit 1 NRC Generic Fundamentals Examination Results ML16201A2232016-07-15015 July 2016 Preparation and Scheduling of Operator Licensing Examinations ML16179A2712016-06-24024 June 2016 (Unit 1) 2016-301 SRO As-Given Written Exam ML16179A2682016-06-24024 June 2016 (Unit 1) 2016-301 RO As-Given Written Exam ML16158A5002016-05-31031 May 2016 VC Summer Operator Licensing Written Examination Approval 05000395/2016301 ML15280A3802015-10-0505 October 2015 September 2015 - NRC Generic Fundamentals Examination Results ML17193A9232015-08-10010 August 2015 (U2) 2016-301 Exam Draft Items - Delay Release ML15211A3932015-07-30030 July 2015 Initial Exam 2015-302 Post Exam Comments RC-15-0076, VC Summer 2015-301 Initial Exam Post Exam Comments2015-06-26026 June 2015 VC Summer 2015-301 Initial Exam Post Exam Comments 2022-05-05
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML22125A1762022-05-0505 May 2022 Preparation and Scheduling of Operator Licensing. ML21279A2192021-10-0606 October 2021 301 Post Exam Comments ML21279A2222021-10-0606 October 2021 301 RO NRC Exam ML21279A2282021-10-0606 October 2021 301 SRO NRC Exam ML24053A1862021-09-13013 September 2021 301 ADAMS 2A-3 ML24053A1822021-09-13013 September 2021 301 ADAMS 2A-2 ML24053A1942021-09-0303 September 2021 V.C. Summer 2021-301 ADAMS 2B ML24053A1892021-08-26026 August 2021 301 ADAMS 2B ML21074A2712021-03-12012 March 2021 VCS 2021-301 Corporate Notification Letter Aka 210-day Letter ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 ML24053A1802020-09-0808 September 2020 301 ADAMS 2A-1 ML20105A4342020-04-14014 April 2020 (Vcsns), Unit 1 - NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations ML20043F0942020-02-11011 February 2020 (2) VC Summer 2019-301 Exam Report Items - SRO Written Exam ML20043F0932020-02-11011 February 2020 (1) VC Summer 2019-301 Exam Report Items - RO Written Exam ML19352G6942019-12-16016 December 2019 VC Summer 2019-301 Written Exam Approval Letter ML19340A0612019-12-0606 December 2019 VC Summer 2019-301 Exam Approval Letter ML19022A2132019-01-18018 January 2019 VCS 2019 Corporate Notification Letter Aka 210-Day Letter ML18226A3442018-08-14014 August 2018 VC Summer U2 2017-302 Exam Administrative Items ML18116A6892018-04-26026 April 2018 (Vcsns), Unit 1 - Regulatory Issue Summary, RIS 2018-02: Preparation and Scheduling of Operator Licensing Examinations ML18057A9362018-02-26026 February 2018 301 Exam Administrative Items ML18057B5102018-02-26026 February 2018 V. C. Summer 05000395/2011301 Exam Draft Items 2A ML18057B5352018-02-26026 February 2018 VC Summer 05000395/2011301 Exam Administrative Items 2C ML18057A8142018-02-26026 February 2018 301 Exam Administrative Items (Delayed Release-2 Year) ML18057A7402018-02-26026 February 2018 VCS Unit 1 2017-301 Exam Draft Items (Delayed Release-2 Years) ML18057A7672018-02-26026 February 2018 301 Exam Final Items (Delayed Release-2 Year) ML18032A2372018-02-0101 February 2018 Form ES-201 Vogtle 3&4, V.C. Summer 2&3 Initial NRC Written Exam Sample Plan - ADAMS 2A - Public Exam Draft Items - Delay Release 2 Years ML17298B9692017-10-25025 October 2017 /2016-301 Public Draft Items (ADAMS-2A)- Delay Release 2 Yrs ML17298A5532017-10-25025 October 2017 VC Summer 05000395/2017301 Exam Report Items RO As-Given Written Exam ML17298C0122017-10-25025 October 2017 V. C. Summer, Unit 2, 05200027/2016301 Public Administrative Items (ADAMS-2C)- Delay Release 2 Yrs ML17193A9262017-07-12012 July 2017 (U1) 2016-301 Exam Administrative Items - Delay Release ML17193A9242017-07-12012 July 2017 (U1) 2016-301 Exam Final Items - Delay Release ML17181A3672017-06-30030 June 2017 V.C. Summer 2015-301 Exam Administrative Items for ADAMS 2C ML17181A3622017-06-30030 June 2017 V.C. Summer 2015-301 Exam Final Items for ADAMS 2B ML17181A3542017-06-30030 June 2017 V.C. Summer 2015-301 Exam Draft Items for ADAMS 2A ML17181A3762017-06-30030 June 2017 V.C. Summer 2015-301 Exam Administrative Items for ADAMS 2D IR 05000395/20173012017-04-0505 April 2017 Notification of Licensed Operator Initial Examination 