Palo Verde Nuclear Generating Station (PVNGS) Units 1, 2 and 3 Docket Nos. STN 50-528, 50-529, and 50-530 Response to Regulatory Issue Summary (RIS) 2014-13, Planned Licensing Action Submittals for all Power Reactor Licensees  
Palo Verde Nuclear Generating Station (PVNGS) Units 1, 2 and 3 Docket Nos. STN 50-528, 50-529, and 50-530 Response to Regulatory Issue Summary (RIS) 2014-13, PlannedLicensing Action Submittals for all Power Reactor Licensees


==Dear Sirs:==
==Dear Sirs:==
Regulatory Issue Summary (RIS) 2014-13, Planned Licensing Action Submittals for all Power Reactor Licensees, dated December 17, 2014, requested licensees to provide information regarding the licensing actions that are planned to be submitted to the NRC staff for review over the next 3 calendar years and power uprate applications planned over the next 5 years.The requested information is strictly voluntary.
 
The NRC staff plans to use the information in allocating its resources for licensing reviews.Arizona Public Service Company (APS) supports the objective of the RIS in promoting early communication with the NRC staff regarding planned licensing activities.
Regulatory Issue Summary (RIS) 2014-13, Planned Licensing Action Submittals for all Power Reactor Licensees, dated December 17, 2014, requested licensees to provide information regarding the licensing actions that are planned to be submitted to the NRC staff for review over the next 3 calendar years and power uprate applications planned over the next 5 years.
Enclosure 1 of this letter is a listing of planned licensing actions over the next 3 years for the Palo Verde Nuclear Generating Station (PVNGS) Units 1, 2 and 3 and Enclosure 2 of this letter is the Annual Power Uprate Survey for PVNGS Units 1, 2 and 3.APS requests that the contents of Enclosure 2 be withheld from public disclosure, pursuant to 10 CFR 2.390. The NRC has waived the affidavit requirements on its own initiative, since the response to the survey contains business-sensitive information, the disclosure of which is likely to cause competitive harm and should, therefore, be classified as proprietary information.
The requested information is strictly voluntary. The NRC staff plans to use the information in allocating its resources for licensing reviews.
A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway .Diablo Canyon -Palo Verde -Wolf Creek 102-06998-TNW/CJS ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Response to Regulatory Issue Summary (RIS) 2014-13, Planned Licensing Action Submittals for all Power Reactor Licensees Page 2 The enclosures reflect the current target dates for the APS submittals.
Arizona Public Service Company (APS) supports the objective of the RIS in promoting early communication with the NRC staff regarding planned licensing activities. Enclosure 1 of this letter is a listing of planned licensing actions over the next 3 years for the Palo Verde Nuclear Generating Station (PVNGS) Units 1, 2 and 3 and Enclosure 2 of this letter is the Annual Power Uprate Survey for PVNGS Units 1, 2 and 3.
These target dates are subject to change. Also, operational considerations may result in the addition of licensing actions that are not currently itemized in the enclosures.
APS requests that the contents of Enclosure 2 be withheld from public disclosure, pursuant to 10 CFR 2.390. The NRC has waived the affidavit requirements on its own initiative, since the response to the survey contains business-sensitive information, the disclosure of which is likely to cause competitive harm and should, therefore, be classified as proprietary information.
A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway . Diablo Canyon -Palo Verde - Wolf Creek
 
102-06998-TNW/CJS ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Response to Regulatory Issue Summary (RIS) 2014-13, Planned Licensing Action Submittals for all Power Reactor Licensees Page 2 The enclosures reflect the current target dates for the APS submittals. These target dates are subject to change. Also, operational considerations may result in the addition of licensing actions that are not currently itemized in the enclosures.
As requested in RIS 2014-13, a copy of this letter and enclosures is being provided to Tracy Orf, Division of Operating Reactor Licensing, Technical Assistant.
As requested in RIS 2014-13, a copy of this letter and enclosures is being provided to Tracy Orf, Division of Operating Reactor Licensing, Technical Assistant.
No commitments are being made to the NRC by this letter. Should you need further information regarding this submittal, please contact me at (623) 393-5764.Sincerely, G"'A%0J/Thomas N. Weber Nuclear Regulatory Affairs Department Leader TNW/CJS/hsc Enclosure 1 -Listing of Planned Licensing Actions for PVNGS Units 1, 2 and 3 Enclosure 2 -Annual Power Uprate Survey for PVNGS Units 1, 2 and 3 cc: M. L. Dapas B. K. Singal M. M. Watford C. A. Peabody T. Orf NRC Region IV Regional Administrator NRC NRR Project Manager for PVNGS NRC NRR Project Manager NRC Senior Resident Inspector for PVNGS NRC Technical Assistant, Division of Operating Reactor Licensing Enclosure 1 Listing of Planned Licensing Actions for PVNGS Units 1, 2 and 3 Listing of Planned Licensing Enclosure 1 Actions for PVNGS Units 1, 2 and 3 LICENSING LICENSING LICENSING ACTION PROJECTED OUTAGE COMMENTS (AS ACTION ACTION DESCRIPTION SUBMITTAL DATE RELATED? NEEDED)NUMBER IS SO, DATE NEEDED 1 Revise Quality Adopts Regulatory Guide February 27, 2015 No 10 CFR 50.54(a) NRC Assurance 1.28 / ASME NQA-1 Approval Program Document 2 License Revises TSs per approved February 27, 2015 No TSTF-439 is a Amendment to TS Task Force (TSTF) prerequisite for the Eliminate Traveler 439, Eliminate planned submittal to Second Second Completion Times adopt risk-informed Completion Limiting Time From completions times Times from Discovery of Failure to per TSTF-505, Technical Meet an LCO Provide Risk-Specifications Informed Extended (TSs) Completion Times -RITSTF Initiative 4b 3 License Revises TSs to adopt June 30, 2015 No Amendment to TSTF-505, Provide Risk-Adopt Risk- Informed Extended Informed TS Completion Times -Completion RITSTF Initiative 4b Times 4 License Revises EALs to adopt NEI Second Quarter No License Amendment Amendment to 99-01, Revision 6, 2015 Required by 10 CFR Update Development of 50.54(q)(4)
No commitments are being made to the NRC by this letter. Should you need further information regarding this submittal, please contact me at (623) 393-5764.
Emergency Emergency Action Levels Action Level for Non-Passive Reactors (EAL) Scheme 1 Enclosure 2 Annual Power Uprate Survey for PVNGS Units 1, 2 and 3 LICENSING LICENSING LICENSING ACTION PROJECTED OUTAGE COMMENTS (AS ACTION ACTION DESCRIPTION SUBMITTAL DATE RELATED? NEEDED)NUMBER IS SO, DATE NEEDED 5 License Revises SFP Criticality Third Quarter 2015 No Resolves non-Amendment to TSs, incorporating new conservative TS and Revise Spent analysis and SFP design addresses next Fuel Pool (SFP) characteristics generation fuel as Criticality TSs part of the new analysis 6 License Implements a design December 18, 2015 No Commitment related Amendment to change to shorten to DVRs in APS letter Revise Degraded degraded voltage relay number 102-06948, Voltage Relay (DVR) time delay when an dated September 26, (DVR) Time accident signal is present 2014 Delay (TS Surveillance Requirement 3.3.7.3)7 License Implements next March 30, 2016 Yes Schedule still under Amendment and generation fuel design September 30, review Exemption which requires Exemption 2017 Request for Next to 10 CFR 50, Appendix K Generation Fuel 8 License Implements notes in TS March 30, 2016 No Commitment from Amendment to for as-found and as-left prior power uprate, Adopt set-points per TSTF-493, described in APS Recommended Clarify Application of letter number 102-Notes for TS Setpoint Methodology for 06982, dated Setpoints Limiting Safety System December 30, 2014 Settings 2 Enclosure 2 Survey for PVNGS Units 1, 2 and 3 Annual Power Uprate LICENSING LICENSING LICENSING ACTION PROJECTED OUTAGE COMMENTS (AS ACTION ACTION DESCRIPTION SUBMITTAL DATE RELATED? NEEDED)NUMBER IS SO, DATE NEEDED 9 License Adopt TSTF-523, Generic June 30, 2016 No Generic Letter 2008-Amendment to Letter 2008-01, Managing 01 commitment, Implement Gas Accumulation described in APS Surveillance letter number 102-Requirements to 06982, dated Monitor Gas December 30, 2014 Accumulation 10 License Revises TS 5.5.16 to March 31, 2017 Yes Amendment to adopt ILRT (Type A Test) March 3, 2023 Make 15 year interval Containment permanently Integrated Leak Rate Test (ILRT)Interval every 15 Years 3}}
Sincerely, G"'A%                 0J/
Thomas N. Weber Nuclear Regulatory Affairs Department Leader TNW/CJS/hsc - Listing of Planned Licensing Actions for PVNGS Units 1, 2 and 3 - Annual Power Uprate Survey for PVNGS Units 1, 2 and 3 cc:
M. L. Dapas         NRC Region IV Regional Administrator B. K. Singal         NRC NRR Project Manager for PVNGS M. M. Watford       NRC NRR Project Manager C. A. Peabody       NRC Senior Resident Inspector for PVNGS T. Orf              NRC Technical Assistant, Division of Operating Reactor Licensing
 