05000395/2017301 ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 ML16279A3232016-10-0303 October 2016 September 2016 - Summer Unit 1 NRC Generic Fundamentals Examination Results ML16201A2232016-07-15015 July 2016 Preparation and Scheduling of Operator Licensing Examinations ML16179A2682016-06-24024 June 2016 (Unit 1) 2016-301 RO As-Given Written Exam ML16179A2712016-06-24024 June 2016 (Unit 1) 2016-301 SRO As-Given Written Exam ML16158A5002016-05-31031 May 2016 VC Summer Operator Licensing Written Examination Approval 05000395/2016301 ML17193A9232015-08-10010 August 2015 (U2) 2016-301 Exam Draft Items - Delay Release ML15211A3932015-07-30030 July 2015 Initial Exam 2015-302 Post Exam Comments ML15173A4402015-06-26026 June 2015 VC Summer 2015-301 Initial Exam Post Exam Comments RC-15-0076, VC Summer 2015-301 Initial Exam Post Exam Comments2015-06-26026 June 2015 VC Summer 2015-301 Initial Exam Post Exam Comments ML15173A4382015-06-22022 June 2015 VC Summer 2015-301 Initial Examination 2015-301 Final RO Written Exam RC-15-0076, VC Summer 2015-301 Initial Examination 2015-301 Final RO Written Exam2015-06-22022 June 2015 VC Summer 2015-301 Initial Examination 2015-301 Final RO Written Exam ML15173A4392015-05-20020 May 2015 VC Summer 2015-301 Initial Exam Final SRO Written Exam ML15140A6092015-05-19019 May 2015 VC Summer Nuclear Power Plant - Operator Licensing Written Examination Approval 05000395/2015-301 2022-05-05
[Table view] |
Text
FACILITY POST-EXAMINATION COMMENTS AND NRC RESOLUTIONS A complete text of the licensees post-examination comments can be found in ADAMS under Accession Number MLXXXXXXX.
Question # 57, 103K1.02 Comment: The question gives a set of plant conditions and asks based on those conditions what isolation feature has not functioned correctly. The facility recommends that there is no correct answer and that the question should be deleted from the exam.
Facility Basis:
This question requires the candidate to determine, from the given information, the Containment Isolation function that has failed and the actions required by EOP-1.0, REACTOR TRIP/
SAFETY INJECTION ACTUATION to respond to the malfunction. The following is given as a condition:
The following Containment Isolation Valve MCB Status Lights are BRIGHT:
- RCP SL WTR ISOL 8100
- LTDNISOL8152 During the examination, one candidate asked the proctor for the panel and the entire set of words as they are read on the status lights. While this does not have a bearing on any candidates contention of this question, it is included here for completeness. After consultation with the chief examiner, the panel numbers were not given but the sub-bullets were expanded to read as follows (changes are bolded):
The following Containment Isolation Valve MCB Status Lights are BRIGHT:
- RCP SL WTR ISOL 8100 CLSD
- LTDN ISOL 8152 CLSD The BRIGHT indication as stated in the given condition is actually the condition that indicates that the associated valves have closed properly to isolate containment This was true for both the original and changed version of the question. Thus, the premise of a malfunction is invalid because no information is given that indicates that either a Phase A or Phase B containment isolation failure has occurred. There is, therefore, no correct answer.
NRC Resolution: Recommendation accepted. There is no condition given in the question that would suggest that a failure of Phase A or Phase B had occurred. This question will be deleted from the exam.
Question # 62, G2.2.39 Comment: The question asks that if a RCP is lost while at 2% power, what actions would satisfy the TS requirement to be in Mode 3 in one hour. The facility recommends that there are two correct answers.
Facility Basis:
This question requires the candidate to identify an action that will satisfy technical specifications, if performed within one hour, after a RCP trip due to a loss of a 7.2 KV bus in while in Mode 2.
In accordance with 3/4.4.1 REACTOR COOLANT LOOPS AND COOLANT CIRCULATION, the plant must be taken to Mode 3 within one hour.