Enclosure 1 Listing of Planned Licensing Actions for PVNGS Units 1, 2 and 3
 
Enclosure 1 Listing of Planned Licensing Actions for PVNGS Units 1, 2 and 3 LICENSING   LICENSING       LICENSING ACTION               PROJECTED         OUTAGE         COMMENTS (AS ACTION       ACTION           DESCRIPTION           SUBMITTAL DATE       RELATED?           NEEDED)
NUMBER                                                                   IS SO, DATE NEEDED 1   Revise Quality Adopts Regulatory Guide       February 27, 2015       No       10 CFR 50.54(a) NRC Assurance     1.28 / ASME NQA-1                                               Approval Program Document 2   License       Revises TSs per approved     February 27, 2015       No       TSTF-439 is a Amendment to   TS Task Force (TSTF)                                             prerequisite for the Eliminate     Traveler 439, Eliminate                                         planned submittal to Second         Second Completion Times                                         adopt risk-informed Completion     Limiting Time From                                               completions times Times from     Discovery of Failure to                                         per TSTF-505, Technical     Meet an LCO                                                     Provide Risk-Specifications                                                                 Informed Extended (TSs)                                                                           Completion Times -
RITSTF Initiative 4b 3   License       Revises TSs to adopt             June 30, 2015         No Amendment to   TSTF-505, Provide Risk-Adopt Risk-   Informed Extended Informed TS   Completion Times -
Completion     RITSTF Initiative 4b Times 4   License       Revises EALs to adopt NEI       Second Quarter         No       License Amendment Amendment to   99-01, Revision 6,                   2015                       Required by 10 CFR Update         Development of                                                   50.54(q)(4)
Emergency     Emergency Action Levels Action Level   for Non-Passive Reactors (EAL) Scheme 1
 
Enclosure 2 Annual Power Uprate Survey for PVNGS Units 1, 2 and 3 LICENSING   LICENSING         LICENSING ACTION           PROJECTED         OUTAGE       COMMENTS (AS ACTION       ACTION           DESCRIPTION           SUBMITTAL DATE     RELATED?           NEEDED)
NUMBER                                                                   IS SO, DATE NEEDED 5   License         Revises SFP Criticality     Third Quarter 2015       No     Resolves non-Amendment to     TSs, incorporating new                                       conservative TS and Revise Spent     analysis and SFP design                                     addresses next Fuel Pool (SFP) characteristics                                             generation fuel as Criticality TSs                                                               part of the new analysis 6   License         Implements a design         December 18, 2015       No     Commitment related Amendment to     change to shorten                                           to DVRs in APS letter Revise Degraded degraded voltage relay                                       number 102-06948, Voltage Relay   (DVR) time delay when an                                     dated September 26, (DVR) Time       accident signal is present                                   2014 Delay           (TS Surveillance Requirement 3.3.7.3) 7   License         Implements next               March 30, 2016         Yes     Schedule still under Amendment and   generation fuel design                         September 30, review Exemption       which requires Exemption                           2017 Request for Next to 10 CFR 50, Appendix K Generation Fuel 8   License         Implements notes in TS       March 30, 2016         No     Commitment from Amendment to     for as-found and as-left                                     prior power uprate, Adopt           set-points per TSTF-493,                                     described in APS Recommended     Clarify Application of                                       letter number 102-Notes for TS     Setpoint Methodology for                                     06982, dated Setpoints       Limiting Safety System                                       December 30, 2014 Settings 2
 