The definitions for Modes 2 and 3, in accordance with V.C. Summer Technical Specifications, are as follows:
Mode 2 (STARTUP) KEFF>O. 99, Rated Thermal Power <5%, and Average RCS Temperature >350°F Mode 3 (HOT STANDBY) KEFF < 0.99, Rated Thermal Power <0%, and Average RCS Temperature >350°F Answer B. states that only the Control Rods will be driven in to 0 steps. During a Startup in accordance with GOP-3, REACTOR STARTUP FROM HOT STANDBY TO STARTUP (MODE 3 TO MODE 2), Mode 2 is procedurally entered after the withdrawal of Shutdown Banks and before withdrawal of Control Bank A. This procedure served as the technical basis for the question.
In GOP-5 REACTOR SHUTDOWN FROM STARTUP TO HOT STANDBY (MODE 2 TO MODE 3), however, Mode 3 is entered after all Control Banks have been fully inserted and the option is contained in the procedure to leave Shutdown banks withdrawn. It can be assumed that the Mode 3 shutdown margin requirements were met prior to the startup in accordance with Technical Specifications and procedures. Insertion of the Control Rods to 0 steps as stated in B. would therefore restore the reactivity required for Mode 3. This makes answer B.
correct.
V.C. Summer requests that both answers B and D be accepted as correct answers.
NRC Resolution: Recommendation accepted. The question states that the plant is at low power when a loss of an electrical bus occurs. The question asks which condition will satisfy Technical Specification requirements for these plant conditions. The applicant is expected to determine that a shutdown to Mode 3 is required within one hour. The correct answer was a manual trip of the reactor. One other answer was to insert the Control Bank Rods ONLY. This was assumed to be incorrect due to being in the Startup procedure which required declaring transition to Mode 2 before the Shutdown Bank Rods were withdrawn. The logic being that the Shutdown Banks would have to be inserted before Mode 3 would be declared when shutting down.
The shutdown procedure however, directs insertion of the Control Bank Rods then gives the option of inserting the Shutdown Bank Rods before declaring Mode 3.
Integral Rod Worth data from the VC Summer curve book supports the fact that inserting Control Bank rods from Bank D at 115 steps (as stated in the question) to all Control Bank rods in would add sufficient reactivity to decrease Keff to < 0.99. Therefore, with ONLY the Control Bank rods inserted, the plant meets the Tech Spec definition of Mode 3 and therefore, Tech Spec requirements are satisfied.
Answer selection B is to be used as the correct answer as well as choice D.
Question # 96, G2.2.17 Comment: The question asks what position or group authorizes the start of work for an ORANGE risk activity. The facility recommends that there is no correct answer and that the question be deleted from the exam.
Facility Basis:
This question requires the candidate to identify the factors used for calculating EOOS (Equipment Out Of Service) Risk and the position or group that must approve the work for an ORANGE risk activity.
Candidates expressed that the second question was worded incorrectly, specifically, in the use of the words authorizes the start of work. Procedure SAP-102, STATEMENT OF ESPONSIBILITIES, OPERATIONS establishes the responsibilities for authorizing work activities, as follows:
B. The Work Control Center Senior Reactor Operator (WCC SRO) is responsible for:
- 1.
The WOO SRO reports to the Work Control Supervisor.
- 2.
Acting as Tagout Authorizer and Work Authorizer for the implementation of scheduled activities.
- 3.
An SRO or Shift Engineer can assume the duties of the WCC SRO.
- a. The Work Control Center Auxiliary Operator (WOO AO) is a qualified Danger Tagger and reports to the WOO SRO.
6.0 PROCEDURE 6.1 Specific administrative procedures and implementing procedures detail the means of performance of specific tasks to fulfill the Operations Department responsibilities. While additional management approvals for elevated risk activities are required, authorization to actually start work is the responsibility of those individuals delineated in SAP-102 as stated above. Since the GMNPO, Management Duty Supervisor and the Plant Safety Review Committee are not cited in SAP-102, there is not a correct answer.
NRC Resolution: Recommendation not accepted. In OAP-102.1 CONDUCT OF OPERATIONS SHCEDULING UNIT it specifically states in 6.1.a.4)c) the required approval levels for High, Elevated or Moderate Risk Level that (2) Elevated Risk level (ORANGE) -
Requires GMNPO/MDS approval to work. This question was asking for upper level approval due to the risk impact with the choices being GMNPO / Management Duty Supervisor OR the Plant Safety Review Committee. The Work Control Center SRO does not appear in the question as an option. Since there were no questions asked during the exam about this question, it is an adequate assumption that the applicants knew the intent of this question. No changes will be made.