Enclosure 2 Annual Power Uprate Survey for PVNGS Units 1, 2 and 3 LICENSING   LICENSING       LICENSING ACTION           PROJECTED       OUTAGE         COMMENTS (AS ACTION     ACTION             DESCRIPTION         SUBMITTAL DATE     RELATED?           NEEDED)
NUMBER                                                                 IS SO, DATE NEEDED 9   License         Adopt TSTF-523, Generic     June 30, 2016       No       Generic Letter 2008-Amendment to     Letter 2008-01, Managing                                   01 commitment, Implement       Gas Accumulation                                           described in APS Surveillance                                                               letter number 102-Requirements to                                                             06982, dated Monitor Gas                                                                 December 30, 2014 Accumulation 10   License         Revises TS 5.5.16 to       March 31, 2017       Yes Amendment to     adopt ILRT (Type A Test)                     March 3, 2023 Make             15 year interval Containment     permanently Integrated Leak Rate Test (ILRT)
Interval every 15 Years 3}}

Latest revision as of 17:03, 31 October 2019

Response to Regulatory Issue Summary (RIS) 2014-13, Planned Licensing Action Submittals for All Power Reactor Licensees
ML15037A085
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 01/29/2015
From: Weber T
Arizona Public Service Co
To:
Document Control Desk, NRC/NMSS/SFST
Shared Package
ML15037A106 List:
References
102-06998-TNW/CJS
Download: ML15037A085 (6)


Text

The content of Enclosure 2 is PROPRIETARY and should be withheld From Public Disclosure pursuant to 10 CFR 2.390 10 CFR 50.90 Palo Verde Nuclear Generating Station 5801 S. Wintersburg Road Tonopah, AZ 85354 102-06998-TNW/CJS January 29, 2015 ATTN: Document Control Desk Director, Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Subject:

Palo Verde Nuclear Generating Station (PVNGS) Units 1, 2 and 3 Docket Nos. STN 50-528, 50-529, and 50-530 Response to Regulatory Issue Summary (RIS) 2014-13, PlannedLicensing Action Submittals for all Power Reactor Licensees

Dear Sirs:

Regulatory Issue Summary (RIS) 2014-13, Planned Licensing Action Submittals for all Power Reactor Licensees, dated December 17, 2014, requested licensees to provide information regarding the licensing actions that are planned to be submitted to the NRC staff for review over the next 3 calendar years and power uprate applications planned over the next 5 years.

The requested information is strictly voluntary. The NRC staff plans to use the information in allocating its resources for licensing reviews.

Arizona Public Service Company (APS) supports the objective of the RIS in promoting early communication with the NRC staff regarding planned licensing activities. Enclosure 1 of this letter is a listing of planned licensing actions over the next 3 years for the Palo Verde Nuclear Generating Station (PVNGS) Units 1, 2 and 3 and Enclosure 2 of this letter is the Annual Power Uprate Survey for PVNGS Units 1, 2 and 3.

APS requests that the contents of Enclosure 2 be withheld from public disclosure, pursuant to 10 CFR 2.390. The NRC has waived the affidavit requirements on its own initiative, since the response to the survey contains business-sensitive information, the disclosure of which is likely to cause competitive harm and should, therefore, be classified as proprietary information.

A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway . Diablo Canyon -Palo Verde - Wolf Creek

102-06998-TNW/CJS ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Response to Regulatory Issue Summary (RIS) 2014-13, Planned Licensing Action Submittals for all Power Reactor Licensees Page 2 The enclosures reflect the current target dates for the APS submittals. These target dates are subject to change. Also, operational considerations may result in the addition of licensing actions that are not currently itemized in the enclosures.

As requested in RIS 2014-13, a copy of this letter and enclosures is being provided to Tracy Orf, Division of Operating Reactor Licensing, Technical Assistant.

No commitments are being made to the NRC by this letter. Should you need further information regarding this submittal, please contact me at (623) 393-5764.

Sincerely, G"'A% 0J/

Thomas N. Weber Nuclear Regulatory Affairs Department Leader TNW/CJS/hsc - Listing of Planned Licensing Actions for PVNGS Units 1, 2 and 3 - Annual Power Uprate Survey for PVNGS Units 1, 2 and 3 cc:

M. L. Dapas NRC Region IV Regional Administrator B. K. Singal NRC NRR Project Manager for PVNGS M. M. Watford NRC NRR Project Manager C. A. Peabody NRC Senior Resident Inspector for PVNGS T. Orf NRC Technical Assistant, Division of Operating Reactor Licensing

Enclosure 1 Listing of Planned Licensing Actions for PVNGS Units 1, 2 and 3

Enclosure 1 Listing of Planned Licensing Actions for PVNGS Units 1, 2 and 3 LICENSING LICENSING LICENSING ACTION PROJECTED OUTAGE COMMENTS (AS ACTION ACTION DESCRIPTION SUBMITTAL DATE RELATED? NEEDED)

NUMBER IS SO, DATE NEEDED 1 Revise Quality Adopts Regulatory Guide February 27, 2015 No 10 CFR 50.54(a) NRC Assurance 1.28 / ASME NQA-1 Approval Program Document 2 License Revises TSs per approved February 27, 2015 No TSTF-439 is a Amendment to TS Task Force (TSTF) prerequisite for the Eliminate Traveler 439, Eliminate planned submittal to Second Second Completion Times adopt risk-informed Completion Limiting Time From completions times Times from Discovery of Failure to per TSTF-505, Technical Meet an LCO Provide Risk-Specifications Informed Extended (TSs) Completion Times -

RITSTF Initiative 4b 3 License Revises TSs to adopt June 30, 2015 No Amendment to TSTF-505, Provide Risk-Adopt Risk- Informed Extended Informed TS Completion Times -

Completion RITSTF Initiative 4b Times 4 License Revises EALs to adopt NEI Second Quarter No License Amendment Amendment to 99-01, Revision 6, 2015 Required by 10 CFR Update Development of 50.54(q)(4)

Emergency Emergency Action Levels Action Level for Non-Passive Reactors (EAL) Scheme 1

Enclosure 2 Annual Power Uprate Survey for PVNGS Units 1, 2 and 3 LICENSING LICENSING LICENSING ACTION PROJECTED OUTAGE COMMENTS (AS ACTION ACTION DESCRIPTION SUBMITTAL DATE RELATED? NEEDED)

NUMBER IS SO, DATE NEEDED 5 License Revises SFP Criticality Third Quarter 2015 No Resolves non-Amendment to TSs, incorporating new conservative TS and Revise Spent analysis and SFP design addresses next Fuel Pool (SFP) characteristics generation fuel as Criticality TSs part of the new analysis 6 License Implements a design December 18, 2015 No Commitment related Amendment to change to shorten to DVRs in APS letter Revise Degraded degraded voltage relay number 102-06948, Voltage Relay (DVR) time delay when an dated September 26, (DVR) Time accident signal is present 2014 Delay (TS Surveillance Requirement 3.3.7.3) 7 License Implements next March 30, 2016 Yes Schedule still under Amendment and generation fuel design September 30, review Exemption which requires Exemption 2017 Request for Next to 10 CFR 50, Appendix K Generation Fuel 8 License Implements notes in TS March 30, 2016 No Commitment from Amendment to for as-found and as-left prior power uprate, Adopt set-points per TSTF-493, described in APS Recommended Clarify Application of letter number 102-Notes for TS Setpoint Methodology for 06982, dated Setpoints Limiting Safety System December 30, 2014 Settings 2

Enclosure 2 Annual Power Uprate Survey for PVNGS Units 1, 2 and 3 LICENSING LICENSING LICENSING ACTION PROJECTED OUTAGE COMMENTS (AS ACTION ACTION DESCRIPTION SUBMITTAL DATE RELATED? NEEDED)

NUMBER IS SO, DATE NEEDED 9 License Adopt TSTF-523, Generic June 30, 2016 No Generic Letter 2008-Amendment to Letter 2008-01, Managing 01 commitment, Implement Gas Accumulation described in APS Surveillance letter number 102-Requirements to 06982, dated Monitor Gas December 30, 2014 Accumulation 10 License Revises TS 5.5.16 to March 31, 2017 Yes Amendment to adopt ILRT (Type A Test) March 3, 2023 Make 15 year interval Containment permanently Integrated Leak Rate Test (ILRT)

Interval every 15 Years 3